CN103276720B - A kind of soft soil roadbed consolidation by freezing method - Google Patents

A kind of soft soil roadbed consolidation by freezing method Download PDF

Info

Publication number
CN103276720B
CN103276720B CN201310213762.5A CN201310213762A CN103276720B CN 103276720 B CN103276720 B CN 103276720B CN 201310213762 A CN201310213762 A CN 201310213762A CN 103276720 B CN103276720 B CN 103276720B
Authority
CN
China
Prior art keywords
frigo
soft soil
roadbed
freezing
soil roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310213762.5A
Other languages
Chinese (zh)
Other versions
CN103276720A (en
Inventor
宋雷
杨维好
黄家会
孙锡乐
李海鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201310213762.5A priority Critical patent/CN103276720B/en
Publication of CN103276720A publication Critical patent/CN103276720A/en
Application granted granted Critical
Publication of CN103276720B publication Critical patent/CN103276720B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of soft soil roadbed consolidation by freezing method, it comprises the following steps: soft soil roadbed character and the surface conditions of construction are intended in (1) test; (2) according to the situation that step (1) is tested, determine road surface freezing method and select frigo; (3) determine quantity and the riding position of frigo, lay frigo; (4) external equipment is installed to frigo in step (3); (5) implement manual pipe jacking, make quick freezing in its 3 days, roadbed solidification point is-20 ° of C, and freezes the supporting capacity that roadbed has 100kN, and the vehicle within allowing 80 tons passes through.Beneficial effect is that low temperature refrigerant only need be sent into stratum by consolidation by freezing method of the present invention, namely can the soft soil roadbed frozen soils structure being frozen into some strength in the short time; Construction is simple, and the construction equipment of needs is few, occupied ground is little, speed of application is fast, also can according to the needs of different terrain, and adopt different freezer units to carry out consolidation by freezing to soft soil roadbed, consolidation effect is good, practical.

Description

A kind of soft soil roadbed consolidation by freezing method
Technical field
The present invention relates to a kind of soft soil roadbed reinforcement means, be specifically a kind ofly applicable to soft soil roadbed consolidation by freezing method.
Background technology
In natural calamity, war etc. in particular cases, need to realize the current of road fast on soft soil roadbed.Particularly in the laying of the interim sidewalk of road foundation or rescue requiring rapid construction, realize the current particularly important of road fast.
At present, adopt change banket, the method such as vacuum preloading, cement-soil campshed is reinforcing road bed.These subgrade strengthening methods have the advantages that earth volume is large, construction speed is slow, long in time limit, often can not realize the current of road in reality fast.Adopt the method also to need equipment is many, material is many, cannot complete admission and the construction of personnel and equipment at short notice simultaneously.
Summary of the invention
For above-mentioned prior art Problems existing, the invention provides a kind of soft soil roadbed consolidation by freezing method, soft soil roadbed quick freezing is reinforced, to meet the requirement of road.
To achieve these goals, the soft soil roadbed consolidation by freezing method of one of the present invention, comprises the following steps:
(1) soft soil roadbed character and the roadbed situation of construction is intended in test;
(2) the soft soil roadbed character recorded according to step 1 and roadbed situation, determine roadbed freezing method and select frigo,
Frigo is rectilinear frigo or film covering type frigo;
(3) determine quantity and the riding position of frigo, lay frigo;
(4) external equipment is installed to frigo in step 3, wherein refrigerant is that the frigo external equipment of liquid nitrogen is primarily of storage nitrogen groove, liquid nitrogen tank car and distributor composition, refrigerant is the frigo external equipment of hypothermic saline is Freezing Station, Freezing Station forms primarily of compressor, condenser, evaporimeter, brine pump and choke valve
(5) implement manual pipe jacking, make quick freezing in its 3 days, roadbed solidification point reaches-20 DEG C, and freezes roadbed and reach and have 100kN
Supporting capacity, the vehicle within allowing 80 tons passes through; For step (2) according to rectilinear frigo, the guarantor that need lay
Temperature isolation layer, it also should have the ability that carrying 80 tons of vehicles pass through.
Step of the present invention (2) in, there is weak substratum in soft soil roadbed or the Soft Soil Layer degree of depth is different, adopt difference freezing method, frigo adopts rectilinear frigo; When soft soil roadbed middle Soft Soil Layer distribution is relatively more even, adopt bulk freezing mode,
1. soft soil roadbed is horizontal roadbed, and frigo adopts rectilinear frigo or film covering type frigo, 2. soft soil roadbed be vertical or
The roadbed tilted, frigo adopts film covering type frigo; When soft soil roadbed on road distributed areas more scattered, adopt point
Sheet freezing method, 1. soft soil roadbed is horizontal roadbed, and frigo adopts rectilinear frigo or film covering type frigo, 2. weak soil
Roadbed is roadbed that is vertical or that tilt, and frigo adopts film covering type frigo.
Step of the present invention (3) in, there is weak substratum in soft soil roadbed or the Soft Soil Layer degree of depth is different, rectilinear frigo be placed in the Soft Soil Layer of weak substratum or certain depth; When soft soil roadbed middle Soft Soil Layer distribution is relatively more even, frigo is settled in design; When soft soil roadbed on road distributed areas more scattered, then frigo is according to the Position Design riding position coordinate point of distributed areas.
Step of the present invention (2) in, rectilinear frigo is the freezing pipe of taper by bottom and freezes loop and form, and the diameter of freezing pipe is 80cm.
The invention has the beneficial effects as follows: this consolidation by freezing method utilizes artificial cooling equipment and frigo, only low temperature refrigerant need be sent into stratum, in the short time, namely the soft soil roadbed frozen soils structure being frozen into some strength, the requirement of road can be met.
Compared with the method for traditional consolidated subsoil, consolidation by freezing method construction of the present invention is simple, the construction equipment needed is few, occupied ground is little, speed of application is fast, can also according to different terrain need adopt rectilinear frigo or film covering type frigo to carry out quick freezing reinforcing to soft soil roadbed, consolidation effect is good, practical.
Accompanying drawing explanation
Fig. 1 is the structural representation of rectilinear frigo;
Fig. 2 is that the difference of Fig. 1 freezes figure;
Fig. 3 is bulk freezing figure of the present invention;
Fig. 4 is that burst of the present invention freezes figure.
In figure: 1, road surface, 2, frozen region, 3, heat insulation layer, 4, rectilinear frigo.
Wherein, Fig. 3 is the bulk freezing figure of rectilinear frigo when freezing pipe is isometric of Fig. 1,
Fig. 4 is that the burst of rectilinear frigo when freezing pipe is isometric of Fig. 1 freezes figure; .
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described.
The frigo adopted in the present invention, can be rectilinear frigo 4 or film covering type frigo, its refrigerant can be liquid nitrogen or hypothermic saline, but is not limited to this type of refrigerant.
Rectilinear frigo 4 is that the freezing pipe of taper forms with the loop of freezing being connected freezing pipe by bottom.It adopts high strength seamless steel pipe or composite material to make, and uses static(al) plunging to be pressed in soil layer to meet in soft soil layer.As
Shown in Fig. 1, Fig. 2, this rectilinear frigo 4 freezes along the degree of depth at the direction of inserting and place, is specially adapted to need to freeze deep mixed roadbed; For preventing heat losses, one layer of heat preservation isolation layer 3 need be laid on its soil layer surface.In this rectilinear frigo, freezing pipe diameter is 80cm, and when laying, it is evenly arranged with the interval of 50cm.
Film covering type frigo forms by with the tabular or membranaceous slice structure of freezing loop and heat-barrier material, freezes loop and is made up of seamless steel pipe and is placed in below heat-barrier material, lay the plate of rigidity or the film of flexibility above heat-barrier material.Straight during use
Be connected on soil layer and lay, by the assembling between slice structure, can be deployed in rapidly in working face and it is frozen
Knot construction.As shown in Figure 3, Figure 4, this film covering type frigo evenly freezes along face, isolation layer place, is applicable to vertical or inclination roadbed; The every block length 5m of this film covering type frigo, end is interconnected in a flexible manner.
The soft soil roadbed consolidation by freezing method of one of the present invention, it comprises the following steps:
(1) soft soil roadbed character and the roadbed situation of construction is intended in test;
(2) the soft soil roadbed character recorded according to step 1 and roadbed situation, determine road surface freezing method and select frigo;
I) be divided into three kinds of situations according to the soft soil roadbed character of plan construction: as shown in Figure 2, the first situation is soft soil roadbed
In to there is weak substratum or the Soft Soil Layer degree of depth different, adopt difference freezing method, for this roadbed freeze can only pass through
The method of the rectilinear frigo 4 of vertical insertion realizes; As shown in Figure 3, the second situation is soft soil roadbed middle Soft Soil Layer distribution
Relatively more even, adopt the mode of bulk freezing, this freezes by vertically inserting rectilinear frigo or directly laying film covering type
The method of frigo realizes; As shown in Figure 4, the third situation be soft soil roadbed on road distributed areas more scattered, adopt
By the mode that burst freezes, the mode namely by reinforcing separately reaches the object of soft soil roadbed integral reinforcing, to save
Cost and time, this kind of frozen form is by the vertical method inserted rectilinear frigo or directly lay film covering type frigo
Realize,
II) be divided into two classes according to the soft soil roadbed situation intending construction: a class is horizontal roadbed, and frigo adopts rectilinear frigo or film covering type frigo; One class is roadbed that is vertical or that tilt, and from easy construction and safety, frigo adopts and covers
Membrane type frigo, selects frigo, three kinds of soft soil roadbed for plan construction situations need be combined with soft soil roadbed type and consider,
(3) determine quantity and the riding position of frigo, lay frigo;
The first situation be soft soil roadbed in there is weak substratum or the Soft Soil Layer degree of depth different, rectilinear frigo 4 is placed in the Soft Soil Layer of weak substratum or certain depth; The second situation is that soft soil roadbed middle Soft Soil Layer distribution is relatively more even, and frigo is settled in design; The third situation be soft soil roadbed on road distributed areas more scattered, then frigo is according to the Position Design riding position point of distributed areas; When adopting rectilinear frigo 4, be evenly arranged with 50cm interval; When adopting film covering type frigo, every 5m is put
Put one;
(4) install external equipment to frigo in step (3), this external equipment provides energy to frigo, and wherein refrigerant is
The frigo external equipment of liquid nitrogen is primarily of storage nitrogen groove, liquid nitrogen tank car and distributor composition, and refrigerant is the frigo of hypothermic saline
External equipment is Freezing Station, and Freezing Station forms primarily of compressor, condenser, evaporimeter, brine pump and choke valve;
(5) manual pipe jacking is implemented, make quick freezing in its 3 days, roadbed solidification point reaches-20 DEG C, and freeze the supporting capacity that roadbed has 100kN, vehicle within allowing 80 tons passes through, freezer unit provides energy with liquid nitrogen, hypothermic saline or other refrigerants to construction stratum, makes soft soil roadbed freezing, realizes soft soil roadbed reinforcing; For step (2) according to rectilinear frigo 4, the heat insulation layer 3 that need lay, it also has the ability that carrying 80 tons of vehicles pass through.

Claims (3)

1. a soft soil roadbed consolidation by freezing method, is characterized in that, described consolidation by freezing method comprises the following steps:
1. soft soil roadbed character and the roadbed situation of construction is intended in test;
2. the soft soil roadbed character 1. recorded according to step and roadbed situation, determine roadbed freezing method and select frigo, freezing method is divided into difference freezing method, bulk freezing mode and burst freezing method, and frigo is rectilinear frigo (4) or film covering type frigo; In soft soil roadbed, there is weak substratum or Soft Soil Layer degree of depth difference, adopt difference freezing method, frigo adopts rectilinear frigo (4); When soft soil roadbed middle Soft Soil Layer distribution is more even, adopt bulk freezing mode, a) soft soil roadbed is horizontal roadbed, and frigo adopts rectilinear frigo or film covering type frigo, b) soft soil roadbed is roadbed that is vertical or that tilt, and frigo adopts film covering type frigo; When soft soil roadbed on road distributed areas more scattered, adopt burst freezing method, a) soft soil roadbed is horizontal roadbed, and frigo adopts rectilinear frigo or film covering type frigo, b) soft soil roadbed is roadbed that is vertical or that tilt, and frigo adopts film covering type frigo; Wherein film covering type frigo forms by with the tabular or membranaceous slice structure of freezing loop and heat-barrier material, freezes loop and is made up of seamless steel pipe and is placed in below heat-barrier material, lay the plate of rigidity or the film of flexibility above heat-barrier material; Rectilinear frigo (4) need in road surfacing heat insulation layer (3);
3. determine quantity and the riding position of frigo, lay frigo;
4. install external equipment to frigo, wherein refrigerant is that the frigo external equipment of liquid nitrogen is primarily of storage nitrogen groove, liquid nitrogen tank car and distributor composition; Refrigerant is the frigo external equipment of hypothermic saline is Freezing Station, and Freezing Station forms primarily of compressor, condenser, evaporimeter, brine pump and choke valve;
5. pass into refrigerant to implement to freeze, make roadbed quick freezing in three days, roadbed solidification point reaches-20 DEG C.
2. the soft soil roadbed consolidation by freezing method of one according to claim 1, it is characterized in that, described step 3. in, there is weak substratum in soft soil roadbed or the Soft Soil Layer degree of depth is different, rectilinear frigo (4) be placed in the Soft Soil Layer of weak substratum or certain depth; When soft soil roadbed middle Soft Soil Layer distribution is relatively more even, frigo is settled in design; When soft soil roadbed on road distributed areas more scattered, then frigo is according to the Position Design riding position point of distributed areas, install frigo.
3. the soft soil roadbed consolidation by freezing method of one according to claim 1, is characterized in that, described step 2. in, described rectilinear frigo is the freezing pipe of taper by bottom and freezes loop and form, and the diameter of described freezing pipe is 80cm.
CN201310213762.5A 2013-05-31 2013-05-31 A kind of soft soil roadbed consolidation by freezing method Active CN103276720B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310213762.5A CN103276720B (en) 2013-05-31 2013-05-31 A kind of soft soil roadbed consolidation by freezing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310213762.5A CN103276720B (en) 2013-05-31 2013-05-31 A kind of soft soil roadbed consolidation by freezing method

Publications (2)

Publication Number Publication Date
CN103276720A CN103276720A (en) 2013-09-04
CN103276720B true CN103276720B (en) 2015-12-02

Family

ID=49059326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310213762.5A Active CN103276720B (en) 2013-05-31 2013-05-31 A kind of soft soil roadbed consolidation by freezing method

Country Status (1)

Country Link
CN (1) CN103276720B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111472343A (en) * 2020-03-19 2020-07-31 中国矿业大学 Bidirectional reinforced freezing device and working method

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103850244B (en) * 2014-03-04 2016-01-13 中交四航工程研究院有限公司 Bagged sand bed course deep level of processing soft soil foundation reinforcing method under a kind of refrigerated environment
CN104532826A (en) * 2014-07-07 2015-04-22 中国科学院寒区旱区环境与工程研究所 Refrigeration structure of power transmission tower foundation in permafrost region
CN104594149B (en) * 2014-12-03 2017-01-11 中国科学院青海盐湖研究所 Frozen soil layer road structure and construction method thereof
CN105239557B (en) * 2015-08-30 2017-04-12 中国科学院武汉岩土力学研究所 Device and method for accelerating consolidation of soft soil through combination of frost heaving and melting shrinking method and vacuum preloading
CN105421334A (en) * 2015-11-10 2016-03-23 上海市机械施工集团有限公司 Construction method for soil freezing
DE102016012843A1 (en) * 2016-10-27 2018-05-03 Linde Aktiengesellschaft Combined freezer head for nitrogen brine icing
CN112663468A (en) * 2020-12-11 2021-04-16 郑州铁路职业技术学院 Non-excavation repairing method for frozen soil roadbed

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1534142A (en) * 2003-04-01 2004-10-06 中国矿业大学 Underground continuous wall frozen construction method
CN101881024A (en) * 2010-06-28 2010-11-10 连云港港口工程设计研究院有限公司 Freeze thawing consolidation method for silt soft foundation
CN102912788A (en) * 2012-11-15 2013-02-06 陈绍文 Method for constructing emergency passages rapidly on soft soil foundations

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3228728B2 (en) * 1999-06-18 2001-11-12 錦城護謨株式会社 Ground improvement method by board drain using freeze-thaw

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1534142A (en) * 2003-04-01 2004-10-06 中国矿业大学 Underground continuous wall frozen construction method
CN101881024A (en) * 2010-06-28 2010-11-10 连云港港口工程设计研究院有限公司 Freeze thawing consolidation method for silt soft foundation
CN102912788A (en) * 2012-11-15 2013-02-06 陈绍文 Method for constructing emergency passages rapidly on soft soil foundations

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
人工冻土强制解冻基本理论和技术研究;邱凡;《中国优秀硕士学位论文全文数据库.工程科技Ⅱ辑》;20070615(第6期);第16-21页 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111472343A (en) * 2020-03-19 2020-07-31 中国矿业大学 Bidirectional reinforced freezing device and working method
CN111472343B (en) * 2020-03-19 2021-07-09 中国矿业大学 Bidirectional reinforced freezing device and working method

Also Published As

Publication number Publication date
CN103276720A (en) 2013-09-04

Similar Documents

Publication Publication Date Title
CN103276720B (en) A kind of soft soil roadbed consolidation by freezing method
SHENG et al. A potential new frost heave mechanism in high-speed railway embankments
CN104695964B (en) Subway shield tunnel freeze entering method
CN105804761B (en) Construction method suitable for liquefied sand stratum shield near-distance passing through building
CN206784453U (en) The concrete foundation anti-freeze expansion structure of Frozen Ground Area
CN110080202B (en) Horizontal freezing reinforcement structure for foundation pit bottom and construction method
CN105239585A (en) In-pile freezing structure of deep underground space and constructing method
CN104675408A (en) Liquid nitrogen freezing system of high water pressure super-long-distance large-sectional tunnel and method of quickly changing shield tail brushes
CN103541762B (en) A kind of High aititude severe cold rich water tunnel faces the antifreeze water discharge method of combination forever
CN104806253A (en) Construction method for opening hole between rectangular pipe jacking channels
CN103061230B (en) Construction method of technology utilizing ground source heat pump to cool and melt frozen road surfaces and drain boards for construction
CN105239606A (en) Inter-pile freezing structure of deep underground space and constructing method
Han et al. Use of geosynthetics for performance enhancement of earth structures in cold regions
CN101892620A (en) High intensity freezing damage prevention waterproof cushion layer
CN105421178A (en) Heating-layer pavement for cold region and construction technology thereof
CN101418565A (en) Qinghai-tibet railway permafrost wetland ground treatment technique
CN103836258B (en) Permafrost region buried pipeline thaw collapse prevention and controls that hot pin combines with coarse-grained soil and device
CN110055980A (en) A kind of thermoelectric cooling friction pile and construction method
CN109339075A (en) Landslide emergency control technology management method
CN105908587B (en) A kind of Frozen Ground Area roadbed heat insulating construction method
CN109268068A (en) Frozen Ground Area constructing metro tunnel causes the prediction technique of surface settlement control value
CN205557533U (en) Freeze structure in deep underground space's stake
CN109537630B (en) Reinforcing method for synergistic effect of steel pipe shed and frozen soil
CN112031008A (en) Controllable reinforced concrete strong freezing pile continuous wall and construction method thereof
CN104594149B (en) Frozen soil layer road structure and construction method thereof

Legal Events

Date Code Title Description