CN1293290A - Technology for forming pile by under-reaming and grouting - Google Patents

Technology for forming pile by under-reaming and grouting Download PDF

Info

Publication number
CN1293290A
CN1293290A CN 00132892 CN00132892A CN1293290A CN 1293290 A CN1293290 A CN 1293290A CN 00132892 CN00132892 CN 00132892 CN 00132892 A CN00132892 A CN 00132892A CN 1293290 A CN1293290 A CN 1293290A
Authority
CN
China
Prior art keywords
pile
grouting
technology
reaming
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 00132892
Other languages
Chinese (zh)
Other versions
CN1148494C (en
Inventor
李珠
黄鹤
梁仁旺
白晓红
Original Assignee
李珠
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 李珠 filed Critical 李珠
Priority to CNB001328921A priority Critical patent/CN1148494C/en
Publication of CN1293290A publication Critical patent/CN1293290A/en
Application granted granted Critical
Publication of CN1148494C publication Critical patent/CN1148494C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

A technology for forming expanded bottom and post-grouted pile includes under-reaming, forming pile hole and grouting. Its advantages include high quality of pile body, high load bearing capacity in creased by 100% and short construction period reduced by 50% as compared with ordinary R.C. cast pile, and bearing capacity increased by 15% and saving raw material by 10% as compared with post-grouted pile with squeezed expanded bearing discs.

Description

The process of forming pile by under-reaming and grouting
The present invention relates to the construction field of building foundation, be specially a kind of process of forming pile by under-reaming and grouting.
The deposited reinforced concrete pile that adopts in the geotechnical engineering field at present mainly contains three kinds of ordinary reinforced concrete castinplace piles, grouting behind shaft or drift lining deposited reinforced concrete pile, extruding-enlarging branch tray deposited reinforced concrete pile.The two kinds of castinplace piles in back are new concrete castinplace piles of releasing in the recent period, the problem that post grouting pile exists grouting amount to be difficult to determine, the bad bearing capacity that not only can not reduce construction costs but also can not effectively improve stake of grouting amount control; The transfer law of compacted bearing disk pile power is indeterminate, and whether compacted bearing disk pile has permanent, stable bearing capacity does not have experimental data and theory analysis to prove at present, and this is disadvantageous to promoting the use of of compacted bearing disk pile.Post grouting pile and compacted bearing disk pile still require than higher the mud thickness in stake week and the control of pile bottom sediment amount, and this is to shortening the construction period and guaranteeing that the quality of stake is disadvantageous.
Purpose of the present invention is the defective that overcomes the existing concrete castinplace pile, and a kind of pile-formation process method--process of forming pile by under-reaming and grouting of new castinplace pile is provided.
The present invention adopts following measure to realize: the process of this expansion bottom post-grouting pile comprises the moulding and the grouting behind shaft or drift lining bored pile piling technology method two parts in bottom-enlarging filling pile stake hole.The stake hole of extruding-enlarging branch tray deposited reinforced concrete pile of the prior art vertically is provided with a plurality of dishes, be used to improve its bearing capacity, but because there is above-mentioned deficiency in it, the present invention has only kept a dish at the bottom of stake, form the bottom-enlarging filling pile hole, and the process of grouting behind shaft or drift lining bored pile piling is above-mentioned maturation process method, therefore, content of the present invention comes down to the improvement of extruding-enlarging branch tray bored pile piling technology and combining of grouting behind shaft or drift lining bored pile piling technology, it has utilized post grouting pile technology to improve the pile peripheral friction force of castinplace pile simultaneously, eliminating pile bottom sediment and compacted bearing disk pile technology increases the advantage of bearing capacity of pile tip, overcome the defective and the deficiency of post grouting pile technology and compacted bearing disk pile technology, this combination has produced outstanding, significant effect.Because grouting behind shaft or drift lining bored pile piling technology method is existing maturation process, the present invention does not do concrete description to it in claims.
Expansion bottom post-grouting stake power transport mechanism of the present invention is clear and definite, pile quality is good, can increase substantially deposited reinforced concrete pile bearing capacity, reduce construction costs, shorten construction period of pile foundation engineering, compare with the ordinary reinforced concrete castinplace pile and can improve bearing capacity 100%, save raw material 50%, shorten the construction period 50%, compare with compacted bearing disk pile with post grouting pile and can improve bearing capacity 15%, save raw material 10%, remarkably productive, obvious.Other can form on the ground in a hole applicable to general cohesive soil, silt, sandy soil, gravelly sand, cobble, strong-weathered rock etc. in this expansion bottom post-grouting stake.
Accompanying drawing is the structural representation of the concrete enforcement of process of the present invention;
The present invention is specifically described as follows below in conjunction with accompanying drawing: the pile-formation process method of this expansion bottom post-grouting stake comprises the moulding and the grouting behind shaft or drift lining bored pile piling technology in bottom-enlarging filling pile stake hole, during concrete enforcement, utilize special equipment to get bottom-enlarging filling pile stake hole 1, carry out grouting behind shaft or drift lining perfusion pile-formation process then, this technology comprises the steps: to be lowered to reinforcing cage in the stake hole, the reinforcing cage middle part is around slip casting flexible pipe 4 porose on it, be connected with middle part slip casting flexible pipe 2 with the slip casting all flex tee, be arranged vertically the bottom slip casting steel pipe 3 that the end has one way valve 6 hole week along stake, be provided with the high pressure valve 7 of avoiding slip casting to reflux in the upper end of Grouting Pipe; To stake hole concrete perfusion, when treating that concrete strength reaches 70% left and right sides of design strength, be pressed into cement paste by bottom and middle part Grouting Pipe respectively, eliminate pile bottom sediment and all inherent shortcomings of stake by the modes such as expansion, compacted and splitting densification of oozing of slurries, improve stake pedosphere face, make the soil body in the Zhou Yiding scope obtain reinforcing, soil strength increases, increase pile side resistance, improve the bearing capacity of stake end.

Claims (1)

1, a kind of process of forming pile by under-reaming and grouting is characterized by: this process comprises the moulding and the grouting behind shaft or drift lining bored pile piling technology two parts in bottom-enlarging filling pile stake hole.
CNB001328921A 2000-11-10 2000-11-10 Technology for forming pile by under-reaming and grouting Expired - Fee Related CN1148494C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB001328921A CN1148494C (en) 2000-11-10 2000-11-10 Technology for forming pile by under-reaming and grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB001328921A CN1148494C (en) 2000-11-10 2000-11-10 Technology for forming pile by under-reaming and grouting

Publications (2)

Publication Number Publication Date
CN1293290A true CN1293290A (en) 2001-05-02
CN1148494C CN1148494C (en) 2004-05-05

Family

ID=4595457

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB001328921A Expired - Fee Related CN1148494C (en) 2000-11-10 2000-11-10 Technology for forming pile by under-reaming and grouting

Country Status (1)

Country Link
CN (1) CN1148494C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793027A (en) * 2010-04-02 2010-08-04 孔超 Core-grouted static pressure anchor rod pile
CN102162247A (en) * 2010-02-21 2011-08-24 韩顺和 Construction method of branch cast-in-place pile
CN104074184A (en) * 2014-05-07 2014-10-01 孔超 Pile base post-grouted expanded-base bored pile
CN104805834A (en) * 2015-04-29 2015-07-29 上海市机械施工集团有限公司 Cast-in-place and precast integrated pile (ICP pile) and manufacturing method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162247A (en) * 2010-02-21 2011-08-24 韩顺和 Construction method of branch cast-in-place pile
CN102162247B (en) * 2010-02-21 2013-02-27 韩顺和 Construction method of branch cast-in-place pile
CN101793027A (en) * 2010-04-02 2010-08-04 孔超 Core-grouted static pressure anchor rod pile
CN101793027B (en) * 2010-04-02 2015-02-25 孔超 Core-grouted static pressure anchor rod pile
CN104074184A (en) * 2014-05-07 2014-10-01 孔超 Pile base post-grouted expanded-base bored pile
CN104074184B (en) * 2014-05-07 2017-01-25 孔超 Pile base post-grouted expanded-base bored pile
CN104805834A (en) * 2015-04-29 2015-07-29 上海市机械施工集团有限公司 Cast-in-place and precast integrated pile (ICP pile) and manufacturing method thereof

Also Published As

Publication number Publication date
CN1148494C (en) 2004-05-05

Similar Documents

Publication Publication Date Title
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN105625294A (en) Composite foundation and construction method thereof
CN107012861B (en) A kind of discrete material core expansive concrete stake and its construction method
CN104234034B (en) After a kind of first draining, plugging plate holds the construction method of formula embankment
CN204000851U (en) The stake of a kind of outsourcing water permeability concrete reinforced pipe gravel slip-casting
CN103195060B (en) Soft soil foundation prestressing bolt anchorage structure and uses thereof
CN201770942U (en) Support for soft soil foundation cast-in-place concrete continuous beam bridge
CN1148494C (en) Technology for forming pile by under-reaming and grouting
CN110820772A (en) Bulk accumulation body side slope slide-resistant pile and structured cementing combined reinforcing method and construction process
CN106087976A (en) A kind of prefabricated friction pile of new concrete and pile sinking process
CN104746512A (en) Reinforced cement soil composite pile and method for forming the pile
CN212772306U (en) Device for improving vertical compression-resistant bearing capacity of steel pipe anchor rod static pressure pile
CN104480947A (en) Construction method of prestress cast-in-place pile and soil cement pile engagement support
CN105421446B (en) A kind of construction method of composite soil extruding solidification prefabricated pile for treatment of soft foundation
CN212656252U (en) Novel transmission line tower foundation
CN204530685U (en) A kind of cement-soil stiff composite pile
CN202124857U (en) Splitting pile
CN104594331B (en) A kind of method that highway high roadbed culvert foundation is reinforced
CN207959201U (en) Synchronous grouting pile for prestressed pipe
CN106939596A (en) A kind of cast-in-place slub type slurry drilled pile
CN203174586U (en) Concrete pipe pile for reinforcing railway soft soil foundation
CN205857160U (en) A kind of prefabricated friction pile of new concrete
CN101892665A (en) Construction method for grouting and vibro-replacement stone pile composite foundation
CN220202700U (en) Integrated device for uniform settlement of foundation edge facing platform
CN214993782U (en) Bored concrete pile structure with sleeve device

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20040505

Termination date: 20141110

EXPY Termination of patent right or utility model