CN110826127A - Design optimization method for large industrial site - Google Patents

Design optimization method for large industrial site Download PDF

Info

Publication number
CN110826127A
CN110826127A CN201911022996.5A CN201911022996A CN110826127A CN 110826127 A CN110826127 A CN 110826127A CN 201911022996 A CN201911022996 A CN 201911022996A CN 110826127 A CN110826127 A CN 110826127A
Authority
CN
China
Prior art keywords
design
earthwork
site
elevation
determining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911022996.5A
Other languages
Chinese (zh)
Inventor
李柏松
袁松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TONGLING NONFERROUS DESIGN AND RESEARCH INSTITUTE
Tongling Nonferrous Metals Group Co Ltd
Original Assignee
TONGLING NONFERROUS DESIGN AND RESEARCH INSTITUTE
Tongling Nonferrous Metals Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TONGLING NONFERROUS DESIGN AND RESEARCH INSTITUTE, Tongling Nonferrous Metals Group Co Ltd filed Critical TONGLING NONFERROUS DESIGN AND RESEARCH INSTITUTE
Priority to CN201911022996.5A priority Critical patent/CN110826127A/en
Publication of CN110826127A publication Critical patent/CN110826127A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a design optimization method for a large-scale industrial site, which comprises the following steps: 1. reasonably constructing a site design boundary; determining a reasonable design elevation according to the surrounding terrain and the road network condition; 2. determining the inner surface soil condition of each subarea according to the field condition, and independently constructing a field design boundary by using the later-stage soil capable of being used as greening planting soil; 3. calculating earthwork engineering quantities (including slope earthwork) of each subarea by using earthwork calculation software; 4. and optimizing, namely, according to the soil plowing amount required by the later greening area, aiming at the filling and digging amount, the field earthwork engineering design is required to be adjusted downward by 0.3m on the basis of the vertical design, and if a soft soil layer exists in the field, the field earthwork engineering design is required to be adjusted downward by 0.5m on the basis of the vertical design. The method has the advantages that the design gradient of the site is optimized according to the later-stage work exploration conditions, the flat foundation elevation is reasonably determined, and the investment can be reduced by about 3-5 yuan/m2And the environmental pollution of secondary transportation is reduced, and the efficiency is improved.

Description

Design optimization method for large industrial site
Technical Field
The invention relates to regional analysis, in particular to a design optimization method for a large-scale industrial site.
Background
At present, the design of the total plane of a large-scale industrial enterprise is mainly based on the process requirements, and the design of the plane and the vertical direction also mainly meets the process requirements. At present, the general plane overall design of industrial enterprises is mainly in a flat slope type or step type or a combination mode of the flat slope type or the step type, a field in a platform in the flat slope type or the step type is mainly in the flat slope type, the field earthwork calculation is generally only considered, the earthwork of a road base layer in the later stage and the earthwork of a terrace structure layer in a factory building are not considered, the surface earthwork required by factory greening in the later stage is not considered, the secondary transportation of the earthwork in the later stage or the surface soil recycling required by greening are caused, the investment is increased, and the secondary pollution is caused to the external environment.
Disclosure of Invention
The technical problem to be solved by the invention is that the earth volume calculation of the site of the existing industrial enterprise planar design does not consider the earth of the road base layer and the terrace structure layer in the factory building in the later period and the surface earth required by factory greening in the later period, so that the investment is increased and the secondary pollution is caused to the external environment, thereby providing a design optimization method of the large-scale industrial site.
The technical scheme of the invention is as follows: a design optimization method for a large-scale industrial site comprises the following steps: (1): according to the topographic map, defining contour lines and natural elevation discrete points; (2): constructing a site design boundary comprising a side slope or a retaining wall connected with peripheral blocks according to a land red line and yielding requirements, and dividing the site boundary containing the ploughing and planting soil according to an investigation report; (3): drawing an earthwork grid, and calculating a rule according to the earthwork; (4): using computing software to perform grid processing and corner point elevation processing; (5): firstly, performing tillage and planting soil calculation of surface soil according to a designed elevation, and counting the tillage and planting soil engineering quantity; (6): checking the site elevation according to the design elevation, and counting the engineering quantity; (7): according to the work investigation report, optimally calculating the design elevation by 0.3-0.5m on the basis of the existing design elevation, and counting the engineering quantity; (8): determining road base, factory building terrace methods and pile foundation earthwork, and calculating engineering quantity; according to the geotechnical test, determining the backfill compaction coefficient of earthwork and determining the earthwork engineering quantity; (9): and performing three kinds of optimization calculation on the site according to the counted engineering quantity, wherein the design elevation is reduced by 0.3, 0.4 and 0.5m, and one of the minimum earth outsourcing of the site is selected as the design elevation.
The protocol of step (3) in the above protocol is 20x20 or 10x 10.
The earthwork backfill compaction coefficient in the step (8) in the scheme is determined by the ring cutting method.
The calculation software of the step (4) in the scheme is Hongyaofang calculation software.
The method has the advantages that the design gradient of the site is optimized according to the later-stage work exploration conditions, the flat foundation elevation is reasonably determined, and the investment can be reduced by about 3-5 yuan/m2And the environmental pollution of secondary transportation is reduced, the efficiency is improved, and the method has better effect on optimizing the site design of large-scale industrial enterprises.
Detailed Description
The technical solution of the present invention is clearly and completely described below with reference to the following embodiments. It is to be understood that the described embodiments are merely exemplary of the invention, and not restrictive of the full scope of the invention. All other embodiments based on the embodiments in the present invention, without any inventive work, will be apparent to those skilled in the art from the following description.
The key point of the invention is that partition boundaries are reasonably determined according to the total plane layout and the vertical design; and then reasonably determining the level foundation elevation according to the work survey report and the connection condition of the peripheral road network.
The determination of the partition boundary is an important factor of the invention, and the reasonable gradient is set and the partition is reasonable according to the partition condition of industrial production and the combination of site design and drainage pipeline arrangement condition, and the earthwork boundary is constructed according to the partition condition.
According to the functional area determined by the total plane design, the site optimization design steps are as follows: 1. reasonably constructing a site design boundary; determining a reasonable design elevation according to the surrounding terrain and the road network condition; 2. determining the inner surface soil condition of each subarea according to the field condition, and independently constructing a field design boundary by using the later-stage soil capable of being used as greening planting soil; 3. calculating earthwork engineering quantities (including slope earthwork) of each subarea by using earthwork calculation software; 4. and optimizing, namely, according to the soil plowing amount required by the later greening area, aiming at the filling and digging amount, the field earthwork engineering design is required to be adjusted downward by 0.3m on the basis of the vertical design, and if a soft soil layer exists in the field, the field earthwork engineering design is required to be adjusted downward by 0.5m on the basis of the vertical design. The problems that the number of earthwork such as a road base layer, an indoor floor of a factory building, a pile foundation and the like is not considered in the original field calculation, so that secondary transportation of the earthwork is caused, and investment is optimized are solved; the cultivated soil is taken in situ, so that the later transportation from outside is avoided, and the investment is also saved.
Taking an enterprise industrial park as an example, the site design is optimized by using Hongyen earthwork calculation software. The first step is as follows: according to the topographic map, defining a contour line elevation and a natural elevation discrete point elevation; the second step is that: constructing a site design boundary comprising a side slope or a retaining wall connected with peripheral blocks according to a land red line and yielding requirements, and dividing the site boundary containing the ploughing and planting soil according to an investigation report; the third step: drawing an earthwork grid, typically 20X20 or 10X10, according to the earthwork calculation protocol; the fourth step: using computing software to perform grid processing and corner point elevation processing; the fifth step: firstly, performing tillage and planting soil calculation of surface soil according to a designed elevation, and counting the tillage and planting soil engineering quantity; checking the site elevation according to the design elevation, and counting the engineering quantity; the seventh step: according to the work investigation report, optimally calculating the design elevation by 0.3-0.5m on the basis of the existing design elevation, and counting the engineering quantity; eighth step: determining road base, factory building terrace methods and pile foundation earthwork, and calculating engineering quantity; according to the geotechnical test, determining an earthwork backfill compaction coefficient (determined by a ring cutter method for the test), and determining the earthwork engineering quantity; the ninth step: and according to the calculated engineering quantity, performing three-step optimization calculation on the site, reducing the design elevation by 0.3, 0.4 and 0.5m respectively, and optimizing and determining the site design elevation under the conditions of ensuring that the site is reasonably connected with the surrounding municipal roads and ensuring that the earthwork of the site is not transported outside as much as possible.

Claims (4)

1. A design optimization method for a large-scale industrial site is characterized by comprising the following steps: it comprises the following steps: (1): according to the topographic map, defining contour lines and natural elevation discrete points; (2): constructing a site design boundary comprising a side slope or a retaining wall connected with peripheral blocks according to a land red line and yielding requirements, and dividing the site boundary containing the ploughing and planting soil according to an investigation report; (3): drawing an earthwork grid, and calculating a rule according to the earthwork; (4): using computing software to perform grid processing and corner point elevation processing; (5): firstly, performing tillage and planting soil calculation of surface soil according to a designed elevation, and counting the tillage and planting soil engineering quantity; (6): checking the site elevation according to the design elevation, and counting the engineering quantity; (7): according to the work investigation report, optimally calculating the design elevation by 0.3-0.5m on the basis of the existing design elevation, and counting the engineering quantity; (8): determining road base, factory building terrace methods and pile foundation earthwork, and calculating engineering quantity; according to the geotechnical test, determining the backfill compaction coefficient of earthwork and determining the earthwork engineering quantity; (9): and performing three kinds of optimization calculation on the site according to the counted engineering quantity, wherein the design elevation is reduced by 0.3, 0.4 and 0.5m, and one of the minimum earth outsourcing of the site is selected as the design elevation.
2. The design optimization method for the large-scale industrial site as claimed in claim 1, which is characterized in that: the protocol of step (3) is 20x20 or 10x 10.
3. The design optimization method for the large-scale industrial site as claimed in claim 1, which is characterized in that: and (4) detecting and determining the earth backfill compaction coefficient in the step (8) by a cutting ring method.
4. The design optimization method for the large-scale industrial site as claimed in claim 1, which is characterized in that: the calculation software of the step (4) is Hongye earthwork calculation software.
CN201911022996.5A 2019-10-25 2019-10-25 Design optimization method for large industrial site Pending CN110826127A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911022996.5A CN110826127A (en) 2019-10-25 2019-10-25 Design optimization method for large industrial site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911022996.5A CN110826127A (en) 2019-10-25 2019-10-25 Design optimization method for large industrial site

Publications (1)

Publication Number Publication Date
CN110826127A true CN110826127A (en) 2020-02-21

Family

ID=69550523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911022996.5A Pending CN110826127A (en) 2019-10-25 2019-10-25 Design optimization method for large industrial site

Country Status (1)

Country Link
CN (1) CN110826127A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111428964A (en) * 2020-02-25 2020-07-17 哈尔滨工业大学 Site planning method for verifying key metering index detection equipment of highway

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473394A (en) * 2013-08-20 2013-12-25 中冶集团武汉勘察研究院有限公司 Earthwork balance optimization design method for multiple station section type field leveling layout
CN104088491A (en) * 2014-07-30 2014-10-08 湖南省电力勘测设计院 220 kV transformer substation slope-type vertical arrangement method
CN109829195A (en) * 2018-12-28 2019-05-31 浙江大境筑科技发展有限公司 Earthwork calculation method based on BIM

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473394A (en) * 2013-08-20 2013-12-25 中冶集团武汉勘察研究院有限公司 Earthwork balance optimization design method for multiple station section type field leveling layout
CN104088491A (en) * 2014-07-30 2014-10-08 湖南省电力勘测设计院 220 kV transformer substation slope-type vertical arrangement method
CN109829195A (en) * 2018-12-28 2019-05-31 浙江大境筑科技发展有限公司 Earthwork calculation method based on BIM

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐剑等: "方格网法土方计算在公路服务区场地计算中的应用", 《工程与建设》 *
王中芳: "湿陷性黄土地区的土方平衡优化分析", 《科技经济导刊》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111428964A (en) * 2020-02-25 2020-07-17 哈尔滨工业大学 Site planning method for verifying key metering index detection equipment of highway
CN111428964B (en) * 2020-02-25 2023-06-06 哈尔滨工业大学 Site planning method for calibrating road key metering index detection equipment

Similar Documents

Publication Publication Date Title
Li et al. A review on anthropogenic geomorphology
CN102609782B (en) Bian Caibian based on coal-mining subsidence simulation and second ploughing rate answers the method for optimizing on opportunity
CN101422094A (en) Thick-bed mining subsidence-land dynamic pre-reclamation method at plane mining-area
CN108876918B (en) High fill loess body settlement deformation prediction method
CN104598296A (en) Numerical simulation analysis method for deformation of soft soil deep foundation pit
US7383157B1 (en) Decision-making support system for sewer maintenance and control method thereof
CN110031596A (en) A kind of real-time dynamic monitoring method for inland river basin in arid zone underground water
CN114820957B (en) Three-dimensional intelligent design method for railway line-side terrace
CN113536414B (en) Rock slope stability analysis method, system and medium based on three-dimensional modeling
CN110826127A (en) Design optimization method for large industrial site
CN114018225A (en) Ultra-large square construction measurement control method
CN112270030B (en) Method, device, equipment and medium for optimal design of complex terrain wind power plant road
CN113609547B (en) Building indoor terrace elevation calculation method based on planning and design points
CN115130724A (en) Dynamic adjustment method and system for urban underground water mining planning
CN115369885A (en) BIM and unmanned aerial vehicle-based dynamic monitoring method for deep foundation pit construction
CN111080077B (en) Method for evaluating land damage of embankment interference area based on different construction units
Vartolomei et al. The Intensification of Antropic Pressure Through the Expansion of the Constructed Area in the Subcarpathian Sector of the Prahova Valley/Romania (1800-2008)
Merrick et al. Modelling of the groundwater impact of a sunken urban motorway in Sydney, Australia
Pham et al. Feasibility of low impact development measures to mitigate inundation in tidal–impacted urban area: A case in Ho Chi Minh City, Vietnam
CN112365063B (en) Loess plateau region excavation slope ditch slope protection measure optimal configuration method
M Al-Taiee et al. Simulation and prediction of groundwater paths and flow vectors at Mosul city
Bourne Land at Unit 2, Broad Lane Industrial Estate, Cottenham. An Archaeological Evaluation.
CN116090244A (en) Method for investigating historical landform building bad geological condition
Liu et al. Design and monitoring analysis of foundation pit support for sewage treatment plant
Fullard Launceston-a city on a floodplain protecting Launceston from a 1 in 200 ARI flood

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200221