CN116596243A - Project progress management system and method for constructional engineering - Google Patents
Project progress management system and method for constructional engineering Download PDFInfo
- Publication number
- CN116596243A CN116596243A CN202310563124.XA CN202310563124A CN116596243A CN 116596243 A CN116596243 A CN 116596243A CN 202310563124 A CN202310563124 A CN 202310563124A CN 116596243 A CN116596243 A CN 116596243A
- Authority
- CN
- China
- Prior art keywords
- construction
- engineering
- project
- data
- dimensional model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 17
- 238000010276 construction Methods 0.000 claims abstract description 251
- 238000007726 management method Methods 0.000 claims abstract description 36
- 238000013144 data compression Methods 0.000 claims abstract description 9
- 238000007906 compression Methods 0.000 claims abstract description 5
- 230000006835 compression Effects 0.000 claims abstract description 5
- 238000012937 correction Methods 0.000 claims description 62
- 239000000463 material Substances 0.000 claims description 21
- 238000006243 chemical reaction Methods 0.000 claims description 18
- 238000000605 extraction Methods 0.000 claims description 8
- 238000013461 design Methods 0.000 claims description 4
- 239000004566 building material Substances 0.000 claims description 3
- 238000012986 modification Methods 0.000 claims description 3
- 230000004048 modification Effects 0.000 claims description 3
- 230000009286 beneficial effect Effects 0.000 description 11
- 238000000889 atomisation Methods 0.000 description 6
- 238000011156 evaluation Methods 0.000 description 3
- 238000007670 refining Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000007405 data analysis Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000013139 quantization Methods 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063116—Schedule adjustment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F18/00—Pattern recognition
- G06F18/20—Analysing
- G06F18/22—Matching criteria, e.g. proximity measures
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T2210/00—Indexing scheme for image generation or computer graphics
- G06T2210/04—Architectural design, interior design
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Theoretical Computer Science (AREA)
- Strategic Management (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Data Mining & Analysis (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Educational Administration (AREA)
- Bioinformatics & Computational Biology (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Game Theory and Decision Science (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Life Sciences & Earth Sciences (AREA)
- Artificial Intelligence (AREA)
- Bioinformatics & Cheminformatics (AREA)
- Development Economics (AREA)
- Computer Vision & Pattern Recognition (AREA)
- Evolutionary Biology (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Computer Graphics (AREA)
- Geometry (AREA)
- Software Systems (AREA)
- Health & Medical Sciences (AREA)
Abstract
Project progress management system and method for construction engineering, comprising: acquiring a three-dimensional model of the building engineering, and performing data compression on the three-dimensional model to obtain a compact three-dimensional model; converting the construction engineering quantity of the compact three-dimensional model to obtain an atomic member of the construction engineering; combining corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type; and (5) making a construction plan according to the construction minimum unit, and tracking the construction progress. A project progress management system for construction projects, comprising: a compression module; a deconstructing module; a combination module; and executing the module.
Description
Technical Field
The invention relates to the field of project management, in particular to a project progress management system and method for constructional engineering.
Background
The construction project progress management is mainly carried out by means of a professional progress management system and a construction project management system, the completion condition of construction tasks in the construction project management system is generally fed back to a team project manager by means of team filling paper daily report, then the team is fed back to the engineering department manager, the task feedback process is long in duration, the on-site construction task state feedback is not timely, and the situation of asynchronism exists at each professional statistics time point. In addition, most of data feedback is in the form of tables, etc., the correction degree of the construction progress needs to be further analyzed, the display mode is not visual enough, and the calculated correction degree of the construction progress has hysteresis because of hysteresis of field data and asynchronism of each professional statistics time point, so that the field construction progress cannot be monitored in real time.
Disclosure of Invention
The invention provides a project progress management system and method for construction engineering, which are used for solving the problems that the on-site construction task state feedback is not timely, the calculated construction progress correction degree has hysteresis in each professional statistics time point, the on-site construction progress cannot be monitored in real time, and the like.
A project progress management method for construction projects, comprising:
acquiring a three-dimensional model of the building engineering, and performing data compression on the three-dimensional model to obtain a compact three-dimensional model;
converting the construction engineering quantity of the compact three-dimensional model to obtain an atomic member of the construction engineering;
combining corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type;
and (5) making a construction plan according to the construction minimum unit, and tracking the construction progress.
Preferably, the construction engineering quantity conversion is performed on the compact three-dimensional model, which comprises the following steps:
building engineering data conversion is carried out on the compact three-dimensional model, and the converted data are sent to a budget data unit of a building project management platform;
extracting construction models of various work types from a big data platform;
performing construction point number conversion on the construction engineering quantity of each construction model;
each construction point number corresponds to the workload of qualified personnel of the work class in unit time.
Preferably, the construction plan is formulated according to the construction minimum unit, and the construction progress is tracked, including:
the correction degree of the manual work is determined according to the difference between the estimated work time and the actual work time, and the correction degree of the construction progress is determined according to the difference between the estimated work time and the planned work time;
when the difference between the estimated working hours and the actual working hours is smaller than zero, manually inputting an out-of-standard correction value by the difference;
when the difference between the estimated working hours and the actual working hours is larger than zero, the difference saves a correction value by manual investment;
when the difference between the estimated working hours and the planned working hours is smaller than zero, the difference is a field progress hysteresis correction value;
when the difference between the estimated time and the planned time is greater than zero, the difference is the on-site progress advanced correction value.
Preferably, the method further comprises the steps of:
correcting the correction degree of the construction progress and the correction degree in manual work.
Preferably, the correction degree of the construction progress includes:
correcting degree of point construction progress and correcting degree of construction engineering quantity;
the correction degree of the point construction progress is the correction degree of the point planning quantity and the point actual quantity of the building engineering quantity, and the correction degree of the building engineering quantity is the correction degree of each professional construction planning quantity and the construction actual quantity.
Preferably, before the building engineering obtains the three-dimensional model of the building engineering, the method further comprises:
and carrying out depth design on the three-dimensional model of the building engineering.
Preferably, the project progress management method further comprises; the construction engineering cost estimation method comprises the following steps:
reading the building materials and the site cost data to obtain quantity information materials and unit price data materials;
correspondingly matching the quantity information material and the unit price data material with the construction engineering quantity to obtain estimated construction engineering cost;
and matching the similarity of the construction information of the estimated construction project and the similar construction project, and judging whether to adopt the estimated construction project cost according to the similarity.
Preferably, the matching of the similarity of the construction information between the estimated construction project and the similar construction project, and judging whether to adopt the estimated construction project cost according to the similarity comprises:
obtaining the cost estimation scheme of other building projects of the same type as the estimated building project from a big data platform as a comparison building project;
carrying out data feature extraction on the number of atomic components and the number of works of the estimated building engineering and the comparison building engineering to obtain data feature parameters;
and calculating the similarity according to the extracted data characteristic parameters, and estimating the construction cost if the similarity is greater than or equal to a preset similarity threshold value.
A project progress management system for construction projects, comprising:
the compression module is used for acquiring a three-dimensional model of the building engineering and carrying out data compression on the three-dimensional model to obtain a compact three-dimensional model;
the deconstructing module is used for carrying out construction engineering quantity conversion on the compact three-dimensional model to obtain an atomic member of the construction engineering;
the combination module is used for combining the corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type;
and the execution module is used for making a construction plan according to the construction minimum unit and tracking the construction progress.
Preferably, the deconstructing module includes:
the data sub-module is used for converting the construction engineering data of the compact three-dimensional model and transmitting the converted data to a budget data unit of the construction project management platform;
the extraction submodule is used for extracting construction models of various work types from the big data platform;
and the point counting sub-module is used for converting construction points of the construction engineering quantity of each construction model.
The beneficial effects of the invention are as follows:
the invention realizes the atomization deconstructing of the whole construction engineering, so that the atomic component can be combined into a construction minimum unit according to different work types based on a minimum atomization unit, namely the atomic component, when the project progress is tracked, the synchronization of professional statistics time points is ensured, and the hysteresis of the calculated construction progress correction is eliminated; the minimum construction unit is used as a reference for tracking project plans, so that the on-site construction progress can be monitored conveniently in real time, the on-site construction task state is guaranteed to be fed back in time, and the on-site construction progress is monitored in real time.
Drawings
The accompanying drawings are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate the invention and together with the embodiments of the invention, serve to explain the invention.
In the drawings:
FIG. 1 is a general flow chart of the method of the present invention;
FIG. 2 is a flow chart of a cost estimation evaluation of the present invention;
fig. 3 is a system overview of the present invention.
Detailed Description
The preferred embodiments of the present invention will be described below with reference to the accompanying drawings, it being understood that the preferred embodiments described herein are for illustration and explanation of the present invention only, and are not intended to limit the present invention.
A project progress management method for construction projects, comprising:
acquiring a three-dimensional model of the building engineering, and performing data compression on the three-dimensional model to obtain a compact three-dimensional model;
converting the construction engineering quantity of the compact three-dimensional model to obtain an atomic member of the construction engineering;
combining corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type;
and (5) making a construction plan according to the construction minimum unit, and tracking the construction progress.
The working principle and beneficial effects of the embodiment of the invention are as follows:
as shown in fig. 1, firstly, a three-dimensional model of a building engineering is obtained, and data compression is carried out on the three-dimensional model to obtain a compact three-dimensional model, wherein the compression is a conventional method in the field; then, carrying out construction engineering quantity conversion on the compact three-dimensional model to obtain an atomic member of the construction engineering; then, corresponding atomic components are combined according to the construction conditions of each work type on the large data platform of the building engineering, so as to obtain a construction minimum unit of each work type; and finally, making a construction plan according to the construction minimum unit, and tracking the construction progress.
The invention realizes the atomization deconstructing of the whole construction engineering, so that the atomic component can be combined into a construction minimum unit according to different work types based on a minimum atomization unit, namely the atomic component, when the project progress is tracked, the synchronization of professional statistics time points is ensured, and the hysteresis of the calculated construction progress correction is eliminated; the minimum construction unit is used as a reference for tracking project plans, so that the on-site construction progress can be monitored conveniently in real time, the on-site construction task state is guaranteed to be fed back in time, and the on-site construction progress is monitored in real time.
Preferably, the construction engineering quantity conversion is performed on the compact three-dimensional model, which comprises the following steps:
building engineering data conversion is carried out on the compact three-dimensional model, and the converted data are sent to a budget data unit of a building project management platform;
extracting construction models of various work types from a big data platform;
performing construction point number conversion on the construction engineering quantity of each construction model;
each construction point number corresponds to the workload of qualified personnel of the work class in unit time.
The working principle and beneficial effects of the embodiment of the invention are as follows:
firstly, building engineering data conversion is carried out on a compact three-dimensional model, and converted data are sent to a budget data unit of a building project management platform, so that data summarization is realized; then, extracting construction models of each work type from the big data platform, refining the data, and ensuring the synchronization of professional statistics time points; and then, carrying out construction point number conversion on the construction engineering quantity of each construction model so as to facilitate the overall statistics of the workload.
Each construction point number corresponds to the workload of qualified personnel of the work class in unit time.
Preferably, the construction plan is formulated according to the construction minimum unit, and the construction progress is tracked, including:
the correction degree of the manual work is determined according to the difference between the estimated work time and the actual work time, and the correction degree of the construction progress is determined according to the difference between the estimated work time and the planned work time;
when the difference between the estimated working hours and the actual working hours is smaller than zero, manually inputting an out-of-standard correction value by the difference;
when the difference between the estimated working hours and the actual working hours is larger than zero, the difference saves a correction value by manual investment;
when the difference between the estimated working hours and the planned working hours is smaller than zero, the difference is a field progress hysteresis correction value;
when the difference between the estimated time and the planned time is greater than zero, the difference is the on-site progress advanced correction value.
The working principle and beneficial effects of the embodiment of the invention are as follows:
the correction degree of the manual work is determined according to the difference between the estimated work time and the actual work time, and the correction degree of the construction progress is determined according to the difference between the estimated work time and the planned work time; when the difference between the estimated working hours and the actual working hours is smaller than zero, manually inputting an out-of-standard correction value by the difference; when the difference between the estimated working hours and the actual working hours is larger than zero, the difference saves a correction value by manual investment; when the difference between the estimated working hours and the planned working hours is smaller than zero, the difference is a field progress hysteresis correction value; when the difference between the estimated time and the planned time is greater than zero, the difference is the on-site progress advanced correction value.
And after each component of the compact three-dimensional model is combined to obtain construction minimum units of each work, receiving a construction task scheduling plan, and enabling atomic components corresponding to the construction minimum units to have planning attributes. The schedule attributes include, but are not limited to, bundle code, schedule start time, schedule end time, and the like.
And determining the correction degree of the construction minimum unit in manual time and the correction degree of the construction progress according to the site task backfill list, and updating the planned progress of the construction minimum unit in real time or at regular time according to the data fed back by the corresponding site, so as to determine the correction degree of the project in real time in manual time and the correction degree of the construction progress.
Specifically, the construction minimum unit obtains the correction degree of the construction progress and the correction degree of the manual work according to the estimated work hour, the planned work hour and the actual work hour; the product of the number of actually completed working points and the work efficiency of standard personnel is used for obtaining the estimated working hours; obtaining planning man-hour through the product of the number of the corresponding working points of the plan and the working efficiency of standard personnel; the actual man-hour is obtained by summing the man-hour of each person who has actually completed the work input.
Preferably, the method further comprises the steps of:
correcting the correction degree of the construction progress and the correction degree in manual work.
The working principle and beneficial effects of the embodiment of the invention are as follows:
the on-site construction task state is timely fed back, so that the on-site construction progress can be monitored in real time.
Preferably, the correction degree of the construction progress includes:
correcting degree of point construction progress and correcting degree of construction engineering quantity;
the correction degree of the point construction progress is the correction degree of the point planning quantity and the point actual quantity of the building engineering quantity, and the correction degree of the building engineering quantity is the correction degree of each professional construction planning quantity and the construction actual quantity.
The working principle and beneficial effects of the embodiment of the invention are as follows:
correcting degree of point construction progress and correcting degree of construction engineering quantity; the correction degree of the point construction progress is the correction degree of the point planning quantity and the point actual quantity of the building engineering quantity, and the correction degree of the building engineering quantity is the correction degree of each professional construction planning quantity and the construction actual quantity.
Contributing to a more accurate quantization effort.
Preferably, before the building engineering obtains the three-dimensional model of the building engineering, the method further comprises:
and carrying out depth design on the three-dimensional model of the building engineering.
The working principle and beneficial effects of the embodiment of the invention are as follows:
the depth design is carried out on the three-dimensional model of the building engineering, and the three-dimensional model can be deconstructed more accurately and efficiently.
Preferably, the project progress management method further comprises; the construction engineering cost estimation method comprises the following steps:
reading the building materials and the site cost data to obtain quantity information materials and unit price data materials;
correspondingly matching the quantity information material and the unit price data material with the construction engineering quantity to obtain estimated construction engineering cost;
and matching the similarity of the construction information of the estimated construction project and the similar construction project, and judging whether to adopt the estimated construction project cost according to the similarity.
The working principle and beneficial effects of the embodiment of the invention are as follows:
firstly, building engineering data uploaded by workers in the process of engineering project reading are monitored in real time, and quantity information materials recorded in the engineering data, namely the quantity information of the workers and the quantity information of materials entering and exiting a field are obtained; then, the site cost data uploaded by the main authorities are monitored and read in real time, and monovalent data materials in the site cost data, namely artificial monovalent data and engineering material monovalent data, are obtained; then, automatically matching the staff number information and the field material number information with the manual unit price data and the engineering material unit price data in a mode of automatically calling and matching corresponding data to acquire labor cost and material cost in the implementation process of engineering projects; further, according to the proportion principle of the engineering cost occupied by the labor cost and the material cost, estimating the total amount range of the engineering cost by utilizing the labor cost and the material cost; and finally, matching the similarity of the project information of the estimated project and the similarity project, and judging whether to adopt the estimated project cost according to the similarity.
Preferably, the matching of the similarity of the construction information between the estimated construction project and the similar construction project, and judging whether to adopt the estimated construction project cost according to the similarity comprises:
obtaining the cost estimation scheme of other building projects of the same type as the estimated building project from a big data platform as a comparison building project;
carrying out data feature extraction on the number of atomic components and the number of works of the estimated building engineering and the comparison building engineering to obtain data feature parameters;
and calculating the similarity according to the extracted data characteristic parameters, and estimating the construction cost if the similarity is greater than or equal to a preset similarity threshold value.
The working principle and beneficial effects of the embodiment of the invention are as follows:
as shown in fig. 2, the actual building engineering with the same type as the estimated building engineering is found from large data platforms such as professional websites commonly accepted in industry and used as a comparison building engineering, and the number of atomic components and the number of work types of the estimated building engineering and the comparison building engineering are respectively extracted for data feature extraction to obtain data feature parameters of the number of atomic components and the number of work types; the data characteristic parameters of the building engineering and the data characteristic parameters of the contrast building engineering are weighted and compared, and the similarity of the estimated building engineering and the contrast building engineering is obtained: when the similarity is higher than 90%, adopting a manufacturing cost scheme; when the similarity is less than 90%, a redesign of the cost scheme is required.
The invention provides a construction project cost estimation method based on construction project data analysis, which ensures the reliability of estimated construction project cost estimation through similarity comparison with similar construction projects; and meanwhile, the feature extraction is carried out on the number of the atomic components and the number of the work types, so that the reliability of an analysis basis of a construction engineering cost estimation scheme is ensured, and the problems of unreliable evaluation surfaces and evaluation results caused by single feature parameters are avoided.
As shown in fig. 3, a project progress management system for construction projects includes:
the compression module is used for acquiring a three-dimensional model of the building engineering and carrying out data compression on the three-dimensional model to obtain a compact three-dimensional model;
the deconstructing module is used for carrying out construction engineering quantity conversion on the compact three-dimensional model to obtain an atomic member of the construction engineering;
the combination module is used for combining the corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type;
and the execution module is used for making a construction plan according to the construction minimum unit and tracking the construction progress.
The working principle and beneficial effects of the embodiment of the invention are as follows:
firstly, acquiring a three-dimensional model of a building engineering, and carrying out data compression on the three-dimensional model to obtain a compact three-dimensional model; then, carrying out construction engineering quantity conversion on the compact three-dimensional model to obtain an atomic member of the construction engineering; then, corresponding atomic components are combined according to the construction conditions of each work type on the large data platform of the building engineering, so as to obtain a construction minimum unit of each work type; and finally, making a construction plan according to the construction minimum unit, and tracking the construction progress.
The invention realizes the atomization deconstructing of the whole construction engineering, so that the atomic component can be combined into a construction minimum unit according to different work types based on a minimum atomization unit, namely the atomic component, when the project progress is tracked, the synchronization of professional statistics time points is ensured, and the hysteresis of the calculated construction progress correction is eliminated; the minimum construction unit is used as a reference for tracking project plans, so that the on-site construction progress can be monitored conveniently in real time, the on-site construction task state is guaranteed to be fed back in time, and the on-site construction progress is monitored in real time.
Preferably, the deconstructing module includes:
the data sub-module is used for converting the construction engineering data of the compact three-dimensional model and transmitting the converted data to a budget data unit of the construction project management platform;
the extraction submodule is used for extracting construction models of various work types from the big data platform;
and the point counting sub-module is used for converting construction points of the construction engineering quantity of each construction model.
The working principle and beneficial effects of the embodiment of the invention are as follows:
firstly, building engineering data conversion is carried out on a compact three-dimensional model, and converted data are sent to a budget data unit of a building project management platform, so that data summarization is realized; then, extracting construction models of each work type from the big data platform, refining the data, and ensuring the synchronization of professional statistics time points; and then, carrying out construction point number conversion on the construction engineering quantity of each construction model so as to facilitate the overall statistics of the workload.
Each construction point number corresponds to the workload of qualified personnel of the work class in unit time.
And so on
It will be apparent to those skilled in the art that various modifications and variations can be made to the present invention without departing from the spirit or scope of the invention. Thus, it is intended that the present invention also include such modifications and alterations insofar as they come within the scope of the appended claims or the equivalents thereof.
Claims (10)
1. A project progress management method for construction projects, comprising:
acquiring a three-dimensional model of the building engineering, and performing data compression on the three-dimensional model to obtain a compact three-dimensional model;
converting the construction engineering quantity of the compact three-dimensional model to obtain an atomic member of the construction engineering;
combining corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type;
and (5) making a construction plan according to the construction minimum unit, and tracking the construction progress.
2. The project progress management method for construction engineering according to claim 1, wherein the construction engineering amount conversion is performed on the compact three-dimensional model, comprising:
building engineering data conversion is carried out on the compact three-dimensional model, and the converted data are sent to a budget data unit of a building project management platform;
extracting construction models of various work types from a big data platform;
performing construction point number conversion on the construction engineering quantity of each construction model;
each construction point number corresponds to the workload of qualified personnel of the work class in unit time.
3. The project progress management method for construction engineering according to claim 1, wherein making a construction plan based on a construction minimum unit and tracking a construction progress comprises:
the correction degree of the manual work is determined according to the difference between the estimated work time and the actual work time, and the correction degree of the construction progress is determined according to the difference between the estimated work time and the planned work time;
when the difference between the estimated working hours and the actual working hours is smaller than zero, manually inputting an out-of-standard correction value by the difference;
when the difference between the estimated working hours and the actual working hours is larger than zero, the difference saves a correction value by manual investment;
when the difference between the estimated working hours and the planned working hours is smaller than zero, the difference is a field progress hysteresis correction value;
when the difference between the estimated time and the planned time is greater than zero, the difference is the on-site progress advanced correction value.
4. The project progress management method for construction engineering according to claim 3, wherein after obtaining the correction degree of the construction progress and the correction degree at the time of manual work according to the work budgeted man-hour, the planned man-hour and the actual man-hour, further comprising:
correcting the correction degree of the construction progress and the correction degree in manual work.
5. The project progress management method for construction engineering according to claim 4, wherein the degree of modification of the construction progress comprises:
correcting degree of point construction progress and correcting degree of construction engineering quantity;
the correction degree of the point construction progress is the correction degree of the point planning quantity and the point actual quantity of the building engineering quantity, and the correction degree of the building engineering quantity is the correction degree of each professional construction planning quantity and the construction actual quantity.
6. The project progress management method for construction engineering according to claim 1, wherein before the construction engineering obtains the three-dimensional model of the construction engineering, further comprising:
and carrying out depth design on the three-dimensional model of the building engineering.
7. The project progress management method for construction projects according to claim 1, wherein the project progress management method further comprises; the construction engineering cost estimation method comprises the following steps:
reading the building materials and the site cost data to obtain quantity information materials and unit price data materials;
correspondingly matching the quantity information material and the unit price data material with the construction engineering quantity to obtain estimated construction engineering cost;
and matching the similarity of the construction information of the estimated construction project and the similar construction project, and judging whether to adopt the estimated construction project cost according to the similarity.
8. The project progress management method for construction projects according to claim 1, wherein the management method further comprises:
matching the similarity of the construction information of the estimated construction project and the similar construction project, judging whether to adopt the estimated construction project cost according to the similarity, comprising:
acquiring a cost estimation scheme of other projects of the same type as the estimated project from a big data platform as a comparison project;
carrying out data feature extraction on the number of atomic components and the number of work types of the estimated engineering and the comparison engineering to obtain data feature parameters;
and calculating the similarity according to the extracted data characteristic parameters, and if the similarity is greater than or equal to a preset similarity threshold value, adopting the estimated engineering cost.
9. A project progress management system for construction projects, comprising:
the compression module is used for acquiring a three-dimensional model of the building engineering and carrying out data compression on the three-dimensional model to obtain a compact three-dimensional model;
the deconstructing module is used for carrying out construction engineering quantity conversion on the compact three-dimensional model to obtain an atomic member of the construction engineering;
the combination module is used for combining the corresponding atomic members according to the construction conditions of each work type on the large data platform of the building engineering to obtain a construction minimum unit of each work type;
and the execution module is used for making a construction plan according to the construction minimum unit and tracking the construction progress.
10. The project progress management system for construction projects of claim 9, wherein the deconstructing module comprises:
the data sub-module is used for converting the construction engineering data of the compact three-dimensional model and transmitting the converted data to a budget data unit of the construction project management platform;
the extraction submodule is used for extracting construction models of various work types from the big data platform;
and the point counting sub-module is used for converting construction points of the construction engineering quantity of each construction model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202310563124.XA CN116596243A (en) | 2023-05-18 | 2023-05-18 | Project progress management system and method for constructional engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202310563124.XA CN116596243A (en) | 2023-05-18 | 2023-05-18 | Project progress management system and method for constructional engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN116596243A true CN116596243A (en) | 2023-08-15 |
Family
ID=87589294
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202310563124.XA Pending CN116596243A (en) | 2023-05-18 | 2023-05-18 | Project progress management system and method for constructional engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN116596243A (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115775068A (en) * | 2022-12-08 | 2023-03-10 | 中国核工业第五建设有限公司 | Nuclear power project progress monitoring method and system |
CN115936765A (en) * | 2022-12-19 | 2023-04-07 | 北京天辰信科技有限公司 | Engineering data analysis-based engineering cost prediction method and system |
-
2023
- 2023-05-18 CN CN202310563124.XA patent/CN116596243A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115775068A (en) * | 2022-12-08 | 2023-03-10 | 中国核工业第五建设有限公司 | Nuclear power project progress monitoring method and system |
CN115936765A (en) * | 2022-12-19 | 2023-04-07 | 北京天辰信科技有限公司 | Engineering data analysis-based engineering cost prediction method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Halligan et al. | Action-response model and loss of productivity in construction | |
Mahnic et al. | Measuring progress of scrum-based software projects | |
CN109214679B (en) | Project engineering management system based on building information model | |
Lee et al. | Building information modeling for quality management in infrastructure construction projects | |
Memon et al. | An automatic project progress monitoring model by integrating auto CAD and digital photos | |
CN111681054A (en) | Intelligent pricing method for project cost list | |
KR20030068661A (en) | Integrated construction management system and method using portable terminal | |
US20120179512A1 (en) | Change management system | |
CN113807661A (en) | Project progress monitoring management system and method based on three-dimensional video acquisition | |
CN115775068A (en) | Nuclear power project progress monitoring method and system | |
CN114418369A (en) | Metering payment method and system based on BIM (building information modeling) | |
CN116596243A (en) | Project progress management system and method for constructional engineering | |
CN113011629A (en) | Software project budget estimation method based on development team role | |
CN116342177B (en) | BIM-based whole-process cost consultation service management system | |
CN116645044A (en) | Full-flow management method and system for scientific research device construction | |
CN116051055A (en) | Digital project management system | |
CN116167582A (en) | Intelligent construction progress monitoring system based on BIM technology | |
CN115860562A (en) | Software workload rationality evaluation method, device and equipment | |
Moragane et al. | Application of computer vision for construction progress monitoring. | |
CN112541730A (en) | Project working hour statistical method, device and storage medium | |
CA2832806C (en) | Method for optimizing schedule compression in projects using accelerating and overlapping of activities | |
Saito | Case study: reducing labor cost using industrial engineering techniques | |
CN110866690A (en) | Application of BIM model data in intelligent construction site | |
Kim et al. | Development of an automated As-planned schedule system for efficient scheduling | |
CN113095296B (en) | Civil engineering material calculation system and method based on Internet of things |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |