CN1256531C - Construction method for river crossing pipeline - Google Patents

Construction method for river crossing pipeline Download PDF

Info

Publication number
CN1256531C
CN1256531C CN 200410023552 CN200410023552A CN1256531C CN 1256531 C CN1256531 C CN 1256531C CN 200410023552 CN200410023552 CN 200410023552 CN 200410023552 A CN200410023552 A CN 200410023552A CN 1256531 C CN1256531 C CN 1256531C
Authority
CN
China
Prior art keywords
pipeline
construction
water
pipe
river
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200410023552
Other languages
Chinese (zh)
Other versions
CN1558129A (en
Inventor
蒿振亮
张克明
菅宪忠
高勇
刘勇
李新峰
衣华锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No3 Plant Of Shengli Oilfield Shengli Petrochemical Construction Co Ltd
Original Assignee
No3 Plant Of Shengli Oilfield Shengli Petrochemical Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No3 Plant Of Shengli Oilfield Shengli Petrochemical Construction Co Ltd filed Critical No3 Plant Of Shengli Oilfield Shengli Petrochemical Construction Co Ltd
Priority to CN 200410023552 priority Critical patent/CN1256531C/en
Publication of CN1558129A publication Critical patent/CN1558129A/en
Application granted granted Critical
Publication of CN1256531C publication Critical patent/CN1256531C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The present invention discloses a construction method for river crossing pipelines, which belongs to the technical field of underwater pipeline laying. The present invention is characterized in that a long-arm monobucket excavator ditches under water on a self-fabricated floating box, and then, both ends of the prefabricated crossing pipeline are plugged. With the characteristic that sealed pipelines can float on water, the pipeline can be drawn by a construction device to drift and cross rivers to a set position. Then, water is injected in the pipeline, the pipeline is sunk in a pipeline ditch, finally, the pipeline is pressed stably, and the pipeline ditch is backfilled. A construction process step comprises construction preparation, measurement and line laying, underwater ditch excavation, pipeline drift and sinking, pipeline stabilization and pipeline ditch backfill. The construction method has been tried in water network areas in the south of the Yangtze River of western gas eastward delivery pipeline construction, the pipelines successfully cross eight 60m to 100m of navigable rivers, and the total width of the pipelines is more than 800m. Construction quality achieves design requirements and national standards, and compared with a construction method for crossing rivers of 'diversion channel excavation, dam enclosure and flow cutting, water pumping, sludge removal, heavy excavation', the present invention has the advantages of shortened construction periods, no influence to normal navigation, safe construction and no pollution and breakage to environment and saves a large amount of funds.

Description

The pipeline river crossing method of construction
(1) technical field
The present invention relates to the method for construction technical field of tubing under water, particularly is a kind of pipeline river crossing method of construction.
(2) background technique
Pipeline river crossing especially passes through navigable river, is known as " project of primary importance " in the long distance pipeline construction, technical difficulty height not only, and investment is many, and long in time limit, has a big risk.My company adopts " the mud circulation secondary is put the wet top of pipe method " at home first in March, 1970, and the oil transport pipeline of 159 millimeters of long 474 meters, diameter is successfully passed through the bottom, the Yellow River.Adopt first at home again after 2 years " mechanically-propelled, sluicing, curve pass through the secondary pipe jacking method ", the cased pipe road integral body of long 438 meters, 219 millimeters of tubing diameters, 273 millimeters of middle casing diameters, 325 millimeters of outer layer sleeve diameters is passed through the Yellow River, its bosom below the riverbed face 23.47 meters.In June, 1973, adopt first at home again " towards suction formula water conservancy ditching immersed tunnelling method ", will grow 748 meters, the cased pipe road of 426 millimeters of tubing diameters, 630 millimeters of casing diameters successfully is laid under the Yellow River.
Wherein back two pipeline river crossing new technologies were won national science conference award in 1978.Nineteen ninety-five, my company used " barge-loading type seabeach pipeline excavator " (patent No. 95110332.6) of development voluntarily, successfully laid China's article one seabed gas pipeline in Bohai Sea Gulf.Use " Heiden land, beach pipeline pipe dragging method and isolated plant " (patent No. 00129318), " submarine pipeline land prefabricated tube section plunge into the commercial sea transmitter installation " (patent No. 00256422) of development voluntarily in 2000, successfully lay Heiden land, domestic article one beach oil transport pipeline in Bohai Sea Gulf.68 kilometers of calendar year 2001 my company acceptance of the bid pipeline of transferring natural gas from the west to the east engineering the 26th bid sections, 1016 millimeters of pipe diameters, 26.2 millimeters of wall thickness, working pressure 10MPa is positioned at Wuxi, the south of the River, Suzhou dense waterway net region.68 kilometers pipeline trunk lines will pass through surplus 102 in pond, the river 90, and wherein navigable river is 8, and river width is generally about 60~100 meters.Because water surface broad, river flows, the small boat shipping is frequent, can't adopt iceound, cofferdam, the desilting of drawing water, open method of construction such as diversion channel, heavy excavation, also should not adopt above-mentioned " curve pipe jacking method ", " waterpower is dashed and inhaled immersed tunnelling method " and the extra large pipeline construction method in beach.Patent documentation by retrieval, wherein " relevant improvement of laying submarine pipeline " (patent No. 97122627) is to lay submarine pipeline with pipe laying barge, we can't adopt." River dredger " (98250388) also are not suitable for digging under water pipe trench.Above-mentioned prior art all can not solve the construction difficult problem that we face, and can only use for reference some construction experience.
(3) summary of the invention
In view of above-mentioned prior art all can not be used for the pipeline of transferring natural gas from the west to the east engineering in the construction of dense waterway net region river crossing, the south of the River, we are off the beaten track, have the courage to bring forth new ideas, and adopt " ditching under water, floating immersed tube " river crossing method of construction at home first, and succeed.
The present invention is realized by following technical proposals:
The basic technical features of pipeline river crossing method of construction is: adopt long-armed power shovel to carry out ditching under water on the self-control buoyancy tank, crossing pipeline two ends shutoff that will be prefabricated then, utilize the closed conduit can floating on the water characteristic, cross the river in place with the drift of construction equipment traction pipeline, water filling sinks in the pipe trench it in pipeline again, the firm and backfill of last pressure pipe.Its working procedure is: preparation of construction, measure unwrapping wire, ditching under water, float pipe immersed tube, underwater pipeline stabilizing backfill.The technology contents of each operation (or claiming sub-operation) is:
Preparation of construction: comprise pipe prefabrication and flaw detection, anticorrosive coat detects and repairs, pipe end shutoff and installation water inlet, waste pipe.Earth anchor is buried in buoyancy tank haul, water and assembling down, is wire rope.Buoyancy tank on the excavator, and anti-skidding fixing, constitute furrow making dveice under water thus.
Measure unwrapping wire: according to Design Requirement Drawing, remove lime on the both sides, riverbank earlier, insert checkmark field, marker peg, determine pipe trench center line, pipe trench sideline and construction operation band edge boundary line.According to soil property, water velocity, cutting depth etc., determine data such as the pipe trench degree width and the pipe trench gradient, the bottom of trench width is that caliber adds 3~4 meters, the gradient 1: 2~1: 6.
Ditching under water: by the marker of long-armed power shovel, on buoyancy tank, carry out ditching operation under water, and require the pipe trench single forming according to the both sides, riverbank, through measure qualified after again the mobile position continue ditching operation, scrape out until the whole piece pipe trench.On close limit, riverbank, the river silt that digs out directly is placed on the riverbank, far river silt can be placed on the small-sized hopper from the riverbank and transport on the bank.After underwater trench is shaped, dig the land pipe trench that the slope section is put on the both sides, riverbank again.Whole to pipe trench by the diver then towards putting down with high pressure water gun, reach designing requirement.
Float the pipe immersed tube: in the pipe canal digging of river bed, dig out a transmission ditch in prefabricated pipeline section one side, send the straight-through river bank of ditch, make river enter the transmission ditch, its depth of water can be floated pipeline section for about 1 meter.With sideboom tractor pipeline section is put into the transmission ditch, pipeline section is in floating condition, floats with construction equipment traction pipeline section and delivers to the position.In pipeline section, inject clean water with water pump, make prefabricated tube section slowly sink to bottom of trench.
The underwater pipeline stabilizing backfill: immersed tube is in place reach designing requirement after, cooperate by the diver, with buoyancy tank and loop wheel machine shape of a saddle cement briquetting is installed one by one and is pressed on the manned pipeline backfill then.In the pipe ends cofferdam, expose tube head at last, ponding in the pipeline is scanned out, for pipeline connects ready with air compressor and wiper.
Above-mentioned pipeline river crossing method of construction, on probation in the zone, the network of rivers, the south of the River of pipeline of transferring natural gas from the west to the east engineering the 26th bid section, successfully pass through 8 of navigable rivers, more than 800 meter of overall width, construction quality satisfies the requirement of design document and NBS standard.This method of construction and " excavation diversion channel, cofferdam dam, draw water desilting, heavy excavation " river crossing method of construction contrast, shift to an earlier date 60 days durations, 777.2 ten thousand yuan of saving funds, and do not influence normal shipping basically, industrial accident and equipment accident are few in the work progress, local water and soil and ecotope are not caused any pollution and destruction, be subjected to engineering each side and local resident's favorable comment deeply.This method of construction will have good popularizing application prospect when the heavy caliber long distance pipeline passes through middle or small navigable river from now on.
(4) description of drawings
Accompanying drawing 1 is the concise and to the point technology contents block diagram of working procedure flow process of the present invention and each operation.
Accompanying drawing 2 is schematic representation of ditching under water of the present invention.
(5) embodiment
Embodiment of accompanying drawings:
As shown in Figure 1, working procedure of the present invention is: preparation of construction, measure unwrapping wire, ditching under water, float pipe immersed tube, underwater pipeline stabilizing backfill.The technology contents of each operation is: the preparation of construction operation comprises buoyancy tank on pipe prefabrication and flaw detection, anticorrosive coat detection and repairing, pipe end shutoff, buoyancy tank haul, water and assembling down, the excavator.Measure the unwrapping wire operation comprise insert checkmark field center line and sideline, determine the pipe trench sized data.Ditching operation under water comprises that slope section ditching is put in river bed ditching and measurement, two sides, pipe trench is smooth.Floating immersed tube operation comprise dig send ditch, swing pipe hyposulculus, traction float pipe put in place, manage in the water filling immersed tube.Underwater pipeline stabilizing backfill operation comprise the pouring weight pressure pipe of slinging, backfill, pipe end cofferdam appear, clear away the pipe in ponding.
When the river water surface and ground, riverbank drop were big, transmission trench depth on the bank needn't be dug and can be advanced river, otherwise shoveling amount and backfill amount are too big.Also can be in anhydrous transmission ditch D before the swing pipe hyposulculus uniform several high-pressure gasbags, pass through drop tube segment on air bag, floating in place by water under the construction equipment traction pipeline section under sideboom tractor and situation that the air bag roll-sliding is tied mutually, and be strictly on guard against the destruction anticorrosive coat.
By shown in Figure 2, furrow making dveice comprises buoyancy tank 1, long-armed power shovel 2, wire rope 3 and earth anchor 4 under water.18 meters of excavator 2 brachiums firmly are placed on the buoyancy tank 1.Buoyancy tank 1 is assembled by four 12 * 2.5 * 1.5 meters little buoyancy tank and is one, and load-carrying is more than 70 tons.Totally four of wire rope 3, totally four of earth anchors 4, A is the river, and B is the riverbank, and C is the river bed pipe trench, and D sends ditch on the bank.After excavator 2 scraped out one section pipe trench, buoyancy tank 1 moved forward a position by wire rope 3 tractions and continues ditching.Whether and it is qualified to detect pipe trench at any time, until scraping out the whole piece underwater trench.If two sides, river landform is open, earth anchor 4 also can be substituted by jumboes such as bulldozer or sideboom tractors, is more convenient for adjusting wire rope 3 like this buoyancy tank 1 is shifted forward again and again.

Claims (2)

1. pipeline river crossing method of construction is characterized in that working procedure is:
Preparation of construction: comprise pipe prefabrication and flaw detection, anticorrosive coat detects and repairs, pipe end shutoff and installation water inlet, waste pipe, earth anchor (4) is buried in buoyancy tank (1) haul, water and assembling down, is wire rope (3), excavator (2) is gone up buoyancy tank (1) and anti-skidding fixing, constitutes furrow making dveice under water thus;
Measure unwrapping wire: according to Design Requirement Drawing, (B) both sides are spread lime, are inserted checkmark field, marker peg on the riverbank earlier, determine pipe trench center line, pipe trench sideline and construction operation band edge line, according to soil property, water velocity, cutting depth, determine bottom of trench width and pipe trench gradient data, the bottom of trench width is that caliber has added 3~4 meters, the gradient 1: 2~1: 6;
Ditching under water: by the marker of long-armed power shovel (2) according to both sides, riverbank (B), on buoyancy tank (1), carry out ditching operation under water, and require pipe trench (C) single forming, through measure qualified after again the mobile position continue ditching operation, (C) scrapes out until the whole piece pipe trench, dig both sides, riverbank (B) again and put the land pipe trench of slope section, whole to pipe trench (C) by the diver then towards putting down with high pressure water gun, reach designing requirement;
Float the pipe immersed tube: in river bed pipe trench (C) excavation, dig out a transmission ditch (D) in prefabricated pipeline section one side, send the straight-through river bank of ditch (D), river is entered send ditch (D), its depth of water can be floated pipeline section for about 1 meter, with sideboom tractor pipeline section is put into and is sent ditch (D), pipeline section is in floating condition, float with construction equipment traction pipeline section and to deliver to the position, in pipeline section, inject clean water then, make it slowly sink to bottom of trench;
The underwater pipeline stabilizing backfill: immersed tube is in place reach designing requirement after, cooperate by the diver, with buoyancy tank and loop wheel machine shape of a saddle cement briquetting is installed one by one and to be pressed on the manned pipeline, backfill then, at last in the pipe ends cofferdam, expose tube head, ponding scans out in will managing with air compressor and wiper, gets ready for pipeline connects.
2. pipeline river crossing method of construction according to claim 1, it is characterized in that furrow making dveice comprises buoyancy tank (1), long-armed power shovel (2), wire rope (3) and earth anchor (4) under water, 18 meters of excavator (2) brachiums, firmly be placed on the buoyancy tank (1), buoyancy tank (1) is assembled by four 12 * 2.5 * 1.5 meters little buoyancy tank and is one, totally four of wire rope (3), totally four of earth anchors (4), wire rope (3) one ends are earth anchor (4), and the other end is tied on the buoyancy tank (1).
CN 200410023552 2004-01-30 2004-01-30 Construction method for river crossing pipeline Expired - Fee Related CN1256531C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200410023552 CN1256531C (en) 2004-01-30 2004-01-30 Construction method for river crossing pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200410023552 CN1256531C (en) 2004-01-30 2004-01-30 Construction method for river crossing pipeline

Publications (2)

Publication Number Publication Date
CN1558129A CN1558129A (en) 2004-12-29
CN1256531C true CN1256531C (en) 2006-05-17

Family

ID=34352180

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200410023552 Expired - Fee Related CN1256531C (en) 2004-01-30 2004-01-30 Construction method for river crossing pipeline

Country Status (1)

Country Link
CN (1) CN1256531C (en)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892632B (en) * 2009-05-19 2012-05-30 上海市基础工程有限公司 Construction method of structural system of river under no-cutoff working condition
CN102261519B (en) * 2011-04-15 2012-11-14 胜利油田胜利石油化工建设有限责任公司 Method for assisting sliding, floating and down-ditching of pipeline by air bags
CN102434719A (en) * 2011-08-28 2012-05-02 中国石油天然气集团公司 Construction technology for hierarchical excavation and pipeline sinking
CN102878351A (en) * 2012-10-18 2013-01-16 中煤科工集团武汉设计研究院 Pipeline laying method of long-distance coal conveying pipeline
CN103266591A (en) * 2013-05-30 2013-08-28 中国石油集团海洋工程有限公司 Foundation treatment method of seabed oil and gas pipeline paving sand milling area
CN103912721B (en) * 2014-04-23 2016-01-13 中国化学工程第三建设有限公司 A kind of method of construction of fluting, immersed tube river crossing under water
CN104676108B (en) * 2015-03-18 2016-08-31 广东省水利电力勘测设计研究院 A kind of method for designing of steel immersed tube over strait
CN105042183A (en) * 2015-07-08 2015-11-11 中国十七冶集团有限公司 Method for installing super-long pipeline crossing river
CN105387273A (en) * 2015-12-10 2016-03-09 上海煤气第一管线工程有限公司 Method for constructing natural gas pipelines in mountain environment
CN105927792A (en) * 2016-04-07 2016-09-07 广东省水利水电第三工程局有限公司 Water floating transportation method for prestressed concrete cylinder pipes
CN106120859B (en) * 2016-07-02 2021-07-16 天鸿建设集团有限公司 Construction method for river crossing by multi-pipe-section immersed tube
CN106337971B (en) * 2016-10-09 2019-05-10 中国矿业大学 A kind of buoyancy can be changed buoyancy tank and its application
CN106402492A (en) * 2016-10-26 2017-02-15 朱育盼 Method and device for pipeline laying
CN107763307A (en) * 2017-09-27 2018-03-06 广西建工集团第五建筑工程有限责任公司 A kind of water filling nature immersed tube crosses the installation method of river pipeline
CN108193713A (en) * 2017-12-25 2018-06-22 中冶天工集团有限公司 Large-diameter Steel pipeline Immersed tunnel technique under a kind of no precipitation condition
CN108506569A (en) * 2018-04-26 2018-09-07 云南建投安装股份有限公司 Heavy caliber water intaking siphon piping immersed tube method over long distances
CN110067892B (en) * 2019-04-04 2021-07-30 中国市政工程中南设计研究总院有限公司 Method for construction of steel pipe by water buoyancy auxiliary casing internal dragging
CN110611286A (en) * 2019-10-30 2019-12-24 海风电气(江苏)有限公司 Ocean engineering power cable system and arrangement method thereof
CN112663642A (en) * 2020-12-18 2021-04-16 贵州天然气管网有限责任公司 Construction method for natural gas pipeline crossing by adopting secondary cofferdam diversion method

Also Published As

Publication number Publication date
CN1558129A (en) 2004-12-29

Similar Documents

Publication Publication Date Title
CN1256531C (en) Construction method for river crossing pipeline
CN105672195B (en) Suction Dredging Construction engineering method is twisted under a kind of urban ecology urban river water
CN109056761A (en) Channel cleanout method
CN101315139B (en) Immersed pipe construction technique of river crossing pipe
CN102605697A (en) Sand dredger filling construction method of soft soil foundation embankment
CN104846787A (en) Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger
CN107763307A (en) A kind of water filling nature immersed tube crosses the installation method of river pipeline
CN109137943B (en) Earth filling construction process for sea reclamation
CN110656621A (en) River channel closure system structure and construction method
CN204491693U (en) Long distance blast system
CN102261519B (en) Method for assisting sliding, floating and down-ditching of pipeline by air bags
CN108532546B (en) Method for reversed-order excavation of harbor basin and channel
CN202969343U (en) Diffusion device in discharging thick seawater into sea
CN109083100B (en) River channel excavation construction process after mud blowing and landing
CN101929162B (en) Construction method for three-stay mudflat earthwork diker
CN112663558A (en) Construction process for excavating weathered rock in inland river harbor pool
CN1262780C (en) Construction method for polyvinyl plastic pipeline long distance deep water crossing river
CN201580547U (en) Pontoon applicable to excavation operation on water surface
CN107587497B (en) A method of improving hydraulic reclamation flatness
CN106368217A (en) Assembly wharf boat overwater operation platform and construction method thereof
CN206143774U (en) Assembling wharf boat overwater operation platform
CN102434719A (en) Construction technology for hierarchical excavation and pipeline sinking
CN112253848B (en) Sand geology water network swamp area pipeline construction method
CN2679245Y (en) Underwater ditcher for pipeline-crossing river
CN210288280U (en) Open type cofferdam-free coral sand island reef reclamation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee