CN1281934A - Open-cut reversed construction method for rehabilitating underground space - Google Patents

Open-cut reversed construction method for rehabilitating underground space Download PDF

Info

Publication number
CN1281934A
CN1281934A CN 99115035 CN99115035A CN1281934A CN 1281934 A CN1281934 A CN 1281934A CN 99115035 CN99115035 CN 99115035 CN 99115035 A CN99115035 A CN 99115035A CN 1281934 A CN1281934 A CN 1281934A
Authority
CN
China
Prior art keywords
construction method
underground space
open
around
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 99115035
Other languages
Chinese (zh)
Inventor
牟延林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 99115035 priority Critical patent/CN1281934A/en
Publication of CN1281934A publication Critical patent/CN1281934A/en
Pending legal-status Critical Current

Links

Abstract

The invented construction method includes the following steps: on a ground surface, from its all around, using mechanical cutting machine to groove to a certain depth, then using manual or mechanical method to take out stone material and earth from middle portion of groove, then making reinforced concrete frame between wall and template and depositing concrete to form reinforced concrete retaining wall, then downwards repeating the above-mentioned operation steps so as to implement reinforced concrete pouring engineering from top to bottom layer-by-layer. Said invention is low in cost, simple in construction process, short in construction period, can be safely and quickly used for building underground space.

Description

Open-cut reversed construction method for rehabilitating underground space
The present invention relates to a kind of underground space construction method of building, show that especially building the underground space takes the open cut reversed construction method.
At present, to the building underground construction, divide open cut and tunneling two kinds of job practicess substantially both at home and abroad.Built-in in the city proper " people's air defense ", or underground constructions such as " subways ", the conventional open cutting construction method of general employing, urban operating mechanism engineering at first to having built up, open the broken tripe of intestines, boring then, blow out, deslagging, dig basic part always, just carry out at last major project is constructed, after underground major project is built up, waste residue is transported back filled and led up again, also to come disrupted urban operating mechanism full recovery at last, this job practices, it is big to exist investment, the cost height, long construction period is made troubles to citizen's life, good geologic structure is destroyed with good building materials become refuse, weak point such as also be restricted to the construction depth of underground excavation.In the patent disclosure of number of patent application 91103214.2 " a kind of method of building the large-scale underground space ", also exist the construction technology complexity, cost height, shortcoming such as the cycle is long.
The objective of the invention is to solve in the above-mentioned technology and have weak point, and propose a kind of underground space open cutting construction method of building.
The present invention also aims to provide reversed construction method from top to bottom.
The objective of the invention is to realize by following content, begin when slotting certain depth downwards with mechanical cutter all around from ground, middle building stones or the earth that to hold groove with artificial or mechanical means all around successfully take out, carry out between wall and the template after the steel bar concrete water engineering finishes forming, around downwards level carries out, slot, get material, steel bar concrete water again, top-down whole reinforced concrete works is watered finish in layer.
In order to guarantee the mechanical slotting normal operation, the trough that one deck is opened can not be vertical with the trough that last layer is opened, and mechanical cutter is return a bit, stays a small stair, and is simultaneously that the blade of mechanical cutter is more outward-dipping, makes the both sides wall form zigzag.
Indication of the present invention " oppositely " construction is and the rightabout job practices of routine job practices from bottom to top.As building underground construction routinely, be to have dug the tunnel earlier, to carry out post, wall, plate, beam from the basis, tunnel and carry out from bottom to top, this job practices claims " forward " construction method; Otherwise,, be called " reverse " construction method from last and down construct from level to level.
It is low that the present invention has cost, small investment, and construction technology is simple to be grasped easily, and the duration is short, characteristics such as construction safety.
The present invention is further described below in conjunction with accompanying drawing.
Accompanying drawing is one embodiment of the present of invention sectional structure schematic diagram.
Among the figure: trough 7-reinforcing anchor pole that the soil 6-mechanical cutter of 1-ground, 2-steel concrete primary and secondary beam, 3-reinforced concrete floor, 4-steel concrete barricade 5-do not dig is cut
Shown in accompanying drawing, the trough 6 that cut with mechanical cutter downwards 1 both sides from ground, the trough 6 that mechanical cutter is cut outwards is a steel concrete shelves wall 4, steel concrete primary and secondary beam 2 and reinforced concrete floor 3 that each level is arranged between steel concrete shelves wall 4, if the wall of the trough 6 that mechanical cutter is cut finds to have situations such as crack, fragmentation, reinforce the soil 5 that does not dig with reinforcing anchor pole 7.

Claims (2)

1. open-cut reversed construction method for rehabilitating underground space, it is characterized in that (1) begins when slotting certain depth downwards with mechanical cutter all around from ground, middle building stones or the earth that to hold groove with artificial or mechanical means all around successfully take out, carry out steel bar concrete water to forming between wall and the template, form steel concrete barricade (4), around downwards level carries out, slot, get material, steel bar concrete water again, top-down whole reinforced concrete works is watered finish in layer.
2. a kind of open-cut reversed construction method for rehabilitating underground space according to claim 1 is characterized in that mechanical cutter returns a bit, stays a small stair, and is simultaneously that the blade of mechanical cutter is more outward-dipping, makes the both sides wall form zigzag.
CN 99115035 1999-07-21 1999-07-21 Open-cut reversed construction method for rehabilitating underground space Pending CN1281934A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99115035 CN1281934A (en) 1999-07-21 1999-07-21 Open-cut reversed construction method for rehabilitating underground space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99115035 CN1281934A (en) 1999-07-21 1999-07-21 Open-cut reversed construction method for rehabilitating underground space

Publications (1)

Publication Number Publication Date
CN1281934A true CN1281934A (en) 2001-01-31

Family

ID=5278056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99115035 Pending CN1281934A (en) 1999-07-21 1999-07-21 Open-cut reversed construction method for rehabilitating underground space

Country Status (1)

Country Link
CN (1) CN1281934A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296961A (en) * 2011-05-31 2011-12-28 中铁二十局集团有限公司 Karst tunnel large-scale cavern processing method
CN105370300A (en) * 2015-11-17 2016-03-02 中铁工程装备集团有限公司 Two-layer or multi-layer underground space construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296961A (en) * 2011-05-31 2011-12-28 中铁二十局集团有限公司 Karst tunnel large-scale cavern processing method
CN105370300A (en) * 2015-11-17 2016-03-02 中铁工程装备集团有限公司 Two-layer or multi-layer underground space construction method

Similar Documents

Publication Publication Date Title
CN101539008B (en) Ground stereoscopic discharge and mining method of coal bed methane
CN201137148Y (en) Double rows bamboo pile composite soil nail defending system
CN108360972A (en) A kind of rotary drilling rig is combined with percussive drill carries out bored pile construction method
Wright Ancient Building Technology, Volume 2: Materials (2 Vols)
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN104652839B (en) Method for reducing height of reinforced concrete frame structure
CN104711974A (en) Steel tube recycled concrete composite bearing base pile and manufacturing method thereof
CN108049395A (en) A kind of anti-collapse impact holing construction method in complex karst place
CN111997616A (en) Method for continuously recycling residual top-bottom column by adopting large section
CN202360116U (en) U-shaped shed roadway junction support device
CN105019917B (en) Impact drilling type advanced jet grouting pipe shed construction device and construction method
CN1281934A (en) Open-cut reversed construction method for rehabilitating underground space
CN214993929U (en) Foundation pit support soil nail
CN104988981B (en) A kind of well construction method of riding on present situation operation shield method drainage pipeline
Reich et al. Jerusalem, City of David
CN100593052C (en) Open cut foundation pit supporting and protecting method
CN2498331Y (en) Support shed for underground engineering
CN2431334Y (en) Border-laying prefabricated hollow brick
CN1320215C (en) Method for making foundation piles in high embankment region
CN204715502U (en) To ride well system
CN1101515C (en) Ming method utilizing substituting isolating roof
CN215330015U (en) Assembled tunnel portal structure
CN102704473A (en) Steel bar implanting construction method of manual hole digging pile in quicksand layer
CN1048063C (en) Continuous underground wall construction method suitable for cobble layer site

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication