CN104818835B - Toilet threshold stone waterproof structure and construction method - Google Patents

Toilet threshold stone waterproof structure and construction method Download PDF

Info

Publication number
CN104818835B
CN104818835B CN201510253449.3A CN201510253449A CN104818835B CN 104818835 B CN104818835 B CN 104818835B CN 201510253449 A CN201510253449 A CN 201510253449A CN 104818835 B CN104818835 B CN 104818835B
Authority
CN
China
Prior art keywords
layer
waterproof
threshold stone
ground
cement mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510253449.3A
Other languages
Chinese (zh)
Other versions
CN104818835A (en
Inventor
贾杨
高建伟
杨苏春
李兆龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongqing Jianan Construction Group Co Ltd
Original Assignee
Qingdao Jianan Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Jianan Construction Group Co Ltd filed Critical Qingdao Jianan Construction Group Co Ltd
Priority to CN201510253449.3A priority Critical patent/CN104818835B/en
Publication of CN104818835A publication Critical patent/CN104818835A/en
Application granted granted Critical
Publication of CN104818835B publication Critical patent/CN104818835B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a toilet threshold stone waterproof structure and a construction method, wherein the toilet threshold stone waterproof structure orderly comprises a threshold stone, a cement mortar paste layer, a waterproof layer and a ground beam from top to bottom, prevents water on toilet ground from downwardly permeating to a civil engineering structure layer by arranging the waterproof layer, blocks water steam which leaks onto the lower surface of a toilet ground tile complete surface to leak to wood decorative ground through the threshold stone by adding the trapezoid ground beam, collects waste water which is leaked on the toilet ground tile complete surface and the cement mortar paste layer by adding a floor drain in the cement mortar paste layer, and discharges the waste water by adding a floor drain drainage vertical pipe, thereby effectively preventing a structure layer between the waterproof layer and a ground tile layer from storing water for long time to be in a damp state. The toilet threshold stone waterproof structure is strong in waterproof reliability, accords with the demands of elevation difference of the toilet ground and the wood decorative ground, and is beautiful and practical. The construction method is strong in maneuverability, smoothly completes the whole construction process, does not need to stop construction, saves construction cost, and reduces construction strength.

Description

Toilet threshold stone waterproof construction and construction method
Technical field
The present invention relates to a kind of buildings waterproof structure, specifically, is related to a kind of toilet threshold stone waterproof construction and applies Work method.
Background technology
Generally when washing one's face and rinsing one's mouth or having a bath, accomodation ground can stockpile substantial amounts of water, therefore accomodation ground can all do waterproof Measure, even if water is leaked into also will not leak into downstairs below toilet floor tile, leaking into the water of bottom can only store stream to defending Doorway between life.If waterproof is not carried out in metope and the region outside toilet, logical the producing of current can inhale on metope, cause wall breast Shellac varnish is chronically at dampness, and the peeling that comes off is caused in the course of time.Furthermore because parlor outside toilet etc. mostly adopts Solid wooden floor board, wood materials are easy to absorb moisture, and of long duration, the easily mouldy blackening of plank affects the U.S. on parlor ground very much The property seen.
Water to avoid toilet is penetrated into living room floors, it is common practice that:Set up with ground joint portion in toilet and defend Threshold stone between life, and the mode of wet-laying is taken, applied along the surrounding of threshold stone with waterproof material and brushed one times, and in threshold stone and door The waterproof material of the joint portion brushing certain altitude of girder construction, is inhaled with the water for preventing toilet on metope.This way Really play certain waterproof effect, but because threshold stone can not be above ground level too many in case threshold stone is tripped, once and health Between ground water accumulation it is excessive, waterproof material cannot also play good interception function, and the water that still can there is toilet is crossed Threshold stone and the waterproof material brushed penetrate into the floor in parlor.
China Patent No. CN202990369 discloses a kind of toilet threshold stone sealing belting, by toilet stone material Waterstop is set up with the junction of threshold stone, waterstop adopts pea gravel concreten, and pea gravel concreten is arranged at basic unit and waterproof Between layer, the waterproof problem of waterproof layer lower floor can be well solved, for not doing any between waterproof layer and threshold stone Waterproof measure, find that still having outside binder courses of the part water along between threshold stone OR gate sill stone and waterproof layer oozes in practice Thoroughly to wood floor.And mention in the construction method:After the construction of waterstop pea gravel concreten completes 7 days, waterproof material is smeared, Complete threshold stone construction operation.It can be seen that, the construction period that the waterproofing process needs is longer, is unsuitable for surface construction in large area.
The content of the invention
It is an object of the invention to provide a kind of toilet threshold stone waterproof construction and construction method, solve existing bathroom door The infiltration problem on the waterproof layer upper strata of sill stone, improves the reliability of waterproof at toilet threshold.
The technical scheme is that:Toilet threshold stone waterproof construction, is arranged at accomodation ground with plank ornamentally The joint portion in face, the waterproof construction includes successively from top to bottom threshold stone, cement mortar adhered layer, waterproof layer and grade beam, described The upper surface of threshold stone and the upper surface flush of solid wooden floor board layer, the lower surface of threshold stone is neat with the upper surface of floor tile finished surface It is flat;The grade beam is built into trapezoidal, and grade beam is arranged under threshold stone civil engineering structure layer and threshold stone by accomodation ground side Joint portion, the upper surface of grade beam is less than the lower surface of floor tile finished surface, and the lower surface of grade beam is higher than the water of accomodation ground side The upper surface of cement mortar tack coat;The waterproof layer is covered in the upper surface of grade beam, and waterproof layer near accomodation ground one end It is downward-sloping to be connected with the waterproof layer of accomodation ground, civil engineering of the waterproof layer near plank decorative ground one end below threshold stone Structure sheaf upper surface is laid, and turns on vertical with plank decorative ground junction and be connected with the waterproof layer of plank decorative ground; Waterproof adhesive layer, the width of waterproof adhesive layer are set between the waterproof layer upper surface and threshold stone lower surface directly over the grade beam It is consistent with the width at bottom on trapezoidal grade beam;The cement mortar adhered layer be filled in waterproof layer upper surface and threshold stone lower surface it Between.
Further, it is the caking property of raising threshold stone and civil engineering structure layer, and strengthens the water proofing property of intermediate adhesive layer, it is described Cement mortar adhered layer adopts 20mm thickness 1:3 cement mortar, preferred excessive glue mud, the threshold stone of the trapezoidal grade beam left and right sides is by overflowing Clay is bonded in civil engineering structure layer.
Further, it is the caking property and water proofing property that improve threshold stone lower section and trapezoidal grade beam upper surface joint portion, it is described Using plastic-steel mud or fluid sealant, the thickness of waterproof adhesive layer is 3-5mm to the material of waterproof adhesive layer, trapezoidal grade beam upper surface with it is right The threshold stone lower surface answered is by the waterproof adhesive layer bonding.
Further, to prevent toilet floor tile from completing the infiltration towards threshold stone left and right sides metope, threshold stone or so two 300mm is turned on the metope of side waterproof layer is set.
Structure sheaf is avoided to make moist to ooze sewage under collection, the accomodation ground of the waterproof construction is provided with standing floor drain and increasing If floor drain, standing floor drain is arranged at the joint portion between waterproof layer and floor tile finished surface, and standing floor drain soil stack is vertically worn Cross civil engineering structure;The side that floor drain is installed on standing floor drain is set up, the cement mortar that floor drain is arranged above waterproof layer is set up and is prevented In water conservation layer, and covering drainage screen gauze between the upper surface of floor drain and the lower surface of cement mortar tack coat is set up, set up Floor drain soil stack passed perpendicularly through and connected with standing floor drain soil stack after civil engineering structure.
Preferably, the upper end for setting up floor drain adopts upwardly opening horn-like structure, and horn-like structure and water Smear waterproof layer in cement mortar fish tail and waterproof layer contact position.
Preferably, upper surface of the drain cover of the standing floor drain less than floor tile finished surface, and cement mortar tack coat Inclining to standing floor drain side near standing floor drain one end, angle of inclination is 1 °.
Invention additionally discloses a kind of construction method of toilet threshold stone waterproof construction, including following methods step:
1) the civil engineering structure layer below threshold stone is levelling, and the civil engineering structure layer height of threshold stone is less than plank decorative ground Waterproof layer and higher than the waterproof layer of floor tile finished surface;
2) trapezoidal grade beam is built after upper surface of the civil engineering structure layer near accomodation ground side, grade beam upper surface is less than ground Brick finished surface upper surface 3-5mm, grade beam both sides incline at an angle relative to civil engineering structure layer;
3) upper surface along trapezoidal grade beam and civil engineering structure layer integrally lays waterproof layer, and waterproof layer is near accomodation ground one The downward-sloping waterproof layer with accomodation ground in end is overlapped, waterproof layer near plank decorative ground one end it is vertical on turn over and plank dress The waterproof layer overlap joint on decorations ground;
4) bondd using fluid sealant between the waterproof layer and threshold stone directly over trapezoidal grade beam, and the width of fluid sealant and ladder The width at bottom is consistent on shape grade beam;
5) the upper surface brushing cement mortar tack coat of trapezoidal grade beam both sides waterproof layer, the upper surface of cement mortar tack coat With the upper surface flush of floor tile finished surface and less than the lower surface of solid wooden floor board layer;
6) threshold stone is layed in the upper surface of cement mortar tack coat, and the upper surface of threshold stone is upper with solid wooden floor board layer Surface flushes.The present invention having the beneficial effect that compared with prior art:
The waterproof construction can effectively solve the infiltration problem on the waterproof layer upper strata of existing toilet threshold stone, improve and defend Between life at threshold waterproof reliability, by lay waterproof layer prevent the water of accomodation ground from infiltrating into civil engineering structure layer downwards, By set up trapezoidal grade beam prevent to leak out to the steam of toilet floor tile finished surface lower surface by threshold stone to plank ornamentally Face seepage, by being arranged at cement mortar fish tail and waterproof layer in set up floor drain, floor tile finished surface and cement mortar are bondd On layer the sewage collecting of seepage and by set up floor drain soil stack discharge, effectively prevent waterproof layer and ground brick layer between structure Layer long-term storage is in state of making moist.The waterproof of the waterproof construction is highly reliable, meets accomodation ground and plank decorative ground Elevation difference require, it is and both artistic and practical;The construction method is workable, and whole work progress accomplishs without any letup, and stops without the need for construction Stay, save construction cost and reduce construction intensity.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is threshold Plumbum preparatium position enlarged drawing;
Fig. 3 is with the waterproof construction schematic diagram for setting up floor drain.
In figure,
101 civil engineering structures;102 waterproof layers;103 cement mortar fish tail and waterproof layers;104 cement mortar tack coats;105 floor tiles Finished surface;
201 civil engineering structure layers;202 wood floor cushion layers;203 waterproof layers;204 solid wooden floor board layers;
301 threshold stones;302 cement mortar adhered layers;303 waterproof layers;304 grade beams;305 civil engineering structure layers;306 marine glues Glutinous layer;
401 set up floor drain;402 set up floor drain soil stack;403 drainage screen gauzes;
501 standing floor drains;502 standing floor drain soil stacks;503 drain covers.
Specific embodiment
To make purpose, technical scheme and the advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is The embodiment of a part of the invention, rather than the embodiment of whole.Based on the embodiment in the present invention, those skilled in the art exist The every other embodiment obtained on the premise of not making creative work, belongs to protection scope of the present invention.
Embodiment 1
A kind of toilet threshold stone waterproof construction, is arranged at the joint portion of accomodation ground and plank decorative ground.
Referring to Fig. 1 and Fig. 2, accomodation ground includes that from bottom to up civil engineering structure layer 101, waterproof layer 102, cement mortar are prevented Water conservation layer 103, cement mortar tack coat 104 and floor tile finished surface 105.Cement mortar fish tail and waterproof layer 103 adopts 5mm thickness 1: 2.5 cement mortar, cement mortar tack coat 103 adopts 20mm thickness 1:3 cement mortar.Waterproof layer 102 is layed in whole soil Build the upper surface of structure sheaf, for stopping floor tile finished surface 105 under the water penetration oozed to civil engineering structure layer 101.
Plank decorative ground includes from bottom to up civil engineering structure layer 201, wood floor cushion layer 202, waterproof layer 203 and solid wood ground Flaggy 204.Solid wooden floor board layer 204 adopts the abundant wood composite floors of 12mm.It is close that waterproof layer 203 is layed in wood floor cushion layer 202 The upper surface of threshold stone side, for stopping that the waterborne of civil engineering structure layer 201 is oozed to solid wooden floor board layer 204.
The waterproof construction includes successively from top to bottom threshold stone 301, cement mortar adhered layer 302, waterproof layer 303 and grade beam 304, threshold stone 301 adopts 18mm thickness stone material threshold stones, and the upper surface of the upper surface of threshold stone 301 and solid wooden floor board layer 204 Flush, the lower surface of threshold stone 301 and the upper surface flush of floor tile finished surface 105.
Grade beam 304 is built into trapezoidal, and trapezoidal grade beam adopts isosceles trapezoid grade beam, and 304 liang of waists of grade beam are relative to civil engineering structure Layer 305 is in 45 ° of inclinations.The upper bottom width of trapezoidal grade beam 304 is preferably 50mm, and grade beam 304 is arranged at threshold stone and leans on health 301 times Between ground side civil engineering structure layer 101 and threshold stone 301 joint portion, the upper surface of grade beam 304 is less than floor tile finished surface 105 Lower surface, the lower surface of grade beam 304, can higher than the upper surface of the cement mortar fish tail and waterproof layer 103 of accomodation ground side Effectively prevent the steam for leaking out to the lower surface of toilet floor tile finished surface 105 by threshold stone 301 to plank decorative ground seepage.
Waterproof layer 303 is covered in the upper surface of grade beam 304, and waterproof layer 303 is downward-sloping near accomodation ground one end It is connected with the waterproof layer 102 of accomodation ground, soil of the waterproof layer 303 near plank decorative ground one end below threshold stone 301 The laying of the upper surface of structure sheaf 305 is built, and the waterproof layer with plank decorative ground is turned on vertical with plank decorative ground junction 203 connections.
Waterproof adhesive layer 306 is provided between the upper surface of waterproof layer 303 and the lower surface of threshold stone 301 directly over grade beam 304, The width of waterproof adhesive layer 306 is consistent with the width at bottom on trapezoidal grade beam 304, and the material of waterproof adhesive layer 306 is preferably plastic-steel Mud or fluid sealant.The thickness of waterproof adhesive layer 306 is the waterproof layer of 3-5mm, the i.e. lower surface of threshold stone 301 and the top of grade beam 304 The waterproof adhesive layer of 3-5mm is formed between 303 upper surfaces.
Cement mortar adhered layer 302 adopts 20mm thickness 1:3 cement mortar tack coats, preferably excessive glue mud, and be filled in anti- Between the upper surface of water layer 303 and the lower surface of threshold stone 301, excessive glue mud not only may act as the tack coat of threshold stone 301, by threshold stone 301 civil engineering structure layers 305 for being bonded in lower section, and excessive glue mud is a kind of rigidity water-proofing material, possess certain hardness and impervious Permeability.
To prevent the water of accomodation ground by wall leakage of the threshold stone 301 to threshold stone both sides, threshold stone or so two 300mm is turned on the metope of side waterproof layer is set.
Invention additionally discloses a kind of construction method of toilet threshold stone waterproof construction, comprises the following steps that:
1) the civil engineering structure layer 305 of the lower section of threshold stone 301 is levelling, and the height of civil engineering structure layer 305 of threshold stone 301 is less than wood The waterproof layer 203 of plate decorative ground and higher than the waterproof layer 102 of floor tile finished surface;
2) trapezoidal grade beam 304 is built after upper surface of the civil engineering structure layer 305 near accomodation ground side, on grade beam 304 Surface is less than the upper surface 3-5mm of floor tile finished surface 105, and the both sides of grade beam 304 are inclined at an angle relative to civil engineering structure layer 305 Tiltedly;
3) upper surface along trapezoidal grade beam 304 and civil engineering structure layer 305 integrally lays waterproof layer 303, and waterproof layer 303 is close The downward-sloping waterproof layer 102 with accomodation ground in accomodation ground one end is overlapped, and waterproof layer 303 is near plank decorative ground one Turn on end is vertical and overlapped with the waterproof layer 203 of plank decorative ground;
4) using the bonding of 3-5mm thickness fluid sealants between the waterproof layer 303 and threshold stone 301 directly over trapezoidal grade beam 304, And the width of fluid sealant is consistent with the width at bottom on trapezoidal grade beam 304;
5) the upper surface brushing 20mm thickness 1 of trapezoidal grade beam both sides waterproof layer 303:3 cement mortar tack coats 302, cement bonded sand The upper surface of slurry tack coat 302 is with the upper surface flush of floor tile finished surface 105 and less than the lower surface of solid wooden floor board layer 204;
6) threshold stone 301 is layed in the upper surface of cement mortar tack coat 302, and the upper surface and solid wood of threshold stone 301 The upper surface flush of floor layer 204.
The construction method is workable, and whole work progress accomplishs without any letup, and without the need for stopping, is prevented by laying waterproof layer The water of accomodation ground infiltrates into downwards civil engineering structure layer, prevents to leak out to toilet floor tile finished surface by setting up trapezoidal grade beam The steam of lower surface is by threshold stone to plank decorative ground seepage, and waterproof is highly reliable, meets accomodation ground and plank dress The elevation difference requirement on decorations ground, and it is both artistic and practical.
Embodiment 2
The structure of the waterproof construction of embodiment 2 is essentially identical with composition with composition and the structure of the waterproof construction of embodiment 1, Distinguishing characteristicss are:
Referring to Fig. 3, the accomodation ground of the waterproof construction is provided with standing floor drain 501 and sets up floor drain 401, sets up floor drain 501 are arranged at the joint portion between waterproof layer 102 and floor tile finished surface 105.
The drain cover 503 of standing floor drain 501 is less than the upper surface of floor tile finished surface 105, and cement mortar tack coat 104 is adopted 1:2.5 cement mortar, cement mortar tack coat 104 is being inclined near standing one end of floor drain 501 to standing floor drain side, is inclined Angle is 1 °, is easy to the sewage following current of floor tile finished surface 105 into standing floor drain 501.
Standing floor drain soil stack 502 is installed on the lower end of standing floor drain 501, and standing floor drain soil stack 502 is vertical Through civil engineering structure 101, by the sewage transport collected in standing floor drain 501 to sewage draining exit.
Standing floor drain 501 is only used for collecting the current collected on floor tile finished surface 105, and part of contaminated water can be completed by floor tile Ooze under face 105, under the sewage that oozes discharges cannot be collected by standing floor drain 501, cause waterproof layer 102 and floor tile finished surface Structure sheaf long-term storage between 105 is in state of making moist, destruction floor tile finished surface 105.
To ooze sewage under collection, it is to avoid structure sheaf makes moist, floor drain 401 is set up in the neighbouring installation of standing floor drain 501, set up Floor drain 401 is arranged at the cement mortar fish tail and waterproof layer 103 of the top of waterproof layer 102, and sets up the upper surface and cement of floor drain 401 Drainage screen gauze 403 is covered between the lower surface of mortar bonding layer 104, once the sewage of the seepage of floor tile finished surface 105 flow to water Cement mortar tack coat 104, after drainage screen gauze 403 of the sewage Jing setting up on floor drain 401 is filtered, will along set up floor drain 401 to Lower discharge.
Set up floor drain soil stack 402 and be installed on and set up the lower end of floor drain 401, and it is vertical to set up floor drain soil stack 402 Connect with standing floor drain soil stack 502 through after civil engineering structure 101, the sewage discharge collected in floor drain will be set up.
To improve the collection seepage rate for setting up floor drain 401, the upper end for setting up floor drain 104 adopts upwardly opening horn-like knot Structure, and flare openings smear waterproof layer with the contact position of cement mortar fish tail and waterproof layer 103, prevent sewage edge from setting up floor drain draining The outer tube arm of standpipe 402 flows out, and seepage occurs.

Claims (7)

1. toilet threshold stone waterproof construction, is arranged at the joint portion of accomodation ground and plank decorative ground, it is characterised in that: The waterproof construction includes successively from top to bottom threshold stone, cement mortar adhered layer, waterproof layer and grade beam, the upper table of the threshold stone Face and the upper surface flush of solid wooden floor board layer, the lower surface of threshold stone and the upper surface flush of floor tile finished surface;The grade beam is built In echelon, grade beam is arranged under threshold stone the joint portion of the civil engineering structure layer by accomodation ground side and threshold stone, grade beam Less than the lower surface of floor tile finished surface, the lower surface of grade beam is higher than the cement mortar waterproofing protection of accomodation ground side to upper surface The upper surface of layer;The waterproof layer is covered in the upper surface of grade beam, and waterproof layer near accomodation ground one end it is downward-sloping with The waterproof layer connection of accomodation ground, civil engineering structure layer upper table of the waterproof layer near plank decorative ground one end below threshold stone Face is laid, and is turned on vertical with plank decorative ground junction and be connected with the waterproof layer of plank decorative ground;The grade beam is just Waterproof adhesive layer, the width of waterproof adhesive layer and trapezoidal grade beam are set between the waterproof layer upper surface and threshold stone lower surface of top The width at upper bottom is consistent;The cement mortar adhered layer is filled between waterproof layer upper surface and threshold stone lower surface;The waterproof The accomodation ground of structure is provided with standing floor drain and sets up floor drain, and standing floor drain is arranged between waterproof layer and floor tile finished surface Joint portion, and standing floor drain soil stack passes perpendicularly through civil engineering structure;The side that floor drain is installed on standing floor drain is set up, is set up Floor drain is arranged in the cement mortar fish tail and waterproof layer above waterproof layer, and sets up the upper surface and cement mortar tack coat of floor drain Lower surface between cover drainage screen gauze, set up floor drain soil stack pass perpendicularly through it is vertical with standing floor drain draining after civil engineering structure Pipe is connected.
2. toilet threshold stone waterproof construction according to claim 1, it is characterised in that:The cement mortar adhered layer is adopted With 20mm thickness 1:3 cement mortar, the threshold stone of the trapezoidal grade beam left and right sides is bonded in civil engineering structure layer by the cement mortar.
3. toilet threshold stone waterproof construction according to claim 1 and 2, it is characterised in that:The waterproof adhesive layer Using plastic-steel mud or fluid sealant, the thickness of waterproof adhesive layer is 3-5mm to material, trapezoidal grade beam upper surface with corresponding threshold stone Surface is by the waterproof adhesive layer bonding.
4. toilet threshold stone waterproof construction according to claim 1, it is characterised in that:The metope of the threshold stone left and right sides On turn over 300mm arrange waterproof layer.
5. toilet threshold stone waterproof construction according to claim 1, it is characterised in that:Adopt the upper end for setting up floor drain With upwardly opening horn-like structure, and horn-like structure smears waterproof layer with cement mortar fish tail and waterproof layer contact position.
6. toilet threshold stone waterproof construction according to claim 1, it is characterised in that:The drain cover of the standing floor drain Incline to standing floor drain side in close standing floor drain one end less than the upper surface of floor tile finished surface, and cement mortar tack coat, Angle of inclination is 1 °.
7. a kind of toilet threshold stone waterproof construction method of toilet threshold stone waterproof construction as claimed in claim 1, it is special Levy is to include following methods step:
1) the civil engineering structure layer below threshold stone is levelling, and the civil engineering structure layer height of threshold stone is less than the waterproof of plank decorative ground Layer and higher than the waterproof layer of floor tile finished surface;
2) trapezoidal grade beam is built after upper surface of the civil engineering structure layer near accomodation ground side, grade beam upper surface is complete less than floor tile Into face upper surface 3-5mm, grade beam both sides incline at an angle relative to civil engineering structure layer;
3) upper surface along trapezoidal grade beam and civil engineering structure layer integrally lays waterproof layer, waterproof layer near accomodation ground one end to Lower inclination is overlapped with the waterproof layer of accomodation ground, waterproof layer near plank decorative ground one end it is vertical on turn over plank ornamentally The waterproof layer overlap joint in face;
4) bondd using fluid sealant between the waterproof layer and threshold stone directly over trapezoidal grade beam, and the width of fluid sealant with it is trapezoidal The width at bottom is consistent on beam;
5) the upper surface brushing cement mortar tack coat of trapezoidal grade beam both sides waterproof layer, upper surface and the ground of cement mortar tack coat The upper surface flush of brick finished surface and less than the lower surface of solid wooden floor board layer;
6) threshold stone is layed in the upper surface of cement mortar tack coat, and the upper surface of the upper surface of threshold stone and solid wooden floor board layer Flush.
CN201510253449.3A 2015-05-18 2015-05-18 Toilet threshold stone waterproof structure and construction method Active CN104818835B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510253449.3A CN104818835B (en) 2015-05-18 2015-05-18 Toilet threshold stone waterproof structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510253449.3A CN104818835B (en) 2015-05-18 2015-05-18 Toilet threshold stone waterproof structure and construction method

Publications (2)

Publication Number Publication Date
CN104818835A CN104818835A (en) 2015-08-05
CN104818835B true CN104818835B (en) 2017-04-19

Family

ID=53729295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510253449.3A Active CN104818835B (en) 2015-05-18 2015-05-18 Toilet threshold stone waterproof structure and construction method

Country Status (1)

Country Link
CN (1) CN104818835B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447948A (en) * 2017-08-23 2017-12-08 浙江宏恩装饰工程有限公司 A kind of construction technology of subsided rest room
CN113431292A (en) * 2021-06-17 2021-09-24 深圳海外装饰工程有限公司 Dry-method overall paving structure of fabricated ground

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030066922A (en) * 2002-02-06 2003-08-14 이병석 The method of sound and vibration proof in concrete structure
TW201239176A (en) * 2012-05-11 2012-10-01 Jhih-Cheng Syu Completion of the construction of floor structure after the reduction of sound construction methods and its tectonic
CN202467495U (en) * 2011-12-28 2012-10-03 深圳市名雕丹迪设计有限公司 Waterproof doorsill
CN202990369U (en) * 2012-12-05 2013-06-12 华鼎建筑装饰工程有限公司 Water stop device with bathroom threshold stones
CN203347182U (en) * 2013-07-18 2013-12-18 北京丽贝亚建筑装饰工程有限公司 Water-impermeable structural layer for toilet
CN204609233U (en) * 2015-05-18 2015-09-02 青岛建安建设集团有限公司 Washroom threshold stone waterproof construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030066922A (en) * 2002-02-06 2003-08-14 이병석 The method of sound and vibration proof in concrete structure
CN202467495U (en) * 2011-12-28 2012-10-03 深圳市名雕丹迪设计有限公司 Waterproof doorsill
TW201239176A (en) * 2012-05-11 2012-10-01 Jhih-Cheng Syu Completion of the construction of floor structure after the reduction of sound construction methods and its tectonic
CN202990369U (en) * 2012-12-05 2013-06-12 华鼎建筑装饰工程有限公司 Water stop device with bathroom threshold stones
CN203347182U (en) * 2013-07-18 2013-12-18 北京丽贝亚建筑装饰工程有限公司 Water-impermeable structural layer for toilet
CN204609233U (en) * 2015-05-18 2015-09-02 青岛建安建设集团有限公司 Washroom threshold stone waterproof construction

Also Published As

Publication number Publication date
CN104818835A (en) 2015-08-05

Similar Documents

Publication Publication Date Title
CN113186985B (en) Anti-seepage treatment method for basement bottom plate construction joint
CN105201025B (en) Basement waterproofing construction and its construction method
CN105951893A (en) Uplift pile head node waterproof structure and construction method thereof
CN207110817U (en) Toilet threshold waterproof construction
CN109750758A (en) The construction method that prefabricated sandwich heat preservation shear wall exterior wall is laterally stitched and vertically stitched
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN104818835B (en) Toilet threshold stone waterproof structure and construction method
CN206205167U (en) A kind of indoor toilets threshold stone water proof structure
CN101131007A (en) Preventing method for exterior wall leakage of face tile
CN206070602U (en) Resistance to plucking pile head node waterproof structure
CN206220272U (en) Ground hot water lays heating toilet doorway sealing damp proof insulation construction
CN107227823A (en) A kind of foreign-style house waterproof roof-working method
CN204609233U (en) Washroom threshold stone waterproof construction
CN206205168U (en) A kind of bathroom door pin waterproof treatment structure
CN106978845A (en) Plough groove type rainwater collection pool and rainwater on road surface collection method
CN107675811B (en) Bathroom waterproof system and construction method
CN109881794A (en) A kind of swimming pool waterproof construction
CN218324144U (en) Basement high pressure joins in marriage electrical room bottom plate
CN216007579U (en) Waterproof integration roofing structure permeates water
CN208167997U (en) Waterproof construction at a kind of toilet threshold
CN204849510U (en) What be adapted to gardens and residential quarter prevents accumulation of salt in surface soil pavement structure
CN211950114U (en) Threshold stagnant water structure
CN206015833U (en) Toilet waterproofing structure
CN214531706U (en) Deodorant laying structure of floor tile
CN110924451A (en) Drainage method for seepage of reservoir cracks

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 266000 Shandong province Qingdao City, Shandong Road No. 168

Applicant after: Qingdao Jianan Construction Group Co., Ltd.

Address before: 266000 Shandong Province, Qingdao city Shandong Road No. 16 building 26

Applicant before: Qingdao Jianan Construction Group Co., Ltd.

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 266000 Shandong province Qingdao City, Shandong Road No. 168

Patentee after: ZHONGQING JIANAN CONSTRUCTION GROUP Co.,Ltd.

Address before: 266000 Shandong province Qingdao City, Shandong Road No. 168

Patentee before: QINGDAO JIANAN CONSTRUCTION GROUP Co.,Ltd.