CN116122102A - Concrete inclined plane curb for urban updating road and construction method thereof - Google Patents

Concrete inclined plane curb for urban updating road and construction method thereof Download PDF

Info

Publication number
CN116122102A
CN116122102A CN202310054021.0A CN202310054021A CN116122102A CN 116122102 A CN116122102 A CN 116122102A CN 202310054021 A CN202310054021 A CN 202310054021A CN 116122102 A CN116122102 A CN 116122102A
Authority
CN
China
Prior art keywords
curb
road
concrete
urban
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310054021.0A
Other languages
Chinese (zh)
Inventor
董有
鞠树森
杨亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhufu Beijing Urban Renewal And Construction Group Co ltd
Original Assignee
Zhufu Beijing Urban Renewal And Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhufu Beijing Urban Renewal And Construction Group Co ltd filed Critical Zhufu Beijing Urban Renewal And Construction Group Co ltd
Priority to CN202310054021.0A priority Critical patent/CN116122102A/en
Publication of CN116122102A publication Critical patent/CN116122102A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/221Kerbs or like edging members, e.g. flush kerbs, shoulder retaining means ; Joint members, connecting or load-transfer means specially for kerbs
    • E01C11/222Raised kerbs, e.g. for sidewalks ; Integrated or portable means for facilitating ascent or descent
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to a concrete slope curb used for urban updating roads and a construction method thereof, wherein the concrete slope curb is divided into two types of straight concrete slope curbstone and curved concrete slope curbstone, and is characterized in that: the road surface comprises a curb top surface, a curb inclined surface, a curb front surface, a curb bottom surface, a curb back surface, a round corner and a road surface horizontal line; the urban road is reformed by adopting the concrete inclined-plane curb, the height difference between the bottom edge of the curb inclined-plane and the road surface is reduced to 0-25 mm, so that the wheelchair can conveniently load and unload the curb, the ambulance or the fire truck temporarily load and unload the cargoes, and the danger of supporting the vehicle can be avoided, and meanwhile, the damage to the tires and the shock absorber caused by the height difference is avoided.

Description

Concrete inclined plane curb for urban updating road and construction method thereof
Technical Field
The invention relates to a concrete inclined plane curb for an urban road update and a construction method thereof, belonging to the technical field of urban road update and reconstruction.
Background
Kerbs are strip-shaped structures between the road surface and shoulders on both sides of a road, and are also commonly referred to as "curbs" because of the fall. The curb of urban roads is generally about 100mm higher than the road surface, and the height of the curb of some cities is 120mm or 150mm, even up to 200mm. The curb has the function of replacing the belt in urban traffic, can standardize urban pedestrian driving, can limit vehicles to only drive on the lane so as to separate people from vehicles, induce vision, and also has the function of centralized drainage, rainwater can be collected to the edge of the curb after rain, and the rainwater can be collected to the sewer outlet along the curb. The types of the curbs of the urban roads are various, and the curbs made of natural stone, the curbs made of concrete and the like are common in gray colors. Another effect of the curb of urban roads is to limit the travel of vehicles to sidewalks or walkways, avoiding crushing of the sidewalks or walkways. In real life, however, there are many vehicles that need to go up and down the curb, which not only brings trouble to the vehicles, but also damages the curb, for example: wheelchair up-down kerbs, non-motor vehicles temporarily load and unload goods, ambulances or fire-fighting vehicles temporarily up-down kerbs and the like, or else, the wheelchair up-down kerbs and the non-motor vehicles only can detour to a ramp and then turn back, so that great inconvenience is brought to life.
Disclosure of Invention
The invention provides a concrete inclined plane curb used for an urban updating road and a construction method thereof, which mainly aim to solve the problems that a wheelchair can conveniently and temporarily load and unload the curb, a non-motor vehicle can temporarily load and unload goods, an ambulance or a fire truck can temporarily load and unload the curb, and the like in real life, and simultaneously ensure the integrity and durability of the urban road curb to be normally used.
The technical scheme of the invention is as follows:
the utility model provides a city updating road adopts concrete inclined plane curb and construction method thereof, and concrete inclined plane curb falls into two types of sharp concrete inclined plane curb and curved concrete inclined plane curb, and see the fig. 1-3 shows, including curb top surface, curb inclined plane, curb front surface, curb bottom surface, curb back, fillet and road surface horizon, its characterized in that: the length of the urban road linear concrete inclined surface curb is 1000mm; the arc length of the curve-shaped concrete slope curb of the urban road is 1000mm; the urban road linear concrete inclined surface curb and the curved concrete inclined surface curb are prepared from fine aggregate and coarse aggregate, or fly ash or industrial waste residue, and the cement is ordinary Portland cement; the width dimension of the top surface section of the curb is 200mm; the inclined plane section of the curb is formed by 60mm of a and 150mm of b; the height of the front section of the curb is 240mm; the width of the cross section of the bottom surface of the curb is 350mm; the height of the cross section of the back surface of the curb is 300mm; the round angle is R50; the road surface horizontal line is the installation height between the bottom edge of the curb inclined plane and the road surface.
The urban updating road adopts the concrete inclined plane curb and the construction method thereof, and comprises the following steps:
step one: measurement lofting
Before the concrete slope curb is installed, the road center line should be checked, and the concrete slope curb installation control pile is tested.
Step two: curb mounting
Firstly, paving a bottom by adopting dry and hard mortar, and then, paving curb stones, wherein the curb stone is firmly and smoothly paved, and the width of gaps between the curb stones is 8-10 mm. The height of the exposed horizontal line of the curb slope bottom edge on the horse pavement is about 20 mm. And after all the curb is installed, hanging wires, and adjusting to be straight and smooth.
Step three: crack pouring and maintenance
Before the seam is filled, soil and sundries in the curb stone seam are removed, the curb stone seam is wetted by water, then the cement mortar filling seam meeting the design requirement is filled closely, the pointing seam is 2-3 mm lower than the surface of the curb stone, and the surplus mortar is removed. And (3) curing the curb mortar by using wine after finishing the curb mortar joint, wherein the curing period is not less than 3 days.
Step four: curb back support
The back of the curb should be supported by concrete pouring according to the design requirement, when the geometric design of the support is not required, the height is preferably 1/2-1/3 of the height of the curb, and the width is not less than 150mm.
The beneficial effects are that:
the invention has the most remarkable advantages that the curved concrete inclined surface curb is adopted, and meanwhile, the linear concrete inclined surface curb is matched to reform the urban road, so that the height difference between the inclined surface bottom edge of the curb and the road surface is reduced to 0-25 mm, the wheelchair can conveniently and temporarily load and unload cargoes up and down the curb, the ambulance or the fire truck, and the danger of supporting the vehicle bottom can be avoided, and meanwhile, the damage to the tires and the shock absorber caused by the height difference is avoided. If the technology is popularized and applied in the urban updating road reconstruction, the technology has obvious economic and social benefits.
Drawings
FIG. 1 is a perspective view of a straight concrete bevel curb;
FIG. 2 is a perspective view of a curved concrete beveled curb;
fig. 3 is a cross-sectional view of fig. 1.
In the figure, 1: a curb top surface; 2: a curb slope; 3: the front of the curb; 4: the back of the curb; 5: a curb bottom surface; 6, preparing a base material; horse road surface horizontal line; 7: round corners; 8: the bottom edge of the slope of the curb.
Detailed Description
The utility model provides a city updating road adopts concrete inclined plane curb and construction method thereof, and concrete inclined plane curb divide into straight line concrete inclined plane curb and curved concrete inclined plane curb two kinds, see the shown in fig. 1 ~ 3, including curb top surface 1, curb inclined plane 2, curb front surface 3, curb bottom surface 5, curb back surface 4, fillet 7 and road surface horizon 6, its characterized in that: the length of the urban road linear concrete inclined surface curb is 1000mm; the arc length of the curve-shaped concrete slope curb of the urban road is 1000mm; the urban road linear concrete inclined surface curb and the curved concrete inclined surface curb are prepared from fine aggregate and coarse aggregate, or fly ash or industrial waste residue, and the cement is ordinary Portland cement; the width dimension of the section of the top surface 1 of the curb is 200mm; the cross section of the curb inclined surface 2 is formed by 60mm of a and 150mm of b; the height of the section 3 in front of the curb is 240mm; the width of the section of the bottom surface 5 of the curb is 350mm; the height of the section 4 of the back surface of the curb is 300mm; the round angle 7 is R50; the road surface horizontal line is the installation height between the bottom edge of the curb inclined plane and the road surface.
The urban updating road adopts the concrete inclined plane curb and the construction method thereof, and comprises the following steps:
step one: measurement lofting
Before the concrete slope curb is installed, the road center line should be checked, and the concrete slope curb installation control pile is tested.
Step two: curb mounting
Firstly, paving a bottom by adopting dry and hard mortar, then, paving curb stones, wherein the curb stone is firmly and smoothly paved, the width of a gap between the curb stones is 8-10 mm, and the height of the bottom edge 8 of the slope of the curb stone exposed out of the horizontal line 6 of the road surface is about 20 mm. And after all the curb is installed, hanging wires, and adjusting to be straight and smooth.
Step three: crack pouring and maintenance
Before the seam is filled, soil and sundries in the curb stone seam are removed, the curb stone seam is wetted by water, then the cement mortar filling seam meeting the design requirement is filled closely, the pointing seam is 2-3 mm lower than the surface of the curb stone, and the surplus mortar is removed. And (3) curing the curb mortar by using wine after finishing the curb mortar joint, wherein the curing period is not less than 3 days.
Step four: curb back support
The back of the curb should be supported by concrete pouring according to the design requirement, when the geometric design of the support is not required, the height is preferably 1/2-1/3 of the height of the curb, and the width is not less than 150mm.
The foregoing is an exemplary embodiment of the present invention, and the implementation of the present invention is not limited thereto.

Claims (8)

1. A concrete slope curb and a construction method thereof are adopted for urban updating roads, the concrete slope curb is divided into two types of straight concrete slope curb and curved concrete slope curb, and the method is characterized in that: the road surface horizontal line comprises a curb top surface (1), a curb inclined surface (2), a curb front surface (3), a curb bottom surface (5), a curb back surface (4), round corners (7) and a road surface horizontal line (6); the length of the urban road linear concrete inclined surface curb is 1000mm; the arc length of the curve-shaped concrete slope curb of the urban road is 1000mm; the urban road linear concrete inclined surface curb and the curved concrete inclined surface curb are prepared from fine aggregate and coarse aggregate, or fly ash or industrial waste residue, and the cement is ordinary Portland cement; the road surface horizontal line (6) is the installation height between the bottom edge (8) of the curb inclined plane and the road surface.
2. The urban updating road adopts concrete slope kerb and the construction method thereof according to claim 1, which is characterized in that: the width dimension of the cross section of the top surface (1) of the curb is 200mm.
3. The urban updating road adopts concrete slope kerb and the construction method thereof according to claim 1, which is characterized in that: the cross section of the curb inclined plane (2) is composed of 60mm of a and 150mm of b.
4. The urban updating road adopts concrete slope kerb and the construction method thereof according to claim 1, which is characterized in that: the height of the section of the front surface (3) of the curb is 240mm.
5. The urban updating road adopts concrete slope kerb and the construction method thereof according to claim 1, which is characterized in that: the width of the cross section of the bottom surface (5) of the curb is 350mm.
6. The urban updating road adopts concrete slope kerb and the construction method thereof according to claim 1, which is characterized in that: the height of the section of the back surface (4) of the curb is 300mm.
7. The urban updating road adopts concrete slope kerb and the construction method thereof according to claim 1, which is characterized in that: the round angle (7) is R50.
8. The concrete ramp curb for urban update road and construction method thereof according to any one of claims 1-7, wherein: the method comprises the following steps:
step one: measurement lofting
Before the concrete slope curb is installed, the road center line should be checked, and the concrete slope curb installation control pile is tested.
Step two: curb mounting
Firstly, paving a bottom by adopting dry and hard mortar, then, paving curb stones, wherein the curb stone is firmly and smoothly paved, the width of a gap between the curb stones is 8-10 mm, and the height of a horizontal line (6) of a road surface exposed by the bottom edge (8) of a slope of the curb stone is about 20 mm. And after all the curb is installed, hanging wires, and adjusting to be straight and smooth.
Step three: crack pouring and maintenance
Before the seam is filled, soil and sundries in the curb stone seam are removed, the curb stone seam is wetted by water, then the cement mortar filling seam meeting the design requirement is filled closely, the pointing seam is 2-3 mm lower than the surface of the curb stone, and the surplus mortar is removed. And (3) curing the curb mortar by using wine after finishing the curb mortar joint, wherein the curing period is not less than 3 days.
Step four: curb back support
The back of the curb should be supported by concrete pouring according to the design requirement, when the geometric design of the support is not required, the height is preferably 1/2-1/3 of the height of the curb, and the width is not less than 150mm.
CN202310054021.0A 2023-01-30 2023-01-30 Concrete inclined plane curb for urban updating road and construction method thereof Pending CN116122102A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310054021.0A CN116122102A (en) 2023-01-30 2023-01-30 Concrete inclined plane curb for urban updating road and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310054021.0A CN116122102A (en) 2023-01-30 2023-01-30 Concrete inclined plane curb for urban updating road and construction method thereof

Publications (1)

Publication Number Publication Date
CN116122102A true CN116122102A (en) 2023-05-16

Family

ID=86298875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310054021.0A Pending CN116122102A (en) 2023-01-30 2023-01-30 Concrete inclined plane curb for urban updating road and construction method thereof

Country Status (1)

Country Link
CN (1) CN116122102A (en)

Similar Documents

Publication Publication Date Title
CN104652210B (en) Assembled concrete traffic pavement and construction method thereof
Garber et al. Guide to cement-based integrated pavement solutions.
CN105421571A (en) Sewer well and rainwater well construction process
CN111648408A (en) Inspection well lifting construction method
KR100889252B1 (en) Block having a load divergence function and manufacturing and road constructing method for the same
CN107151958B (en) Permanent rural highway cement road surface of easy maintenance
CN116122102A (en) Concrete inclined plane curb for urban updating road and construction method thereof
CN215405359U (en) Lane pavement structure
CN204475099U (en) A kind of assembly concrete traffic
RU2394959C1 (en) Road surface structure
CN208346585U (en) A kind of permeable pavement floor tile
CN210916876U (en) Urban road rebuilds people's way pavement structure of mating formation that permeates water of engineering
CN208701457U (en) Pavement bricks, the pavement using pavement bricks and engineering road
CN116103973A (en) Linear concrete slope curb for urban road
KR100698487B1 (en) Construction work method of road pavement
CN209759935U (en) Rural tomb highway bituminous paving cold regeneration structure of cement
CN116065446A (en) Urban road curve-shaped concrete inclined plane curb
CN110629634A (en) Anti-warping rapid-drainage sidewalk brick and curb device and integral assembling method
JP2005029993A (en) Pavement structure of concrete block
CN112095394A (en) Composite pavement with excellent drainage function and construction method thereof
KR200413525Y1 (en) Pavement Material and Method for Paving by Using Same
CN212077527U (en) Asphalt composite road pavement structure
RU2422581C1 (en) Method to repair and construct arterial highways
CN218203670U (en) Mosaic type water permeability pavement brick
CN110158396B (en) Construction method of permeable pavement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination