CN104594331A - Method for reinforcing road high-stacked culvert foundation - Google Patents

Method for reinforcing road high-stacked culvert foundation Download PDF

Info

Publication number
CN104594331A
CN104594331A CN201510049597.3A CN201510049597A CN104594331A CN 104594331 A CN104594331 A CN 104594331A CN 201510049597 A CN201510049597 A CN 201510049597A CN 104594331 A CN104594331 A CN 104594331A
Authority
CN
China
Prior art keywords
foundation
culvert
backfill
grooves
fill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510049597.3A
Other languages
Chinese (zh)
Other versions
CN104594331B (en
Inventor
马强
肖衡林
李丽华
刘永莉
史宏才
朱健
邢文文
胡兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201510049597.3A priority Critical patent/CN104594331B/en
Publication of CN104594331A publication Critical patent/CN104594331A/en
Application granted granted Critical
Publication of CN104594331B publication Critical patent/CN104594331B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a method for reinforcing a road high-stacked culvert foundation. The method comprises the following steps: (1) excavating refilling grooves through an excavator along a direction parallel to the axial direction of a culvert; (2) refilling broken stones into the refilling grooves, and grouting cement paste into broken stone gaps, wherein the grouted cement paste and the broken stones are constructed into a reinforcing area for carrying upper load together with foundation soil; (3) checking the reinforcing effect by adopting a static load test after 6-9 days of the completion of grouting, and performing upper structure construction and roadbed filling after the design requirement is met by the carrying force. According to the method, the grooves are excavated with the excavator along the axial direction of the culvert, the reinforcing area is constructed by refilling the broken stones and grouting the cement paste, and the reinforcing area and foundation soil on both sides carry upper load together, thereby forming a novel bilaterally-reinforced composite foundation. The rigidity of the foundation is adjusted by adjusting the depths of the formed grooves and the distances among the formed grooves. Compared with the prior art, the method for reinforcing the road high-stacked culvert foundation is low in cost, is easy to operate, is wide in adaptability, and is easy for ensuring the quality.

Description

一种公路高填方涵洞地基加固的方法A method for foundation reinforcement of high-fill culverts in highways

技术领域 technical field

本发明涉及建筑施工技术领域,具体的说是一种公路高填方涵洞地基加固方法。 The invention relates to the technical field of building construction, in particular to a foundation reinforcement method for high-fill culverts in highways.

背景技术 Background technique

公路高填方涵洞上覆填土高度通常超过10 m,有的甚至会超过50 m。由于填土荷载大,涵洞的地基承受较大的竖向荷载,涵洞地基存在应力集中和过度变形等问题,容易引起涵洞的不均匀沉降和过大沉降等的病害。这些病害轻则引起涵洞开裂、渗漏或积水,重则致使涵洞结构破坏,甚至出现垮塌,严重影响涵洞和公路的正常使用。 High fill culverts on highways usually have a height of more than 10 m, and some even exceed 50 m. Due to the large filling load, the foundation of the culvert bears a large vertical load, and there are problems such as stress concentration and excessive deformation of the foundation of the culvert, which may easily cause diseases such as uneven settlement and excessive settlement of the culvert. These diseases can cause cracking, leakage or water accumulation in culverts, or cause damage to culvert structures, or even collapse, seriously affecting the normal use of culverts and roads.

目前,对公路高填方涵洞的地基加固措施主要以换填垫层法为主。换填垫层法是在建(构)筑物基础下的持力层比较软弱、不能满足上部结构荷载对地基的要求时,将基础下一定范围内的软弱土层挖去,然后回填强度较大的砂、砂石或灰土等并压实作为地基的持力层的方法。虽然换填垫层法能够在一定程度是起到提高地基承载能力和减小地基压缩量的作用,但其仍存在以下几个方面不足:(1)换填垫层法处理深度一般不超过3m,不适于较深软弱地基的处理;(2)换填垫层法砂石填料的压实度不易保证;(3)大面积换填砂石填料施工周期长,成本高,对环境破坏大。 At present, the foundation reinforcement measures for high-fill culverts in highways are mainly based on the replacement of cushions. The replacement cushion method is to excavate the weak soil layer within a certain range under the foundation when the bearing layer under the foundation of the building (structure) is relatively weak and cannot meet the requirements of the superstructure load on the foundation, and then backfill it with a lower strength. A method of compacting large sand, gravel or lime soil, etc., as the bearing layer of the foundation. Although the cushion replacement method can improve the bearing capacity of the foundation and reduce the compression of the foundation to a certain extent, it still has the following shortcomings: (1) The treatment depth of the cushion replacement method generally does not exceed 3m , It is not suitable for the treatment of deep and weak foundations; (2) It is not easy to ensure the compaction of sand and gravel fillers by replacing the cushion method; (3) The construction period of large-area replacement of sand and gravel fillers is long, the cost is high, and the damage to the environment is great.

发明内容 Contents of the invention

本发明的目的在于为了避免上述现有技术的不足而提出一种低成本、高可靠度、易于调整控制、适应性广、技术经济性好的公路高填方涵洞地基加固方法。 The object of the present invention is to propose a low-cost, high-reliability, easy-to-adjust control, wide adaptability, and good technical and economical highway high-fill culvert foundation reinforcement method in order to avoid the above-mentioned deficiencies in the prior art.

本发明一种公路高填方涵洞地基加固方法,适用于承载力不足的高填方涵洞地基加固,包括以下步骤: The invention discloses a method for reinforcing the foundation of a high-fill culvert for highways, which is suitable for the reinforcement of the foundation of a high-fill culvert with insufficient bearing capacity, and comprises the following steps:

⑴通过挖掘机沿平行于涵洞轴线方向开挖回填槽; ⑴Excavate the backfill groove along the direction parallel to the axis of the culvert through the excavator;

⑵向回填槽中回填碎石,并在碎石空隙灌注水泥浆,注浆和碎石共同构成加固区,与地基土一起用于承担上部荷载; (2) Backfill gravel into the backfill groove, and pour cement slurry into the gaps of the gravel. The grouting and gravel together constitute a reinforcement area, which together with the foundation soil is used to bear the upper load;

⑶待灌注完成6-9天后,采用静载荷试验检验加固效果,待承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 ⑶ 6-9 days after the pouring is completed, use the static load test to check the reinforcement effect, and after the bearing capacity meets the design requirements, carry out the superstructure construction and embankment filling.

所述回填槽开挖宽度等于挖掘机的抓斗宽度。 The excavation width of the backfill groove is equal to the width of the grab bucket of the excavator.

所述回填槽开挖深度根据地基承载力要求通过载荷试验确定。 The excavation depth of the backfill groove is determined through a load test according to the requirements of the bearing capacity of the foundation.

所述回填槽之间的间距,按照复合地基理论中计算面积置换率的方法进行计算和确定。 The distance between the backfill grooves is calculated and determined according to the method of calculating the area replacement rate in the composite foundation theory.

所述碎石的直径为20-50mm,含泥量小于10%。 The diameter of the crushed stone is 20-50mm, and the mud content is less than 10%.

所述水泥浆为素水泥浆,水灰比为0.4-0.45。 The cement slurry is plain cement slurry, and the water-cement ratio is 0.4-0.45.

本发明的有益效果是:本发明采用挖掘机沿涵洞轴线方向开挖成槽,并回填碎石灌注水泥浆形成加固区,加固区与两侧地基土共同承担上部荷载,形成一种新型的双向增强型复合地基。通过调整成槽深度和槽间间距调整地基刚度,同现有类似技术相比是一种低成本、易操作、适用性广、质量容易保证的高填方涵洞地基加固方法。 The beneficial effects of the present invention are: the present invention adopts the excavator to excavate the groove along the axis of the culvert, and backfills gravel and pours cement slurry to form a reinforcement area, and the reinforcement area and the foundation soil on both sides bear the upper load jointly, forming a new type of two-way Enhanced composite foundation. By adjusting the groove depth and groove spacing to adjust the foundation stiffness, compared with the existing similar technology, it is a low-cost, easy-to-operate, wide-applicability, and quality-guaranteed foundation reinforcement method for high fill culverts.

附图说明 Description of drawings

图1是采用本发明方法后的涵洞结构示意图。 Fig. 1 is the schematic diagram of the culvert structure after adopting the method of the present invention.

图中标记:1-涵洞,2-地基,3-回填槽,4-碎石,5-水泥浆,6-加固区。 Marks in the figure: 1-culvert, 2-foundation, 3-backfill tank, 4-gravel, 5-cement slurry, 6-reinforcement area.

具体实施方式 Detailed ways

本发明的公路高填方涵洞地基加固方法,适用于承载力不足时高填方涵洞1的地基加固,该方法首先通过挖掘机在地基2上沿涵洞轴线方向开挖回填槽3,在回填槽3中回填碎石4后灌注水泥浆5构成加固区6,使地基土2和加固区6一起构成一种新型的复合地基,达到加固软弱地基的目的。通过调整成槽深度和槽间间距调整地基刚度,是一种低成本、高可靠度、易于调整控制、适应性广、技术经济性好的地基加固方法。 The foundation reinforcement method for high-fill culverts in highways of the present invention is suitable for the foundation reinforcement of high-fill culverts 1 when the bearing capacity is insufficient. The method first excavates the backfill groove 3 on the foundation 2 along the axis of the culvert by an excavator. In step 3, backfill gravel 4 and pour cement slurry 5 to form reinforcement area 6, so that foundation soil 2 and reinforcement area 6 together form a new type of composite foundation to achieve the purpose of strengthening the weak foundation. Adjusting the foundation stiffness by adjusting the depth of grooves and the distance between grooves is a low-cost, high-reliability, easy-to-adjust control, wide adaptability, and good technical and economical foundation reinforcement method.

具体包括如下步骤: Specifically include the following steps:

A:依据高填方涵洞地基承载力要求,按照复合地基理论中计算面积置换率的方法初步确定所需开挖回填槽的深度和间距,回填槽中注浆加固区模量通过室内试验确定。 A: According to the requirements of the bearing capacity of the high-fill culvert foundation, the depth and spacing of the required excavation and backfilling grooves are preliminarily determined according to the method of calculating the area replacement rate in the composite foundation theory, and the modulus of the grouting reinforcement area in the backfilling grooves is determined through laboratory tests.

B:在地基中,按照上一步计算确定的开挖深度和间距,采用挖掘机沿着涵洞轴线方向开挖回填槽,回填槽宽度于挖掘机抓斗相等。 B: In the foundation, according to the excavation depth and spacing determined in the previous step, use the excavator to excavate the backfill groove along the axis of the culvert, and the width of the backfill groove is equal to that of the excavator grab.

C:在回填槽中回填碎石填料,同时灌注水泥浆并进行搅拌,使碎石均匀凝结形成加固区。待施工完成7天后,采用静载荷试验检验加固效果,验证地基承载力是否满足要求。 C: Backfill the gravel filler in the backfill tank, pour cement slurry and stir at the same time, so that the gravel can be uniformly coagulated to form a reinforcement area. Seven days after the construction is completed, the static load test is used to check the reinforcement effect and verify whether the bearing capacity of the foundation meets the requirements.

下面结合具体实施例对木发明作进一步详细说明: Wooden invention is described in further detail below in conjunction with specific embodiment:

实施例1 Example 1

某山区高速公路高填方涵洞地基为:0-0.8m为杂填土,0.8-3.4m为粉质黏土:黄褐色;3.4-5.8m黏性土,黄、褐灰色,可塑~硬塑。现场测试地面以下3.6m处地基承载力为240kPa,高填方涵洞地基承载力设计值为320kPa,承载力不能满足设计要求。 The foundation of a high-fill culvert on a highway in a mountainous area is: 0-0.8m is miscellaneous fill, 0.8-3.4m is silty clay: yellowish brown; 3.4-5.8m is clay, yellow, brown-gray, plastic to hard plastic. The bearing capacity of the foundation at 3.6m below the ground is 240kPa in field tests, and the design value of the foundation bearing capacity of the high fill culvert is 320kPa, which cannot meet the design requirements.

设计回填槽开挖深度为4.0m,面积置换率为40%,掺入碎石粒径为3-5cm,灌注水泥浆的水灰比为0.42。 The design excavation depth of the backfill tank is 4.0m, the area replacement rate is 40%, the particle size of the mixed gravel is 3-5cm, and the water-cement ratio of the cement slurry is 0.42.

施工时,采用液压履带式反铲挖掘机在地基上成槽,成槽深度约为3.5m,成槽完成后,进行人工清底,清底完成后,回填直径3-5cm的碎石,并采用325号普通硅酸盐水泥配置水泥浆,水泥浆的水灰比为0.42,将水泥浆灌注在碎石间的缝隙形成加固区,注浆完成7天后进行现场静载荷试验确定所达到的承载力。承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 During construction, a hydraulic crawler backhoe excavator is used to form grooves on the foundation, and the depth of the grooves is about 3.5m. After the grooves are completed, the bottom is cleaned manually. Ordinary Portland cement No. 325 is used to configure the cement slurry. The water-cement ratio of the cement slurry is 0.42. The cement slurry is poured into the gap between the crushed stones to form a reinforcement area. After the grouting is completed 7 days, the on-site static load test is carried out to determine the bearing capacity achieved. force. After the bearing capacity meets the design requirements, the superstructure construction and embankment filling will be carried out.

实施例2 Example 2

某高速公路高填方涵洞地基为:0-3m粉质黏土:灰、褐灰色,粘性强;3-7m黏性土,黄、褐灰色,硬塑。 The foundation of a high-fill culvert on an expressway is: 0-3m silty clay: gray, brown-gray, strong viscosity; 3-7m clay, yellow, brown-gray, hard plastic.

设计回填槽开挖深度为3.5m,面积置换率为50%,掺入碎石粒径为4-5cm,灌注水泥浆的水灰比为0.42。 The excavation depth of the backfill tank is designed to be 3.5m, the area replacement rate is 50%, the particle size of the mixed gravel is 4-5cm, and the water-cement ratio of the cement slurry is 0.42.

施工时,采用液压履带式反铲挖掘机在地基上成槽,成槽深度约为3.5m,成槽完成后,进行人工清底,清底完成后,回填直径4-5cm的碎石,并采用325号普通硅酸盐水泥配置水泥浆,水泥浆的水灰比为0.42,将水泥浆灌注在碎石间的缝隙形成加固区,注浆完成7天后进行现场静载荷试验确定承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 During construction, a hydraulic crawler-type backhoe excavator is used to form grooves on the foundation, and the depth of the grooves is about 3.5m. After the grooves are completed, the bottom is cleaned manually. Ordinary Portland cement No. 325 is used to configure the cement slurry. The water-cement ratio of the cement slurry is 0.42. The cement slurry is poured into the gaps between the crushed stones to form a reinforcement area. After the grouting is completed 7 days, the on-site static load test is carried out to confirm that the bearing capacity meets the design. Upon request, carry out superstructure construction and embankment filling.

上述具体实施方式只是本发明的优选实施方式,并不是用来限制本发明的实施与权利要求范围的,凡依据本发明申请专利保护范围所述的内容做出的等效变化和修饰,均应包括于本实发明申请范围内。 The above-mentioned specific embodiment is only the preferred embodiment of the present invention, and is not used to limit the implementation of the present invention and the scope of claims. All equivalent changes and modifications made according to the content described in the patent protection scope of the present invention application shall be Included in the application scope of the present invention.

Claims (6)

1.一种公路高填方涵洞地基加固方法,其特征在于包括以下步骤: 1. A high filling culvert foundation reinforcement method for highway, is characterized in that comprising the following steps: ⑴通过挖掘机沿平行于涵洞轴线方向开挖回填槽; ⑴Excavate the backfill groove along the direction parallel to the axis of the culvert through the excavator; ⑵向回填槽中回填碎石,并在碎石空隙灌注水泥浆,注浆和碎石共同构成加固区,与地基土一起用于承担上部荷载; (2) Backfill gravel into the backfill groove, and pour cement slurry into the gaps of the gravel. The grouting and gravel together constitute a reinforcement area, which together with the foundation soil is used to bear the upper load; ⑶待灌注完成6-9天后,采用静载荷试验检验加固效果,待承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 ⑶ 6-9 days after the pouring is completed, use the static load test to check the reinforcement effect, and after the bearing capacity meets the design requirements, carry out the superstructure construction and embankment filling. 2.如权利要求1所述的公路高填方涵洞地基加固方法,其特征在于:所述回填槽开挖宽度等于挖掘机的抓斗宽度。 2. The method for strengthening the foundation of high-fill culverts in highways according to claim 1, wherein the excavation width of the backfill groove is equal to the width of the grab bucket of the excavator. 3.如权利要求1所述的公路高填方涵洞地基加固方法,其特征在于:所述回填槽开挖深度根据地基承载力要求通过载荷试验确定。 3. The method for strengthening the foundation of high fill culverts in highways according to claim 1, characterized in that: the excavation depth of the backfill trench is determined through a load test according to the requirements of the bearing capacity of the foundation. 4.如权利要求1所述的公路高填方涵洞地基加固方法,其特征在于:所述回填槽之间的间距,按照复合地基理论中计算面积置换率的方法进行计算和确定。 4. The method for strengthening the foundation of high fill culverts in highways as claimed in claim 1, characterized in that: the distance between the backfill grooves is calculated and determined according to the method for calculating the area replacement rate in the composite foundation theory. 5.如权利要求1所述的公路高填方涵洞地基加固方法,其特征在于:所述碎石的直径为20-50mm,含泥量小于10%。 5. The method for strengthening the foundation of high-fill culverts in highways according to claim 1, wherein the crushed stones have a diameter of 20-50 mm and a mud content of less than 10%. 6.如权利要求1所述的公路高填方涵洞地基加固方法,其特征在于:所述水泥浆为素水泥浆,水灰比为0.4-0.45。 6. The method for strengthening the foundation of high-fill culverts in highways according to claim 1, wherein the cement slurry is plain cement slurry, and the water-cement ratio is 0.4-0.45.
CN201510049597.3A 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced Active CN104594331B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510049597.3A CN104594331B (en) 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510049597.3A CN104594331B (en) 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced

Publications (2)

Publication Number Publication Date
CN104594331A true CN104594331A (en) 2015-05-06
CN104594331B CN104594331B (en) 2016-08-17

Family

ID=53120358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510049597.3A Active CN104594331B (en) 2015-01-30 2015-01-30 A kind of method that highway high roadbed culvert foundation is reinforced

Country Status (1)

Country Link
CN (1) CN104594331B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106703836A (en) * 2016-12-29 2017-05-24 中铁隧道勘测设计院有限公司 Treatment method of the bedding soft soil of existing circular shield tunnel
CN106836034A (en) * 2017-03-09 2017-06-13 山西省交通科学研究院 A kind of high roadbed slab culvert flexibility off-load system and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088562A (en) * 1996-09-10 1998-04-07 Maeda Kousen Kk Soil improvement method and soil improvement unit
JP2008019562A (en) * 2006-07-11 2008-01-31 Port & Airport Research Institute Liquefaction countermeasure method under breakwater
CN103469781A (en) * 2013-10-17 2013-12-25 中国建筑东北设计研究院有限公司 Complete applying method of wall-column-combined ground treatment in coastal soft soil area

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088562A (en) * 1996-09-10 1998-04-07 Maeda Kousen Kk Soil improvement method and soil improvement unit
JP2008019562A (en) * 2006-07-11 2008-01-31 Port & Airport Research Institute Liquefaction countermeasure method under breakwater
CN103469781A (en) * 2013-10-17 2013-12-25 中国建筑东北设计研究院有限公司 Complete applying method of wall-column-combined ground treatment in coastal soft soil area

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106703836A (en) * 2016-12-29 2017-05-24 中铁隧道勘测设计院有限公司 Treatment method of the bedding soft soil of existing circular shield tunnel
CN106836034A (en) * 2017-03-09 2017-06-13 山西省交通科学研究院 A kind of high roadbed slab culvert flexibility off-load system and construction method

Also Published As

Publication number Publication date
CN104594331B (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN102277867B (en) A construction method of collapsible loess foundation
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN203174453U (en) Light-mass embankment structure for managing bump at bridge head
CN101967794B (en) New technology for treating vehicle bump at bridge ends
CN108560542B (en) A kind of bidirectional reinforcement of waste tire covering building slag and construction method thereof
CN107419630A (en) A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN103174074B (en) Sedimentation control structure of passable road highway roadbed and construction method
CN204849508U (en) Roadbed structure of soft soil foundation highway road bridge changeover portion
CN206902488U (en) A kind of soft soil foundation high-filled embankment of effectively control settlement after construction
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN106676993B (en) Reinforced broken stone frame structure roadbed reinforcing system and reinforcing method thereof
CN113216147B (en) Soft rock roadbed longitudinal crack disease treatment method
CN110158367A (en) A kind of structure and deformation control method for helping the existing high-speed railway subgrade of width
CN103452093A (en) Compound foundation formed by serial connection of water-permeable concrete pile and gravel pile and foundation treatment method
CN108412016A (en) Underground tube body assures construction method
CN106592608A (en) Differential settlement control method for new foundation and old roadbed of utility tunnel
CN111549598A (en) A kind of reinforced bridge head roadbed and construction method of expressway in collapsible loess area
CN204570720U (en) A kind of widening of subgrade culvert foundation
CN206625096U (en) A kind of reinforced rubble frame structure subgrade strengthening system
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN111519477A (en) An overhead pile-plate structure and a transition section structure of an embankment and its construction method
CN110485230A (en) A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig
CN104594331B (en) A kind of method that highway high roadbed culvert foundation is reinforced
CN114439017A (en) A backfill structure using a new type of backfill material and its construction method
CN106836034B (en) A flexible load-reducing system and construction method of high-fill cover slab culvert

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ma Qiang

Inventor after: Zhang Ke

Inventor after: Xiao Henglin

Inventor after: Li Lihua

Inventor after: Liu Yongli

Inventor after: Shi Hongcai

Inventor after: Zhu Jian

Inventor after: Xing Wenwen

Inventor after: Hu Xing

Inventor before: Ma Qiang

Inventor before: Xiao Henglin

Inventor before: Li Lihua

Inventor before: Liu Yongli

Inventor before: Shi Hongcai

Inventor before: Zhu Jian

Inventor before: Xing Wenwen

Inventor before: Hu Xing