CN117090318A - Waterproof construction process for building engineering - Google Patents

Waterproof construction process for building engineering Download PDF

Info

Publication number
CN117090318A
CN117090318A CN202311204517.8A CN202311204517A CN117090318A CN 117090318 A CN117090318 A CN 117090318A CN 202311204517 A CN202311204517 A CN 202311204517A CN 117090318 A CN117090318 A CN 117090318A
Authority
CN
China
Prior art keywords
layer
waterproof
wall
construction
cement mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311204517.8A
Other languages
Chinese (zh)
Inventor
林立艳
莫俊杰
吴艺湛
周天文
叶彩君
刘飞祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Intercontinental Construction Engineering Group Co ltd
Original Assignee
Guangdong Intercontinental Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Intercontinental Construction Engineering Group Co ltd filed Critical Guangdong Intercontinental Construction Engineering Group Co ltd
Priority to CN202311204517.8A priority Critical patent/CN117090318A/en
Publication of CN117090318A publication Critical patent/CN117090318A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/0407Floor drains for indoor use
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/06Gully gratings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6806Waterstops
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Electromagnetism (AREA)
  • Hydrology & Water Resources (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Acoustics & Sound (AREA)
  • Building Environments (AREA)

Abstract

The application relates to the technical field of building construction, in particular to a waterproof construction process of building engineering, which comprises the following construction steps: concrete layer treatment; treating the outer wall of the basement; toilet treatment; performing terrace treatment; and (3) processing operation nodes, wherein in any construction step from S1 to S5, concrete guide walls are required to be arranged at the bottoms of all walls which leak due to accumulated water, the width of the concrete guide walls is consistent with that of the building walls, and the height elevation of the surface of the building walls is not lower than that of the surface of the accumulated water on the periphery, so that the waterproof performance of the building can be further improved.

Description

Waterproof construction process for building engineering
Technical Field
The application relates to the technical field of building construction, in particular to a waterproof construction process of building engineering.
Background
The building is subjected to waterproof treatment, so that the building structure is not corroded and damaged by moisture, the indoor environment is ensured to be dry, sanitary and healthy, and the existing building waterproof mode is mainly divided into material waterproof mode and structural waterproof mode according to different measures and means.
The building surface is cleaned and treated by selecting a proper waterproof material, and then the waterproof material is covered on the building layer, so that a waterproof layer is formed on the building surface, and the building layer can be protected by the waterproof layer, so that the durability of the building layer is improved.
The waterproof structure is formed by adding a drainage system in the building, including a drainage pipeline, a waterproof board, a floor drain and the like, so as to ensure that accumulated moisture can be smoothly discharged.
However, in practical application, the waterproof layer is only used, or the drainage pipeline is additionally arranged, or the waterproof layer and the drainage pipeline are combined, so that the building cannot be completely protected from water, gaps are easily formed around structures such as the drainage pipeline and the floor drain, water leakage occurs to the drainage pipeline and the floor drain under long-time use, waterproof materials covering the surface of the building layer expand, and the glue in the gaps is easy to fall off after being wetted, so that the waterproof performance is poor.
Disclosure of Invention
In order to further improve the waterproof performance of a building, the application provides a waterproof construction process for building engineering.
The application provides a waterproof construction process for building engineering, which adopts the following technical scheme:
the construction process for building engineering waterproof construction comprises the following construction steps:
s1: concrete layer treatment: and (5) carrying out surface compaction and light receiving on the original pulp light finding concrete layer.
S2: basement exterior wall treatment: and (3) sealing paste filling is carried out on the joints of the outer wall of the basement, and a waterproof layer is coated on the outer side of the outer wall of the basement.
S3, toilet treatment: leveling the toilet flat area, covering a waterproof layer, and paving a waterproof coiled material at a toilet door opening.
S4, terrace processing: and a waterproof groove is formed in the insulating layer of the terrace close to one side of the outdoor, sealing paste is filled at the joint of the waterproof groove and the insulating layer, and a waterproof layer is coated on the inner wall of the waterproof groove.
S5, processing operation nodes: the operation node comprises a screw hole, an air conditioner reserved hole, a floor penetrating pipeline hole, a flue, an internal corner, a pipeline root, a floor drain and a drainage ditch hole, and the position of the operation node is confirmed and waterproof treatment is carried out on the operation node.
In any construction step of S1-S5, the bottoms of all walls which leak due to accumulated water are provided with concrete guide walls, and the width of the concrete guide walls is consistent with that of the building walls and is not lower than the elevation of the finishing surface of the surrounding accumulated water ground.
By adopting the technical scheme, the surface compaction light receiving is carried out on the original pulp light finding concrete layer, so that the surface of the original pulp light finding concrete layer is smoother, the impermeability of the original pulp light finding concrete layer can be improved, and each area in the building is subjected to waterproof reinforcement treatment through the treatment of the outer wall of a basement, the treatment of a toilet, the treatment of a terrace and the treatment of an operation node, so that gaps and microcracks can be reduced, the compactness of concrete in each area is ensured, and the waterproof performance of the building is improved.
Preferably, in the step of S4, a drip line slot is formed at the top of the outer wall of the terrace, and a waterproof layer is coated on the area of the outer wall placed at the bottom of the drip line slot.
Through adopting above-mentioned technical scheme, the setting of drip wire casing can make the rainwater flow down along the outer wall of terrace, and the setting of waterproof layer can effectively reduce external moisture infiltration wall body and lead to the wall body to damage or the phenomenon of leaking, under the cooperation effect of both, can play the effect of protection to the structure and the wall body of building.
Preferably, in the construction step S3, after the waterproof coiled material is laid at the door opening of the toilet, the waterproof coiled material is closed by a metal pressing strip, or a pressing groove, or a groove.
Through adopting above-mentioned technical scheme, close up the processing to waterproofing membrane and can ensure the integrality and the leakproofness of waterproof layer to reduce the infiltration of moisture and to in the building structure, can strengthen waterproofing membrane's tensile strength and durability, make it be difficult for easily destroying and warp in long-term use, guarantee the water-proof effects.
Preferably, in the step of S3, when the water supply pipe is installed in the toilet, the method includes the following construction steps:
s3.1: the water supply pipe is arranged in the masonry wall in a penetrating way by returning a certain distance on the outer elevation of the reverse ridge.
Alternatively, S3.2: after the water supply pipe is buried for a certain distance along the reverse ridge direction, the water supply pipe is returned to the masonry wall surface, the water supply pipe does not directly pass through the reverse ridge, and the elbow part of the water supply pipe is arranged at the middle part of the cross section distance of the reverse ridge and does not need to form a through leakage point in the reverse ridge.
Wherein, the distance is set to be L,180mm < L < 220mm.
Through adopting above-mentioned technical scheme, reduce the water supply pipe and directly pass through masonry wall, reduce the area of contact between water supply pipe and the wall body, can reduce the risk of water supply pipe seepage, simultaneously, when follow-up water supply pipe breaks down or needs maintenance, make operating personnel under the prerequisite that does not destroy whole wall structure, can easily maintain.
Preferably, in the construction step of S5, when the floor drain is installed, the construction process includes:
s5.1: and pouring a reinforced concrete layer on the bottom layer, filling by fine stone concrete, continuously pouring and tamping, compacting, and vertically embedding the vertical pipe in the concrete layer.
S5.2: the funnel is installed at the one end of the top surface of the riser extending out of the concrete layer.
S5.3: and pouring a first cement mortar leveling layer outside the funnel until the first cement mortar leveling layer covers over the top of the funnel.
S5.4: the waterproof layer, the second cement mortar leveling layer and the facing layer are sequentially arranged on the top surface of the cement mortar leveling layer, meanwhile, a water outlet is reserved at the top of the upright post, and one side, close to the water outlet, of the waterproof layer, the second cement mortar leveling layer and the facing layer is distributed on the same inclined plane with the inner surface of the outer wall of the funnel.
S5.5: and the joints where the funnel is assembled with the facing layer, the second cement mortar leveling layer, the waterproof layer, the first cement mortar leveling layer, the reinforced concrete layer or the upright post are filled with sealing paste.
Through adopting above-mentioned technical scheme, can realize the installation of stand, funnel and each layer structure, install the stand through pre-buried mode, reduce space and microcrack effectively, guarantee the compactness of stand and reinforced concrete layer looks assembly department, be favorable to improving the waterproof nature of building, under waterproof layer, second cement mortar screed-coat, finish coat's effect, make the tight laminating in the outside of stand in the field of funnel, make the moisture in the top fall funnel can not spill over, through filling sealing paste in each assembly node department, further strengthen the connection density of assembly node, reach high-efficient drainage, lasting waterproof purpose.
Preferably, the top end of the water outlet is detachably provided with a first grate, a second grate and a third grate, and the first grate, the second grate and the third grate are sequentially arranged.
Through adopting above-mentioned technical scheme, under the cooperation effect of first comb, second comb, third comb, first aspect makes the space between the three form a vortex structure, can buffer memory to partial ponding, realizes the function of quick drainage, reduces ponding refluence condition simultaneously, and the second aspect can multiple isolated external impurity fall into in the riser, helps reducing stand blocking phenomenon, makes falling into water can smoothly drain away.
Preferably, in the construction step of S5.3, the first cement mortar leveling layer is obliquely arranged from the outside to the top end of the funnel, and an inclination angle between the first cement mortar leveling layer and the horizontal plane is set to be a;
in the construction step of S5.4, the finishing layer is inclined from the outside to the top end of the first grate, and an inclination angle B between the finishing layer and the horizontal plane is set, wherein a > B.
Through adopting above-mentioned technical scheme, there is inclination between first cement mortar screed-coat and the horizontal plane for A, can increase the filling quantity of first cement mortar screed-coat to play the effect of further ramming the basis, make funnel and riser can embed in each layer structure steadily, have inclination B between finish coat and the horizontal plane, can make outside moisture flow into in the funnel smoothly, guarantee finish coat and outlet more gentle transition simultaneously, guarantee user's safety in utilization.
Preferably, in the construction step of S5.2, the funnel is mounted on the top end of the riser before the reinforced concrete layer is poured, the reinforced concrete layer covers the bottom end portion of the funnel, the outer wall of the portion of the funnel extending out of the reinforced concrete layer is covered by the first cement mortar leveling layer, and the portion of the funnel assembled with the upright is subjected to sealing treatment.
Through adopting above-mentioned technical scheme, the funnel adopts pre-buried formula to install on reinforced concrete layer, makes the space between funnel and the reinforced concrete layer littleer to reduce the crack between the two, thereby make both have good compactness and waterproof nature, in addition, under the effect of first cement mortar screed-coat, make the funnel can fix in the outside of stand steadily, make outside moisture can easily transition to in the funnel, reduce the circumstances of infiltration, overflow.
Preferably, in any one of the construction steps S1 to S5, all the parts where the pipeline penetrates through the wall need to be coated with sealant, and the hole area is provided with dry and hard cement mortar for plugging.
Through adopting above-mentioned technical scheme, scribble the sealant and can form the sealing layer in the part that the pipeline was worn the wall, and have good elasticity and adhesive property, so that dry and hard cement mortar carries out the shutoff to the entrance to a cave region, thereby fill the clearance between pipeline and the wall body, reduce the infiltration of moisture from wall body gap indoor or ooze outdoor, secondly, under the cooperation effect of sealant and dry and hard cement mortar, can reduce air and dust and flow at this interval, help reinforcing the connection stability between wall body and the pipeline, make the sealed effect of both more lasting.
Preferably, after the waterproof layer is constructed, a waterproof protective coating, waterproof protective mortar or waterproof protective plates are paved on the top surface of the waterproof layer.
By adopting the technical scheme, the durability, the puncture resistance and the impact resistance of the waterproof layer are enhanced, so that the waterproof layer can be protected.
In summary, the present application includes at least one of the following beneficial technical effects:
1. compared with the prior art, the waterproof method has the advantages that the waterproof capability of each area easy to generate ponding leakage is enhanced, gaps are reduced from the root, the waterproof effect of the building is more durable, and the overall quality of the building is ensured;
2. the water supply pipe is reduced to directly penetrate through the masonry wall, the contact area between the water supply pipe and the wall is reduced, the risk of leakage of the water supply pipe can be reduced, and meanwhile, when the subsequent water supply pipe breaks down or needs to be maintained, operators can easily maintain the water supply pipe on the premise of not damaging the whole wall structure.
Drawings
FIG. 1 is a schematic view of a basement exterior wall treatment according to an embodiment of the present application.
Fig. 2 is an enlarged view of a in fig. 1.
Fig. 3 is a schematic view of a structure of a toilet according to an embodiment of the present application.
Fig. 4 is a schematic view of a structure of a terrace processing in an embodiment of the present application.
Fig. 5 is a schematic view of the fit between the funnel and the column in an embodiment of the application.
FIG. 6 is a schematic diagram of the structure of an uncased riser in an embodiment of the present application.
Reference numerals illustrate: 1. a basement exterior wall; 11. an outer wall body; 12. a mounting groove; 13. a steel wire mesh; 14. a plastering layer; 15. exterior wall facing; 16. a lawn; 17. a flow guide channel; 18. an outer wall waterproof protective layer; 2. a waterproof layer; 3. sealing paste; 4. waterproof coiled materials; 5. a toilet; 51. reinforced concrete floor slab; 52. a leveling layer; 53. a protective layer; 54. a surface layer; 55. bathroom door opening; 6. a terrace; 61. a heat preservation layer; 62. an inclined plane; 63. a water-repellent tank; 64. an assembly groove; 65. a drip line slot; 71. a floor drain; 711. a first grate; 712. a second grate; 713. a third grate; 72. a facing layer; 73. a second cement mortar leveling layer; 74. a first cement mortar leveling layer; 75. a reinforced concrete layer; 76. a column; 77. a water outlet; 81. dry hard fine stone concrete; 82. and (5) a concrete platform.
Detailed Description
The application is described in further detail below with reference to fig. 1-6.
The embodiment of the application discloses a waterproof construction process for building engineering.
The construction process for building engineering waterproof construction comprises the following construction steps:
s1: concrete layer treatment: and (5) carrying out surface compaction and light receiving on the original pulp light finding concrete layer.
In the application, when a building foundation is poured, the magma light finding concrete is poured, compacted and surface compacted and light-receiving, wherein the basement bottom plate, the top plate and the roof and the terrace 6 are required to be compacted and light-receiving by magma, and the concrete at other parts can be processed by magma compaction and light-receiving or other modes, so that operators can perform operations for different construction scenes, and the application is beneficial to saving the construction time and the cost.
Specifically, in the concrete curing process, when the concrete is finally cured, the curing time of the part with the waterproof requirement is not less than 14 days, and the curing time of the part without the waterproof requirement is not less than 7 days. The parts of the flat roof, the toilet 5, the terrace 6 and the like are maintained by water storage, and the depth of water storage is 100mm. And covering concrete on the sloping roof by using gunny bags and spraying water for maintenance. The floor concrete without waterproof requirement is maintained by watering or spraying water covered with plastic film. The concrete cement ratio of the basement side wall is independently set, and the concrete cement ratio of the basement side wall is not more than 0.5. The basement side wall should be provided with a mould for more than 7 days, and the mould is removed and then the basement side wall is subjected to water spraying maintenance, and the total maintenance time is not less than 14 days. And (3) spraying water for curing when other shear walls and column concrete are provided with the mould, and watering for curing after the mould is removed, wherein the curing time is not less than 7 days. Under the condition of low-temperature weather, after the concrete is finally solidified, the concrete should be covered and maintained in time.
During the concrete curing, the temperature and the humidity of the surface of the concrete are monitored, the situations of premature drying and temperature overheating are reduced, the concrete layer is ensured to be kept at proper temperature and moisture, the hardening and the strength development of the concrete are promoted, the situations of cracking or deformation and the like in the subsequent concrete use process are reduced, and the quality and the stability of the concrete are ensured.
Before the waterproof construction of the parts such as the flat roof, the toilet 5, the basement roof, the terrace 6 and the like, and after the concrete is fully cured and maintained, the water-blocking test of the structure is carried out, the water depth is 30-50 mm, and the water depth is 20mm or more higher than the highest part of the floor, and the test time is not less than 24 hours.
In the face of common defects, concrete surface cracks with the crack width smaller than 0.2mm, air holes and common defects, filling and leveling with concrete repair glue, polishing and leveling after drying, sealing the surface layer 54 again with polymer cement mortar, grooving and burying pipes on the concrete surface when the crack width exceeds 0.2mm, repairing the concrete cracks by adopting a pressure grouting method, and closing water again after defect treatment until the structure has no leakage and waterproof construction can be started.
S2: basement exterior wall treatment: and (3) sealing the joints of the basement outer wall 1 by using the sealing paste 3, and coating a waterproof layer 2 on the outer side of the basement outer wall 1.
Referring to fig. 1 and 2, specifically, the basement outer wall 1 includes an outer wall body 11, an installation groove 12 is reserved at one side of the outer wall body 11 outside, a waterproof layer 2 is laid along the outer side of the outer wall body 11, so that the end of the waterproof layer 2 stretches into the installation groove 12, a steel wire mesh 13, a plastering layer 14 and an outer wall facing 15 are sequentially arranged at the outer side of the waterproof layer 2, wherein a plurality of outer wall waterproof protection layers 18 are added to the area of the outer wall facing 15, which is close to a lawn 16, and the outer wall waterproof protection layers 18 can be waterproof paint, asphalt, polymer, waterproof coiled materials 4 or the like.
And, set up the diversion channel 17 on the top of the area that the exterior wall facing 15 is close to the lawn 16, the diversion channel 17 is inclined downwards from exterior wall facing 15 to outside, make the terminal of diversion channel 17 point to the lawn 16 top surface, realize the quick drainage function. Meanwhile, the sealing paste 3 is filled in the corner between the guide channel 17 and the exterior wall facing 15 and in the mounting groove 12, so that the basement exterior wall 1 has good waterproof performance.
S3, toilet treatment: leveling treatment is carried out on the flat area of the toilet 5, the waterproof layer 2 is covered, and a waterproof roll 4 is paved at a toilet door opening 55.
Specifically, referring to fig. 3, the bathroom structural wall includes a reinforced concrete floor 51, a leveling layer 52, a waterproof layer 2, a protective layer 53 and a facing layer 54, and the reinforced concrete floor 51, the leveling layer 52, the waterproof layer 2, the protective layer 53 and the facing layer 54 are sequentially laid from bottom to top, so that the elevation of the bathroom structural roof is lower than that of the living room structural roof, and a stepped structure is formed at the junction position of the living room structural roof and the bathroom structural roof, so that moisture can be easily discharged.
The door opening is reserved in the bathroom structural wall so as to facilitate the subsequent installation of the bathroom door, waterproof coiled materials 4 are paved on all side walls of the door opening, then the waterproof coiled materials 4 are plugged through dry and hard cement mortar, and after the waterproof coiled materials 4 are paved at the bathroom door opening 55, the waterproof coiled materials 4 are closed up through metal pressing strips, pressing grooves or grooves.
In the present application, the actual material of the waterproof layer 2 is not limited, and the waterproof layer 2 may be a waterproof roll 4, or a composite layer composed of the waterproof roll 4, or an asphalt waterproof material, or an elastomer waterproof material, or a cement mortar waterproof material, or a polymer waterproof material, and an operator selects an appropriate waterproof material according to specific construction needs and use environments to perform construction so as to ensure the waterproof effect and durability of the building.
But needs to ensure the flatness and cohesiveness of the building base layer, then lay the waterproof layer 2, the base layer treating agent, joint adhesive, sealing material selected in the process need to be compatible with the material property of the waterproof coiled material 4, after finishing the waterproof material laying, then lay the waterproof coiled material 4 on this basis, the waterproof coiled material 4 adopts the high polymer modified asphalt waterproof coiled material 4, in order to achieve the dual waterproof effect.
During the process, the situation of the waterproof finishing surface is strictly monitored, when the waterproof coiled material 4 is used for laying, the waterproof coiled material 4 is in a flat and straight state, the lap joint size is correct, no distortion and no crease are required, the seam is tightly sealed by a sealing material, the width of the seam is not less than 10mm, the coiled material is tightly sealed, and the fixation is firm; when the coating waterproof layer 2 is used for coating, the coating waterproof layer 2 is required to finish the surface, the coating waterproof layer 2 is firmly bonded with a base layer, the coating is uniform, the surface is in a flat state, the defects of flowing, creasing, bubbling, matrix exposure, edge warping and the like cannot exist, the average thickness of the coating waterproof layer 2 is required to meet the design requirement, the minimum thickness cannot be less than 80% of the design thickness, the protective layer 53 of the side wall coating waterproof layer 2 is firmly bonded with the waterproof layer 2, the bonding is tight, and the thickness is uniform.
Specifically, in the embodiment of the application, when the waterproof coiled material 4 is adopted or a composite layer consisting of the waterproof coiled material 4 is adopted as the waterproof layer 2, the method is specifically divided into the following conditions that firstly, metal batten necking is adopted, metal batten pressing is adopted at the coiled material necking position, a nail gun is used for driving and fixing nails at intervals of not more than 250mm, the nails are required to be provided with nail caps, manual nailing is forbidden, nails are required to be driven at two ends of each batten, the battens are not overlapped, and then special coiled material sealing paste 3 is used for covering and sealing; secondly, closing up by adopting a pressing groove, reserving a groove or picking up a groove on the edge of the coiled material, pressing the edge of the coiled material in, sealing by using weather-proof sealant, firmly bonding the lower opening of the waterproof coiled material 4, and covering the sealing closing up by using special coiled material sealant 3; thirdly, adopting groove closing-in, reserving a waterproof layer 2 closing-in groove when pouring, wherein the height of the groove is 300mm higher than the finishing surface of the roof veneer, the waterproof layer 2 is fixed in the groove closing-in, the groove is required to be filled with sealant, cement mortar with the thickness of 1:2 is smeared outside the parapet waterproof layer 2, and the cement mortar starts to be 50mm higher from the roof.
In addition, when the waterproof coiled material 4 is closed at the positions of the pipe, the sleeve, the vertical or side drainage gutter, the finished gutter or the water tank, the first type of the waterproof coiled material is a metal product, the coiled material is thermally fused and adhered with the components, and then the closing is covered by a waterproof coating; and the second, the pipe, the sleeve and the gully are nonmetallic products, the bonding by a hot melt method is forbidden, a self-adhesive coiled material is adopted at the periphery of the pipe, the self-adhesive bonding is adopted, then the closing is covered by a waterproof coating, the closing mode is not adopted in winter when the outdoor air temperature is lower than 5 ℃, wherein the first is the condition of preference, and the second is the condition of substitution.
The application also requires that all risers and sleeves of the roof and terrace 6 are fastened and bordered by metal hoops on the waterproof coiled material 4 and the sealing closing is covered by the special coiled material sealing paste 3 so as to ensure the integrity and the tightness of the waterproof layer 2, reduce the penetration of moisture into the building structure, and enhance the tensile strength and the durability of the waterproof coiled material 4, so that the waterproof coiled material is not easy to be damaged and deformed in long-term use and ensures the waterproof effect.
In the construction step of S3, when the water supply pipe is additionally installed in the toilet 5, the water supply pipe cannot directly pass through the guide wall, and one of the following two penetrating modes can be selected:
s3.1: the water supply pipe is arranged on the outer elevation of the reverse ridge in a penetrating way from the masonry wall; alternatively, S3.2: after the water supply pipe is buried for a certain distance along the reverse ridge direction, the water supply pipe is returned to the masonry wall surface, the water supply pipe does not directly pass through the reverse ridge, the elbow part of the water supply pipe is arranged in the middle part of the section distance of the reverse ridge, and a through leakage point is not formed in the reverse ridge, wherein the distance is set to be L,180mm < L < 220mm, and in the application, L=200 mm is preferable. Through reducing the water supply pipe and directly crossing the brickwork wall body, reduce the area of contact between water supply pipe and the wall body, can reduce the risk of water supply pipe seepage, simultaneously, when follow-up water supply pipe breaks down or needs maintenance, make operating personnel under the prerequisite that does not destroy whole wall structure, can easily maintain.
The water-proof treatment procedures of the floor and the water supply pipe in the kitchen are consistent with the corresponding water-proof treatment procedures of the toilet 5, and detailed description is omitted here, so that the kitchen and the toilet 5 are guaranteed to have good water-proof effects.
S4, terrace processing: the heat preservation layer 61 of the terrace 6 near outdoor side is provided with a waterproof groove 63, the joint of the waterproof groove 63 and the heat preservation layer 61 is filled with sealing paste 3, and the waterproof layer 2 is coated along the inner wall of the waterproof groove 63.
Referring to fig. 4, specifically, an insulating layer 61 is provided in an area of the terrace 6 exposed to the outside, the insulating layer 61 can play a role in insulating heat and water for the terrace, the terrace 6 is in a "U" shaped structure, and an inclined surface 62 is disposed on one inner side of the terrace 6, and the inclined surface 62 is inclined downward from the top surface of the terrace 6 to the center of the bottom surface of the terrace 6, so as to play a role in draining rainwater to a certain extent.
The waterproof groove 63 of the heat insulation layer 61 arranged on the outdoor side of the terrace 6 is in an L-shaped cross section, correspondingly, the inclined surface 62 of the terrace 6 is provided with the assembly groove 64, the opening of the assembly groove 64 faces the other inner side of the terrace 6, and the waterproof coiled material 4 is paved along the extending directions of the waterproof groove 63 and the assembly groove 64, namely, the waterproof coiled material 4 is smoothly extended along the short side of the waterproof groove 63, the long side of the waterproof groove 63, the inclined surface 62 area between the long side of the waterproof groove 63 and the assembly groove 64 and the middle part of the assembly groove 64, so that the inner side surface and the inner bottom surface of the terrace 6 have good waterproof performance.
In addition, a drip line groove 65 is formed in the top of the outer wall of the terrace 6, the drip line groove 65 can be a olecranon-shaped line groove or a -shaped line groove, and a waterproof layer 2 is coated on the area of the outer wall placed at the bottom of the drip line groove 65. Under the cooperation of the drip groove 65 and the waterproof layer 2, rainwater can flow down along the outer wall of the terrace 6, and the phenomenon that the wall is damaged or leaked due to the penetration of external moisture into the wall is effectively reduced, so that the protection effect on the structure and the wall of a building is facilitated.
S5, processing operation nodes: in the application, the operation node is suitable for any scene of a basement, a toilet 5, a kitchen, a flue, a terrace 6, a bay window, an air conditioner plate root wall body and an outer wall, and comprises a screw hole, an air conditioner reserved hole, a floor penetrating pipeline hole, a flue, an internal corner, a pipeline root, a floor drain 71 and a drainage ditch opening, and the position of the operation node is confirmed and is subjected to waterproof treatment.
When the floor drain 71 is installed, the following construction process is included:
s5.1: the reinforced concrete layer 75 is poured on the bottom layer, is filled with fine stone concrete and is continuously poured and compacted, and the vertical pipe is vertically embedded in the concrete layer.
Specifically, referring to fig. 5 and 6, if the riser does not have the sleeve, the gaps between the riser and the structures of different material layers are filled with the dry hard fine stone concrete 81 to be compacted, the filling amount of the dry hard fine stone concrete 81 is gradually reduced from top to bottom by a plurality of material layers, the dry hard fine stone concrete 81 is enabled to be covered outside the upright post 76 in a truncated cone-shaped structure, the waterproof coiled material 4 is paved between the structure of the top material layer and the structure of the sub-layer material layer, and is sealed in the manner of closing up the waterproof coiled material 4, the sealing glue is filled at the closing-up position of the waterproof coiled material 4, and the concrete table 82 is poured in the region, so that the closing-up part of the waterproof coiled material 4 can be buried in the concrete table 82, and further sealing effect is achieved.
If the riser is provided with a pipe sleeve, the installation mode of the riser is different from that of the riser without the pipe sleeve in that the concrete platform 82 is replaced by a water stop ring, and a gap between the water stop ring and a material layer structure assembled by the water stop ring is filled with sealant, so that stable connection of the water stop ring and the material layer structure is realized.
S5.2: the funnel is installed in the top surface's of the reinforced concrete layer one end that the top surface of concrete layer was stretched out to the riser, and wherein, the top of riser is installed to the funnel before pouring reinforced concrete layer 75, and reinforced concrete layer 75 covers the bottom part of funnel, and the part outer wall that the funnel stretched out in reinforced concrete layer 75 all is covered by first cement mortar screed 74, and the part that the funnel was assembled mutually with stand 76 is sealed and is handled, promptly, scribbles the sealant between the two, makes both closely laminating installation.
In the application, the funnel is mounted on the reinforced concrete layer 75 in a pre-buried manner, so that the gap between the funnel and the reinforced concrete layer 75 is smaller, and cracks between the funnel and the reinforced concrete layer 75 are reduced, so that the funnel has good compactness and waterproofness.
S5.3: pouring a first cement mortar leveling layer 74 outside the funnel until the first cement mortar leveling layer 74 covers more than the top of the funnel;
s5.4: the waterproof layer 2, the second cement mortar leveling layer 73 and the finish coat 72 are sequentially arranged on the top surface of the first cement mortar leveling layer 74, meanwhile, a water outlet 77 is reserved at the top of the upright post 76, and one side, close to the water outlet 77, of the waterproof layer 2, the second cement mortar leveling layer 73 and the finish coat 72 is distributed on the same inclined plane 62 with the inner surface of the outer wall of the funnel;
in the construction step of S5.3, the first cement mortar leveling layer 74 is obliquely arranged from the outside to the top end of the funnel, and the inclination angle between the first cement mortar leveling layer 74 and the horizontal plane is set to be a, so that the filling amount of the first cement mortar leveling layer 74 can be increased, the foundation is further compacted, and the funnel and the vertical pipe can be stably embedded in each layer of structure.
In the construction step of S5.4, the facing layer 72 is inclined from the outside to the top end of the first grate 711, and the inclination angle B between the facing layer 72 and the horizontal plane is set, so that the external moisture smoothly flows into the funnel, and a more gentle transition between the facing layer 72 and the drain port 77 is ensured.
In the application, A is more than B, so that the structural stability of the water inlet end of the water outlet 77 is stronger and is not easy to be corroded and damaged by water, in addition, the inclined angle B is not a direct dip of the horizontal plane to set an angle limit value, but an intermediate angle is additionally arranged between the horizontal plane and the inclined angle B, so that the finish layer 72 can be smoothly transited from the horizontal plane to the set angle limit value, thereby being beneficial to reducing the sharp angle of the structural layer and ensuring the use safety of users.
S5.5: the joints where the funnel is assembled with the facing layer 72, the waterproof layer 73, the second cement mortar leveling layer 73, the waterproof layer 2, the first cement mortar leveling layer 74, the reinforced concrete layer 75 or the upright posts 76 are filled with the sealing paste 3, the upright posts 76, the funnel and each layer structure are installed, gaps and microcracks are effectively reduced by installing the upright posts 76 in a pre-embedded mode, compactness of the assembled parts of the upright posts 76 and the reinforced concrete layer 75 is guaranteed, the waterproof performance of a building is improved, the funnel is tightly attached to the outer part of the upright posts 76 under the action of the waterproof layer 2, the second cement mortar leveling layer 73 and the facing layer 72, moisture in the top falling funnel cannot overflow, and the connection density of the assembled joints is further enhanced by filling the sealing paste 3 at each assembled joint, so that the aims of high-efficiency drainage and lasting waterproof are achieved.
In the application, the top end of the drain port 77 is detachably provided with a first grate 711, a second grate 712 and a third grate 713, correspondingly, the funnel is a truncated cone-shaped funnel, the first grate 711 and the second grate 712 are plane grates, the section of the third grate 713 is , the first grate 711, the second grate 712 and the third grate 713 are sequentially arranged, so that the plane area of the first grate 711 is larger than that of the second grate 712, and the third cover is covered on the top end of the upright post 76.
Under the cooperation of the first grate 711, the second grate 712 and the third grate 713, the space between the first grate 711, the second grate 712 and the third grate 713 forms a vortex structure, so that partial accumulated water can be buffered, the function of quick drainage is realized, the condition of accumulated water backflow is reduced, in addition, external impurities can be isolated from multiple and fall into the vertical pipe, the blocking phenomenon of the vertical pipe 76 is reduced, and the water can be smoothly drained.
In any construction step of S1-S5, all parts where the pipeline penetrates through the wall are required to be coated with sealant, and dry and hard cement mortar is arranged in the hole area for blocking. The pipe wall-through includes, but is not limited to, a kitchen flue node, a wall-through pipe node, and a wall-through screw node.
The sealing layer can be formed at the wall penetrating part of the pipeline through brushing the sealant, and the sealing layer has good elasticity and adhesion performance, so that the dry and hard cement mortar can be used for plugging the hole area, thereby filling the gap between the pipeline and the wall, reducing the infiltration of moisture into the room or the exudation of the moisture out of the room from the gap between the wall, and secondly, under the matching effect of the sealing sealant and the dry and hard cement mortar, the flowing of air and dust in the area can be reduced, thereby being beneficial to enhancing the connection stability between the wall and the pipeline, and enabling the sealing effect of the sealing layer and the wall to be more durable.
In the screw hole node treatment procedure, firstly, a trumpet-shaped hole is drilled on the outer side of a screw hole, then, after flushing and wetting, the hole is filled with waterproof mortar, at the moment, attention is required to avoid the condition of empty holes, a round cake shape is complemented on the outer side and protrudes out of a wall surface, and finally, a hole is maintained through mortar, so that fine cracks or empty drums cannot be obtained; if the screw hole node appears on the basement outer wall 1, a water stop bolt is needed to replace the process.
In the air conditioner reserved hole node treatment process, the PVC sleeve reserved by the air conditioner is reserved, meanwhile, the steel sleeve is reserved in the beam, a prefabricated concrete block is reserved in the wall body, the reserved pipe is required to be inclined outdoors, the inner pipe orifice is 20-30 mm higher than the outer pipe orifice, and the outer pipe orifice protrudes out of the outer wall decoration surface by 60-80 mm, so that the inner pipe orifice is flush with the inner wall decoration surface.
In the floor pipeline hole processing procedure, a sleeve is required to be arranged when a pipeline penetrates through a roof, the sleeve is required to be paid out on a template and accurately and firmly fixed before a floor is poured, the upper opening of the sleeve is higher than the ground finishing surface by not less than 50mm, the lower opening is flush with the floor bottom, and when no design requirement exists, the pipe diameter of the sleeve is required to be larger than that of the pipeline for a small-pipe-diameter pipeline; for large-diameter pipelines, the diameter of the sleeve is larger than the outer diameter of the pipeline by 50mm, and in addition, when floor slab concrete is poured, the two ends of the sleeve are sealed by rubberized fabrics, so that the blockage is avoided.
In the application, a sleeve is required to be arranged when a pipeline penetrates through a floor slab; when the through floor pipe is not sleeved, the hole position must be accurately reserved on the floor during the construction of the structure, so that the later drilling and the punching are avoided. In order to facilitate hole plugging, a shaping template can be used for reserving holes in structural construction, the holes are made into a shape with a large upper part and a small lower part, the diameter of the upper part is 40mm larger than that of the lower part, and the holes are timely demoulded after the concrete is finally set. The reserved holes are preferably 60mm larger than the outer diameter of the pipeline, pipe clamps are required to be arranged for fixing all the floor penetrating pipelines during installation, fine stone concrete is adopted for blocking the pipe holes for two times for preventing leakage, and a 20mm groove is required to be reserved after the second time of blocking. After the water is closed and inspected to be qualified, the waterproof construction of the periphery of the pipeline can be started.
In the flue node treatment procedure, in order to reduce the large accumulated sedimentation caused by stack of the flue layers, the floor waterproof layer 2 is damaged and the flue gas duct is cracked, the lower part of the flue is arranged on the reverse ridge, the upper part of the flue props against the structural floor slab, and the gap between the upper part and the lower part of the flue is tightly blocked by cement mortar.
And, flue preparation height = floor clear height-anti bank height-30 mm,30mm be cock seam and height-adjusting, need to accept its size and outward appearance before the flue is installed, and the surface is not allowed to have the crack, and the cross-section size is within plus-minus deviation 5 mm.
When the wall body around the flue is a masonry, masonry and plastering construction are finished firstly, and then a flue is installed; the lowest smoke duct should be installed last to facilitate the removal of the waste in the smoke duct.
In any construction step of S1-S5, the bottom of the wall body which is leaked due to accumulated water is provided with a concrete guide wall, the width of the concrete guide wall is consistent with that of the building wall body, the width of the concrete guide wall is not lower than the elevation of the surface finished by the accumulated water on the periphery, and when no special requirement exists in design, the reinforcement is arranged according to the construction requirement, such as the addition of longitudinal reinforcement or hooping. The concrete guide wall and the floor concrete can be poured together or secondarily poured, but before the secondarily poured concrete guide wall is constructed, the concrete at the lower part of the parapet wall needs to be roughened, cleaned and fully wetted.
After the construction of the waterproof layer 2 is completed, a waterproof protective coating, waterproof protective mortar or waterproof protective plates are paved on the top surface of the waterproof layer 2, so that the influence of external factors on the waterproof layer 2 is reduced, or the waterproof layer 2 is damaged, the durability, puncture resistance and impact resistance of the waterproof layer 2 can be enhanced, and the protection effect on the waterproof layer 2 is achieved.
The foregoing is illustrative of the present application, and is not meant to limit the scope of the application in any way, therefore: all equivalent changes in structure, shape and principle of the application should be covered in the scope of protection of the application.

Claims (10)

1. The construction process for building engineering waterproof construction is characterized by comprising the following construction steps:
s1: concrete layer treatment: carrying out surface compaction and light receiving on the original pulp light finding concrete layer;
s2: basement exterior wall treatment: sealing paste (3) is filled in joints of the basement outer wall (1), and a waterproof layer (2) is coated on the outer side of the basement outer wall (1);
s3, toilet treatment: leveling treatment is carried out on the flat ground area of the toilet (5) and a waterproof layer (2) is covered, and a waterproof coiled material (4) is paved at a toilet door opening (55);
s4, terrace processing: a waterproof groove (63) is formed in the insulating layer (61) of the terrace (6) close to the outdoor side, sealing paste (3) is filled at the intersection joint of the waterproof groove (63) and the insulating layer (61), and a waterproof layer (2) is coated along the inner wall of the waterproof groove (63);
s5, processing operation nodes: the operation node comprises a screw hole, an air conditioner reserved hole, a floor penetrating pipeline hole, a flue, an internal corner, a pipeline root, a floor drain (71) and a drainage ditch hole, and the position of the operation node is confirmed and is subjected to waterproof treatment;
in any construction step of S1-S5, the bottoms of all walls which leak due to accumulated water are provided with concrete guide walls, and the width of the concrete guide walls is consistent with that of the building walls and is not lower than the elevation of the finishing surface of the surrounding accumulated water ground.
2. The construction process for building engineering waterproof according to claim 1, wherein in the construction step S4, a drip line groove (65) is formed in the top of the outer wall of the terrace (6), and a waterproof layer (2) is coated on the area of the outer wall placed at the bottom of the drip line groove (65).
3. The construction process according to claim 1, wherein in the step S3, after the waterproof roll (4) is laid at the toilet door opening (55), the waterproof roll (4) is closed by a metal bead, or a pressing groove, or a groove.
4. A construction process according to claim 3, wherein in the construction step S3, when a water supply pipe is added to the toilet (5), the construction process comprises the steps of:
s3.1: the water supply pipe is arranged on the outer elevation of the reverse ridge in a penetrating way from the masonry wall;
alternatively, S3.2: the water supply pipe is buried for a certain distance along the reverse ridge direction and then is returned to the masonry wall surface, the water supply pipe does not directly pass through the reverse ridge, and the elbow part of the water supply pipe is arranged at the middle part of the cross section distance of the reverse ridge and cannot form a through leakage point in the reverse ridge;
wherein, the distance is set to be L,180mm < L < 220mm.
5. A construction process according to claim 3, wherein in the construction step of S5, when installing the floor drain (71), the construction process comprises the steps of:
s5.1: pouring a reinforced concrete layer (75) at the bottom layer, filling by fine stone concrete, continuously pouring and compacting, and vertically pre-burying a vertical pipe in the concrete layer;
s5.2: the funnel is arranged at one end of the vertical pipe extending out of the top surface of the concrete layer;
s5.3: pouring a first cement mortar leveling layer (74) outside the funnel until the first cement mortar leveling layer (74) covers more than the top of the funnel;
s5.4: a waterproof layer (2), a second cement mortar leveling layer (73) and a facing layer (72) are sequentially arranged on the top surface of the first cement mortar leveling layer (74), meanwhile, a water outlet (77) is reserved at the top of the upright post (76), and one side, close to the water outlet (77), of the waterproof layer (2), the second cement mortar leveling layer (73) and the facing layer (72) is distributed on the same inclined plane (62) with the inner surface of the outer wall of the funnel;
s5.5: the joints where the funnel is assembled with the facing layer (72), or the second cement mortar leveling layer (73), or the waterproof layer (2), or the first cement mortar leveling layer (74), or the reinforced concrete layer (75) or the upright posts (76) are filled with the sealing paste (3).
6. The construction engineering waterproof construction process according to claim 5, wherein the top end of the water outlet (77) is detachably provided with a first grate (711), a second grate (712) and a third grate (713), and the first grate (711), the second grate (712) and the third grate (713) are sequentially arranged.
7. The construction process according to claim 1, wherein in the construction step of S5.3, the first cement mortar leveling layer (74) is provided obliquely from the outside to the top end of the hopper, and the inclination angle between the first cement mortar leveling layer (74) and the horizontal plane is set to be a;
in the construction step of S5.4, the finish layer (72) is obliquely arranged from outside to the top end of the first grate (711), and an inclination angle B between the finish layer (72) and the horizontal plane is set, wherein A is larger than B.
8. The construction process according to claim 5, wherein in the construction step of S5.2, the funnel is mounted with the top end of the riser before pouring the reinforced concrete layer (75), the reinforced concrete layer (75) covers the bottom end portion of the funnel, the outer walls of the parts of the funnel extending out of the reinforced concrete layer (75) are covered with the first cement mortar leveling layer (74), and the parts of the funnel assembled with the upright (76) are sealed.
9. The construction process according to claim 5, wherein in any one of the steps S1 to S5, the sealant is applied to all the parts where the pipeline passes through the wall, and the dry and hard cement mortar is set in the hole area for plugging.
10. The construction process according to any one of claims 1 to 8, wherein a waterproof protective coating, waterproof protective mortar, or waterproof protective sheet is laid on the top surface of the waterproof layer (2) after the waterproof layer (2) is constructed.
CN202311204517.8A 2023-09-18 2023-09-18 Waterproof construction process for building engineering Pending CN117090318A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311204517.8A CN117090318A (en) 2023-09-18 2023-09-18 Waterproof construction process for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311204517.8A CN117090318A (en) 2023-09-18 2023-09-18 Waterproof construction process for building engineering

Publications (1)

Publication Number Publication Date
CN117090318A true CN117090318A (en) 2023-11-21

Family

ID=88771833

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311204517.8A Pending CN117090318A (en) 2023-09-18 2023-09-18 Waterproof construction process for building engineering

Country Status (1)

Country Link
CN (1) CN117090318A (en)

Similar Documents

Publication Publication Date Title
CN110080530B (en) Anchoring construction method for glazed tile slope roof in severe cold region
CN206319910U (en) Infiltration disposal system is reinforced in a kind of tunnel-liner
CN113186985B (en) Anti-seepage treatment method for basement bottom plate construction joint
CN107313560B (en) Reinforced waterproof roof of archaize building and construction method thereof
CN104153522A (en) Asphalt shingle roof waterproof system of sloping roof high-rise building and construction method of asphalt shingle roof waterproof system
CN102912945B (en) Roof compound seepage-proofing steam exhausting hole detail treatment technology
KR100744727B1 (en) Expoused double waterproof plus film of paint and sheet in the building and construction method of the same
CN108797903B (en) Roof waterproof structure and construction process thereof
CN112695959A (en) Passive heat-bridge-free slope roof 300 mm-thick heat-insulation and decoration integrated construction process
CN107675811B (en) Bathroom waterproof system and construction method
CN109339355A (en) The construction method of the aluminium sheet roofing waterproofing node of structural slab is done using ALC plate
CN111350315A (en) Waterproof closing-in pre-embedding method for roof parapet
CN117090318A (en) Waterproof construction process for building engineering
CN110067346A (en) A kind of roof construction method of bridge cut-off water-proof roofing gutter spout funnel
CN107989287A (en) Inverted roof light and shade drainage system construction method
CN212336545U (en) Oblique roofing tile hanging anti-leakage structure
CN212671027U (en) Leakage-proof structure for terrace roof
CN104818835B (en) Toilet threshold stone waterproof structure and construction method
CN111456484B (en) Roof waterproof repairing method for large-scale buildings in the ages
CN214739146U (en) Arc roofing structure
CN212153924U (en) Parapet waterproof repairing structure
RU2728045C1 (en) Method of overhaul of flat roofing by covering with panels
CN209975897U (en) Waterproof parapet of light steel building
Borle et al. Comparative study of conventional and modern waterproofing techniques
KR101466644B1 (en) The construction method for root

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination