CN117057025A - Power distribution room design method and system and power distribution room - Google Patents

Power distribution room design method and system and power distribution room Download PDF

Info

Publication number
CN117057025A
CN117057025A CN202311314664.0A CN202311314664A CN117057025A CN 117057025 A CN117057025 A CN 117057025A CN 202311314664 A CN202311314664 A CN 202311314664A CN 117057025 A CN117057025 A CN 117057025A
Authority
CN
China
Prior art keywords
power distribution
distribution room
model
settlement
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202311314664.0A
Other languages
Chinese (zh)
Other versions
CN117057025B (en
Inventor
李玲
周涵
姚超
邢洪弟
刘玉华
宋宾宾
马文立
苗勇
张丰智
古继涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yutai Power Supply Co Of State Grid Shandong Electric Power Co
Jining Power Supply Co
Original Assignee
Yutai Power Supply Co Of State Grid Shandong Electric Power Co
Jining Power Supply Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yutai Power Supply Co Of State Grid Shandong Electric Power Co, Jining Power Supply Co filed Critical Yutai Power Supply Co Of State Grid Shandong Electric Power Co
Priority to CN202311314664.0A priority Critical patent/CN117057025B/en
Publication of CN117057025A publication Critical patent/CN117057025A/en
Application granted granted Critical
Publication of CN117057025B publication Critical patent/CN117057025B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • E04H5/04Transformer houses; Substations or switchgear houses
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Architecture (AREA)
  • Geometry (AREA)
  • Computer Hardware Design (AREA)
  • General Physics & Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Power Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the field of building design, and provides a power distribution room design method and system and a power distribution room, wherein the method comprises the following steps: establishing a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and performing sedimentation simulation; designing a power distribution room simulation basic model according to the settlement simulation result, and performing settlement simulation to obtain a first settlement result; manufacturing and installing a power distribution room simulation foundation, and observing the installed settlement amount to obtain a second settlement result; calculating an error between the first sedimentation result and the second sedimentation result, and adjusting the three-dimensional geological model according to the error; designing a final power distribution room foundation model and a final power distribution room overall model by using the adjusted three-dimensional geological model, and manufacturing a power distribution room foundation, a prefabricated wall body and a prefabricated roof; installing a power distribution room foundation and pre-correcting inclination; and installing a prefabricated wall body and a prefabricated roof on the basis of the power distribution room after pre-correcting the inclination. The invention can realize the correction compensation of consolidation settlement.

Description

Power distribution room design method and system and power distribution room
Technical Field
The invention relates to the field of building design, in particular to a power distribution room design method and system and a power distribution room.
Background
The statements in this section merely provide background information related to the present disclosure and may not necessarily constitute prior art.
The power distribution room is called a power distribution substation, and is an important power distribution building. In order to realize standardized manufacturing and simplify the construction flow, the current distribution room is mostly an assembled distribution room, and various prefabricated members are installed after a prefabricated foundation is installed on a foundation so as to realize the assembly of the distribution room. Irregular settlement of a building foundation can occur under the action of long-term load, and because the connecting structure of the assembled power distribution room is not particularly stable, after settlement occurs, the structural connection part of the power distribution room can be cracked by directly adopting a traditional inclination correction method.
The Chinese patent publication No. CN115828381A discloses a design method of a power distribution room foundation, which is convenient for correcting inclination, provides a design concept of correcting inclination first and then installing the power distribution room, and avoids the problem of structural cracking possibly caused by correcting inclination of the assembled power distribution room. However, the patent only considers the initial sedimentation of the power distribution room, namely the instantaneous sedimentation after load application, but does not consider the consolidation sedimentation generated with time after load application, and the correction compensation of the consolidation sedimentation cannot be performed.
Disclosure of Invention
In order to solve the problems, the invention provides a power distribution room design method, a system and a power distribution room, wherein settlement of the power distribution room is simulated, pre-correction is performed on the power distribution room according to a simulation result, and correction compensation of consolidation settlement is realized.
In order to achieve the above purpose, the present invention adopts the following technical scheme:
one or more embodiments provide a power distribution room design method, comprising:
establishing a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and performing sedimentation simulation on the initial power distribution room foundation model and the initial power distribution room overall model;
designing a power distribution room simulation basic model according to the settlement simulation result, and performing settlement simulation on the power distribution room simulation basic model to obtain a first settlement result;
manufacturing and installing a power distribution room simulation foundation according to the designed power distribution room simulation foundation model, and observing sedimentation after the power distribution room simulation foundation is installed to obtain a second sedimentation result;
calculating an error between the first sedimentation result and the second sedimentation result, and adjusting the three-dimensional geological model according to the error;
designing a final power distribution room basic model and a final power distribution room integral model by using the adjusted three-dimensional geological model;
manufacturing a power distribution room foundation, a prefabricated wall body and a prefabricated roof according to the final power distribution room foundation model and the final power distribution room overall model;
installing a power distribution room foundation, and pre-correcting inclination of the power distribution room foundation;
and installing a prefabricated wall body and a prefabricated roof on the basis of the power distribution room after pre-correcting the inclination.
Preferably, the designing a power distribution room simulation basic model according to the sedimentation simulation result includes:
if the settlement of the initial power distribution room integral model does not meet the requirement, reinforcing a power distribution room foundation or replacing the installation position of the power distribution room;
if the settlement amount of the initial power distribution room integral model meets the requirements, and the settlement deviation of the initial power distribution room base model and the settlement deviation of the initial power distribution room integral model do not meet the requirements, redesigning the initial power distribution room base model and the initial power distribution room integral model according to the simulation result, or reinforcing a power distribution room foundation, and then re-simulating;
if the settlement amount of the initial power distribution room integral model meets the requirements, the settlement deviation of the initial power distribution room basic model does not meet the requirements, but the settlement deviation of the initial power distribution room integral model meets the requirements, and the initial power distribution room basic model is the power distribution room simulation basic model at the moment;
if the settlement amount of the initial power distribution room integral model meets the requirements, the settlement deviation of the initial power distribution room basic model meets the requirements, but the settlement deviation of the initial power distribution room integral model does not meet the requirements, modifying the initial power distribution room integral model, adjusting load distribution, and re-simulating; if the whole model of the initial power distribution room still does not meet the sedimentation deviation requirement after modification, reinforcing a power distribution room foundation or increasing the contact area between the basic model of the initial power distribution room and the ground;
if the settlement amount of the initial power distribution room integral model meets the requirements, and the settlement deviation of the initial power distribution room base model and the settlement deviation of the initial power distribution room integral model meet the requirements, the initial power distribution room base model is the power distribution room simulation base model.
Preferably, the initial power distribution room integral model comprises an initial power distribution room foundation, an initial power distribution room prefabricated wall body, an initial power distribution room prefabricated roof and initial power distribution room equipment.
Preferably, the first sedimentation result includes a first sedimentation amount and a first offset amount, and the second sedimentation result includes a second sedimentation amount and a second offset amount.
Preferably, the calculation method of the error between the first sedimentation result and the second sedimentation result is as follows:
wherein a is an error,for the first settlement amount, ++>For the second settlement amount->For the first offset, +>And m is a sedimentation weight coefficient, and n is an offset weight coefficient.
Preferably, said adjusting the three-dimensional geologic model according to the error includes: and adjusting parameters of the three-dimensional geological model according to the error, and repeatedly calculating by utilizing the adjusted model until the error is smaller than the error setting threshold value to obtain the adjusted three-dimensional geological model.
Preferably, the pre-rectifying the foundation of the power distribution room includes: if the offset of the final overall power distribution room model is smaller than the simulated offset setting threshold, pre-correcting the inclination by using a shallow soil excavation inclination correction method, and setting the offset of the foundation inclination of the power distribution room according to the offset of the final overall power distribution room model; if the offset of the final power distribution room overall model is larger than the simulated offset setting threshold, pre-rectifying inclination by using a shallow soil-drawing inclination-rectifying method, enabling the power distribution room foundation to incline back to set the offset according to the settlement of the final power distribution room overall model, and simultaneously carrying out inclination-preventing reinforcement on the simulated power distribution room foundation in an inclined direction.
Preferably, the method further comprises the steps of observing the power distribution room after the prefabricated wall body and the prefabricated roof are installed, and installing power distribution room equipment according to a final power distribution room integral model if the power distribution room is not inclined within a set time; if the power distribution room is inclined within the set time and the offset does not exceed the offset set threshold, determining the installation position of the power distribution room equipment according to the offset when the power distribution room equipment is installed.
One or more embodiments provide a power distribution room design system comprising:
the initial settlement simulation module is configured to establish a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and perform settlement simulation on the initial power distribution room foundation model and the initial power distribution room overall model;
the power distribution room simulation basic design module is configured to design a power distribution room simulation basic model according to the settlement simulation result, and perform settlement simulation on the power distribution room simulation basic model to obtain a first settlement result;
the settlement observation module is configured to manufacture and install a power distribution room simulation foundation according to a designed power distribution room simulation foundation model, observe settlement after the power distribution room simulation foundation is installed, and obtain a second settlement result;
the model adjustment module is configured to calculate an error between the first sedimentation result and the second sedimentation result and adjust the three-dimensional geological model according to the error;
a final model design module configured to design a final power distribution room base model and a final power distribution room overall model using the adjusted three-dimensional geologic model;
a manufacturing module configured to manufacture a power distribution room foundation, a prefabricated wall, and a prefabricated roof based on the final power distribution room foundation model and the final power distribution room overall model;
the pre-rectification module is configured to install a power distribution room foundation and pre-rectify the power distribution room foundation;
and the installation module is configured to install the prefabricated wall body and the prefabricated roof on the basis of the power distribution room after pre-correcting the inclination.
The power distribution room comprises a power distribution room foundation, a prefabricated wall body and a prefabricated roof, and is designed by adopting the power distribution room design method.
Compared with the prior art, the invention has the beneficial effects that:
according to the invention, by designing the power distribution room simulation foundation, the error between the settlement simulation result (first settlement result) and the actual settlement observation result (second settlement result) of the power distribution room simulation foundation is obtained, so that the established three-dimensional geological model is corrected, and the model simulation accuracy is improved; and (3) designing a final power distribution room basic model and a final power distribution room overall model by using the corrected model, and pre-correcting inclination according to a simulation result after the power distribution room foundation is installed, so that inclination correction compensation for consolidation settlement is realized.
The advantages of the present invention, as well as additional aspects of the invention, will be described in detail in the following detailed examples.
Drawings
Fig. 1 is an overall flow chart of a first embodiment of the present invention.
Detailed Description
The invention will be further described with reference to the drawings and examples.
Example 1
In one or more embodiments, as shown in fig. 1, a power distribution room design method is provided, which includes the following steps:
s1, establishing a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and performing sedimentation simulation on the initial power distribution room foundation model and the initial power distribution room overall model;
s2, designing a power distribution room simulation basic model according to the settlement simulation result, and performing settlement simulation on the power distribution room simulation basic model to obtain a first settlement result;
s3, manufacturing and installing a power distribution room simulation foundation according to the designed power distribution room simulation foundation model, and observing sedimentation after the power distribution room simulation foundation is installed to obtain a second sedimentation result;
s4, calculating an error between the first sedimentation result and the second sedimentation result, and adjusting the three-dimensional geological model according to the error;
s5, designing a final power distribution room basic model and a final power distribution room integral model by using the adjusted three-dimensional geological model;
s6, manufacturing a power distribution room foundation, a prefabricated wall body and a prefabricated roof according to the final power distribution room foundation model and the final power distribution room overall model;
s7, installing a power distribution room foundation, and pre-correcting inclination of the power distribution room foundation;
and S8, installing a prefabricated wall body and a prefabricated roof on the basis of the power distribution room after pre-correcting the inclination.
The settlement of a building under long-term load generally comprises initial settlement, also called instantaneous settlement, which is the settlement occurring at the moment of load application, and consolidation settlement, which comprises primary consolidation settlement and secondary consolidation settlement, which is the settlement occurring in the process of continuously removing pore water in foundation soil after load application. Because consolidation sedimentation is sedimentation which occurs with time after load is applied, the prior art can only correct the initial sedimentation without considering the consolidation sedimentation, and therefore, the embodiment provides a brand new design method aiming at correction and compensation of the consolidation sedimentation.
In step S1, a three-dimensional geological model of a formation on a construction site needs to be acquired first, and the three-dimensional geological model can be built based on site drilling data and engineering geological profile information, or can be built through rayleigh wave detection and other modes.
The initial power distribution room basic model and the initial power distribution room overall model can be designed according to the existing design specifications, and the model established in the past can be directly used, and the model is required to be adjusted according to the simulation result in the follow-up process, so that the design is carried out according to a conventional design method.
And the settlement simulation simulates the settlement condition by using a finite element analysis mode, inputs finite element calculation parameters according to a three-dimensional geological model, respectively carries out settlement simulation on an initial power distribution room base model and an initial power distribution room integral model, and judges whether settlement amount and settlement deviation meet design requirements. The design requirements can refer to the allowable settlement and inclination of the building in national standards, and can also be specifically required according to the design specifications of the actual power distribution room.
In step S2, designing a power distribution room simulation basic model according to the sedimentation simulation result, including:
s21, if the settlement of the initial power distribution room integral model does not meet the requirement, reinforcing a power distribution room foundation or replacing the installation position of the power distribution room;
s22, if the settlement amount of the initial power distribution room integral model meets the requirements, and the settlement deviation of the initial power distribution room base model and the settlement deviation of the initial power distribution room integral model do not meet the requirements, redesigning the initial power distribution room base model and the initial power distribution room integral model according to the simulation result, or reinforcing a power distribution room foundation, and then re-simulating;
s23, if the settlement amount of the initial power distribution room integral model meets the requirements, the settlement offset of the initial power distribution room basic model does not meet the requirements, but the settlement offset of the initial power distribution room integral model meets the requirements, and the initial power distribution room basic model is the power distribution room simulation basic model at the moment;
s24, if the settlement amount of the initial power distribution room integral model meets the requirements, the settlement offset of the initial power distribution room basic model meets the requirements, but the settlement offset of the initial power distribution room integral model does not meet the requirements, modifying the initial power distribution room integral model, adjusting load distribution, and re-simulating; if the whole model of the initial power distribution room still does not meet the sedimentation deviation requirement after modification, reinforcing a power distribution room foundation or increasing the contact area between the basic model of the initial power distribution room and the ground;
s25, if the settlement amount of the initial power distribution room overall model meets the requirements, and the settlement offset of the initial power distribution room basic model and the settlement offset of the initial power distribution room overall model meet the requirements, the initial power distribution room basic model is the power distribution room simulation basic model. The settlement amount is the settlement amount of the whole building, corresponds to the settlement amount in the standard, and the settlement offset is the whole inclination condition of the building, corresponds to the inclination amount in the standard.
In step S21, since the initial power distribution room overall model includes the initial power distribution room foundation, the initial power distribution room prefabricated wall, the initial power distribution room prefabricated roof and the initial power distribution room equipment, that is, the initial power distribution room overall model itself includes the initial power distribution room foundation model, if the settlement of the initial power distribution room overall model does not meet the requirement, the settlement of the initial power distribution room foundation model does not meet the requirement, so that the settlement is judged by only analyzing the initial power distribution room overall model. When the settlement of the integral model of the initial power distribution room does not meet the requirement, the soil structure under the topography of the place is loose, or the pore water in the soil is more, so that the settlement is larger. The bearing capacity of the foundation can be increased by the methods of reinforcing the foundation, thickening the foundation and the like, so that sedimentation is reduced, or the installation position of the power distribution room is selected again.
If the settlement of the whole model of the initial power distribution room meets the requirement, entering a subsequent step, and judging the settlement offset.
In step S22, if the sedimentation deviation of the initial power distribution room basic model and the initial power distribution room overall model is not satisfactory, it may be caused by the uneven distribution of the underground soil or the current model may be problematic. Judging whether the load is mainly caused by uneven distribution of underground soil according to the three-dimensional geological model, if so, reinforcing the power distribution room foundation simultaneously to reduce settlement offset, or redesigning an initial power distribution room foundation model and an initial power distribution room integral model, mainly redistributing the load so that the load is mainly loaded on one side with smaller settlement amount, and then, carrying out simulation again to observe whether the design requirement can be met; if the settlement deviation is mainly caused by the model problem, the initial power distribution room base model and the initial power distribution room overall model are redesigned according to the simulation result, and then the simulation is carried out again. When the initial power distribution room foundation model and the initial power distribution room overall model are redesigned, the settlement deviation requirement of the initial power distribution room overall model is mainly considered to be met, the layout position of initial power distribution room equipment in the model can be adjusted at first to adjust load distribution, if the design requirement still cannot be met after adjustment, the initial power distribution room foundation model can be adjusted, the quality distribution of the initial power distribution room foundation model is adjusted, or the contact area between the power distribution room foundation model and the ground is increased.
In step S23, if the settlement offset of the initial power distribution room basic model does not meet the requirement, but the settlement offset of the initial power distribution room overall model meets the requirement, the initial power distribution room basic model is the power distribution room simulation basic model at this time as long as the settlement offset of the initial power distribution room overall model can be ensured to meet the requirement because the initial power distribution room overall model corresponds to the finally installed power distribution room.
In step S24, if the settlement offset of the basic model of the initial power distribution room meets the requirement, but the settlement offset of the overall model of the initial power distribution room does not meet the requirement, it indicates that after the loads of the prefabricated wall body of the initial power distribution room, the prefabricated roof of the initial power distribution room and the initial power distribution room equipment are increased, additional settlement offset is caused, at this time, the overall model of the initial power distribution room needs to be modified, the load distribution (the position of the initial power distribution room equipment is preferentially adjusted), and the simulation is performed again; and if the whole model of the initial power distribution room still does not meet the sedimentation deviation requirement after modification, reinforcing the foundation of the power distribution room, or increasing the contact area between the foundation model of the initial power distribution room and the ground.
In step S25, if the settlement amount and the settlement offset can meet the requirements, it is indicated that the initial power distribution room base model and the initial power distribution room overall model established at this time are reasonable, and the initial power distribution room base model is used as a power distribution room simulation base model.
In step S2, a first sedimentation result is obtained through simulation, where the first sedimentation result includes a first sedimentation amount and a first offset amount, and is used for subsequent error calculation, so as to adjust the three-dimensional geological model according to the actual situation, and improve the simulation accuracy.
In step S3, according to the power distribution room simulation basic model obtained in step S23 or S25, manufacturing and installing a power distribution room simulation basic, observing the sedimentation occurring after the installation of the power distribution room simulation basic, and obtaining a second sedimentation result, where the second sedimentation result includes a second sedimentation amount and a second offset, and the second sedimentation result can directly measure the sedimentation after the installation of the power distribution room simulation basic, i.e. initial sedimentation, or can be kept stand for a period of time after the installation of the power distribution room simulation basic, and measure the consolidation sedimentation occurring in the period of time so as to improve the subsequent simulation precision, specifically how to select, and can be selected according to actual conditions (such as requirements of construction period).
In step S4, an error between the first sedimentation result and the second sedimentation result is calculated, and the calculation method is as follows:
wherein a is an error,for the first settlement amount, ++>For the second settlement amount->For the first offset, +>And m is a sedimentation weight coefficient, and n is an offset weight coefficient.
The error a is a schematic value, which does not have an actual physical meaning, but can be merely used as a schematic of an error between the first sedimentation result and the second sedimentation result. Because the observation time is limited, the first sedimentation result and the second sedimentation result are both dominated by initial sedimentation, namely the absolute value of the sedimentation quantity is larger than or far larger than the absolute value of the offset quantity, so that in order to balance the relation between the first sedimentation result and the second sedimentation result, a weight coefficient is required to be introduced for compensation, and the size of the offset weight coefficient n is larger than the sedimentation weight coefficient m so as to improve the influence of the offset quantity on the error a.
And after the error a is obtained, adjusting the three-dimensional geological model according to the error a. Presetting an error setting threshold value x, adjusting parameters of a three-dimensional geological model according to the error a, re-simulating sedimentation of a simulation basic model of the power distribution room by using the adjusted model, and calculating the re-simulated error; and (3) through iterative adjustment until the error a is smaller than the error setting threshold value x, at the moment, the parameters of the three-dimensional geological model are considered to be matched with the actual address characteristics of the construction site, and the adjusted three-dimensional geological model is obtained and is used for subsequent simulation design.
In step S5, the adjusted three-dimensional geological model is used for designing a final power distribution room basic model and a final power distribution room overall model. Because the three-dimensional geological model is adjusted, the result of subsidence simulation can be influenced, and the adjusted three-dimensional geological model is needed to be used for carrying out subsidence simulation on the power distribution room simulation basic model and the initial power distribution room overall model which are established before. And if the simulation result still meets the requirement, taking the power distribution room simulation basic model as a final power distribution room basic model, and taking the initial power distribution room overall model as a final power distribution room overall model. If the simulation result of the initial power distribution room overall model does not meet the requirement, the initial power distribution room overall model needs to be adjusted, and the adjusted model is used as a final power distribution room overall model.
In step S7, after the power distribution room foundation is installed, pre-correcting the power distribution room foundation according to the sedimentation simulation result of the final power distribution room overall model in step S5. The shallow soil excavation inclination correction method can be used for correcting inclination, and small-amplitude shallow soil excavation is carried out on a position with small settlement in settlement simulation, so that settlement amount at the position is properly increased, inclination degree after a power distribution room is installed is reduced, and solidification settlement is compensated during installation. Because the overall installation back height of electricity distribution room is lower, and the fixed setting of internal equipment is subaerial, and the focus is lower, can allow to exist the slope of a small margin when being under construction. When pre-rectifying, the pre-rectifying amplitude needs to be controlled, and because the prefabricated wall body of the power distribution room, the prefabricated roof of the power distribution room and the power distribution room equipment are not installed at the moment, the consolidation settlement at the moment can be compensated only when the settlement simulation of the final power distribution room foundation model and the final power distribution room overall model incline towards the same direction in general, and the inclination amount of the power distribution room foundation after pre-rectifying needs to meet the requirements of national standards or design standards.
The final power distribution room integral model is designed according to the adjusted three-dimensional geological model, so that the final power distribution room integral model is designed after the design construction requirement and the requirement on the inclination amount in the standard are comprehensively considered, and a certain deviation amount can be designed within the inclination degree allowed by the standard in order to meet the actual construction and use requirements.
And setting a simulated deviation setting threshold according to actual conditions, if the deviation amount of the final overall power distribution room model is smaller than the simulated deviation setting threshold, pre-correcting the inclination by directly using a shallow soil excavation inclination correction method, and setting the deviation amount by back inclination of a power distribution room foundation according to the deviation amount of the final overall power distribution room model. The amplitude of the camber may typically be one-fourth to one-third of the amount of offset of the simulation, and should not exceed one-half. If the deviation (the height difference between the highest point and the lowest point of the foundation of the power distribution room) of the final overall model of the power distribution room obtained through simulation is 5cm, the foundation of the power distribution room can be tilted back by about 1.5cm during construction, on one hand, the tilting degree is within the standard requirement range, the influence on the overall structural strength of the power distribution room is small, and on the other hand, the follow-up consolidation settlement can be compensated to a certain degree; and after tilting back, the load changes, so that the load acts more on the position where the original settlement is smaller (namely the geological structure is tighter), the settlement condition of consolidation settlement can be slightly changed, and the subsequent offset is reduced.
If the offset of the final overall power distribution room model is larger than the simulated offset setting threshold, pre-correcting inclination can be carried out by using a shallow soil excavation inclination correction method, and the foundation inclination of the power distribution room is set to be offset according to the settlement of the final overall power distribution room model; in addition, the simulated inclined direction power distribution room foundation needs to be reinforced in an anti-tilting mode. Because the inclination correction effect is limited in a mode of correcting the inclination in advance through the inclination correction, when the designed offset is larger than the analog offset set threshold value, other measures are needed to be additionally taken to perform inclination prevention reinforcement on the power distribution room foundation, the strength of the power distribution room foundation can be improved through the inclination prevention reinforcement on one hand, the future foreseeable inclination is supported, and on the other hand, the possible inclination can be reduced to a certain extent.
The anti-tilting reinforcement mode can be adopted to increase the foundation area, increase the supporting pile body, strengthen the foundation and the like. For the increase basic area, can extend the distribution room basis in earth's surface or underground position, increase the area of contact of one side and ground of distribution room basis incline direction, on the one hand can even load, on the other hand the part that extends can provide certain effort when taking place the slope to reduce the inclination of distribution room itself. To increasing the support pile body, can additionally set up many support piles in the bottom of distribution room foundation incline direction, carry out the additional support to the distribution room of slope one side through the support pile. To consolidate the ground, can cooperate to increase to support pile body synchronous implementation, consolidate the processing through the ground to the distribution room foundation below of slope one side, increase this partial intensity of ground to reduce subsidence, cooperation support pile supports the distribution room foundation behind the increase foundation intensity, in order to further avoid the slope of distribution room.
In step S8, after installing the prefabricated wall body and the prefabricated roof, the method further includes: observing the power distribution room, and if the power distribution room does not incline within a set time, installing power distribution room equipment according to a final power distribution room overall model; if the power distribution room is inclined within the set time and the offset does not exceed the offset set threshold, determining the installation position of the power distribution room equipment according to the offset when the power distribution room equipment is installed.
Because the pre-rectification is performed in step S7, the power distribution room after the installation of the prefabricated wall body and the prefabricated roof needs to be observed for a certain time. If the power distribution room does not incline obviously within the set time (for example, 7 days), the power distribution room equipment can be directly installed according to the whole power distribution room model; if the power distribution room is inclined in a set time, but the offset does not exceed the offset set threshold, the installation position of the power distribution room equipment can be determined according to the offset when the power distribution room equipment is installed, and the position of the power distribution room equipment is properly adjusted, so that the power distribution room equipment is slightly close to a place with small settlement (namely, a higher position in the power distribution room after the inclination occurs), and the inclination degree of the power distribution room is reduced through the redistribution of loads. If the offset exceeds the set threshold, the offset indicates that the deviation exists in the early simulation process or the pre-rectification process, and the construction needs to be performed again, and at the moment, the prefabricated wall body and the prefabricated roof can be rapidly disassembled and rectification is performed again because the power distribution room equipment is not installed yet.
According to the embodiment, the error between the settlement simulation result (first settlement amount) and the actual settlement observation result (second settlement amount) of the power distribution room simulation foundation is obtained by designing the power distribution room simulation foundation, so that the established three-dimensional geological model is corrected, and the model simulation accuracy is improved; and (3) designing a final power distribution room basic model and a final power distribution room overall model by using the corrected model, and pre-correcting inclination according to a simulation result after the power distribution room foundation is installed, so that inclination correction compensation for consolidation settlement is realized.
Example 2
Based on embodiment 1, in this embodiment, a power distribution room design system includes:
the initial settlement simulation module is configured to establish a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and perform settlement simulation on the initial power distribution room foundation model and the initial power distribution room overall model;
the power distribution room simulation basic design module is configured to design a power distribution room simulation basic model according to the settlement simulation result, and perform settlement simulation on the power distribution room simulation basic model to obtain a first settlement result;
the settlement observation module is configured to manufacture and install a power distribution room simulation foundation according to a designed power distribution room simulation foundation model, observe settlement after the power distribution room simulation foundation is installed, and obtain a second settlement result;
the model adjustment module is configured to calculate an error between the first sedimentation result and the second sedimentation result and adjust the three-dimensional geological model according to the error;
a final model design module configured to design a final power distribution room base model and a final power distribution room overall model using the adjusted three-dimensional geologic model;
a manufacturing module configured to manufacture a power distribution room foundation, a prefabricated wall, and a prefabricated roof based on the final power distribution room foundation model and the final power distribution room overall model;
the pre-rectification module is configured to install a power distribution room foundation and pre-rectify the power distribution room foundation;
and the installation module is configured to install the prefabricated wall body and the prefabricated roof on the basis of the power distribution room after pre-correcting the inclination.
Here, the modules in this embodiment are in one-to-one correspondence with the steps in embodiment 1, and the implementation process is the same, which is not described here.
Example 3
The embodiment provides a power distribution room, including power distribution room basis, prefabricated wall body and prefabricated roof, adopts the design of a power distribution room design method that embodiment 1 provided.
The above description is only of the preferred embodiments of the present invention and is not intended to limit the present invention, but various modifications and variations can be made to the present invention by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. A method of power distribution room design, comprising:
establishing a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and performing sedimentation simulation on the initial power distribution room foundation model and the initial power distribution room overall model;
designing a power distribution room simulation basic model according to the settlement simulation result, and performing settlement simulation on the power distribution room simulation basic model to obtain a first settlement result;
manufacturing and installing a power distribution room simulation foundation according to the designed power distribution room simulation foundation model, and observing sedimentation after the power distribution room simulation foundation is installed to obtain a second sedimentation result;
calculating an error between the first sedimentation result and the second sedimentation result, and adjusting the three-dimensional geological model according to the error;
designing a final power distribution room basic model and a final power distribution room integral model by using the adjusted three-dimensional geological model;
manufacturing a power distribution room foundation, a prefabricated wall body and a prefabricated roof according to the final power distribution room foundation model and the final power distribution room overall model;
installing a power distribution room foundation, and pre-correcting inclination of the power distribution room foundation;
and installing a prefabricated wall body and a prefabricated roof on the basis of the power distribution room after pre-correcting the inclination.
2. A method of designing a power distribution room according to claim 1, wherein said designing a power distribution room simulation base model based on the sedimentation simulation result comprises:
if the settlement of the initial power distribution room integral model does not meet the requirement, reinforcing a power distribution room foundation or replacing the installation position of the power distribution room;
if the settlement amount of the initial power distribution room integral model meets the requirements, and the settlement deviation of the initial power distribution room base model and the settlement deviation of the initial power distribution room integral model do not meet the requirements, redesigning the initial power distribution room base model and the initial power distribution room integral model according to the simulation result, or reinforcing a power distribution room foundation, and then re-simulating;
if the settlement amount of the initial power distribution room integral model meets the requirements, the settlement deviation of the initial power distribution room basic model does not meet the requirements, but the settlement deviation of the initial power distribution room integral model meets the requirements, and the initial power distribution room basic model is the power distribution room simulation basic model at the moment;
if the settlement amount of the initial power distribution room integral model meets the requirements, the settlement deviation of the initial power distribution room basic model meets the requirements, but the settlement deviation of the initial power distribution room integral model does not meet the requirements, modifying the initial power distribution room integral model, adjusting load distribution, and re-simulating; if the whole model of the initial power distribution room still does not meet the sedimentation deviation requirement after modification, reinforcing a power distribution room foundation or increasing the contact area between the basic model of the initial power distribution room and the ground;
if the settlement amount of the initial power distribution room integral model meets the requirements, and the settlement deviation of the initial power distribution room base model and the settlement deviation of the initial power distribution room integral model meet the requirements, the initial power distribution room base model is the power distribution room simulation base model.
3. The method of claim 1, wherein the initial power distribution room overall model comprises an initial power distribution room foundation, an initial power distribution room prefabricated wall, an initial power distribution room prefabricated roof, and initial power distribution room equipment.
4. A method of designing a power distribution room as defined in claim 1, wherein the first settlement result includes a first settlement amount and a first offset amount, and the second settlement result includes a second settlement amount and a second offset amount.
5. The electrical room design method of claim 4, wherein the error between the first sedimentation result and the second sedimentation result is calculated by:
wherein a is an error,for the first settlement amount, ++>For the second settlement amount->For the first offset, +>And m is a sedimentation weight coefficient, and n is an offset weight coefficient.
6. A method of power distribution room design as claimed in claim 1, wherein said adjusting the three-dimensional geologic model based on the error comprises: and adjusting parameters of the three-dimensional geological model according to the error, and repeatedly calculating by utilizing the adjusted model until the error is smaller than the error setting threshold value to obtain the adjusted three-dimensional geological model.
7. A method of designing a power distribution room as defined in claim 1, wherein said pre-rectifying said power distribution room foundation comprises:
if the offset of the final overall power distribution room model is smaller than the simulated offset setting threshold, pre-correcting the inclination by using a shallow soil excavation inclination correction method, and setting the offset of the foundation inclination of the power distribution room according to the offset of the final overall power distribution room model;
if the offset of the final power distribution room overall model is larger than the simulated offset setting threshold, pre-rectifying inclination by using a shallow soil-drawing inclination-rectifying method, enabling the power distribution room foundation to incline back to set the offset according to the settlement of the final power distribution room overall model, and simultaneously carrying out inclination-preventing reinforcement on the simulated power distribution room foundation in an inclined direction.
8. The method for designing a power distribution room according to claim 1, further comprising, after installing the prefabricated wall body and the prefabricated roof, observing the power distribution room, and if the power distribution room is not inclined within a set time, installing power distribution room equipment according to a final power distribution room overall model; if the power distribution room is inclined within the set time and the offset does not exceed the offset set threshold, determining the installation position of the power distribution room equipment according to the offset when the power distribution room equipment is installed.
9. A power distribution room design system, comprising:
the initial settlement simulation module is configured to establish a three-dimensional geological model, an initial power distribution room foundation model and an initial power distribution room overall model, and perform settlement simulation on the initial power distribution room foundation model and the initial power distribution room overall model;
the power distribution room simulation basic design module is configured to design a power distribution room simulation basic model according to the settlement simulation result, and perform settlement simulation on the power distribution room simulation basic model to obtain a first settlement result;
the settlement observation module is configured to manufacture and install a power distribution room simulation foundation according to a designed power distribution room simulation foundation model, observe settlement after the power distribution room simulation foundation is installed, and obtain a second settlement result;
the model adjustment module is configured to calculate an error between the first sedimentation result and the second sedimentation result and adjust the three-dimensional geological model according to the error;
a final model design module configured to design a final power distribution room base model and a final power distribution room overall model using the adjusted three-dimensional geologic model;
a manufacturing module configured to manufacture a power distribution room foundation, a prefabricated wall, and a prefabricated roof based on the final power distribution room foundation model and the final power distribution room overall model;
the pre-rectification module is configured to install a power distribution room foundation and pre-rectify the power distribution room foundation;
and the installation module is configured to install the prefabricated wall body and the prefabricated roof on the basis of the power distribution room after pre-correcting the inclination.
10. A power distribution room comprising a power distribution room foundation, prefabricated walls and prefabricated roofs, characterized in that it is designed by a power distribution room design method according to any one of claims 1-8.
CN202311314664.0A 2023-10-12 2023-10-12 Power distribution room design method and system and power distribution room Active CN117057025B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311314664.0A CN117057025B (en) 2023-10-12 2023-10-12 Power distribution room design method and system and power distribution room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311314664.0A CN117057025B (en) 2023-10-12 2023-10-12 Power distribution room design method and system and power distribution room

Publications (2)

Publication Number Publication Date
CN117057025A true CN117057025A (en) 2023-11-14
CN117057025B CN117057025B (en) 2024-01-23

Family

ID=88664829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311314664.0A Active CN117057025B (en) 2023-10-12 2023-10-12 Power distribution room design method and system and power distribution room

Country Status (1)

Country Link
CN (1) CN117057025B (en)

Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061203A (en) * 2000-06-09 2002-02-28 Ohbayashi Corp Uneven settlement controlling foundation of structure
JP2009263907A (en) * 2008-04-23 2009-11-12 Sumitomo Forestry Co Ltd Foundation structure for correcting settlement of building
KR100955598B1 (en) * 2009-08-12 2010-05-03 (주)명성지오시스템 Methode and system for measuring layer settlement of soft ground
JP2012219487A (en) * 2011-04-07 2012-11-12 Maruyama Kogyo Kk Settlement measuring apparatus, method of construction for improving weak foundation using the same, method of grasping dynamic state of foundation to prepare banking structure thereon and method of grasping dynamic state of foundation to bury underground installation therein
JP2014037745A (en) * 2012-08-20 2014-02-27 Jibannet Ltd Soil foundation specification determination method, soil foundation specification determination system and soil foundation specification determination program
CN104881573A (en) * 2015-05-12 2015-09-02 广州地铁设计研究院有限公司 Risk assessment method and system for urban rail traffic engineering
CN106546219A (en) * 2016-12-06 2017-03-29 国网山东省电力公司鄄城县供电公司 Electrical substation monitoring device, method and system
CN109489622A (en) * 2018-11-20 2019-03-19 中煤航测遥感集团有限公司 Model production method and settlement prediction device
CN111625886A (en) * 2020-05-14 2020-09-04 浙江省建筑设计研究院 Estimation method for pile cutting quantity and forced landing quantity in inclination correcting process of high-rise building
CN112179313A (en) * 2020-09-25 2021-01-05 北京大成国测科技有限公司 Settlement monitoring system for building deviation correction
CN113360967A (en) * 2021-04-13 2021-09-07 中国电建集团市政规划设计研究院有限公司 Soft soil foundation consolidation settlement generation method, device and medium
CN113744395A (en) * 2021-11-08 2021-12-03 辽博信息科技(山东)有限公司 Monitoring and early warning method and system for building foundation settlement
CN114357691A (en) * 2021-11-03 2022-04-15 温州电力建设有限公司 Power facility geological foundation deformation safety assessment method
US20220156427A1 (en) * 2020-11-16 2022-05-19 Topcon Corporation Construction management system, construction management method, and storage medium, accompanied by physical simulation
CN115115123A (en) * 2022-07-12 2022-09-27 国网山东省电力公司经济技术研究院 Foundation settlement prediction system and settlement prediction method
CN115492075A (en) * 2022-09-23 2022-12-20 苏悦 Assembly type building foundation settlement monitoring system
CN115828381A (en) * 2022-11-17 2023-03-21 国网山东省电力公司鱼台县供电公司 Power distribution room foundation design method convenient for correcting inclination
CN116776442A (en) * 2023-07-04 2023-09-19 江门市大光明电力设计有限公司 BIM (building information modeling) power distribution room construction method and system based on data association

Patent Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061203A (en) * 2000-06-09 2002-02-28 Ohbayashi Corp Uneven settlement controlling foundation of structure
JP2009263907A (en) * 2008-04-23 2009-11-12 Sumitomo Forestry Co Ltd Foundation structure for correcting settlement of building
KR100955598B1 (en) * 2009-08-12 2010-05-03 (주)명성지오시스템 Methode and system for measuring layer settlement of soft ground
JP2012219487A (en) * 2011-04-07 2012-11-12 Maruyama Kogyo Kk Settlement measuring apparatus, method of construction for improving weak foundation using the same, method of grasping dynamic state of foundation to prepare banking structure thereon and method of grasping dynamic state of foundation to bury underground installation therein
JP2014037745A (en) * 2012-08-20 2014-02-27 Jibannet Ltd Soil foundation specification determination method, soil foundation specification determination system and soil foundation specification determination program
CN104881573A (en) * 2015-05-12 2015-09-02 广州地铁设计研究院有限公司 Risk assessment method and system for urban rail traffic engineering
CN106546219A (en) * 2016-12-06 2017-03-29 国网山东省电力公司鄄城县供电公司 Electrical substation monitoring device, method and system
CN109489622A (en) * 2018-11-20 2019-03-19 中煤航测遥感集团有限公司 Model production method and settlement prediction device
CN111625886A (en) * 2020-05-14 2020-09-04 浙江省建筑设计研究院 Estimation method for pile cutting quantity and forced landing quantity in inclination correcting process of high-rise building
CN112179313A (en) * 2020-09-25 2021-01-05 北京大成国测科技有限公司 Settlement monitoring system for building deviation correction
US20220156427A1 (en) * 2020-11-16 2022-05-19 Topcon Corporation Construction management system, construction management method, and storage medium, accompanied by physical simulation
CN113360967A (en) * 2021-04-13 2021-09-07 中国电建集团市政规划设计研究院有限公司 Soft soil foundation consolidation settlement generation method, device and medium
CN114357691A (en) * 2021-11-03 2022-04-15 温州电力建设有限公司 Power facility geological foundation deformation safety assessment method
CN113744395A (en) * 2021-11-08 2021-12-03 辽博信息科技(山东)有限公司 Monitoring and early warning method and system for building foundation settlement
CN115115123A (en) * 2022-07-12 2022-09-27 国网山东省电力公司经济技术研究院 Foundation settlement prediction system and settlement prediction method
CN115492075A (en) * 2022-09-23 2022-12-20 苏悦 Assembly type building foundation settlement monitoring system
CN115828381A (en) * 2022-11-17 2023-03-21 国网山东省电力公司鱼台县供电公司 Power distribution room foundation design method convenient for correcting inclination
CN116776442A (en) * 2023-07-04 2023-09-19 江门市大光明电力设计有限公司 BIM (building information modeling) power distribution room construction method and system based on data association

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
PAN YUEJIN等: "Prediction of post-construction settlement of airport subgrade and its application", JOURNAL OF HIGHWAY AND TRANSPORTATION RESEARCH AND DEVELOPMENT *
周茂林;王进展;: "粉煤灰回填地基建筑物纠倾的设计与施工", 中国建筑金属结构, no. 16 *
张志伟;胡伍生;钱大林;: "模型误差补偿技术在路基沉降预测中的应用", 东南大学学报(自然科学版), no. 2 *
温晓贵, 魏纲: "某软土地基上倾斜建筑物的纠倾与加固实例", 土木工程学报, no. 08 *
王震宇;向发海;: "软基上建筑物沉降的有限元数值模拟分析", 中国西部科技, no. 12 *
陈庆伟 等: "基于三维地质模型的变电站地基沉降分析", 2021年工业建筑学 2021年工业建筑学术交流会论文集 *

Also Published As

Publication number Publication date
CN117057025B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
EP4332825A1 (en) Integrated cost-reducing optimization design method for support structure of offshore wind turbine
CN117057025B (en) Power distribution room design method and system and power distribution room
CN114462115B (en) Method for calculating horizontal displacement of shaft force automatic compensation steel support foundation pit support structure
CN101806069B (en) Integrated fixation and installation method for bolt
CN109208610A (en) A kind of big load bias excavation of foundation pit horizontal support prestressing force dynamic adjusting method of proximity
CN108052782A (en) Method is determined with the servo steel supporting system axle power of maximum displacement target in order to control
WO2022110621A1 (en) In-situ lifting method for pole and tower
CN212452310U (en) First section steel anchor box positioning accuracy adjusting device of cable-stay bridge
CN203881339U (en) Detachable monitoring pier
CN104727339A (en) Electrical equipment foundation two-step type construction method
CN111827269A (en) Method for leveling long and short pile composite foundation
US9365999B1 (en) Method of installing a housing for an inground vehicle lift
CN209066472U (en) Mountain area transmission line of electricity tower foundation and transmission line of electricity
CN105421455A (en) Overwater pile planting method based on combined type static-pressure pile planting machine
JP5550372B2 (en) Antenna installation method and antenna installation equipment
CN204551489U (en) A kind ofly oblique throwings that regulate of intelligent deformation can support support system for dredging silt matter soil district foundation ditch
Loubser et al. Optimised design of wind turbine gravity foundations
CN211693790U (en) Natural gas line strutting arrangement
CN109137931B (en) Method for calculating embedding length suitable for narrow foundation pit
KR101356587B1 (en) Soft ground subsidence due to solar structure elevation adjustment method
CN113591183A (en) Viscous soil layer multi-fulcrum type envelope structure non-equilibrium calculation method
CN109086505B (en) It builds a dam cofferdam steel-pipe pile force analysis method and system
CN112945189A (en) Automatic monitoring device for foundation settlement
CN109736296A (en) The installation method of pre-buried benchmark and the setting method of workshop benchmark
CN110826127A (en) Design optimization method for large industrial site

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant