CN1534142A - Underground continuous wall frozen construction method - Google Patents

Underground continuous wall frozen construction method Download PDF

Info

Publication number
CN1534142A
CN1534142A CNA031131093A CN03113109A CN1534142A CN 1534142 A CN1534142 A CN 1534142A CN A031131093 A CNA031131093 A CN A031131093A CN 03113109 A CN03113109 A CN 03113109A CN 1534142 A CN1534142 A CN 1534142A
Authority
CN
China
Prior art keywords
wall
construction
frozen
diaphragm wall
slotted eye
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA031131093A
Other languages
Chinese (zh)
Other versions
CN1243162C (en
Inventor
杨维好
黄家会
王衍森
蒋武军
宋雷
任彦龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN 03113109 priority Critical patent/CN1243162C/en
Publication of CN1534142A publication Critical patent/CN1534142A/en
Application granted granted Critical
Publication of CN1243162C publication Critical patent/CN1243162C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

A freezing method for building the continuous underground wall suitable for deep fundation pit includes artifically freezing the ground layer to form a frozen ground wall, manually or mechanically digging slots under protection of said frozen ground wall, and casting concrete walls in said slots. Its advantages are simple technology, high speed, and no need of sludge to protect wall surface.

Description

Diaphragm wall frozen construction worker method
One, technical field
The present invention relates to diaphragm wall frozen construction worker method, be particularly useful for dark, thick construction of continuous concrete wall such as heavy construction deep foundation ditch, large-scale bridge pier deep foundation ditch, also be applicable to other carrying in moisture or caving ground or the construction of water proof body of wall.
Two, background technology
Municipal administration, traffic at present, traditional construction of diaphragm wall in the fields such as construction work, be in the slotted eye digging process, to adopt mud off, under mud, carry out cast of wall section concrete and the construction of wall section joint, though can finish the excavation work of slotted eye, body of wall shape and physical dimension are prone to deviation, walls concrete is prone to nest mud, folder mud phenomenon, grooving equipment is poor to the adaptive capacity of complex geological condition, and the joint quality between each wall section also is difficult for guaranteeing; Then need large-scale or expensive plant equipment to finish for dark, thick construction of continuous concrete wall, its slurry coat method also causes environment pollution easily.
Three, technology contents
1. goal of the invention
In view of the deficiency that prior art exists, the purpose of this invention is to provide a kind of easy construction, diaphragm wall physique amount is easy to guarantee, and is free from environmental pollution, excavates effective diaphragm wall frozen construction worker method.
2. technical scheme
Diaphragm wall frozen construction worker method of the present invention is finished like this: at first adopt artificial stratum freezing process, a distance, the slotted eye outside in the diaphragm wall section of intending construction, freezing of certain density of constructing with boring, in these borings, frigo is installed, provide cold to frigo, make its Freezing stratum as rapid on every side, and form the frozen soil wall that reaches designing requirement, promptly artificial stratum freezing process forms frozen soil wall; Then under the protection of formation frozen soil wall, artificial or Mechanical Method construction slotted eye, last in the slotted eye that construction is finished concreting, and couple together with adjacent wall section.Drilling depth should surpass diaphragm wall design maximum degree of depth certain distance.
3. technique effect
Diaphragm wall frozen construction worker method of the present invention is best suited for dark, thick construction of continuous concrete wall such as heavy construction deep foundation ditch, large-scale bridge pier deep foundation ditch.Adopt artificial stratum freezing process to form frozen soil wall (comprise and freeze rock), under the protection that forms frozen soil wall, the slotted eye of artificial or mechanical means driving and masonry construction wall section, concreting wall section in slotted eye is then handled the joint of wall section simultaneously well.Compare with traditional construction, it is simple that this diaphragm wall frozen construction worker method has construction technology, construction equipment is easy, but multiple spot is constructed simultaneously, and speed of application is fast, the diaphragm wall of can construct under various the complex geological conditions various degree of depth and thickness, need not mud off, the mud-less pollution problem is dry operation, and wall construction quality and wall section joint construction quality are easy to control and guarantee.For dark, thick construction of continuous concrete wall, this method has special advantage, and has practicality widely.
Four, the specific embodiment
Diaphragm wall frozen construction worker method of the present invention, at first in a distance, diaphragm wall design attitude both sides, the usefulness of freezing of certain density of constructing is holed, and drilling depth should surpass diaphragm wall design maximum degree of depth certain distance; Drilling construction finishes, and frigo is installed in freezing hole, implements artificial Freezing stratum as rapid, promptly provides cold to frigo, makes its Freezing stratum as rapid on every side, and forms the frozen soil wall that reaches designing requirement.After frozen soil wall thickness and average temperature reach designing requirement, under the protection of frozen soil wall, adopt well worker or mechanical means to divide groove section cutting slots, and where necessary the slotted eye wall is carried out supporting; Slotted eye is handled wall section joint on earth and after the acceptance(check), then carries out the casting and constructing of steel concrete diaphragm wall body of wall.

Claims (4)

1. diaphragm wall frozen construction worker method is characterized in that:
Step 1: adopt artificial stratum freezing process to form frozen soil wall;
Step 2: under the protection of formation frozen soil wall, artificial or Mechanical Method construction slotted eye, and where necessary the slotted eye wall is carried out supporting;
Step 3: concreting in the slotted eye that construction is finished, and couple together with adjacent wall section.
2. diaphragm wall frozen construction worker method according to claim 1, it is characterized in that: described artificial stratum freezing process is a distance, the slotted eye outside in the diaphragm wall section of intending construction, freezing of certain density of constructing with boring, in these borings, frigo is installed, provide cold to frigo, make its Freezing stratum as rapid on every side, and form the frozen soil wall (comprise and freeze rock) that reaches designing requirement.
3. diaphragm wall frozen construction worker method according to claim 1 and 2 is characterized in that: described drilling depth should surpass diaphragm wall design maximum degree of depth certain distance.
4. according to claim 1 or 2 or described diaphragm wall frozen construction worker method, it is characterized in that: described concreting is to carry out under the situation that does not have mud and water.
CN 03113109 2003-04-01 2003-04-01 Underground continuous wall frozen construction method Expired - Fee Related CN1243162C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 03113109 CN1243162C (en) 2003-04-01 2003-04-01 Underground continuous wall frozen construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 03113109 CN1243162C (en) 2003-04-01 2003-04-01 Underground continuous wall frozen construction method

Publications (2)

Publication Number Publication Date
CN1534142A true CN1534142A (en) 2004-10-06
CN1243162C CN1243162C (en) 2006-02-22

Family

ID=34283725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 03113109 Expired - Fee Related CN1243162C (en) 2003-04-01 2003-04-01 Underground continuous wall frozen construction method

Country Status (1)

Country Link
CN (1) CN1243162C (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102322068A (en) * 2011-07-06 2012-01-18 上海地矿工程勘察有限公司 Pressure reduction dewatering auxiliary trenching construction process
CN103276720A (en) * 2013-05-31 2013-09-04 中国矿业大学 Soft soil subgrade freezing reinforcement method
CN103850258A (en) * 2014-03-24 2014-06-11 北京城建勘测设计研究院有限责任公司 Natural freezing support method
CN105239585A (en) * 2015-10-31 2016-01-13 中国矿业大学(北京) In-pile freezing structure of deep underground space and constructing method
CN105297742A (en) * 2015-10-22 2016-02-03 北京城建集团有限责任公司 Structure and method of water stopping support of underground space
CN106013166A (en) * 2016-06-27 2016-10-12 中国矿业大学 Construction method adopting spoke-type freezing and outwards expanded excavation for excavating ultra-deep foundation pit
CN107165171A (en) * 2015-08-31 2017-09-15 罗海军 Basement supporting frozen construction method
CN111101523A (en) * 2020-01-17 2020-05-05 安徽理工大学 Reinforced ice supporting device for foundation pit and supporting method adopting same
CN111945704A (en) * 2020-08-13 2020-11-17 中铁二十局集团第一工程有限公司 Method for reinforcing water-rich silt stratum by obliquely arranging multiple rows of freezing pipes

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102322068B (en) * 2011-07-06 2013-08-21 上海地矿工程勘察有限公司 Pressure reduction dewatering auxiliary trenching construction process
CN102322068A (en) * 2011-07-06 2012-01-18 上海地矿工程勘察有限公司 Pressure reduction dewatering auxiliary trenching construction process
CN103276720A (en) * 2013-05-31 2013-09-04 中国矿业大学 Soft soil subgrade freezing reinforcement method
CN103276720B (en) * 2013-05-31 2015-12-02 中国矿业大学 A kind of soft soil roadbed consolidation by freezing method
CN103850258B (en) * 2014-03-24 2016-06-29 北京城建勘测设计研究院有限责任公司 A kind of weather freezing method for protecting support
CN103850258A (en) * 2014-03-24 2014-06-11 北京城建勘测设计研究院有限责任公司 Natural freezing support method
CN107165171A (en) * 2015-08-31 2017-09-15 罗海军 Basement supporting frozen construction method
CN107165171B (en) * 2015-08-31 2019-06-07 罗海军 Basement supporting frozen construction method
CN105297742A (en) * 2015-10-22 2016-02-03 北京城建集团有限责任公司 Structure and method of water stopping support of underground space
CN105239585A (en) * 2015-10-31 2016-01-13 中国矿业大学(北京) In-pile freezing structure of deep underground space and constructing method
CN106013166A (en) * 2016-06-27 2016-10-12 中国矿业大学 Construction method adopting spoke-type freezing and outwards expanded excavation for excavating ultra-deep foundation pit
CN106013166B (en) * 2016-06-27 2018-07-03 中国矿业大学 Spoke type freezes to dig the construction method that formula excavates ultra-deep foundation pit outward
CN111101523A (en) * 2020-01-17 2020-05-05 安徽理工大学 Reinforced ice supporting device for foundation pit and supporting method adopting same
CN111945704A (en) * 2020-08-13 2020-11-17 中铁二十局集团第一工程有限公司 Method for reinforcing water-rich silt stratum by obliquely arranging multiple rows of freezing pipes

Also Published As

Publication number Publication date
CN1243162C (en) 2006-02-22

Similar Documents

Publication Publication Date Title
CN103195158B (en) Municipal drainage pipeline slurry balance pipe-jacking construction method
CN101614020B (en) Flexible bladder type anticorrosion device, anticorrosion pile and construction method using same
CN201089893Y (en) Foundation pit circle shield prefabricated driven pile
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN105649012A (en) Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN104775440A (en) Mineshaft-type underground garage deep foundation pit supporting structure
CN108517877A (en) Miscellaneous fill ultra-deep foundation pit consolidates slip casting combination double-row steel pipe stake supporting construction method
CN1265062C (en) Construction for making piles and tools
CN104762955A (en) Manually excavated pedestal pile construction method based on freezing process
CN1243162C (en) Underground continuous wall frozen construction method
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN101768960B (en) Bored concrete pile construction method of permafrost layer
CN105926626B (en) Overlength pneumatic down hole hammer vibrates jet grouting pile construction technique
CN208152063U (en) A kind of superelevation infiltration coefficient sand ovum stratum Groundwater Control system
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN105002912A (en) Construction method for splicing type caisson structure based on prefabricated hollow piles
CN105625299B (en) A kind of wall board type Novel underground diaphragm wall and its construction method
CN205399401U (en) Novel underground continuous wall of wallboard formula
CN112302678B (en) Deformation control construction process for shallow tunnel of underpass building
CN101597903A (en) A kind of construction method of cylindrical slurry core pile that is used for pattern foundation pit supporting structure
CN107476293A (en) A kind of quick spreading structure of soft soil foundation bored concrete pile configures and its spreading method
CN208294522U (en) Waterproof of man in a kind of pilot tunnel of rich water sand-pebble layer
CN111980093A (en) Groove grooving equipment
CN108019211B (en) Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof
CN204753632U (en) Underground parking garage is built to caisson structure based on prefabricated concatenation of stake on an empty stomach formula

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20060222