CN1239796C - Building structural element - Google Patents

Building structural element Download PDF

Info

Publication number
CN1239796C
CN1239796C CNB028112539A CN02811253A CN1239796C CN 1239796 C CN1239796 C CN 1239796C CN B028112539 A CNB028112539 A CN B028112539A CN 02811253 A CN02811253 A CN 02811253A CN 1239796 C CN1239796 C CN 1239796C
Authority
CN
China
Prior art keywords
edge
floor
structural element
building
cementitious material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB028112539A
Other languages
Chinese (zh)
Other versions
CN1524149A (en
Inventor
N·包那西
S·G·罗西特
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BONACCI GROUP Pty Ltd
Original Assignee
BONACCI GROUP Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AUPR5481A external-priority patent/AUPR548101A0/en
Application filed by BONACCI GROUP Pty Ltd filed Critical BONACCI GROUP Pty Ltd
Publication of CN1524149A publication Critical patent/CN1524149A/en
Application granted granted Critical
Publication of CN1239796C publication Critical patent/CN1239796C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/29Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated the prefabricated parts of the beams consisting wholly of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • E04C3/26Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Building Environments (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

A building structural element (1) having a pair of beams (5) joined by a plate member (13) or alternatively a generally U-shaped channel having a pair of opposed side walls (33, 34) joined by a further portion (35). In either case an interior space (57) is defined by either the pair of beams (5) and plate member (13) or by the pair of side walls (33, 34) and the further portion (35). A cementitious material, such as concrete, occupies a substantial volume of the interior space (57) and the building structural element (1) has a post-tensioned pre-stressing force applied thereto.

Description

Structural element of building and preparation method thereof
Technical field
The present invention relates to the structural element of a building and the method for making the fabric structure member.Specifically, the present invention relates to be used for the structural element of the intrasystem building of building floor and the method for making such member.
The present invention also can be used for many other building occupancies, for example, and the ceiling lid above highway tunnel, railroad track etc.It can be used for large-scale multispan floor space, particularly the layer with layer between the size height and/or along the large span of one or two direction and/or such as the high floor space of floor load on the floor that is used for retail business, show business or other purposes.It also can be used for bridge floor and large span and/or any other purposes that must the carrying top load between supporting.
Of the present invention one special aspect relates to the floor joist of the construction that is used for the building floor system, and is preferably made by two kinds of unit construction spares, is preferably made by steel and the cementitious material such as concrete.
Background technology
For the floor system of the building of span, require to have beam usually above 8 to 10 meters.Above-mentioned span generally is that it(?) can not need use beam and extend the upper bound scope or the limit value of floor for structure support.Common 6 to 9 meters at interval of bearing post, wherein common spacing is 8.4 meters.This is a kind of suitable office building module, it holds the width that a post adds three spaces, described space can be used for vehicle parking between two adjacent post, and can be used as the following any layer of parking of office's floor (or retail business floor floor, mechanism's floor floor or other floor) of building.Require Zhuliang between the grid of four posts or between a pair of column jacket of the nuclear core of a building and a tier building or centre portion outward, come bigger yardstick across a rectangle floor.The nuclear core is commonly used to hold enterable other the public space of people on elevator shaft and each aspect.Can and can be many kinds of forms really across the floor system between these beams, it depends on drawing materials on the spot, economy and owner, engineer or builder's preference, or a kind of combination of either party preference among the above-mentioned three parts.
Be about 8 meters floor system along the span of a direction between supporting beam, the form of its various variations has: on traditional template or the concrete slab that forms on the big platform mould, concrete slab on metal bracket, these metal brackets are supported on supporting, the close steel secondary beam at center (2.1 to 3.0 meters) temporarily, and secondary beam is at the plate of unsupported metal bracket template upper support relative thin.Also have some other dedicated system such as various prestressing force slab system, they can cross over 7 to 8 meters distances of not having supporting.
For supporting beam, the upper range that is suitable for the shallow hoop beam of steel concrete is about 10 to 12 meters.For prestressed shallow hoop beam (normally post tensioning), the upper range of applicability is generally 12 to 14 meters.Yet, for the span that surpasses 12 to 14 meters, needing special concern and pay attention to details, common solution is steel floor joist or prestressed concrete floor slab beam.
In steel floor joist system, it is 2.1 to 3.0 meters girder steel that a series of center distance are arranged, and their cross over the bigger distance of rectangle floor level arrangement diagram, and by crossing over more short-range " master " beam support between the bearing post.The specific question that most of engineer or designer faced is in the system that uses floor joist, to require to reduce each beam because the amount of flexibility that static load or mobile load or both combinations cause.The unnecessary large deflection of floor system and vibration can influence the suitability of floor.
Adopt the steel floor joist system that uses at present, disadvantageously, each beam needs firm connection in its supporting place.Beam and junction require usually to apply protectiveness coating so that its can prevent fires.Although can make the floor combinations of this steel floor joist and the relative thin that supports with the shearing short column, because concrete and shear the creep at short column interface place exists a component little, that constantly develop of static deflection.The amount of deflection great majority of the girder steel that is caused by static load take place once doing the time spent in load, and can allow the pre-arch camber of beam to offset.Yet,,, little because the ratio of rigidity of combined girder steel is used for the rigidity of the reinforced concrete beam of identical span or prestressed concrete beam especially for beam than large span because amount of deflection that the mobile load of transient state causes and vibration remain an intrinsic problem.
At present the floor joist system of general other type of using have post tensioning, prestressed concrete floor slab girder system system.They comprise the concrete beam with dark depth-width ratio, in other words, the size of concrete beam be its height greater than its width, and surpass 10 meters beam for span, these concrete beam are generally prestressed.The plate that support concrete beam and they is cast-in-place.Then, realize prestressing force by the post tensioned steel bundle (tendon) of stress application when concrete is being poured into a mould the intensity that has reached enough in 3 to 6 days usually.Concrete beam and adjacent plate form on big platform template usually, and these platform template rise to another floor by crane from a floor.Usually adopt two group platforms, keep the circulation of the floor in preferable about week, in half floor zone cast, provide the work continuity of other various operations.Except the cage of reinforcement (it can comprise or not comprise prestressed reinforcement) of beam, the possibility of prefabricated component is arranged seldom.Any prefabricated cage of reinforcement needs to support the jail well and be placed on the support, so that can be hung in the template of beam by crane.In general, when concrete is connected to beam on the bearing post, the connection that does not have difficulties in supporting place of beam.When a cast-in-place concrete beam is bearing in the concrete nuclear core of " having skipped formation " before the main building plate, this connection can be a simple rebate in the wall of concrete nuclear core, is screwed in the hoop that is anchored at concrete nuclear in-core at the top of beam and the reinforcing bar of bottom.Perhaps, beam may be seated in the depression of staying in the concrete heart wall.
The rigidity that the ratio of rigidity of prestressed concrete floor slab system is crossed over the required steel floor joist system of same distance is big, therefore, is difficult for taking place because of caused vibration of floor of transient load and deflection.Yet, when creep takes place in concrete under the sustained load effect, deflection that floor system takes place increase after floor is occupied, its reason not only is the partition of mobile load and lightweight, and is the significant amount of deflection share that caused by static load because of creep component.The most amount of deflection that but the prestressing force balance is a static load to be caused.Yet, because axial prestress gives beam permanent axial force,, can cause prestressed forfeiture because of the shortening that forms in time, this will cause the further deflection of beam to increase.
Summary of the invention
An object of the present invention is to provide the structural element of a building, it overcomes above-mentioned one or more shortcomings basically.Specifically, the invention provides the structural element of a building, it has minimum amount of deflection, and keeps axial prestressing force wherein basically, and reduces because as this prestressed forfeiture that causes of the axial creep that makes the beam shortening of system in the prior art.
According to a first aspect of the invention, provide the structural element of a building, it comprises:
A pair of beam, each beam in described paired beam have one first edge of a wing part, one second edge of a wing part and a web part of extending between described first edge of a wing part and described second edge of a wing part;
One plate, it is suitable for engaging with part in described first edge of a wing part of each beam or described second edge of a wing part, like this, formation one volume inside in each beam in described paired beam and the described plate;
Wherein, material occupies the main volume of described inner space like the cement, and forming the fabric structure member of a non-integral, and after applying the prestressing force of post tensioning, under action of static load, the structural element of described building has remaining amount of deflection or do not have amount of deflection.
The structural element of building also can comprise one or more reinforcing bar that extends along the length of inner space, and described space is formed on each beam and can is between the described plate of metal bracket form soffit.Each one or more reinforcing bar can apply prestressing force, with provide one offset a part of static load upward to power.After each end was fixing, first edge of a wing part of each beam can support the part of floor span at structural element.Normally, structural element can extend between the nuclear core of a post and a building.Structural element can stop in one short distance of freestone core with from post one short distance, perhaps go out to stop in of the short distance of each end from a post, and in its end, also can also temporarily be bearing on the scaffold at the span centre place.
Each beam preferably is made of the metal such as steel, and cementitious material is preferably concrete.
According to a second aspect of the invention, provide the structural element of a building, it comprises:
The web part that a pair of beam, each beam in described paired beam have the edge of a wing, top part, bottom edge of a wing part and extend between described top edge of a wing part and the edge of a wing, described bottom part;
One plate, its be suitable for described paired beam in the corresponding edge of a wing, the bottom part of each beam engage, like this, form a volume inside in each beam in described paired beam and the described plate;
Wherein, cementitious material occupies the main volume of described inner space, and to form the fabric structure member of a non-integral, after applying the prestressing force of post tensioning, under action of static load, the structural element of described building has remaining amount of deflection or do not have amount of deflection.
Plate can be a metal bracket form soffit, or other suitable horizontal soffit surface.
According to a third aspect of the invention we, provide the structural element of a building, it comprises:
One slot device that roughly takes the shape of the letter U, it has a pair of relative sidewall and another part that connects each sidewall;
Wherein, described paired relative sidewall and another part form an inner space; And
Wherein, cementitious material occupies the main volume of described inner space, to form the fabric structure member of a non-integral in this slot device, after applying the prestressing force of post tensioning, under action of static load, the structural element of described building has remaining amount of deflection or does not have amount of deflection.
According to a forth aspect of the invention, provide a method of making the fabric structure member, it comprises following all steps:
Construct a pair of beam, each beam in described paired beam comprises one first edge of a wing part, one second edge of a wing part and a web part of extending between described first edge of a wing part and described second edge of a wing part;
Form and assemble a plate so that in described first edge of a wing part of plate and each beam or described second edge of a wing part one partly engage, like this, form a volume inside by described paired beam and plate; And
Cementitious material is poured into described inner space, to form the fabric structure member of a non-integral, like this, and after described cementitious material sclerosis and applying the prestressing force of post tensioning, under action of static load, the essentially no amount of deflection of the structural element of described building.
The step of cast can be carried out individually, or as a part of pouring into a mould the adjacent floor span that structural element supported.Structural element can utilize possible extra supporting along span, and originally its end is bearing on the temporary transient supporting construction of permanent overhang bracket of contiguous beam.
Description of drawings
In the mode of example preferred embodiment of the present invention is described below with reference to accompanying drawings, in all accompanying drawings:
Fig. 1 is the plan view of the part of the building floor system of extending between an edge of the nuclear core wall of a building and building;
Fig. 2 resolves into Fig. 2 A and 2B, is the side cross-sectional, view along the line A-A intercepting of Fig. 1;
Fig. 3 be along the line B-B of Fig. 2 intercepting, in use the sectional view of structural element according to an embodiment of the invention;
Fig. 4 is the sectional view along line C-C structural element intercepting, in use of Fig. 2;
Fig. 5 is similar to Fig. 3 and according to the sectional view of the structural element in use of another embodiment;
Fig. 5 (a) to 5 (d) be the lateral view of structural element among Fig. 5, the independent various situations of structural element are shown;
Fig. 6 is the sectional view that is similar to another embodiment of Fig. 4 structural element in use;
Fig. 7 illustrates the side cross-sectional, view that is applied to a tunnel structure of cover plate member;
Fig. 8 is the lateral view of the prefabricated structural element of a prior art; And
Fig. 9 illustrates the plan view and the lateral view of the structural element that traverses a floor span that has time supporting beam.
The specific embodiment
Shown in Figure 1 is the plan view of a pair of structural element 1, and each structural element extends to nuclear core wall 3 in the building core from the side column 2 on building one outward flange.The length that the span of each structural element is extended is 18 meters and above 18 meters, and the spacing between each member 1 depends on the distance between each side column, as discussed previously, this spacing is equivalent to adapt to the space that is used for vehicle in three parking tiers below office's floor, and this spacing can be arbitrary distance in 6 to 9 meters usually.Between side column 2, extend a side bar 16, and floor 4 extends between two adjacent members 1.Side bar 16 can comprise the girder steel of an inside, and it just terminates on the side less than side column 2, and like this, not needing has being connected of any essence with post 2, and is bearing on the same external support frame 19 of this supporting main structural member 1.The steel of side bar 16 part overarches in advance bearing static load, so that along the amount of deflection minimum at the edge of building, this amount of deflection can influence the glass assembling of any facade.Should be noted that in Fig. 1,, can use supporting one to specify the needed any amount of beam in floor zone although two beams only are shown.
With reference to Fig. 3 and 4, member 1 is made of a shell basically, and shell is made by steel usually, and it comprises first and second (side shell) beam 5, and it is I-beam shape, has a web part 30, and there are first and second edge of a wing parts 31 and 32 in 30 two ends in the web part.What extend in the bottom of member 1 is a plate 13 (or forming the Bracket Type soffit), and it is made of metal usually, specifically, make by steel, thus, it extends between each bottom or second edge of a wing part 32 of side shell beam 5, and adheres to or otherwise engage with edge of a wing part 32.Be used to obtain and be poured into the mass action of the cement material in the inner space 57 of the shell that forms by each beam 5 and plate 13 from the web part 30 extended shearing short columns 12 of side shell beam 5.The lashings 23 of the form that roughly takes the shape of the letter U extends downwardly in the inner space 57 in floor 4, and the rib that rises of the height by plate 13.This also can be used as the extra supporting to the cementitious material that is poured into shell inside.In addition, reinforcing bar 24 also is arranged in the member 1.One closure member or distance piece 15 also are positioned in the floor 4, with the colligation of cage structure to side shell beam 5.Prestressing tendon member 10 quantitatively has some, will be introduced with reference to Fig. 2 below.
Should be noted that, paired beam 5 and be used for carrying out in the production line environment of the control that the various reinforcing bars of beam can be outer at the scene prefabricated, and with its reinforcing bar 24 and lashings 23, prestressing tendon member 6,8 and 10 and support 15 that all steel tendon members are remained on the certain position be transported to the scene.Tendon member 6 is the dead end anchorings that are used for one of tendon 10, and tendon member 8 is the pressurized metal forms that comprise movable end anchoring depression.Be used to carry two steel side shell beams 5 that are connected with the support 25 that transmits, the whole assembly of 18 meters the beam that is about 4.5 tons usually is provided on the building site, and with a simple method for improving, its two ends are in place on default scaffold, scaffold is represented with label 18 and 19, and is provided with scaffold 20 at span centre.
With reference to Fig. 2, nuclear core wall 3 places at building, member 1 can be received the rebate 22 that becomes to be adjacent in the wall 3, and single reinforcing bar 14 and 17 is screwed in the hoop 21, hoop 21 is for top and bottom arrangement of reinforcement connecting portion have been embedded in the nuclear core wall 3 of the form of jumping out (jump form), so that difference connecting reinforcement 14 and 17.At the other end of beam, desired with being connected of column jacket 2 is that the reinforcing bar 14 of connection and 17 extend throughs are by the length of the surface requirements of post 2.These reinforcing bars 14 and 17 are only reinforcing bars that need fixed in place of member 1 together with the beam lashings of locating in the end of member 1 11.
Can comprise little (diameter the reaches 150mm) through hole that is used for fire-fighting spraying pipe, soil pipe etc. although pass the web of member 1, but each end of each beam can be become step-like, only need raise the edge of a wing, the bottom part 32 of each steel side shell beam 5, can hold any main common conduit net, and can not strike the height of ceiling.This can clearly show that in Fig. 2, and wherein, step shown in the figure 7 causes space 9 between step and nuclear core wall 3 or the post 2 that a space that is used for such common conduit net (if necessary) is provided.This step also allows to hold activity or the stretch-draw end that is used for one or more prestressing tendons 10.Described tendon 10 is being to carry out post tensioning at the scene, and can comprise any quantity on request, in the inner space between each steel side shell beam 5.A prestressing tendon that is shown among Fig. 2 extends in the edge of a wing, the bottom part 32 between step 7, shown other prestressing tendon 10 extends on the total length of beam, and have one and dangle, in other words, apply prestressing force in recessed mode, the purpose of doing like this provides a power of upwards carrying or a component, its offsets 50% to 100% power of total static load, usually approximately 50-60% is enough for these beams, remaining static load that is provided by the box hat and the cementitious material of precast beam and the ability of transient load.Static load is considered to comprise the weight of floor itself, beam, and the load of the permanent stack such as ceiling surface and floor topping.Two steel side shell beam 5 usually pre-arch cambers like this, in case remove interim support, have then been contained all amounts of deflection that caused by static load.In fact, steel side shell beam 5, prestressing tendon and be filled into concrete core in the inner space of paired beam 5 interact together and bear full payload.Yet, beam 5 and prestressing tendon prevent to join the load that the tendon member bears any important share basically, and in beam deflection before the level, because prestressing tendon adds that the steel side shell beam 5 that arches upward in advance can bear total static load therebetween, so, can not allow concrete generation creep resolutely.
In use, as mentioned above, before construction steel side shell beam 5, shear outer at the scene making of reinforcing bar of short column and prestressing tendon 10 and most of beam, reinforcing bar 14,17 and the lashings 11 that is connected to the end are then made at the scene.Then, member 1 is placed in its interim supporting, just less than nuclear core rebate 22 within the walls, at other end place then just less than post.Then reinforcing bar 14 and 17 is placed in the hoop separately, and after this lashings 11 together with place at the scene, carries out the cast of floor, so that cementitious material or general concrete are poured into floor slab structure, allow to be filled in the main volume of the inner space 57 in the steel side shell beam 5.By with concrete pouring between the girder steel and on the girder steel, also act at first integratedly by the combination of 12, two steel sides of shearing short column shell beam 5 on the inboard of each web 30 that is welded to beam 5 in the factory and hydraulicity (concrete) material.
Therefore, two steel side shell beams 5 increase the content of the axial steel of compound beam significantly, and under the effect of prestressing force load, compound beam rises makes a compression piece, and like this, any loss of prestress that causes owing to the axial creep that beam is shortened will be minimum.Then, this hybrid beam structure also can not have the combined deflection that is caused by static load, and perhaps, before transient load, it can be provided with the remnants that make progress slightly and arch upward.Can assist other two ingredients as all the other firm concrete beam of cracking part not, and its amount of deflection increases owing to mobile load and any other transient load.
Because originally column jacket does not support any floor 4 and member 1, so floor 4 and member 1 and post 2 can be in cast on the same day.Post 2 can be poured into a mould, and the arrangement of reinforcement of the floor 4 between slab form and the hybrid component 1 is installed simultaneously.Can imagine to possess well-organized good labour, by pouring into a mould the floor of half in first day, poured into a mould second half in second day, the 3rd day preparation post and promote the baffle plate etc. of circumference, even big floor zone, three days or even less than the floor circulation can realize with following the prescribed order.
The concrete of member 1 is partly shared, and the fire prevention of taking to simplify in Australia designs, and the load-bearing state is 0.4 times that 1.1 of static load extraordinarily goes up mobile load, adopts similarly numeral in other country.Therefore, if in fact this can provide a solution, then need not carry out fire-resistant protection or complicated anti-firer's journey analysis.The combination ability of steel and prestressed concrete beam more is enough to carry service load, in Australia, service load normally static load 1.25 extraordinarily go up 1.5 times of mobile load, adopt similarly numeral in other country.
The amount of deflection limit value that most of standard is set the corresponding amount of deflection that increases is made as 1/500 of span, and the amount of deflection of this increase refers to because any creep component of static load adds because mobile load adds the amount of deflection that the weight of partition causes.Therefore, for 18 meters spans, this limit value is 36 millimeters.For having any building that is parallel to and is adjacent to the big inside span on the building limit, this contiguous floor (wherein amount of deflection is zero) and obviously too big near the amount of deflection phase residual quantity between the amount of deflection of the span centre at built in beam place (can be close to 2.5 meters) for girder steel floor system built in beam at the post on the building limit.The amount of deflection standard severeer than standard is necessary.The present invention can realize that by the steel and the concrete beam of its mixing for 18 meters span, the maximum amount of deflection that increases progressively is about below 20 millimeters.
With reference to Fig. 5 and 6, another embodiment of the present invention is shown, wherein, structural element 1 is made by a single overall structure or an integrated structure.Specifically, replace as first embodiment by a pair of relative beam of plate connection, the present embodiment in all accompanying drawings has a capable groove of U roughly, its by pair of sidewalls 33 with 34 and the bottom 35 that is connected each sidewall 33 and 34 form.Preferably, this structure is made by steel.Sidewall 33 and 34 top have edge of a wing part 36 and 37 respectively, are used for the floor 4 of supporting part.
With reference to Fig. 5 (a) and (b), (c) and (d), structural element can be made by the steel plate of single-piece, for example, utilizes four knuckles (not adopting welding) at 38,39,40 and 41 places shown in Fig. 5 (a).Perhaps, shown in Fig. 5 (b), provide two plated constructions, this structure can be welded at point 42 places, and keeps four knuckles of 38 to 41.In Fig. 5 (c), a structure that changes of structural element is shown, keep knuckle 38 and 41, but weld at point 43 and 44 places, one or three plated constructions are provided.At last, in Fig. 5 (d), can use five steel plates, not have knuckle, at point 45,46,47 and 48 places four weld seams be arranged as shown in the figure.
Adopt more shallow side shell girder steel, utilize or do not utilize prestressing tendon, and have or do not have recess at the place, bottom of the end of beam and hold Your Majesty's grid altogether, the present invention also can be used for short span.
For the shallow like this beam that does not have common conduit step (two stress anchor point), adopt in the situation of prestressed tendon, then can be after tendon apply prestressing force and grouting, anchoring can apply prestressing force in the rebate cave in the top of the floor of pouring into a mould thereafter.
With reference to Fig. 7, as mentioned above, adopt " cutting and covering " method, the present invention is applicable to highway tunnel.This relates to each structural element and promotes the problem that puts in place, and these structural element have been provided with reinforcing bar and prefabricated component on certain position, and adopts the crane of the ability of low relatively load.This forms contrast with the extremely heavy prestressed concrete beam 49 of precoating that is used for prior art systems, and it is shown among Fig. 8.Precoat prestressed girder 49 of heavy type needs to use extremely big crane promote such member.With reference to Fig. 8, beam 49 has the edge of a wing 50 and the top board 51 of the relative thin that is used for this application.Usually need waterproofing course or adopt the film 52 of waterproof on the gamut plate, it requires the plate 53 of protection wearing and tearing again.Adopt the present invention, can use the integrated poured of watertight, then save all these.Back with reference to Fig. 7, this relates to the employing fluid blocking device, and specifically, equipped sealing sheet 58 and local waterproofing course 54 (or film of employing waterproof) are to guarantee the watertightness of tunnel ceiling.The span of the floor between structural element 1 can be sufficiently thick, and with the suitable dimensions step pouring, if necessary, apply prestressing force between control joint 56.Sealing sheet 53 and local waterproofing course or film 54 are fitted into each control joint 56.
With reference to Fig. 9, as mentioned above, the present invention is also applicable to large-scale multispan floor space, especially high floor and floor yardstick and/or along the large span of one or two direction and/or such as the situation of the high floor load on the floor that is used for retail business, show business or other purposes.Building member 1 can be used to across between the post 59 of secondary beam 60 bolts, with the floor between the supporting construction member 14.
In building course, only need be bearing between the post mobile load when this structural element just can be made the deadweight of crossing over floor slab structure and adds construction simply.
Then, structural element forms steel concrete or prestressed concrete member, and it is Multispans continuous for need by the load that floor supports.

Claims (40)

1. the structural element of a building, it comprises:
The web part that a pair of beam, each beam in described paired beam have one first edge of a wing part, one second edge of a wing part and extend between described first edge of a wing part and described second edge of a wing part;
One plate, it is suitable for engaging with part in described first edge of a wing part of each beam or described second edge of a wing part, like this, formation one volume inside in each beam in described paired beam and the described plate;
Wherein, cementitious material occupies the main volume of described inner space, and forming the fabric structure member of a non-integral, and after applying the prestressing force of post tensioning, under action of static load, the structural element of described building has remaining amount of deflection or do not have amount of deflection.
2. member as claimed in claim 1 is characterized in that, also comprises the reinforcing bar that one or more extends along the length of described inner space.
3. member as claimed in claim 2 is characterized in that, described one or more reinforcing bar respectively applies prestressing force, with provide one offset described static load a part upward to power.
4. member as claimed in claim 1 is characterized in that, it is used for supporting the large span floor zone in the building.
5. member as claimed in claim 4 is characterized in that, described first edge of a wing part of each beam supports the part of the floor span in the described building.
6. member as claimed in claim 5 is characterized in that, an end of described member is fixed on the post of described building, and the other end of described member is fixed on the nuclear core of described building.
7. member as claimed in claim 6 is characterized in that, before each end of fixing described member, described member temporarily is bearing on the scaffold of described each end of described member.
8. member as claimed in claim 1 is characterized in that, member has one or more described web parts in each described beam and extends to shearing short column the described inner space, to become whole with described cementitious material.
9. member as claimed in claim 1 is characterized in that, the supporting arrangement that is the lashings form extends to described inner space, to support described cementitious material.
10. member as claimed in claim 1 is characterized in that, also comprises the many reinforcing bars that extend along the part of described member.
11. member as claimed in claim 10 is characterized in that, the described other end of described member holds in the rebate of the described nuclear in-core that abuts against described building.
12. member as claimed in claim 11 is characterized in that, other hoop device that is formed on described nuclear in-core is fixed on indivedual reinforcing bars of described many reinforcing bars.
13. member as claimed in claim 1 is characterized in that, respectively holding into of described each beam is step-like to hold common conduit.
14. member as claimed in claim 1 is characterized in that, each the beam metal construction in described paired beam.
15. member as claimed in claim 1 is characterized in that, described cementitious material is a concrete.
16. a fabric structure member, it comprises:
One slot device that roughly takes the shape of the letter U, it has a pair of relative sidewall and the another part that is connected each sidewall;
Wherein, described paired relative sidewall and described another part form an inner space; And
Wherein, cementitious material occupies the main volume of described inner space, with the fabric structure member of formation one non-integral in this slot device, and after applying the prestressing force of post tensioning, under action of static load, the structural element of described building has remaining amount of deflection or does not have amount of deflection.
17. member as claimed in claim 16 is characterized in that, member has and one or morely extends to the shearing short column of described inner space from one of each described sidewall, to become whole with described cementitious material.
18. member as claimed in claim 16 is characterized in that, the supporting arrangement that is the lashings form extends to described inner space, to support described cementitious material.
19. member as claimed in claim 16 is characterized in that, also comprises the reinforcing bar that one or more extends along the length of described inner space.
20. member as claimed in claim 19 is characterized in that, described one or more reinforcing bar respectively is prestressed, with provide one offset described static load a part upward to power.
21. member as claimed in claim 16 is characterized in that, each described sidewall has an edge of a wing part of extending from the free end of each sidewall, the part of described edge of a wing part supporting floor.
22. member as claimed in claim 16 is characterized in that, each end of described member is fixed on the supporting construction.
23. member as claimed in claim 22 is characterized in that, before each end with described member was fixed to described supporting construction, described member temporarily was bearing on the scaffold of described each end of described member.
24. member as claimed in claim 16 is characterized in that, also comprises the many reinforcing bars that extend along the part of described member.
25. member as claimed in claim 24 is characterized in that, at least one end in the two ends of described member holds in the rebate that abuts against in the described supporting construction.
26. member as claimed in claim 25 is characterized in that, other hoop device that is formed in the described supporting construction is fixed on indivedual reinforcing bars of described many reinforcing bars.
27. member as claimed in claim 16 is characterized in that, respectively holding into of described each beam is step-like to hold common conduit.
28. member as claimed in claim 16 is characterized in that, described groove textural be whole.
29. member as claimed in claim 16 is characterized in that, described slot device is made of the joint of one or more connection neighbouring parts.
30. member as claimed in claim 16 is characterized in that, described slot device is made of metal.
31. member as claimed in claim 16 is characterized in that, described cementitious material is a concrete.
32. member as claimed in claim 16 is characterized in that, described floor has fluid blocking device, is fluid-tight to guarantee described member.
33. member as claimed in claim 32 is characterized in that, described fluid blocking device comprises a fluid block piece and an anti-fluid film.
34. a fabric structure member, it comprises:
The web part that a pair of beam, each beam in described paired beam have the edge of a wing, top part, bottom edge of a wing part and extend between described top edge of a wing part and the edge of a wing, described bottom part;
One plate, its be suitable for described paired beam in the corresponding edge of a wing, the bottom part of each beam engage, like this, form a volume inside in each beam in described paired beam and the described plate; And
Wherein, cementitious material occupies the main volume of described inner space, and forming the fabric structure member of a non-integral, and after applying the prestressing force of post tensioning, under action of static load, the structural element of described building has remaining amount of deflection or do not have amount of deflection.
35. structural element as claimed in claim 34 is characterized in that, described plate is a soffit.
36. structural element as claimed in claim 35 is characterized in that, described soffit is the soffit of a metal bracket form.
37. a method of making the fabric structure member, it comprises following all steps:
Construct a pair of beam, each beam in described paired beam comprises one first edge of a wing part, one second edge of a wing part and a web part of extending between described first edge of a wing part and described second edge of a wing part;
Form and assemble a plate so that in described first edge of a wing part of plate and each beam or described second edge of a wing part one partly engage, like this, form a volume inside by described paired beam and described plate; And
Cementitious material is poured into described inner space, to form the fabric structure member of a non-integral, like this, and after described cementitious material sclerosis and applying the prestressing force of post tensioning, under action of static load, the essentially no amount of deflection of the structural element of described building.
38. method as claimed in claim 37 is characterized in that, described cast step comprises the described cementitious material of cast as the part of floor, with the same step of adjacent floor in, be poured into described inner space.
39. method as claimed in claim 37 is characterized in that, described cast step comprises the described cementitious material of cast constructing a floor, and described cast is separately carried out for the cast step in the described floor of structure.
40. as any one described method in the claim 37 to 39, it is characterized in that, also comprise when beginning with the overhang bracket of described structural element on the temporary transient supporting construction of the permanent overhang bracket of contiguous described structural element.
CNB028112539A 2001-06-05 2002-06-04 Building structural element Expired - Fee Related CN1239796C (en)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
AUPR5481A AUPR548101A0 (en) 2001-06-05 2001-06-05 Building structural element
AUPR5481 2001-06-05
AU11941/2002 2002-01-18
AU11941/02 2002-01-18
AU11941/02A AU754130B1 (en) 2001-06-05 2002-01-18 Building structural element

Publications (2)

Publication Number Publication Date
CN1524149A CN1524149A (en) 2004-08-25
CN1239796C true CN1239796C (en) 2006-02-01

Family

ID=25614666

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB028112539A Expired - Fee Related CN1239796C (en) 2001-06-05 2002-06-04 Building structural element

Country Status (7)

Country Link
US (1) US20040182027A1 (en)
CN (1) CN1239796C (en)
AU (1) AU754130B1 (en)
BR (1) BR0210182A (en)
CA (1) CA2448629A1 (en)
NZ (1) NZ529942A (en)
WO (1) WO2002099215A1 (en)

Families Citing this family (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2002951787A0 (en) * 2002-10-02 2002-10-17 University Of Western Sydney A composite beam
KR20060024850A (en) * 2004-09-15 2006-03-20 삼성물산 주식회사 Steel-concrete sandwitch type hybrid beam and high strength hybrid structure system using the same
US20070028541A1 (en) * 2005-08-02 2007-02-08 Mark Joseph Pasek Prefabricated shell concrete structural components
US20100242403A1 (en) * 2007-10-24 2010-09-30 Western Forms, Inc. Multiple dimension beam, deck and column system
FR2925088B1 (en) * 2007-12-18 2014-12-26 Soc Civ D Brevets Matiere METHOD FOR PRODUCING AN ARMED CONCRETE BUILDING ELEMENT AND CONSTRUCTION ELEMENT THUS PRODUCED
CN101899877B (en) * 2009-05-19 2014-07-16 柳忠林 Small simulate framework structure of long-span prestress concrete girder slab
CN201962792U (en) * 2010-03-03 2011-09-07 柳忠林 Longspan prestressed concrete beam slab simulation framework structure
FI20145669A (en) * 2014-07-11 2016-01-12 Peikko Group Oy Steel beam
KR101567741B1 (en) * 2015-02-16 2015-11-09 권용근 Composite beam having truss reinforcement embedded in concrete
DE202015104628U1 (en) 2015-09-01 2016-12-05 Pfeifer Holding Gmbh & Co. Kg Support beam for ceiling systems and ceiling system
US10337196B2 (en) * 2017-04-04 2019-07-02 Reigstad & Associates, Inc. Load-carrying concrete floor structure and method for building the load-carrying concrete floor structure
CN107327020A (en) * 2017-07-06 2017-11-07 能诚集团有限公司 A kind of concrete component attachment structure
DE102018212750A1 (en) * 2018-07-31 2020-02-06 Pfeifer Holding Gmbh & Co. Kg Support beams for ceiling systems, ceiling system and process for their production
CN109359343B (en) * 2018-09-20 2023-06-20 北京电子工程总体研究所 Design method of high-speed large-span flexible sliding rail
CN109057152B (en) * 2018-09-21 2024-05-31 苏州光彩建筑钢品有限公司 Beam structure of integrated steel type house
BR112021010372A2 (en) * 2018-11-30 2021-08-24 Vellaisamy Thavamani Pandi System for building composite steel and double u and single u concrete structure for bridges
CN110255208B (en) * 2019-06-27 2024-04-26 中国能源建设集团安徽省电力设计院有限公司 Transfer station crossing original coal conveying trestle and construction method
CA3050000A1 (en) * 2019-07-16 2021-01-16 Invent To Build Inc. Concrete fillable steel joist
CN111914369B (en) * 2020-07-30 2022-12-20 中铁二院工程集团有限责任公司 Automatic design method of U-shaped groove
CN112487678A (en) * 2020-11-20 2021-03-12 合肥工业大学 Performance evaluation method of frame structure after impact
CN215888960U (en) * 2021-09-06 2022-02-22 昊恒(福建)建材科技有限公司 Steel structure beam
CN114837447A (en) * 2022-04-29 2022-08-02 中建二局安装工程有限公司 Pushable overhanging horizontal protection device and construction method thereof
CN115142602B (en) * 2022-07-21 2024-02-13 黑龙江华装清配建筑科技有限公司 Fully assembled prestress string building cover system
CN115928558B (en) * 2023-02-21 2023-06-02 湖南大学 Transverse joint structure of UHPC combined box girder and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1398562A (en) * 1972-08-09 1975-06-25 Taylor R Composite and reinforced concrete structures
US4580380A (en) * 1983-11-07 1986-04-08 Ballard Derryl R Composite filled interior structural box beams
DE3483413D1 (en) * 1983-11-07 1990-11-22 Harumoto Iron Works METHOD FOR PRODUCING A COMPOSED COMPONENT.
US5425152A (en) * 1992-08-14 1995-06-20 Teron International Building Technologies Ltd. Bridge construction

Also Published As

Publication number Publication date
NZ529942A (en) 2004-09-24
BR0210182A (en) 2004-04-27
CN1524149A (en) 2004-08-25
AU754130B1 (en) 2002-11-07
WO2002099215A1 (en) 2002-12-12
CA2448629A1 (en) 2002-12-12
US20040182027A1 (en) 2004-09-23

Similar Documents

Publication Publication Date Title
CN1239796C (en) Building structural element
JP2007016594A (en) Synthetic panel structure, panel bridge structure, and construction method for continuous synthetic beam bridge
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method for continuous composite girder bridge
CN115094951B (en) Local assembly type anti-seismic tough subway station structure
CN110644349A (en) Superstructure for wide box girder and short tower cable-stayed bridge and construction method
CN112342935A (en) Construction method for connecting and widening existing bridge with wide spacing in traffic state
CN111188457A (en) Edge sealing beam structure of super high-rise steel structure building and construction method
CN214784697U (en) Assembled building frame system
CN212656384U (en) High-strength concrete connecting piece, high-strength concrete post-cast assembled frame system and support frame
CN110886217B (en) Precast prestressed concrete anchor beam structure for anchoring stay cable and bridge tower
CN210066817U (en) Assembly integral vault is striden no post underground structure greatly
CN107989247B (en) Assembled superposed hollow floor system and construction method thereof
CN217517829U (en) Connecting structure for building prefabricated floor and roof board
KR100462966B1 (en) Prestressed Concrete U-Girder of compositive girder bridge
CN214939215U (en) Large cantilever assembly type light steel-concrete combined cover beam based on slot type connection
CN216108007U (en) Concrete beam type bridge and cast-in-situ hidden cover beam thereof
KR100588193B1 (en) Hybrid Structere System of Steel and Reinforced Concrete for Slim Floor System and Construction Method thereof
CN211395312U (en) Upper structure for wide box girder and short tower cable-stayed bridge
CN211257069U (en) Prefabricated side wall part with assembled structure and connection structure of prefabricated side wall part and arched plate
CN216446283U (en) Assembled broken line type top cap
CN217758906U (en) Assembled anti-settlement beam slab foundation structure
CN114369994B (en) Fully-prefabricated small box girder type invisible bent cap structure system and construction method thereof
CN215160354U (en) Concrete crane beam structure
JPH04250267A (en) Concrete fill steel pipe arch bearing construction of structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee