CN104594331A - Method for reinforcing road high-stacked culvert foundation - Google Patents
Method for reinforcing road high-stacked culvert foundation Download PDFInfo
- Publication number
- CN104594331A CN104594331A CN201510049597.3A CN201510049597A CN104594331A CN 104594331 A CN104594331 A CN 104594331A CN 201510049597 A CN201510049597 A CN 201510049597A CN 104594331 A CN104594331 A CN 104594331A
- Authority
- CN
- China
- Prior art keywords
- foundation
- culvert
- backfill
- grooves
- fill
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/08—Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/0023—Slurry
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Soil Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
技术领域 technical field
本发明涉及建筑施工技术领域,具体的说是一种公路高填方涵洞地基加固方法。 The invention relates to the technical field of building construction, in particular to a foundation reinforcement method for high-fill culverts in highways.
背景技术 Background technique
公路高填方涵洞上覆填土高度通常超过10 m,有的甚至会超过50 m。由于填土荷载大,涵洞的地基承受较大的竖向荷载,涵洞地基存在应力集中和过度变形等问题,容易引起涵洞的不均匀沉降和过大沉降等的病害。这些病害轻则引起涵洞开裂、渗漏或积水,重则致使涵洞结构破坏,甚至出现垮塌,严重影响涵洞和公路的正常使用。 High fill culverts on highways usually have a height of more than 10 m, and some even exceed 50 m. Due to the large filling load, the foundation of the culvert bears a large vertical load, and there are problems such as stress concentration and excessive deformation of the foundation of the culvert, which may easily cause diseases such as uneven settlement and excessive settlement of the culvert. These diseases can cause cracking, leakage or water accumulation in culverts, or cause damage to culvert structures, or even collapse, seriously affecting the normal use of culverts and roads.
目前,对公路高填方涵洞的地基加固措施主要以换填垫层法为主。换填垫层法是在建(构)筑物基础下的持力层比较软弱、不能满足上部结构荷载对地基的要求时,将基础下一定范围内的软弱土层挖去,然后回填强度较大的砂、砂石或灰土等并压实作为地基的持力层的方法。虽然换填垫层法能够在一定程度是起到提高地基承载能力和减小地基压缩量的作用,但其仍存在以下几个方面不足:(1)换填垫层法处理深度一般不超过3m,不适于较深软弱地基的处理;(2)换填垫层法砂石填料的压实度不易保证;(3)大面积换填砂石填料施工周期长,成本高,对环境破坏大。 At present, the foundation reinforcement measures for high-fill culverts in highways are mainly based on the replacement of cushions. The replacement cushion method is to excavate the weak soil layer within a certain range under the foundation when the bearing layer under the foundation of the building (structure) is relatively weak and cannot meet the requirements of the superstructure load on the foundation, and then backfill it with a lower strength. A method of compacting large sand, gravel or lime soil, etc., as the bearing layer of the foundation. Although the cushion replacement method can improve the bearing capacity of the foundation and reduce the compression of the foundation to a certain extent, it still has the following shortcomings: (1) The treatment depth of the cushion replacement method generally does not exceed 3m , It is not suitable for the treatment of deep and weak foundations; (2) It is not easy to ensure the compaction of sand and gravel fillers by replacing the cushion method; (3) The construction period of large-area replacement of sand and gravel fillers is long, the cost is high, and the damage to the environment is great.
发明内容 Contents of the invention
本发明的目的在于为了避免上述现有技术的不足而提出一种低成本、高可靠度、易于调整控制、适应性广、技术经济性好的公路高填方涵洞地基加固方法。 The object of the present invention is to propose a low-cost, high-reliability, easy-to-adjust control, wide adaptability, and good technical and economical highway high-fill culvert foundation reinforcement method in order to avoid the above-mentioned deficiencies in the prior art.
本发明一种公路高填方涵洞地基加固方法,适用于承载力不足的高填方涵洞地基加固,包括以下步骤: The invention discloses a method for reinforcing the foundation of a high-fill culvert for highways, which is suitable for the reinforcement of the foundation of a high-fill culvert with insufficient bearing capacity, and comprises the following steps:
⑴通过挖掘机沿平行于涵洞轴线方向开挖回填槽; ⑴Excavate the backfill groove along the direction parallel to the axis of the culvert through the excavator;
⑵向回填槽中回填碎石,并在碎石空隙灌注水泥浆,注浆和碎石共同构成加固区,与地基土一起用于承担上部荷载; (2) Backfill gravel into the backfill groove, and pour cement slurry into the gaps of the gravel. The grouting and gravel together constitute a reinforcement area, which together with the foundation soil is used to bear the upper load;
⑶待灌注完成6-9天后,采用静载荷试验检验加固效果,待承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 ⑶ 6-9 days after the pouring is completed, use the static load test to check the reinforcement effect, and after the bearing capacity meets the design requirements, carry out the superstructure construction and embankment filling.
所述回填槽开挖宽度等于挖掘机的抓斗宽度。 The excavation width of the backfill groove is equal to the width of the grab bucket of the excavator.
所述回填槽开挖深度根据地基承载力要求通过载荷试验确定。 The excavation depth of the backfill groove is determined through a load test according to the requirements of the bearing capacity of the foundation.
所述回填槽之间的间距,按照复合地基理论中计算面积置换率的方法进行计算和确定。 The distance between the backfill grooves is calculated and determined according to the method of calculating the area replacement rate in the composite foundation theory.
所述碎石的直径为20-50mm,含泥量小于10%。 The diameter of the crushed stone is 20-50mm, and the mud content is less than 10%.
所述水泥浆为素水泥浆,水灰比为0.4-0.45。 The cement slurry is plain cement slurry, and the water-cement ratio is 0.4-0.45.
本发明的有益效果是:本发明采用挖掘机沿涵洞轴线方向开挖成槽,并回填碎石灌注水泥浆形成加固区,加固区与两侧地基土共同承担上部荷载,形成一种新型的双向增强型复合地基。通过调整成槽深度和槽间间距调整地基刚度,同现有类似技术相比是一种低成本、易操作、适用性广、质量容易保证的高填方涵洞地基加固方法。 The beneficial effects of the present invention are: the present invention adopts the excavator to excavate the groove along the axis of the culvert, and backfills gravel and pours cement slurry to form a reinforcement area, and the reinforcement area and the foundation soil on both sides bear the upper load jointly, forming a new type of two-way Enhanced composite foundation. By adjusting the groove depth and groove spacing to adjust the foundation stiffness, compared with the existing similar technology, it is a low-cost, easy-to-operate, wide-applicability, and quality-guaranteed foundation reinforcement method for high fill culverts.
附图说明 Description of drawings
图1是采用本发明方法后的涵洞结构示意图。 Fig. 1 is the schematic diagram of the culvert structure after adopting the method of the present invention.
图中标记:1-涵洞,2-地基,3-回填槽,4-碎石,5-水泥浆,6-加固区。 Marks in the figure: 1-culvert, 2-foundation, 3-backfill tank, 4-gravel, 5-cement slurry, 6-reinforcement area.
具体实施方式 Detailed ways
本发明的公路高填方涵洞地基加固方法,适用于承载力不足时高填方涵洞1的地基加固,该方法首先通过挖掘机在地基2上沿涵洞轴线方向开挖回填槽3,在回填槽3中回填碎石4后灌注水泥浆5构成加固区6,使地基土2和加固区6一起构成一种新型的复合地基,达到加固软弱地基的目的。通过调整成槽深度和槽间间距调整地基刚度,是一种低成本、高可靠度、易于调整控制、适应性广、技术经济性好的地基加固方法。 The foundation reinforcement method for high-fill culverts in highways of the present invention is suitable for the foundation reinforcement of high-fill culverts 1 when the bearing capacity is insufficient. The method first excavates the backfill groove 3 on the foundation 2 along the axis of the culvert by an excavator. In step 3, backfill gravel 4 and pour cement slurry 5 to form reinforcement area 6, so that foundation soil 2 and reinforcement area 6 together form a new type of composite foundation to achieve the purpose of strengthening the weak foundation. Adjusting the foundation stiffness by adjusting the depth of grooves and the distance between grooves is a low-cost, high-reliability, easy-to-adjust control, wide adaptability, and good technical and economical foundation reinforcement method.
具体包括如下步骤: Specifically include the following steps:
A:依据高填方涵洞地基承载力要求,按照复合地基理论中计算面积置换率的方法初步确定所需开挖回填槽的深度和间距,回填槽中注浆加固区模量通过室内试验确定。 A: According to the requirements of the bearing capacity of the high-fill culvert foundation, the depth and spacing of the required excavation and backfilling grooves are preliminarily determined according to the method of calculating the area replacement rate in the composite foundation theory, and the modulus of the grouting reinforcement area in the backfilling grooves is determined through laboratory tests.
B:在地基中,按照上一步计算确定的开挖深度和间距,采用挖掘机沿着涵洞轴线方向开挖回填槽,回填槽宽度于挖掘机抓斗相等。 B: In the foundation, according to the excavation depth and spacing determined in the previous step, use the excavator to excavate the backfill groove along the axis of the culvert, and the width of the backfill groove is equal to that of the excavator grab.
C:在回填槽中回填碎石填料,同时灌注水泥浆并进行搅拌,使碎石均匀凝结形成加固区。待施工完成7天后,采用静载荷试验检验加固效果,验证地基承载力是否满足要求。 C: Backfill the gravel filler in the backfill tank, pour cement slurry and stir at the same time, so that the gravel can be uniformly coagulated to form a reinforcement area. Seven days after the construction is completed, the static load test is used to check the reinforcement effect and verify whether the bearing capacity of the foundation meets the requirements.
下面结合具体实施例对木发明作进一步详细说明: Wooden invention is described in further detail below in conjunction with specific embodiment:
实施例1 Example 1
某山区高速公路高填方涵洞地基为:0-0.8m为杂填土,0.8-3.4m为粉质黏土:黄褐色;3.4-5.8m黏性土,黄、褐灰色,可塑~硬塑。现场测试地面以下3.6m处地基承载力为240kPa,高填方涵洞地基承载力设计值为320kPa,承载力不能满足设计要求。 The foundation of a high-fill culvert on a highway in a mountainous area is: 0-0.8m is miscellaneous fill, 0.8-3.4m is silty clay: yellowish brown; 3.4-5.8m is clay, yellow, brown-gray, plastic to hard plastic. The bearing capacity of the foundation at 3.6m below the ground is 240kPa in field tests, and the design value of the foundation bearing capacity of the high fill culvert is 320kPa, which cannot meet the design requirements.
设计回填槽开挖深度为4.0m,面积置换率为40%,掺入碎石粒径为3-5cm,灌注水泥浆的水灰比为0.42。 The design excavation depth of the backfill tank is 4.0m, the area replacement rate is 40%, the particle size of the mixed gravel is 3-5cm, and the water-cement ratio of the cement slurry is 0.42.
施工时,采用液压履带式反铲挖掘机在地基上成槽,成槽深度约为3.5m,成槽完成后,进行人工清底,清底完成后,回填直径3-5cm的碎石,并采用325号普通硅酸盐水泥配置水泥浆,水泥浆的水灰比为0.42,将水泥浆灌注在碎石间的缝隙形成加固区,注浆完成7天后进行现场静载荷试验确定所达到的承载力。承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 During construction, a hydraulic crawler backhoe excavator is used to form grooves on the foundation, and the depth of the grooves is about 3.5m. After the grooves are completed, the bottom is cleaned manually. Ordinary Portland cement No. 325 is used to configure the cement slurry. The water-cement ratio of the cement slurry is 0.42. The cement slurry is poured into the gap between the crushed stones to form a reinforcement area. After the grouting is completed 7 days, the on-site static load test is carried out to determine the bearing capacity achieved. force. After the bearing capacity meets the design requirements, the superstructure construction and embankment filling will be carried out.
实施例2 Example 2
某高速公路高填方涵洞地基为:0-3m粉质黏土:灰、褐灰色,粘性强;3-7m黏性土,黄、褐灰色,硬塑。 The foundation of a high-fill culvert on an expressway is: 0-3m silty clay: gray, brown-gray, strong viscosity; 3-7m clay, yellow, brown-gray, hard plastic.
设计回填槽开挖深度为3.5m,面积置换率为50%,掺入碎石粒径为4-5cm,灌注水泥浆的水灰比为0.42。 The excavation depth of the backfill tank is designed to be 3.5m, the area replacement rate is 50%, the particle size of the mixed gravel is 4-5cm, and the water-cement ratio of the cement slurry is 0.42.
施工时,采用液压履带式反铲挖掘机在地基上成槽,成槽深度约为3.5m,成槽完成后,进行人工清底,清底完成后,回填直径4-5cm的碎石,并采用325号普通硅酸盐水泥配置水泥浆,水泥浆的水灰比为0.42,将水泥浆灌注在碎石间的缝隙形成加固区,注浆完成7天后进行现场静载荷试验确定承载力满足设计要求后,进行上部构筑物施工和路堤填筑。 During construction, a hydraulic crawler-type backhoe excavator is used to form grooves on the foundation, and the depth of the grooves is about 3.5m. After the grooves are completed, the bottom is cleaned manually. Ordinary Portland cement No. 325 is used to configure the cement slurry. The water-cement ratio of the cement slurry is 0.42. The cement slurry is poured into the gaps between the crushed stones to form a reinforcement area. After the grouting is completed 7 days, the on-site static load test is carried out to confirm that the bearing capacity meets the design. Upon request, carry out superstructure construction and embankment filling.
上述具体实施方式只是本发明的优选实施方式,并不是用来限制本发明的实施与权利要求范围的,凡依据本发明申请专利保护范围所述的内容做出的等效变化和修饰,均应包括于本实发明申请范围内。 The above-mentioned specific embodiment is only the preferred embodiment of the present invention, and is not used to limit the implementation of the present invention and the scope of claims. All equivalent changes and modifications made according to the content described in the patent protection scope of the present invention application shall be Included in the application scope of the present invention.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510049597.3A CN104594331B (en) | 2015-01-30 | 2015-01-30 | A kind of method that highway high roadbed culvert foundation is reinforced |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510049597.3A CN104594331B (en) | 2015-01-30 | 2015-01-30 | A kind of method that highway high roadbed culvert foundation is reinforced |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104594331A true CN104594331A (en) | 2015-05-06 |
CN104594331B CN104594331B (en) | 2016-08-17 |
Family
ID=53120358
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510049597.3A Active CN104594331B (en) | 2015-01-30 | 2015-01-30 | A kind of method that highway high roadbed culvert foundation is reinforced |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104594331B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106703836A (en) * | 2016-12-29 | 2017-05-24 | 中铁隧道勘测设计院有限公司 | Treatment method of the bedding soft soil of existing circular shield tunnel |
CN106836034A (en) * | 2017-03-09 | 2017-06-13 | 山西省交通科学研究院 | A kind of high roadbed slab culvert flexibility off-load system and construction method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1088562A (en) * | 1996-09-10 | 1998-04-07 | Maeda Kousen Kk | Soil improvement method and soil improvement unit |
JP2008019562A (en) * | 2006-07-11 | 2008-01-31 | Port & Airport Research Institute | Liquefaction countermeasure method under breakwater |
CN103469781A (en) * | 2013-10-17 | 2013-12-25 | 中国建筑东北设计研究院有限公司 | Complete applying method of wall-column-combined ground treatment in coastal soft soil area |
-
2015
- 2015-01-30 CN CN201510049597.3A patent/CN104594331B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1088562A (en) * | 1996-09-10 | 1998-04-07 | Maeda Kousen Kk | Soil improvement method and soil improvement unit |
JP2008019562A (en) * | 2006-07-11 | 2008-01-31 | Port & Airport Research Institute | Liquefaction countermeasure method under breakwater |
CN103469781A (en) * | 2013-10-17 | 2013-12-25 | 中国建筑东北设计研究院有限公司 | Complete applying method of wall-column-combined ground treatment in coastal soft soil area |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106703836A (en) * | 2016-12-29 | 2017-05-24 | 中铁隧道勘测设计院有限公司 | Treatment method of the bedding soft soil of existing circular shield tunnel |
CN106836034A (en) * | 2017-03-09 | 2017-06-13 | 山西省交通科学研究院 | A kind of high roadbed slab culvert flexibility off-load system and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN104594331B (en) | 2016-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102277867B (en) | A construction method of collapsible loess foundation | |
CN204059124U (en) | A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure | |
CN203174453U (en) | Light-mass embankment structure for managing bump at bridge head | |
CN101967794B (en) | New technology for treating vehicle bump at bridge ends | |
CN108560542B (en) | A kind of bidirectional reinforcement of waste tire covering building slag and construction method thereof | |
CN107419630A (en) | A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction | |
CN103174074B (en) | Sedimentation control structure of passable road highway roadbed and construction method | |
CN204849508U (en) | Roadbed structure of soft soil foundation highway road bridge changeover portion | |
CN206902488U (en) | A kind of soft soil foundation high-filled embankment of effectively control settlement after construction | |
CN204401385U (en) | A kind of road structure processing Deep Thick Soft Ground karst foundation | |
CN106676993B (en) | Reinforced broken stone frame structure roadbed reinforcing system and reinforcing method thereof | |
CN113216147B (en) | Soft rock roadbed longitudinal crack disease treatment method | |
CN110158367A (en) | A kind of structure and deformation control method for helping the existing high-speed railway subgrade of width | |
CN103452093A (en) | Compound foundation formed by serial connection of water-permeable concrete pile and gravel pile and foundation treatment method | |
CN108412016A (en) | Underground tube body assures construction method | |
CN106592608A (en) | Differential settlement control method for new foundation and old roadbed of utility tunnel | |
CN111549598A (en) | A kind of reinforced bridge head roadbed and construction method of expressway in collapsible loess area | |
CN204570720U (en) | A kind of widening of subgrade culvert foundation | |
CN206625096U (en) | A kind of reinforced rubble frame structure subgrade strengthening system | |
CN203334154U (en) | Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct | |
CN111519477A (en) | An overhead pile-plate structure and a transition section structure of an embankment and its construction method | |
CN110485230A (en) | A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig | |
CN104594331B (en) | A kind of method that highway high roadbed culvert foundation is reinforced | |
CN114439017A (en) | A backfill structure using a new type of backfill material and its construction method | |
CN106836034B (en) | A flexible load-reducing system and construction method of high-fill cover slab culvert |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Ma Qiang Inventor after: Zhang Ke Inventor after: Xiao Henglin Inventor after: Li Lihua Inventor after: Liu Yongli Inventor after: Shi Hongcai Inventor after: Zhu Jian Inventor after: Xing Wenwen Inventor after: Hu Xing Inventor before: Ma Qiang Inventor before: Xiao Henglin Inventor before: Li Lihua Inventor before: Liu Yongli Inventor before: Shi Hongcai Inventor before: Zhu Jian Inventor before: Xing Wenwen Inventor before: Hu Xing |