CN104594331B - A kind of method that highway high roadbed culvert foundation is reinforced - Google Patents

A kind of method that highway high roadbed culvert foundation is reinforced Download PDF

Info

Publication number
CN104594331B
CN104594331B CN201510049597.3A CN201510049597A CN104594331B CN 104594331 B CN104594331 B CN 104594331B CN 201510049597 A CN201510049597 A CN 201510049597A CN 104594331 B CN104594331 B CN 104594331B
Authority
CN
China
Prior art keywords
foundation
rubble
groove
culvert
high roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510049597.3A
Other languages
Chinese (zh)
Other versions
CN104594331A (en
Inventor
马强
肖衡林
李丽华
刘永莉
史宏才
朱健
邢文文
胡兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201510049597.3A priority Critical patent/CN104594331B/en
Publication of CN104594331A publication Critical patent/CN104594331A/en
Application granted granted Critical
Publication of CN104594331B publication Critical patent/CN104594331B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry

Abstract

A kind of highway high roadbed culvert foundation reinforcement means, comprises the following steps: (1) by excavator along being parallel to culvert axis direction digging up and filling in groove;(2) in backfill groove, backfill rubble, and at rubble space grout injection, slip casting and rubble collectively form stabilization zone, are used for undertaking upper load together with foundation soil;(3), after perfusion completes 69 days, use static load test inspection consolidation effect, after power to be lifted meets design requirement, carry out top structures construction and embankment.The present invention uses excavator along culvert axis direction milling slot, and backfills rubble grout injection and forms stabilization zone, stabilization zone and both sides foundation soil shared upper load, forms a kind of novel two-way enhancement type composite foundation.Adjusting foundation stiffness by being adjusted between groove depth and groove spacing, comparing compared with similar techniques is the high roadbed culvert foundation reinforcement means that a kind of low cost, easily operation, applicability be wide, quality is easily guaranteed that.

Description

A kind of method that highway high roadbed culvert foundation is reinforced
Technical field
The present invention relates to technical field of building construction, a kind of highway high roadbed culvert foundation reinforcement means.
Background technology
The highway high roadbed culvert overlying depth of fill is usually more than 10 m, and have even can be more than 50 m.Owing to filled load is big, the ground of culvert bears bigger vertical load, and culvert foundation exists stress collection and neutralizes the problems such as excessive deformation, easily causes the disease of the differential settlement of culvert and excessive sedimentation etc..These diseases the most then cause culvert cracking, seepage or ponding, heavy then cause culvert structure to destroy, even occur collapsing, and have a strong impact on normally using of culvert and highway.
At present, the foundation stabilization measure to highway high roadbed culvert mainly fills out Sand-gravel-cushion Technioue to change.Change and fill out Sand-gravel-cushion Technioue and be that the supporting course under buildings or structures basis is weaker, when can not meet superstructure load to the requirement of ground, soft layer a range of under basis is cut out, then backfills intensity bigger sand, sandstone or dirt etc. the method being compacted the supporting course as ground.Although changing and filling out Sand-gravel-cushion Technioue to be to a certain degree to play improve foundation capability and reduce the effect of ground decrement, but it is not enough that it still suffers from the following aspects: (1) is changed and filled out Sand-gravel-cushion Technioue and process the degree of depth and be usually no more than 3m, is unsuitable for the process of deeper soft foundation;(2) change and fill out the compactness of Sand-gravel-cushion Technioue sandstone filler and be difficult to ensure;(3) large area changes back-up sand hardcore long construction period, and cost is high, big to environmental disruption.
Summary of the invention
It is an object of the invention to propose in order to avoid above-mentioned the deficiencies in the prior art a kind of low cost, high-reliability, be prone to adjust control, wide adaptability, highway high roadbed culvert foundation reinforcement means that Technical Economy is good.
One highway high roadbed culvert foundation reinforcement means of the present invention, it is adaptable to the high roadbed culvert foundation of Lack of support is reinforced, and comprises the following steps:
(1) by excavator along being parallel to culvert axis direction digging up and filling in groove;
(2) in backfill groove, backfill rubble, and at rubble space grout injection, slip casting and rubble collectively form stabilization zone, are used for undertaking upper load together with foundation soil;
(3), after perfusion completes 6-9 days, use static load test inspection consolidation effect, after power to be lifted meets design requirement, carry out top structures construction and embankment.
Described backfill groove excavation width is equal to the grab bucket width of excavator.
Described backfill groove cutting depth is determined by load test according to ground requirement for bearing capacity.
Spacing between described backfill groove, calculates according to the method calculating area replacement ratio in theory of composite foundation and determines.
A diameter of 20-50mm of described rubble, clay content is less than 10%.
Described cement mortar is plain-water slurry, and the ratio of mud is 0.4-0.45.
The invention has the beneficial effects as follows: the present invention uses excavator along culvert axis direction milling slot, and backfills rubble grout injection and forms stabilization zone, stabilization zone and both sides foundation soil shared upper load, forms a kind of novel two-way enhancement type composite foundation.Adjusting foundation stiffness by being adjusted between groove depth and groove spacing, comparing compared with similar techniques is the high roadbed culvert foundation reinforcement means that a kind of low cost, easily operation, applicability be wide, quality is easily guaranteed that.
Accompanying drawing explanation
Fig. 1 is the culvert structure schematic diagram after using the inventive method.
Figure marks: 1-culvert, 2-ground, 3-backfills groove, 4-rubble, 5-cement mortar, 6-stabilization zone.
Detailed description of the invention
The highway high roadbed culvert foundation reinforcement means of the present invention, it is applicable to the foundation stabilization of high roadbed culvert 1 during Lack of support, the method first passes through excavator on ground 2 along culvert axis direction digging up and filling in groove 3, after backfilling rubble 4 in backfill groove 3, grout injection 5 constitutes stabilization zone 6, make foundation soil 2 constitute a kind of novel composite foundation together with stabilization zone 6, reach the purpose of strengthening soft foundation.Adjust foundation stiffness by being adjusted between groove depth and groove spacing, be a kind of low cost, high-reliability, be prone to adjust control, wide adaptability, foundation reinforcement method that Technical Economy is good.
Specifically include following steps:
A: according to high roadbed culvert foundation requirement for bearing capacity, primarily determines that according to the method calculating area replacement ratio in theory of composite foundation the degree of depth and the spacing of required digging up and filling in groove, backfill Cao Zhong grouting and reinforcing district modulus are determined by laboratory test.
B: in ground, calculates the cutting depth and spacing determined according to previous step, uses excavator along culvert axis direction digging up and filling in groove, and backfill well width is equal in excavator grab bucket.
C: backfill crushed rock filler, simultaneously grout injection being stirred in backfill groove, makes rubble homogeneous condensation form stabilization zone.To be onstructed complete 7 days after, use static load test inspection consolidation effect, checking foundation bearing capacity whether meet requirement.
Below in conjunction with specific embodiment, wood invention is described in further detail:
Embodiment 1
Certain mountainous area highway high roadbed culvert foundation is: 0-0.8m is miscellaneous fill, and 0.8-3.4m is silty clay: yellowish-brown;3.4-5.8m cohesive soil, yellow, taupe gray, plastic~hard plastic.At on-the-spot test below ground 3.6m, foundation bearing capacity is 240kPa, and high roadbed culvert foundation design ultimate bearing capacity is 320kPa, and bearing capacity can not meet design requirement.
Engineered fill groove cutting depth is 4.0m, and area replacement ratio is 40%, and incorporation ballast grain sizes is 3-5cm, and the ratio of mud of grout injection is 0.42.
During construction, use the grooving on ground of hydraulic crawler backacter, become groove depth to be about 3.5m, after grooving completes, carry out the artificial clear end, after the clear end, completes, the rubble of backfill diameter 3-5cm, and use No. 325 Portland cement configuration cement mortars, the ratio of mud of cement mortar is 0.42, by grout pouring formation stabilization zone, gap between rubble, slip casting carries out field static load test after completing 7 days and determines reached bearing capacity.After bearing capacity meets design requirement, carry out top structures construction and embankment.
Embodiment 2
Certain highway high roadbed culvert foundation is: 0-3m silty clay: grey, taupe gray, viscosity is strong;3-7m cohesive soil, yellow, taupe gray, hard plastic.
Engineered fill groove cutting depth is 3.5m, and area replacement ratio is 50%, and incorporation ballast grain sizes is 4-5cm, and the ratio of mud of grout injection is 0.42.
During construction, use the grooving on ground of hydraulic crawler backacter, become groove depth to be about 3.5m, after grooving completes, carry out the artificial clear end, after the clear end, completes, the rubble of backfill diameter 4-5cm, and use No. 325 Portland cement configuration cement mortars, the ratio of mud of cement mortar is 0.42, by grout pouring formation stabilization zone, gap between rubble, slip casting carry out after completing 7 days field static load test determine bearing capacity meet design require after, carry out top structures construction and embankment.
Above-mentioned detailed description of the invention is the preferred embodiment of the present invention; it is not for limiting the enforcement of the present invention and right; all equivalence changes made according to the content described in the present patent application scope of patent protection and modification, in the range of all should being included in this reality patent application.

Claims (5)

1. a highway high roadbed culvert foundation reinforcement means, it is characterised in that comprise the following steps:
(1) by excavator along being parallel to culvert axis direction digging up and filling in groove;Between between described backfill groove Away from, calculate according to the method calculating area replacement ratio in theory of composite foundation and determine;
(2) in backfill groove, backfill rubble, and at rubble space grout injection, slip casting and the common structure of rubble Become stabilization zone, be used for undertaking upper load together with foundation soil;
(3) after perfusion completes 6-9 days, using static load test inspection consolidation effect, power to be lifted meets After design requires, carry out top structures construction and embankment.
2. highway high roadbed culvert foundation reinforcement means as claimed in claim 1, it is characterised in that: Described backfill groove excavation width is equal to the grab bucket width of excavator.
3. highway high roadbed culvert foundation reinforcement means as claimed in claim 1, it is characterised in that: Described backfill groove cutting depth is determined by load test according to ground requirement for bearing capacity.
4. highway high roadbed culvert foundation reinforcement means as claimed in claim 1, it is characterised in that: A diameter of 20-50mm of described rubble, clay content is less than 10%.
5. highway high roadbed culvert foundation reinforcement means as claimed in claim 1, it is characterised in that: Described cement mortar is plain-water slurry, and the ratio of mud is 0.4-0.45.
CN201510049597.3A 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced Active CN104594331B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510049597.3A CN104594331B (en) 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510049597.3A CN104594331B (en) 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced

Publications (2)

Publication Number Publication Date
CN104594331A CN104594331A (en) 2015-05-06
CN104594331B true CN104594331B (en) 2016-08-17

Family

ID=53120358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510049597.3A Active CN104594331B (en) 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced

Country Status (1)

Country Link
CN (1) CN104594331B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106703836A (en) * 2016-12-29 2017-05-24 中铁隧道勘测设计院有限公司 Treatment method of the bedding soft soil of existing circular shield tunnel
CN106836034B (en) * 2017-03-09 2023-04-28 山西省交通科学研究院 High-fill cover plate culvert flexible load shedding system and construction method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3749995B2 (en) * 1996-09-10 2006-03-01 前田工繊株式会社 Ground improvement method and ground improvement body
JP4982632B2 (en) * 2006-07-11 2012-07-25 独立行政法人港湾空港技術研究所 Liquefaction countermeasure method under breakwater
CN103469781B (en) * 2013-10-17 2016-06-08 中国建筑东北设计研究院有限公司 Wall column in conjunction with basement process at the complete application process in coastal soft clay area

Also Published As

Publication number Publication date
CN104594331A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN203174453U (en) Light-mass embankment structure for managing bump at bridge head
CN102296507B (en) Treatment method of subgrade cracks
CN101967794B (en) New technology for treating vehicle bump at bridge ends
CN107419630A (en) A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN103821060B (en) A kind of construction method of existing highway soft foundation Treating technology
CN103174074B (en) Sedimentation control structure of passable road highway roadbed and construction method
CN206902488U (en) A kind of soft soil foundation high-filled embankment of effectively control settlement after construction
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN105625294A (en) Composite foundation and construction method thereof
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN106592608A (en) Differential settlement control method for new foundation and old roadbed of utility tunnel
CN206070508U (en) Device for reinforcing foundation
CN110158367A (en) A kind of structure and deformation control method for helping the existing high-speed railway subgrade of width
CN103195060B (en) Soft soil foundation prestressing bolt anchorage structure and uses thereof
CN103046446A (en) Treatment structure at joint part of reconstruction and extension project of highway
CN107841908A (en) For eliminating the road structure of the high embankment lateral variation sedimentation in high-speed railway abrupt slope
CN206625096U (en) A kind of reinforced rubble frame structure subgrade strengthening system
CN104594331B (en) A kind of method that highway high roadbed culvert foundation is reinforced
CN212001226U (en) Backfill miscellaneous soil composite foundation structure
CN104612142B (en) Integral abutment bridge structure based on composite flexible piles and construction method thereof
Raju et al. Ground improvement: principles and applications in Asia
CN110963765B (en) Foam concrete and method for repairing pavement subsidence by adopting same
CN110284432B (en) Construction method for filling bridge abutment in high-fill area after first construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ma Qiang

Inventor after: Zhang Ke

Inventor after: Xiao Henglin

Inventor after: Li Lihua

Inventor after: Liu Yongli

Inventor after: Shi Hongcai

Inventor after: Zhu Jian

Inventor after: Xing Wenwen

Inventor after: Hu Xing

Inventor before: Ma Qiang

Inventor before: Xiao Henglin

Inventor before: Li Lihua

Inventor before: Liu Yongli

Inventor before: Shi Hongcai

Inventor before: Zhu Jian

Inventor before: Xing Wenwen

Inventor before: Hu Xing