CN1286341A - Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique - Google Patents

Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique Download PDF

Info

Publication number
CN1286341A
CN1286341A CN 99118448 CN99118448A CN1286341A CN 1286341 A CN1286341 A CN 1286341A CN 99118448 CN99118448 CN 99118448 CN 99118448 A CN99118448 A CN 99118448A CN 1286341 A CN1286341 A CN 1286341A
Authority
CN
China
Prior art keywords
template
reinforced concrete
prefabricated reinforced
cylinder
beam body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 99118448
Other languages
Chinese (zh)
Other versions
CN1117202C (en
Inventor
陆根源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 99118448 priority Critical patent/CN1117202C/en
Publication of CN1286341A publication Critical patent/CN1286341A/en
Application granted granted Critical
Publication of CN1117202C publication Critical patent/CN1117202C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The prefabricated reinforced concrete shutterings for the beams and columns of huilding frame and its installation technology are disclosed. The shutterings for bottom, sides and ends of beam are made up concrete and the pulling and retaining rings of reinforcing bars and the holes for inserting reinforcing bors of wall are pre-arranged. For the columns, the side shutterings are made of concrete and the reinforcing bars for linking walls and beams are pre-arranged. After walls and columns are assembled, the beams are put on vertical plane of columns. The main bars and reinforcing bars of columns and beams are inserted into each other. Its advantages are saving labour and time and low cost.

Description

Building frame beam scapus body prefabricated reinforced concrete template and installation technology
The present invention relates to be used to make the template of construction wall, a kind of building frame beam scapus body prefabricated reinforced concrete template and installation technology.
At present, beam is constructed in building operations, the cylinder framework uses punching block, wooden model, bamboo mould, the plastic-steel mould is built steel concrete, it exists defective to be: above-mentioned mould is installed overlap joint, build then, roll over after the curing again and remove mould, need cleaning reparation, transportation often causes template damage in various degree, and building costs is raise.
The purpose of this invention is to provide a kind of building frame beam body, cylinder prefabricated reinforced concrete template and installation technology, standard size requirement according to beam body, cylinder, at first at the place prefab form, transport to the job site and assemble, and then concreting, treat concrete curing after, template directly and the main body concrete become one, do not need to remove, reduce construction cost, save man-hour.
For achieving the above object, the present invention adopts following technical scheme:
Described building frame beam body, cylinder framework prefabricated reinforced concrete template, on certain production site, according to building standard, adopt concrete for making beam body soffit formwork 1, group's template 2, the top template 3 at two ends, the template bottom surface is the light face, be hair side above, and bury embedded bar underground and draw clasp 6, reserve body of wall reinforcing bar jack simultaneously; Cylinder is according to building standard, adopts concrete for making to become cylinder group template 4,5, and each helps on the template pre-buried connection to draw fastener 6, reserves the reinforcing bar that is connected with body of wall beam body simultaneously.
Described building frame beam body, the mounting process of cylinder prefabricated reinforced concrete template, after its prefabricated reinforced concrete template was transported to the scene, stacking required side direction vertically to be close to stacking, needed to soak 4-6 before installing individual hour in the pond.
The on-the-spot mounting process of described building frame beam body, cylinder prefabricated reinforced concrete template.The steel concrete shuttering that to make at production site, be transported to the job site, when making the beam body beam body soffit formwork 1 caught and be located on the frame pipe, again group's template 2 and two ends top template 3 are installed in respectively on the beam body soffit formwork, adopt reinforcing bar to connect template and draw button 6,7 socket, and colligation, fuse with the main body beam main tendon, reinforcing bar is strained and fixed, and meets the beam body of architectural drawing standard profile size, and then direct concreting, treat its curing, body of wall cylinder group template adopts 6 reinforcing bars to make drag hook 7, connects template and draws clasp, colligation is fastening, support with scaffold, when check and correction meets architectural working drawing required standard appearance and size, build column body concrete again, treat its curing, remove support scaffolding and get final product.
The mounting process of described building frame beam body, cylinder prefabricated reinforced concrete template, after its wall column body assembling, the beam body is horizontally placed on the cylinder vertical plane, and in vertical main muscle of cylinder and the stiffener insertion beam body, the main muscle and the stiffener of beam body also insert in the cylinder simultaneously.
The mounting process of described building frame beam body, post prefabricated reinforced concrete template, when its template was installed, the template seam is handled as follows: the cement mortar with 1: 2 was constructed seam, adopt 425 cement, the template seam requires in 1-2MM, treats that template seam intensity reaches at 45% o'clock, begins to build the main body concrete.
Described building frame beam body, the mounting process of cylinder prefabricated reinforced concrete template, because of main body concrete adstante febre needs moisture content, so after the main body concreting, necessary maintenance 15-18 days.
Owing to adopted as above technical scheme, the present invention has following superiority:
Carry out the concrete work main body with the prefabricated reinforced concrete template and build, build finish after, treat that the major project concrete strength reaches at 75% o'clock, scaffold removed got final product, the prefabricated reinforced concrete template just need not be removed, time and labour saving, attenuating expense.
The precast concrete form installation is built the main body concrete and can be become one with Vierendeel girder, post.Being not template during concreting after the installation, also is the topping of reinforcing bar simultaneously, has built concrete and has just become the body frame external surface of body, cylinder of setting a roof beam in place, so just need not remove.
The prefabricated reinforced concrete template is without timber, without steel.Reduce forest, the waste of iron ore deposit.
The prefabricated reinforced concrete pattern plate bolster body of setting a roof beam in place; column body concrete does not increase the profile physical dimension; undertaken by the working drawing standard; controlled and the protection of the attached reinforcing bar of major project master; make and do not reveal the main body reinforcing bar, the prefabricated reinforced concrete template only need be installed, and need not remove; saving of work and time has reduced cost.
The prefabricated reinforced concrete form technology is simple, and is easy to operate, small investment, instant effect.
The production technology of prefabricated reinforced concrete template, require producing prefab form factory has a smooth place, and the producer that can produce various precast concrete forms just can.
The prefabricated reinforced concrete template belongs to disposable tool-typed formwork, and is technical strong, requires physical dimension accurate.
The prefabricated reinforced concrete template strength reaches 100% and can dispatch from the factory, and dispatches from the factory and must show the concrete pressure test sheet.
Prefabricated reinforced concrete template major economic indicators.
1500×300×25=0.01125m 3×1000=1.125m 3
1500 * 300=0.45m 2* 100=45m 2, wherein use the every 1.125m of reinforcing bar φ 5=6 root φ 4=10 root weight: 2Kg=4.8 unit 3With reinforcing bar 200kg * 2.4 yuan=480 yuan
Every cubic metre-labour cost: 40 yuan
Machinery takes: 6.8 yuan.
Cost of materials: 624 yuan
Transport cost: 8 yuan
Add up to: 678.8 yuan
Below in conjunction with the description of drawings specific embodiment:
Fig. 1 is a building frame beam body prefabricated reinforced concrete form assembly structural representation.
Fig. 2 is a building frame cylinder prefabricated reinforced concrete form assembly structural representation.
Fig. 3 is the pre-buried fastener schematic diagram that draws of the precast reinforced coagulation soffit formwork of building frame beam body.
Fig. 4 is building frame beam body, cylinder prefabricated reinforced concrete soffit formwork clasp schematic diagram.
Fig. 5 is building frame beam body, cylinder prefabricated reinforced concrete template holding ﹠ forming knot drag hook schematic diagram.
As shown in FIG.: 1-beam body soffit formwork, 2-beam body group template, the top template at 3-beam body two ends, 4,5-cylinder group template, the 6-embedded bar draws clasp, and the 7-embedded bar draws the button drag hook, the 8-stiffener.
Use cement, rubble, sand, water is in the cooperation ratio, synthetic mixing made the prefab form pug, precast plate divides beam phantom plate, two types of cylinder template, and these two type prefab form common structures are: become button knot ring to be embedded in the template with reinforcement fabrication, become button knot drag hook 7 with reinforcement fabrication, link template built-in fitting 6 when gang form is installed at the scene, and carry out colligation, template and main body reinforcing bar are linked be one.
Prefabricated reinforced concrete form technology flow process:
1, makes formation one block concrete template place.
2, ground on the scene is installed in the mould of making prefab form on the ground.
3, assembling reinforcement and bury and put the drawknot ring.
4, check and correction reinforcing bar, embedded part is with die size.
5, strand mixed concrete
6, build-vibrate
7, maintenance-form removal
8, check-warehouse-in
9, make test specimen
10, dispatch from the factory
11, field test-installation
12, cast in situs main body concrete

Claims (6)

1, a kind of building frame beam body, cylinder prefabricated reinforced concrete template, it is characterized in that: on certain production site, according to building standard, adopt concrete for making beam body soffit formwork (1), group's template (2), the top template at two ends (3), the template bottom surface is the light face, be hair side above, and bury embedded bar underground and draw clasp (6), reserve body of wall reinforcing bar jack simultaneously; Cylinder is according to building standard, adopts concrete for making to become cylinder group template (4), (5), and each helps on the template pre-buried connection to draw fastener drag hook (7).Reserve the reinforcing bar (8) that is connected with body of wall beam body simultaneously.
2, implement building frame beam body as claimed in claim 1, post prefabricated reinforced concrete template and installation technology, it is characterized in that: described prefabricated reinforced concrete template, after its prefabricated reinforced concrete template is transported to the scene, stacking requires side direction vertically to be close to stacking, needs before installing to soak in the pond 4-6 hour
3, implement as claim 1,2 described building frame beam bodies, the mounting process of cylinder prefabricated reinforced concrete template, it is characterized in that: the mounting process of described prefabricated reinforced concrete template, the steel concrete shuttering that to make at production site, be transported to the job site, when making the beam body beam body soffit formwork (1) caught and be located on the frame pipe, again the group template (2 and two ends top template (3) be installed in respectively on the beam body soffit formwork, adopt reinforcing bar to connect template and draw button (6), (7) socket, and colligation, fuse with the main body beam main tendon, reinforcing bar is strained and fixed, and meets the beam body of architectural drawing standard profile size, and then direct concreting, treat its curing, body of wall cylinder group template adopts (6) reinforcing bar to make drag hook (7), connects template and draws clasp, colligation is fastening, support with scaffold, when check and correction meets architectural working drawing required standard appearance and size, build column body concrete again, treat its curing, remove support scaffolding and get final product.
4, as the mounting process of claim 1,2,3 described building frame beam bodies, cylinder prefabricated reinforced concrete template, it is characterized in that: the mounting process of described prefabricated reinforced concrete template, after its body of wall cylinder assembling, the beam body is horizontally placed on the cylinder vertical plane, and vertical main muscle of cylinder and stiffener insert in the beam body, and the main muscle and the stiffener of beam body also insert in the cylinder simultaneously.
5, as the mounting process of claim 1,3,4, described building frame beam body, post prefabricated reinforced concrete template, it is characterized in that: the mounting process of described prefabricated reinforced concrete template, when its template is installed, the template seam is handled as follows: the cement mortar with 1: 2 is constructed seam, adopt 425 cement, the template seam requires in 1-2MM, treats that template seam intensity reaches at 45% o'clock, begins to build the main body concrete.
6, as the mounting process of claim 1,3,4 described building frame beam bodies, post prefabricated reinforced concrete template, it is characterized in that: the mounting process of described prefabricated reinforced concrete template, because of main body concrete adstante febre needs moisture content, so after the main body concreting, necessary maintenance 15-18 days.
CN 99118448 1999-08-31 1999-08-31 Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique Expired - Fee Related CN1117202C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99118448 CN1117202C (en) 1999-08-31 1999-08-31 Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99118448 CN1117202C (en) 1999-08-31 1999-08-31 Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique

Publications (2)

Publication Number Publication Date
CN1286341A true CN1286341A (en) 2001-03-07
CN1117202C CN1117202C (en) 2003-08-06

Family

ID=5280461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99118448 Expired - Fee Related CN1117202C (en) 1999-08-31 1999-08-31 Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique

Country Status (1)

Country Link
CN (1) CN1117202C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040981A (en) * 2015-06-30 2015-11-11 成都点石创想科技有限公司 Method for constructing energy-saving building by using prefabricating method
CN105603843A (en) * 2015-12-30 2016-05-25 中国建筑第二工程局有限公司 Assembled reinforced concrete prefabricated pavement slab and construction method thereof
CN108824700A (en) * 2018-06-26 2018-11-16 江苏新龙兴建设集团有限公司 Equivalent cast-in-place assembled steel reinforced concrete beam construction method
CN112160591A (en) * 2020-09-30 2021-01-01 重庆建工集团股份有限公司 Reinforcing apparatus for building roof beam

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040981A (en) * 2015-06-30 2015-11-11 成都点石创想科技有限公司 Method for constructing energy-saving building by using prefabricating method
CN105603843A (en) * 2015-12-30 2016-05-25 中国建筑第二工程局有限公司 Assembled reinforced concrete prefabricated pavement slab and construction method thereof
CN108824700A (en) * 2018-06-26 2018-11-16 江苏新龙兴建设集团有限公司 Equivalent cast-in-place assembled steel reinforced concrete beam construction method
CN108824700B (en) * 2018-06-26 2020-10-16 江苏新龙兴建设集团有限公司 Construction method of equal cast-in-place assembled steel-concrete beam
CN112160591A (en) * 2020-09-30 2021-01-01 重庆建工集团股份有限公司 Reinforcing apparatus for building roof beam

Also Published As

Publication number Publication date
CN1117202C (en) 2003-08-06

Similar Documents

Publication Publication Date Title
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN103089004B (en) Combination frame module, component frame module and tool set structure and installing and dismantling method thereof
CN107023099A (en) Prefabricated superimposed sheet double combined overlapped shear wall and its construction method
CN1114738C (en) In-situ cast hollow reinforced concrete slab pre-provided with hollow hard thin-wall members and its construction method
CN107130757A (en) Large autoclaved lightweight aerated concrete slab component
CN219527957U (en) Concrete module box
CN2232953Y (en) Permanent combination building section mould
CN1117202C (en) Shutterings for prefabricating reinforced concretes of beams and columns for building frame and their installation technique
CN219547838U (en) Frame lattice beam structure without template
CN211228607U (en) Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure
CN207647033U (en) A kind of precast reinforced basket structure
CN101418602B (en) In-situ casting construction method of reinforced concrete structural system using phosphogypsum as wall material
CN106869331A (en) The connection method of precast shear wall composite beam in assembled RC frame-shear structures
CN107762071B (en) Prefabricated reinforcement cage structure, pouring structure body and structure body construction method
CN106948534A (en) Mesh sheet forms hollow dark contignation and technique with spacer bar cast-in-place concrete
CN207032474U (en) A kind of assembly concrete frame structure beam column rigid connection node
CN206053129U (en) A kind of light steel construction post of T-shaped
CN206769198U (en) Separate combination type armored concrete prefabricated section anchored end supporting construction
KR100264386B1 (en) Method and construction of panel of reinforced siol using unartificial marble
CN110307010A (en) Hydraulic tunnel abutment wall and bottom plate lining construction template system
CN221073465U (en) Template system for seamless pouring of high and large concrete cylinder of clear water
CN216865221U (en) Bearing platform adopting combined prefabricated ceramsite plate
CN214091132U (en) Building structure's reinforcement connecting device
CN214462553U (en) Building structure mould
CN217079310U (en) Truss floor board with reinforcing bar protective layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee