The method of integral jacking roof of reinforced concrete pile single storey industry workshop
Technical field:
The present invention relates to a kind of method of integral jacking roof of reinforced concrete pile single storey industry workshop, belong to house lid integral jacking technical field.
Background technology:
Present existing integral jacking roof technology, general all is the column top that the lifting pin that jacking is used is fixedly connected on the house, just can carry out jacking after then the house column being cut off, as the disclosed denomination of invention of Chinese patent literature be: integrated raising method for self-supporting house roof extremely installs, application number is: 01108408.1 technical scheme, in this technical scheme, the method that is adopted is exactly the method that just can carry out jacking after the house column need being cut off.Yet, for the factory building column that adopts steel bar concrete to make, owing to be difficult to lifting pin is fixed on the reinforced concrete pile, even and lifting pin is fixed on the reinforced concrete pile, but because the fragility of steel bar concrete material, when its reinforced concrete pile is cut off, the one, greatly reduce the intensity of reinforced concrete pile, the 2nd, influence being connected of lifting pin and reinforced concrete pile easily, thereby cause that easily the danger of falling apart is become flexible in appearance in the jacking process, so existing jacking technology only is applicable to the house caping liter of steel post, and be not suitable for the house caping liter of reinforced concrete pile.
Summary of the invention:
The objective of the invention is: provide a kind of simple to operate, with low cost and do not need with column method that cut off, that be applicable to integral jacking roof of reinforced concrete pile single storey industry workshop, to overcome the deficiencies in the prior art.
The present invention is achieved in that it comprises that the employing jack carries out jacking, when the roof system to reinforced concrete pile single storey industry workshop carries out jacking, elder generation's prefabricated cushion block (6), fix two steel bar concrete brackets (2) in two sides, top of the every reinforced concrete pile (1) of reinforced concrete pile single storey industry workshop then, and the end face that makes each bracket (2) is the plane, on the end face of each bracket (2), place a jack (3), lower edge end at the every roof truss (4) of factory building roof system is provided with a girder steel (5), and the two ends that make girder steel (5) are bearing in respectively on the jack (3) of reinforced concrete pile (1) both sides, the connector of all former roof truss (4) head bottom part and reinforced concrete pile (1) end face is disconnected, start the jack (3) of every reinforced concrete pile (1) both sides then synchronously, whole roof system is risen simultaneously, after lifting altitude reaches a stroke, a pad cushion block (6) between the end face of every reinforced concrete pile (1) and roof truss (4) termination, fall every jack (3) then after rise, and below every jack (3) cushion block (6) of a same thickness of pad, and then the jack (3) that starts every reinforced concrete pile (1) both sides synchronously carries out next stroke jacking, and so circulation can be with integral jacking roof to desired location; The material of cushion block (6) can adopt plain concrete, steel bar concrete, timber or metal material to make.
Owing to adopted technique scheme, the present invention compared with prior art, the present invention's operation is very easily simple, because need not cutting off the column in house when jacking, the present invention can carry out jacking, therefore can not influence the intensity of house column, so the present invention is very suitable for the roof system of reinforced concrete pile single storey industry workshop is carried out integral jacking, and because cushion block of the present invention making is very simple, cost of manufacture is also very cheap, and required instrument, material is all fewer, so the present invention has simple to operate, with low cost, and be applicable to the advantage of integral jacking roof of reinforced concrete pile single storey industry workshop.
Description of drawings:
Accompanying drawing 1 is a construction schematic diagram of the present invention;
Accompanying drawing 2 is that the A of accompanying drawing 1 is to schematic diagram.
The specific embodiment:
Embodiments of the invention: jack can adopt fluid pressure type or spiral jack, but preferably adopt spiral jack, when the roof system to reinforced concrete pile single storey industry workshop carries out jacking, elder generation's prefabricated cushion block (6), the material of making cushion block (6) can adopt plain concrete, steel bar concrete, timber or metal material are made, adopting plain concrete material to make under the regular situation gets final product, when making cushion block, note making smooth in two planes it up and down, highly preferably be made into the same height, fix two steel bar concrete brackets (2) in two sides, top of the every reinforced concrete pile (1) of reinforced concrete pile single storey industry workshop then, and the end face that makes each bracket (2) is the plane of equal height, on the end face of each bracket (2), place a jack (3), lower edge end at the every roof truss (4) of factory building roof system is provided with a girder steel (5), and the two ends that make girder steel (5) are bearing in respectively on the jack (3) of reinforced concrete pile (1) both sides, the connector of all former roof truss (4) head bottom part and reinforced concrete pile (1) end face is disconnected, start the jack (3) of every reinforced concrete pile (1) both sides then synchronously, whole roof system is risen simultaneously, reach the stroke of a jack when lifting altitude after, a pad cushion block (6) between the end face of every reinforced concrete pile (1) and roof truss (4) termination, then every jack (3) is fallen back to original position, and below every jack (3) cushion block (6) of a same thickness of pad, and then the jack (3) that starts every reinforced concrete pile (1) both sides synchronously carries out next stroke jacking, and so circulation can be with integral jacking roof to desired location.