CN1483902A - Method of distributing freezers for speeding up freezing soil and rock in local area - Google Patents

Method of distributing freezers for speeding up freezing soil and rock in local area Download PDF

Info

Publication number
CN1483902A
CN1483902A CNA031316115A CN03131611A CN1483902A CN 1483902 A CN1483902 A CN 1483902A CN A031316115 A CNA031316115 A CN A031316115A CN 03131611 A CN03131611 A CN 03131611A CN 1483902 A CN1483902 A CN 1483902A
Authority
CN
China
Prior art keywords
frigo
freezing
linear
arranging
freezer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA031316115A
Other languages
Chinese (zh)
Inventor
杨维好
黄家会
宋雷
王衍森
任彦龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CNA031316115A priority Critical patent/CN1483902A/en
Publication of CN1483902A publication Critical patent/CN1483902A/en
Pending legal-status Critical Current

Links

Images

Abstract

The present invention relates to a freezer arrangement method for accelerating the speed of freezing local area rock-soil for cutting rockshaft with large section, and said method includes the following steps: drilling and cutting freezing hole around entrance for excavating channel, placing freezer formed from steel pipe and plastic pipe in the freezing hole, non-linear arranging or linear and non-linear alternatively arranging the freezer placed in the freezing hole along the excavated channel deep-portion, so that it raises the after-efficiency of freezer, and can accelerate the speed of freezing target area rock-soil, and can reduce freezing time and cost.

Description

The frigo method for arranging of regional area ground is freezed in acceleration
One, technical field
The present invention relates to a kind of acceleration and freeze the frigo method for arranging of regional area ground, be used for the artificial frozen construction worker of geotechnical engineering method, be particularly useful in deep topsoil, digging vertical shaft pit shaft with large diameter, also be applicable to freezing process and dig inclined shaft, footrill (or tunnel) and foundation ditch with freezing process.
Two, background technology
In the geotechnical engineering construction freezing method, the frozen soils structure that manually freezes to form will satisfy the requirement of water proof and the part or all of water and soil pressure of opposing.Along with the expansion of excavated section size and the increase of cutting depth, water shutoff problem and the big problem of work plane distortion of excavating regional bottom (or the place ahead) become increasingly conspicuous.The main way that addresses these problems is thickness and the intensity that increases these target area frozen soil, even freezes real target area.In existing frigo method for arranging, the layout axis of frigo all is designed to vertical curve, horizontal linear or angled straight lines, and the target territory that requires the construction axis not depart from regulation.Though the method for arranging of this frigo can be finished the task of Frozen Rock and Soil, but its time of freezing is longer, and the speed of excavation construction is very fast at present, though thereby top has reached the excavation condition, but also do not have when being excavated to the deep to form frozen soil curtain (or frozen soil curtain of back cover), influenced the construction period greatly and caused unnecessary economic loss with sufficient intensity and rigidity.
Three, technology contents
1. goal of the invention
Problem in view of prior art exists the purpose of this invention is to provide the frigo method for arranging that the regional area ground is freezed in a kind of acceleration, and it can shorten freeze-off time, reduces cost, and guarantees excavation construction safety.
2. technical scheme
The present invention quickens to freeze the frigo method for arranging of regional area ground, Drilling freezing hole around the ground settlement and tunnel inlet, and the frigo that setting is made up of steel pipe and plastic pipe in freezing hole, describedly be put in down frigo in the freezing hole, or to have a frigo at least be that non-linear is arranged along excavation passage deep non-linear layout or linear and non-linear arranged crosswise.
3. technique effect
The present invention quickens to freeze the frigo method for arranging of regional area ground, be best suited in deep topsoil and dig vertical shaft pit shaft with large diameter with freezing process, compare with original linear frigo method for arranging, improved the later stage efficient of frigo, reduced the quantity of freezing hole; Accelerate the freezing speed of target area ground, can save freeze-off time and expense; The shape of frozen soil wall and position can change according to engineering specifications and geological conditions; Solved driving and masonry construction speed fast with the ground freezing speed contradiction between slowly.
Four, description of drawings
Fig. 1 is that frigo of the present invention is arranged embodiment one schematic top plan view.
Fig. 2 is the A-A sectional drawing of Fig. 1.
Fig. 3 is that Fig. 1 is the B-B sectional drawing.
Fig. 4 is that frigo of the present invention is arranged embodiment two schematic top plan view.
Fig. 5 is the A-A sectional drawing of Fig. 4.
Fig. 6 is the B-B sectional drawing of Fig. 4.
Fig. 7 is that schematic diagram is looked on the frigo layout embodiment of the present invention three level right sides.
Fig. 8 is the A-A sectional drawing of Fig. 7.
Five, the specific embodiment
The invention will be further described below in conjunction with the embodiment in the accompanying drawing:
The present invention quickens to freeze the frigo method for arranging of regional area ground, Drilling freezing hole around ground settlement and tunnel inlet 1, and the frigo 2 that setting is made up of steel pipe and plastic pipe in freezing hole, describedly be put in down frigo 2 in the freezing hole, or to have 1 frigo at least be that non-linear is arranged along excavation passage deep non-linear layout or linear and non-linear arranged crosswise.
Embodiment one: as shown in Figure 1, the frigo 2 that linear and non-linear are arranged is spaced, partly (or at interval) frigo 2 is arranged to excavation passage inside bend in the excavation depths, substantially be into broken line shape, be that frigo 2 tops are for vertically arranging, the bottom is to the inboard skew of excavation passage certain distance, as shown in Figure 2; The axis of remaining part frigo 2 still is a rectilinear form, and promptly frigo 2 is vertical layout from top to bottom, as shown in Figure 3.This kind frigo method for arranging can quicken to excavate freezing of channel center's ground, can create conditions for excavating in advance.
Embodiment two: as shown in Figure 4, the frigo 2 that linear and non-linear are arranged is spaced, partly (or at interval) frigo 2 is arranged to excavation passage outside curve in the excavation depths, substantially be into broken line shape, be that frigo 2 tops are for vertically arranging, the bottom is to excavation passage outside skew certain distance, as shown in Figure 5; The axis of remaining part frigo 2 still is a rectilinear form, and promptly frigo 2 is vertical layout from top to bottom, as shown in Figure 6.This kind frigo method for arranging can improve frigo in the efficient in later stage, under the situation that does not increase freezing hole quantity, obtains frozen soil wall thicker and that average temperature is lower in the bottom.
Embodiment three: as shown in Figure 7, freeze all device 2 is arranged to excavation passage inside bend in the excavation depths, substantially be into broken line shape, frigo 2 is arranged for horizontal linear to excavating in the direction setting distance range from the excavation inlet, frigo 2 remainders are to the inboard skew of excavation passage certain distance, as shown in Figure 8.This kind frigo method for arranging can guarantee to be easy to form a Frozen Rock and Soil pad near the frigo afterbody, to prevent that building work plane the place ahead in pick water burst, prominent mud accident occur.

Claims (1)

1. quicken to freeze the frigo method for arranging of regional area ground, at ground settlement and tunnel inlet (1) Drilling freezing hole on every side, and the frigo (2) that setting is made up of steel pipe and plastic pipe in freezing hole, it is characterized in that: describedly be put in down frigo (2) in the freezing hole, or to have a frigo at least be that non-linear is arranged along excavation passage deep non-linear layout or linear and non-linear arranged crosswise.
CNA031316115A 2003-05-29 2003-05-29 Method of distributing freezers for speeding up freezing soil and rock in local area Pending CN1483902A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA031316115A CN1483902A (en) 2003-05-29 2003-05-29 Method of distributing freezers for speeding up freezing soil and rock in local area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA031316115A CN1483902A (en) 2003-05-29 2003-05-29 Method of distributing freezers for speeding up freezing soil and rock in local area

Publications (1)

Publication Number Publication Date
CN1483902A true CN1483902A (en) 2004-03-24

Family

ID=34153815

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA031316115A Pending CN1483902A (en) 2003-05-29 2003-05-29 Method of distributing freezers for speeding up freezing soil and rock in local area

Country Status (1)

Country Link
CN (1) CN1483902A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102278116A (en) * 2011-04-27 2011-12-14 吉林大学 Device and method for manufacturing underground frozen wall in cold areas in winter
CN102536243A (en) * 2012-02-28 2012-07-04 重庆市能源投资集团科技有限责任公司 Coal seam freezing type cross-drift coal uncovering method
CN102839670A (en) * 2011-06-22 2012-12-26 上海市政工程设计研究总院(集团)有限公司 Shallow foundation pit freezing enclosure and construction method thereof
CN102926753A (en) * 2012-10-08 2013-02-13 中南大学 Deep hole caving backfilling stoping method for artificially freezing stope roof
CN104453911A (en) * 2014-12-02 2015-03-25 淮南矿业(集团)有限责任公司 Freezer and vertical shaft freezing system
CN106013166A (en) * 2016-06-27 2016-10-12 中国矿业大学 Construction method adopting spoke-type freezing and outwards expanded excavation for excavating ultra-deep foundation pit
CN106124243A (en) * 2016-06-16 2016-11-16 重庆大学 Coal seam gas-bearing capacity measures advanced freezing sampling method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102278116A (en) * 2011-04-27 2011-12-14 吉林大学 Device and method for manufacturing underground frozen wall in cold areas in winter
CN102278116B (en) * 2011-04-27 2013-06-26 吉林大学 Device and method for manufacturing underground frozen wall in cold areas in winter
CN102839670A (en) * 2011-06-22 2012-12-26 上海市政工程设计研究总院(集团)有限公司 Shallow foundation pit freezing enclosure and construction method thereof
CN102536243A (en) * 2012-02-28 2012-07-04 重庆市能源投资集团科技有限责任公司 Coal seam freezing type cross-drift coal uncovering method
CN102926753A (en) * 2012-10-08 2013-02-13 中南大学 Deep hole caving backfilling stoping method for artificially freezing stope roof
CN104453911A (en) * 2014-12-02 2015-03-25 淮南矿业(集团)有限责任公司 Freezer and vertical shaft freezing system
CN106124243A (en) * 2016-06-16 2016-11-16 重庆大学 Coal seam gas-bearing capacity measures advanced freezing sampling method
CN106013166A (en) * 2016-06-27 2016-10-12 中国矿业大学 Construction method adopting spoke-type freezing and outwards expanded excavation for excavating ultra-deep foundation pit
CN106013166B (en) * 2016-06-27 2018-07-03 中国矿业大学 Spoke type freezes to dig the construction method that formula excavates ultra-deep foundation pit outward

Similar Documents

Publication Publication Date Title
CN105003270B (en) Underwater tunnel construction method suitable for ultra-shallow earthing conditions
US11795643B2 (en) Method for constructing inner dump type strip mine pit bottom reservoirs section by section
CN111577383B (en) Method for treating tunnel leakage water in alpine region
CN103277103A (en) None-full-depth freezing method for penetrating through ultra-thick water-rich bed rock in shaft deepening
CN104806253A (en) Construction method for opening hole between rectangular pipe jacking channels
CN103726495A (en) Offshore deep foundation pit supporting structure and construction method thereof
CN205260041U (en) Method of freezing supporting construction is spouted soon to level
CN1483902A (en) Method of distributing freezers for speeding up freezing soil and rock in local area
CN109930613A (en) A kind of construction method and structure of the roadbed slope drainage system that seeps water
CN105970973A (en) Soft soil foundation pit double-row piles supporting structure considering soil-arch and deformation space effect
CN104775438B (en) The method of tower position foundation pit construction in karst landform basis rainy season
CN105927234A (en) Construction method for reinforcing and excavating horizontal tunnel by multi-vertical-shaft freezing method
CN1737337A (en) Water preventing method for mine in structure of thin base rock and thick loose aquifer
CN108934654B (en) Ancient tree in-situ protection method in river regulation
CN208219453U (en) A kind of expensive soil cutting deep layer discharge structure
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN109594994A (en) Tunneling method under existing building
CN1534142A (en) Underground continuous wall frozen construction method
CN107905219A (en) The construction method of ultra-deep hand excavation stake holes under a kind of complex geological condition
RU2720893C1 (en) Development method of repair trench for replacement of defect section of pipeline
CN205475323U (en) Municipal administration pipeline crowd stridees across underground structure in tunnel
CN1804234B (en) Drainage method and apparatus for red mud dump in karst terrain
CN204357438U (en) A kind of excavation structure of open trench tunnel deep foundation ditch transition tunneling section
CN106285777A (en) The method that flood mine mineral building discharges water in advance
RU2114307C1 (en) Method for opencast mining of flooded mineral deposits

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication