CN116290098A - Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking - Google Patents

Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking Download PDF

Info

Publication number
CN116290098A
CN116290098A CN202310325952.XA CN202310325952A CN116290098A CN 116290098 A CN116290098 A CN 116290098A CN 202310325952 A CN202310325952 A CN 202310325952A CN 116290098 A CN116290098 A CN 116290098A
Authority
CN
China
Prior art keywords
wall
post
concrete precast
leveling
prefabricated plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310325952.XA
Other languages
Chinese (zh)
Inventor
赵嘉
梁广远
彭林林
桂成良
陆良清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202310325952.XA priority Critical patent/CN116290098A/en
Publication of CN116290098A publication Critical patent/CN116290098A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention relates to a construction method for pre-closing a post-pouring zone of an external wall of a ground warehouse without bricking; the construction method comprises the following steps of 1, constructing an outer wall post-pouring belt precast slab; step 2, sealing and blocking the basement outer wall post-pouring belt by adopting a concrete precast slab with the thickness of 100:500:1200: 1200mmC 40; step 3, hanging rings ∅ on the prefabricated plates are cut off after the prefabricated plates are hung, and then the prefabricated plates are hung after leveling is carried out by waterproof mortar; step 4, connecting the concrete precast slabs with the basement outer wall, and tying the concrete precast slabs with the horizontal ribs of the basement outer wall by utilizing ∅ steel bars on the concrete precast slabs; step 5, paving waterproof mortar between the precast slabs for leveling; step 6, the joint of the concrete precast slab and the basement outer wall is smeared into an oblique angle of 45 degrees by waterproof mortar; and 7, paving waterproof coiled materials at the post-pouring belt, and expanding prefabricated plates by 1000mm on two sides. The construction method adopts the steps, solves the problems of low efficiency and poor strength of masonry, thereby accelerating the construction progress, saving the cost and improving the quality.

Description

Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking
Technical Field
The invention relates to the technical field of concrete pouring, in particular to a construction method for pre-closing a post-pouring zone of an external wall of a ground warehouse without bricking.
Background
In many residential engineering at present, many post-cast strips of design drawing ground storehouse are subsided post-cast strips, require all to need main part capping after 2 months and just can pour post-cast strip concrete, have two influences under the circumstances like this: the first post-pouring zone and the post-pouring zone are not closed, the outer wall cannot be constructed in a waterproof manner, backfilling cannot be carried out, and the second post-pouring zone and the post-pouring zone are not backfilled for a long time, so that the danger source of the foundation pit exists for a long time, and the post-pouring zone of the outer wall of the ground warehouse needs to be closed in advance for inserting other and working procedures in advance to eliminate the danger source. If the post-cast strip sealing measures are used for bricking, the bricking engineering is complicated, plastering is performed on the outer side, and the outer wall cannot be immediately inserted into the construction for one day after the plastering is finished (the post-working is performed), so that analysis is performed, and the economic rationality is poor.
Disclosure of Invention
The invention aims to overcome the defects, and provides a construction method for sealing post-cast strips of an external wall of a ground warehouse in advance without bricking, which adopts a precast slab hoisting mode to seal, so that the construction of the procedures of external wall waterproofing and fertilizer groove backfilling can be inserted in advance, the low-efficiency and poor-strength masonry process is solved, the construction progress is integrally accelerated, the cost is saved, and the quality is improved.
In order to achieve the above object, the present invention is achieved by:
a construction method for pre-closing post-pouring zone of external wall of ground warehouse without brick laying comprises
Step 1, construction of an outer wall post-cast strip precast slab:
step 1.1, prefabricating an outer wall post-pouring belt prefabricated plate;
step 1.2, hanging wires;
step 1.3, hoisting;
step 1.4, reinforcing;
step 1.5, leveling waterproof mortar at the splicing position of the plates;
step 1.6, hoisting the subsequent precast slab
Step 1.7, leveling after hoisting is finished;
step 1.8, smearing an arc at the internal corner;
step 1.9, waterproof coiled materials;
step 1.10, sticking an extruded sheet;
step 1.11, backfilling soil;
step 2, sealing and blocking the basement outer wall post-pouring belt by adopting a concrete precast slab with the thickness of 100:500:1200: 1200mmC 40;
step 2.1, sequentially upwards discharging from a foundation slab, wherein the size of the uppermost precast slab is based on the actual measurement size in the field;
step 3, hanging rings ∅ on the prefabricated plates are cut off after the prefabricated plates are hung, and then the prefabricated plates are hung after leveling is carried out by waterproof mortar;
step 4, connecting the concrete precast slabs with the basement outer wall, and tying the concrete precast slabs with the horizontal ribs of the basement outer wall by utilizing ∅ steel bars on the concrete precast slabs;
step 5, paving waterproof mortar between the precast slabs for leveling;
step 6, the joint of the concrete precast slab and the basement outer wall is smeared into an oblique angle of 45 degrees by waterproof mortar;
and 7, paving waterproof coiled materials at the post-pouring belt, and expanding prefabricated plates by 1000mm on two sides.
By adopting the steps, the construction method is capable of inserting the waterproof construction of the external wall and the backfilling process of the fertilizer groove in advance on the premise that the post-cast strip of the external wall cannot be poured, and solves the problems of low efficiency and poor strength of masonry, thereby accelerating the construction progress, saving the cost and improving the quality.
Drawings
FIG. 1 is a schematic diagram of a construction method according to the present invention.
Fig. 2 is a schematic diagram of a construction method according to the present invention.
FIG. 3 is a schematic diagram III of the construction method according to the present invention.
Description of the embodiments
The invention is further illustrated by the following specific examples.
As shown in figures-3, the construction method for the post-cast strip of the external wall of the ground warehouse to be sealed in advance without bricking comprises the following steps of
Step 1, construction of an outer wall post-cast strip precast slab:
step 1.1, prefabricating an outer wall post-pouring belt prefabricated plate;
step 1.2, hanging wires;
step 1.3, hoisting;
step 1.4, reinforcing;
step 1.5, leveling waterproof mortar at the splicing position of the plates;
step 1.6, hoisting the subsequent precast slab
Step 1.7, leveling after hoisting is finished;
step 1.8, smearing an arc at the internal corner;
step 1.9, waterproof coiled materials;
step 1.10, sticking an extruded sheet;
step 1.11, backfilling soil;
step 2, sealing and blocking the basement outer wall post-pouring belt by adopting a concrete precast slab with the thickness of 100:500:1200: 1200mmC 40;
step 2.1, sequentially upwards discharging from a foundation slab, wherein the size of the uppermost precast slab is based on the actual measurement size in the field;
step 3, hanging rings ∅ on the prefabricated plates are cut off after the prefabricated plates are hung, and then the prefabricated plates are hung after leveling is carried out by waterproof mortar;
step 4, connecting the concrete precast slabs with the basement outer wall, and tying the concrete precast slabs with the horizontal ribs of the basement outer wall by utilizing ∅ steel bars on the concrete precast slabs;
step 5, paving waterproof mortar between the precast slabs for leveling;
step 6, the joint of the concrete precast slab and the basement outer wall is smeared into an oblique angle of 45 degrees by waterproof mortar;
and 7, paving waterproof coiled materials at the post-pouring belt, and expanding prefabricated plates by 1000mm on two sides.
By adopting the steps, the construction method is capable of inserting the waterproof construction of the external wall and the backfilling process of the fertilizer groove in advance on the premise that the post-cast strip of the external wall cannot be poured, and solves the problems of low efficiency and poor strength of masonry, thereby accelerating the construction progress, saving the cost and improving the quality.

Claims (1)

1. A construction method for pre-closing post-pouring strips of an external wall of a ground warehouse without bricking is characterized by comprising the following steps: comprising
Step 1, construction of an outer wall post-cast strip precast slab:
step 1.1, prefabricating an outer wall post-pouring belt prefabricated plate;
step 1.2, hanging wires;
step 1.3, hoisting;
step 1.4, reinforcing;
step 1.5, leveling waterproof mortar at the splicing position of the plates;
step 1.6, hoisting the subsequent precast slab
Step 1.7, leveling after hoisting is finished;
step 1.8, smearing an arc at the internal corner;
step 1.9, waterproof coiled materials;
step 1.10, sticking an extruded sheet;
step 1.11, backfilling soil;
step 2, sealing and blocking the basement outer wall post-pouring belt by adopting a concrete precast slab with the thickness of 100:500:1200: 1200mmC 40;
step 2.1, sequentially upwards discharging from a foundation slab, wherein the size of the uppermost precast slab is based on the actual measurement size in the field;
step 3, hanging rings ∅ on the prefabricated plates are cut off after the prefabricated plates are hung, and then the prefabricated plates are hung after leveling is carried out by waterproof mortar;
step 4, connecting the concrete precast slabs with the basement outer wall, and tying the concrete precast slabs with the horizontal ribs of the basement outer wall by utilizing ∅ steel bars on the concrete precast slabs;
step 5, paving waterproof mortar between the precast slabs for leveling;
step 6, the joint of the concrete precast slab and the basement outer wall is smeared into an oblique angle of 45 degrees by waterproof mortar;
and 7, paving waterproof coiled materials at the post-pouring belt, and expanding prefabricated plates by 1000mm on two sides.
CN202310325952.XA 2023-03-30 2023-03-30 Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking Pending CN116290098A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310325952.XA CN116290098A (en) 2023-03-30 2023-03-30 Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310325952.XA CN116290098A (en) 2023-03-30 2023-03-30 Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking

Publications (1)

Publication Number Publication Date
CN116290098A true CN116290098A (en) 2023-06-23

Family

ID=86792512

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310325952.XA Pending CN116290098A (en) 2023-03-30 2023-03-30 Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking

Country Status (1)

Country Link
CN (1) CN116290098A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN213014375U (en) * 2020-07-09 2021-04-20 发达控股集团有限公司 Basement outer wall post-cast strip enclosed construction
CN213952303U (en) * 2020-08-31 2021-08-13 上海建工七建集团有限公司 Basement outer wall post-cast strip assembled protection wall construction structures
CN217758964U (en) * 2022-05-24 2022-11-08 上海建工七建集团有限公司 Basement outer wall post-cast strip closed structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN213014375U (en) * 2020-07-09 2021-04-20 发达控股集团有限公司 Basement outer wall post-cast strip enclosed construction
CN213952303U (en) * 2020-08-31 2021-08-13 上海建工七建集团有限公司 Basement outer wall post-cast strip assembled protection wall construction structures
CN217758964U (en) * 2022-05-24 2022-11-08 上海建工七建集团有限公司 Basement outer wall post-cast strip closed structure

Similar Documents

Publication Publication Date Title
CN212129251U (en) Advanced sealing structure of post-cast strip subsides
CN113513015A (en) Semi-prefabricated concrete reinforcement cage underground continuous wall and construction method
CN201891133U (en) Manual assembled type self-waterproof late poured band prefabricated slab of basement outer wall
CN114457852A (en) Basement exterior wall post-cast strip U-shaped concrete precast slab plugging method
CN207144012U (en) A kind of post-cast strip prefabricated board barricade
CN113374263A (en) Construction method for closing settled post-cast strip in advance
CN116290098A (en) Construction method for pre-closing post-pouring zone of external wall of ground warehouse without bricking
CN210117716U (en) Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft
CN206655313U (en) A kind of vertical post-cast strip plugging structure of basement
CN217758964U (en) Basement outer wall post-cast strip closed structure
CN215519946U (en) Wall body corner constructional column exempts from formwork construction structures
CN216787229U (en) Basement outer wall post-cast strip assembled shutoff steel sheet structure
CN113802699A (en) Construction method for rapidly plugging by applying precast slab of shear wall post-cast strip
CN210288465U (en) Assembled retaining wall post-cast strip plugging member
CN211691450U (en) Slurry leakage prevention device for prefabricated side embedded steel bars of laminated slab beam
CN203373784U (en) Vertical post-cast strip plugging structure of basement
CN107142956A (en) A kind of prefabricated assembled elevator basis
CN220888741U (en) Basement outer wall post-pouring strip advanced plugging structure
CN216379657U (en) Super long basement formula post-cast strip structure that sinks
CN218479532U (en) Assembled post-cast strip closing device
CN219973299U (en) Prefabricated assembled basement roof post-cast strip advanced sealing structure
CN216690050U (en) Advanced sealing member for post-cast strip of underground chamber roof
CN211341220U (en) Quick closing device of basement post-cast strip
CN218148527U (en) Subside post-cast strip structure sealed in advance
CN217299020U (en) Post-cast strip part prefabricated retaining wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination