CN102878351A - Pipeline laying method of long-distance coal conveying pipeline - Google Patents
Pipeline laying method of long-distance coal conveying pipeline Download PDFInfo
- Publication number
- CN102878351A CN102878351A CN2012103956944A CN201210395694A CN102878351A CN 102878351 A CN102878351 A CN 102878351A CN 2012103956944 A CN2012103956944 A CN 2012103956944A CN 201210395694 A CN201210395694 A CN 201210395694A CN 102878351 A CN102878351 A CN 102878351A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- pipe
- trench
- earth
- fine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention discloses a pipeline laying method of a long-distance coal conveying pipeline. The method comprises the following steps that A, a pipeline is imbedded below a frost line, and an earth covering depth from the top of the pipeline to a natural terrace is not less than 1.0 m; B, when the pipeline is laid in a gravel area, the over excavation of 0.2 m is required, a fine earth or fine sand cushion layer which is 0.2 m thick is first paved necessarily at the bottom of a trench, and then, the pipeline can be lifted to be put in the trench after the fine earth or fine sand cushion layer is flat, when the trench for the pipeline in the gravel area is backfilled, the trench is first backfilled to 0.3 m above the top of the pipeline necessarily by using fine earth (sand), and then, the trench can be backfilled by using original earth, the maximal grain size of the backfilling fine earth is not more than 10 mm, and gravel blocks as the backfilling earth are not expected to be more than 250 mm; and C, accident cutoff valves and valve chests are arranged at two ends of the pipeline traversing a large river and at proper positions along the pipeline, and the pipelines within at least 50 m outside outer edge lines of two ends of the pipelines traversing large and medium rivers and gullies are expected to adopt a way the same as a traversing section. Not only is the wear to a pipe wall in a construction process reduced, but also the maintenance cost of the pipeline in a process that the pipeline is used for conveying coal slurry is reduced.
Description
Technical field
The present invention relates to a kind of pipe laying method, be specifically related to the pipe laying method of the defeated coal of a kind of long-distance pipe.
Background technique
For the heavy caliber ore slurry pipeline of diameter more than 600mm, usually adopt " trench digging channelling ", " tube group butt welding " staggered parallel operating type during laying task.Take the corresponding position of laying of single pipe as a pipe station, its sequence of operation is: first stringing, and post-trenching, the welding of forming a team of carrying out again single pipe forms pipeline section, then pipe section lowering in backfill, so staggered carrying out.It all is very rough that there is backfill in this operating type, does not have strict control, and tube wall is had larger infringement, and has strengthened the pipeline maintenance costs etc. in later stage and lack.
Summary of the invention
The purpose of this invention is to provide and a kind ofly according to the long geological condition along the line apart from convey coal pipe different environment is adopted different laying methods, to satisfy the pipe laying method of the long defeated coal of a kind of long-distance pipe apart from the convey coal pipe needs.
Long apart from the convey coal pipe needs in order to satisfy, technological scheme of the present invention is to solve like this: the pipe laying method of the defeated coal of a kind of long-distance pipe be pipeline is imbedded underground, make coal slurry effectively be transported to the destination by pipe safety, its pipe laying method is carried out in the steps below:
A, pipeline are embedded in below the frost line, the thickness of earth-fill cover 〉=1.0m of Guan Dingzhi nature terrace;
When B, gravel area pipe laying, the requirement 0.2m that backbreaks, bottom of trench must at first be laid the thick fine earth of 0.2m or fine sand bed course, can the swing pipe hyposulculus after smooth, during the gravel area backfilling of pipe canal, must at first be backfilled to the above 0.3m in pipe top with fine earth (sand), then can use former earthen backfill, the maximum particle diameter of fine earth backfill is not more than 10mm, and the gravel piece of backfill should be greater than 250mm;
C, Large River are worn two ends and the pipeline of leap and are put according to the geology condition bit along the line, at least five accident block valves and valve chamber are set, pipeline is when wearing the big-and-middle-sized river of leap, rain wash ditch, and the pipelining in the outer at least 50m of two ends border line should the mode identical with the B step be laid;
D, pipeline maximum are laid the gradient for testing the coal slurry drift angle that records, the minimum value of angle of repose;
E, pipe trench bottom of trench width are determined according to external diameter, process for assembling and welding and the engineering geologic factors of pipeline;
F, pipeline try not to occur elbow, bend pipe in through section when highway crossing; For the hillside of large slope, should establish diaphragm wall, retaining wall, crab-bolt, intercepting ditch, guarantee pipeline stabilization;
G, go out inbound, various leap two ends, pipeline fluctuation section at pipeline, the both sides of be unearthed end, the vertical elbow of wide-angle should establish and be fixed pier.
The present invention compared with prior art, because relating to, convey coal pipe of the present invention reaches 1000 kilometers, the topography and geomorphology that passes through along the line is complicated, different environment is adopted different laying methods, not only reduce in work progress the wearing and tearing to tube wall, and reduced in the coal slurry conveyed in pipeline process maintenance cost to pipeline.
Embodiment
Below in conjunction with embodiment summary of the invention is further described:
Embodiment 1
The pipe laying method of the defeated coal of a kind of long-distance pipe is pipeline to be imbedded underground, makes coal slurry effectively be transported to the destination by pipe safety, and the pipe laying method is carried out in the steps below:
A, pipeline are embedded in below the frost line, the thickness of earth-fill cover 〉=1.0m of Guan Dingzhi nature terrace;
When B, gravel area pipe laying, the requirement 0.2m that backbreaks, bottom of trench must at first be laid the thick fine earth of 0.2m or fine sand bed course, can the swing pipe hyposulculus after smooth, during the gravel area backfilling of pipe canal, must at first be backfilled to the above 0.3m in pipe top with fine earth (sand), then can use former earthen backfill, the maximum particle diameter of fine earth backfill is not more than 10mm, and the gravel piece of backfill should be greater than 250mm;
C, Large River are worn two ends and the pipeline of leap and are put according to the geology condition bit along the line, at least five accident block valves and valve chamber are set, pipeline is when wearing the big-and-middle-sized river of leap, rain wash ditch, and the pipelining in the outer at least 50m of two ends border line should the mode identical with the B step be laid;
D, pipeline maximum are laid the gradient for testing the coal slurry drift angle that records, the minimum value of angle of repose;
E, pipe trench bottom of trench width are determined according to external diameter, process for assembling and welding and the engineering geologic factors of pipeline;
F, pipeline try not to occur elbow, bend pipe in through section when highway crossing; For the hillside of large slope, should establish diaphragm wall, retaining wall, crab-bolt, intercepting ditch, guarantee pipeline stabilization;
G, go out inbound, various leap two ends, pipeline fluctuation section at pipeline, the both sides of be unearthed end, the vertical elbow of wide-angle should establish and be fixed pier.
But given embodiment can not be interpreted as limiting the scope of the invention, thereby nonessential improvement and adjustment that the professional and technical personnel has done according to content and the design philosophy of foregoing invention also should belong to protection scope of the present invention.
Claims (1)
1. the pipe laying method of the defeated coal of a long-distance pipe, the method are pipeline to be imbedded underground, make coal slurry effectively be transported to the destination by pipe safety, it is characterized in that the pipe laying method carries out in the steps below:
A, pipeline are embedded in below the frost line, the thickness of earth-fill cover 〉=1.0m of Guan Dingzhi nature terrace;
When B, gravel area pipe laying, the requirement 0.2m that backbreaks, bottom of trench must at first be laid the thick fine earth of 0.2m or fine sand bed course, can the swing pipe hyposulculus after smooth, during the gravel area backfilling of pipe canal, must at first be backfilled to the above 0.3m in pipe top with fine earth (sand), then can use former earthen backfill, the maximum particle diameter of fine earth backfill is not more than 10mm, and the gravel piece of backfill should be greater than 250mm;
C, Large River are worn two ends and the pipeline of leap and are put according to the geology condition bit along the line, at least five accident block valves and valve chamber are set, pipeline is when wearing the big-and-middle-sized river of leap, rain wash ditch, and the pipelining in the outer at least 50m of two ends border line should the mode identical with the B step be laid;
D, pipeline maximum are laid the gradient for testing the coal slurry drift angle that records, the minimum value of angle of repose;
E, pipe trench bottom of trench width are determined according to external diameter, process for assembling and welding and the engineering geologic factors of pipeline;
F, pipeline try not to occur elbow, bend pipe in through section when highway crossing; For the hillside of large slope, should establish diaphragm wall, retaining wall, crab-bolt, intercepting ditch, guarantee pipeline stabilization;
G, go out inbound, various leap two ends, pipeline fluctuation section at pipeline, the both sides of be unearthed end, the vertical elbow of wide-angle should establish and be fixed pier.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012103956944A CN102878351A (en) | 2012-10-18 | 2012-10-18 | Pipeline laying method of long-distance coal conveying pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012103956944A CN102878351A (en) | 2012-10-18 | 2012-10-18 | Pipeline laying method of long-distance coal conveying pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102878351A true CN102878351A (en) | 2013-01-16 |
Family
ID=47479797
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012103956944A Pending CN102878351A (en) | 2012-10-18 | 2012-10-18 | Pipeline laying method of long-distance coal conveying pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102878351A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103234078A (en) * | 2013-05-11 | 2013-08-07 | 中煤科工集团武汉设计研究院 | Laying method of long distance coal conveying pipeline at debris flow gully section |
CN103234077A (en) * | 2013-05-11 | 2013-08-07 | 中煤科工集团武汉设计研究院 | Protection method of long distance coal conveying pipeline at earthquake fault zone |
CN103244752A (en) * | 2013-05-11 | 2013-08-14 | 中煤科工集团武汉设计研究院 | Selection method of embedding modes of coal conveying pipeline when coal conveying pipeline crosses and spans rivers or gullies |
CN103322295A (en) * | 2013-05-11 | 2013-09-25 | 中煤科工集团武汉设计研究院 | Method for laying long-distance coal delivery pipeline and communication optical fiber cables in one ditch |
CN103322297A (en) * | 2013-05-14 | 2013-09-25 | 中煤科工集团武汉设计研究院 | Method for laying coal transporting pipeline and communication optical cable in same ditch across road through heavy excavation |
CN105387273A (en) * | 2015-12-10 | 2016-03-09 | 上海煤气第一管线工程有限公司 | Method for constructing natural gas pipelines in mountain environment |
CN111717604A (en) * | 2020-05-19 | 2020-09-29 | 中交第四航务工程局有限公司 | Method for setting water inlet section of land outbound track of large-diameter ultra-long HDPE pipeline |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1346950A (en) * | 2000-09-25 | 2002-05-01 | 株式会社韩美 | Method for filling protective layer of embedded tube |
RU2221954C1 (en) * | 2003-03-06 | 2004-01-20 | Мухаметдинов Харис Касьянович | Method of building technological crossing over obstacle (versions) |
CN1558129A (en) * | 2004-01-30 | 2004-12-29 | 胜利油田胜利石油化工建设有限责任公 | Construction method for river crossing pipeline |
CN102155583A (en) * | 2011-04-12 | 2011-08-17 | 中国十九冶集团有限公司 | Method and structure for laying ore pulp pipelines in sliding masses, collapse bodies and debris flow areas |
CN102434719A (en) * | 2011-08-28 | 2012-05-02 | 中国石油天然气集团公司 | Construction technology for hierarchical excavation and pipeline sinking |
-
2012
- 2012-10-18 CN CN2012103956944A patent/CN102878351A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1346950A (en) * | 2000-09-25 | 2002-05-01 | 株式会社韩美 | Method for filling protective layer of embedded tube |
RU2221954C1 (en) * | 2003-03-06 | 2004-01-20 | Мухаметдинов Харис Касьянович | Method of building technological crossing over obstacle (versions) |
CN1558129A (en) * | 2004-01-30 | 2004-12-29 | 胜利油田胜利石油化工建设有限责任公 | Construction method for river crossing pipeline |
CN102155583A (en) * | 2011-04-12 | 2011-08-17 | 中国十九冶集团有限公司 | Method and structure for laying ore pulp pipelines in sliding masses, collapse bodies and debris flow areas |
CN102434719A (en) * | 2011-08-28 | 2012-05-02 | 中国石油天然气集团公司 | Construction technology for hierarchical excavation and pipeline sinking |
Non-Patent Citations (2)
Title |
---|
曾多礼: "复杂地域条件的管道改线实践", 《管道技术与设备》 * |
黄志刚: "关于煤浆管线设计与研究的几个问题", 《油气管道技术》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103234078A (en) * | 2013-05-11 | 2013-08-07 | 中煤科工集团武汉设计研究院 | Laying method of long distance coal conveying pipeline at debris flow gully section |
CN103234077A (en) * | 2013-05-11 | 2013-08-07 | 中煤科工集团武汉设计研究院 | Protection method of long distance coal conveying pipeline at earthquake fault zone |
CN103244752A (en) * | 2013-05-11 | 2013-08-14 | 中煤科工集团武汉设计研究院 | Selection method of embedding modes of coal conveying pipeline when coal conveying pipeline crosses and spans rivers or gullies |
CN103322295A (en) * | 2013-05-11 | 2013-09-25 | 中煤科工集团武汉设计研究院 | Method for laying long-distance coal delivery pipeline and communication optical fiber cables in one ditch |
CN103322297A (en) * | 2013-05-14 | 2013-09-25 | 中煤科工集团武汉设计研究院 | Method for laying coal transporting pipeline and communication optical cable in same ditch across road through heavy excavation |
CN105387273A (en) * | 2015-12-10 | 2016-03-09 | 上海煤气第一管线工程有限公司 | Method for constructing natural gas pipelines in mountain environment |
CN111717604A (en) * | 2020-05-19 | 2020-09-29 | 中交第四航务工程局有限公司 | Method for setting water inlet section of land outbound track of large-diameter ultra-long HDPE pipeline |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102878351A (en) | Pipeline laying method of long-distance coal conveying pipeline | |
Lin et al. | Key techniques and important issues for slurry shield under-passing embankments: A case study of Hangzhou Qiantang River Tunnel | |
CN102913250A (en) | Shield tunnel-entering construction method at stratum rich in water powder and soil powder sand | |
Hou et al. | Excavation failure due to pipeline damage during shallow tunnelling in soft ground | |
CN105821909A (en) | Tree-like refuse leachate generated in landfill construction and closure as well as landfill gas guide and exhaust system and method | |
CN104455726A (en) | Pipe-jacking construction method for pipeline bottom grouting reinforcement | |
CN104895173A (en) | Sandy soil buried corrugated pipe subsidence prevention method | |
CN110454223A (en) | Counter-slope TBM tunnels tunnel drainage construction method | |
CN109853702A (en) | Cast-in-place concrete cable conduit construction method | |
CN104533426A (en) | Method for constructing ultra-shallow buried tunnel under-passing highway by large-span covering excavating method | |
CN104594379B (en) | Between rail yard interior lines, be incubated culvert pipe system and burial and construction method | |
CN104929141B (en) | Town road passes through the construction method of river embankment or irrigation canals and ditches | |
CN109812271A (en) | A kind of shield crosses the construction method for invading limit box culvert | |
CN204099720U (en) | The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used | |
CN107401181B (en) | A kind of municipal network system and construction method | |
CN110273424A (en) | A kind of construction method of yard piping | |
CN107724499A (en) | The construction method and pedestal of sewage conduct | |
CN104315251B (en) | Artificial pipe jacking construction method under soil stone combination geological conditions | |
CN105804203A (en) | Plugging method of deep-buried large-diameter waste water pipeline | |
CN109119943A (en) | System of laying optimization method of the cable at push pipe both ends | |
CN109113092A (en) | Construction method is protected in underground large-diameter pipeline original position water flowing | |
CN202451974U (en) | Anti-floating structure of buried pipeline | |
CN101922586A (en) | Method for installing outdoor process pipelines | |
CN105133719A (en) | Construction method for quickly solving sand leakage and gushing caused by dislocation of rain pipes | |
CN208088336U (en) | A kind of installation of gas pipeline structure of combination pipe gallery construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130116 |