CN115506419A - Seamless leakage-proof construction method for basement exterior wall - Google Patents
Seamless leakage-proof construction method for basement exterior wall Download PDFInfo
- Publication number
- CN115506419A CN115506419A CN202211086276.7A CN202211086276A CN115506419A CN 115506419 A CN115506419 A CN 115506419A CN 202211086276 A CN202211086276 A CN 202211086276A CN 115506419 A CN115506419 A CN 115506419A
- Authority
- CN
- China
- Prior art keywords
- floor
- braces
- diagonal
- construction method
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 239000002689 soil Substances 0.000 claims abstract description 40
- 230000008093 supporting effect Effects 0.000 claims abstract description 13
- 239000004567 concrete Substances 0.000 claims abstract description 10
- 229910000831 Steel Inorganic materials 0.000 claims description 32
- 239000010959 steel Substances 0.000 claims description 32
- 238000009434 installation Methods 0.000 claims description 14
- 239000011150 reinforced concrete Substances 0.000 claims description 6
- 238000009412 basement excavation Methods 0.000 claims description 4
- 230000000694 effects Effects 0.000 abstract description 2
- 238000000034 method Methods 0.000 description 5
- 230000005540 biological transmission Effects 0.000 description 4
- 239000000463 material Substances 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 235000004443 Ricinus communis Nutrition 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000003566 sealing material Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000002352 surface water Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明涉及一种地下室外墙无缝防漏的施工方法,包括以下步骤:S1、由上至下依次安装多排用于支撑基坑坑壁的斜抛撑,安装每排斜抛撑后,清除与该排斜抛撑对应的反压土;S2、清除所述基坑内所有的反压土,由底部向上依次对各楼层进行施工;每层楼层的外墙施工前,拆除所述楼层对应的斜抛撑,已经施工完成的楼层的底板上留有对应的斜抛撑孔;对应的斜抛撑是指斜抛撑穿过该楼层的外墙;对拆除斜抛撑后的楼层的上一层进行施工时,用混凝土对斜抛撑孔进行填补。本发明通过先拆除斜抛撑,再进行外墙的施工,以防止外墙上留有斜抛撑孔,保证外墙结构的整体性,以达到防止渗漏的效果。
The invention relates to a construction method for seamless leak-proofing of basement exterior walls, comprising the following steps: S1, installing multiple rows of diagonal braces for supporting the wall of a foundation pit in sequence from top to bottom, and after installing each row of diagonal braces, Clear the anti-pressure soil corresponding to the row of inclined throwing braces; S2. Clear all the anti-pressure soil in the foundation pit, and construct each floor sequentially from the bottom up; before the construction of the outer wall of each floor, remove the corresponding There are corresponding slant brace holes on the bottom plate of the floor that has been constructed; the corresponding slant brace means that the slant brace passes through the outer wall of the floor; During the construction of the first floor, concrete is used to fill the holes of the inclined throws. The present invention firstly removes the slanting braces, and then constructs the outer wall to prevent the slanting brace holes from being left on the outer wall, ensure the integrity of the outer wall structure, and achieve the effect of preventing leakage.
Description
技术领域technical field
本发明涉及建筑施工技术领域,尤其涉及一种地下室外墙无缝防漏的施工方法。The invention relates to the technical field of building construction, in particular to a construction method for seamless leak-proofing of basement exterior walls.
背景技术Background technique
在基坑开挖和地下结构建设中,为了加快施工进度、缩短工期,支撑斜抛撑时,常同时施作地下室外墙及地下室各层楼板等关键部位,待混凝土强度满足要求后,再拆除斜抛撑,此时在斜抛撑与地下室外墙及地下室各层楼板相交处留有较大的孔洞,易造成地表水或地下水渗漏。通常采用防水材料封堵孔洞等防渗漏方法予以处理,但由于封堵材料随着时间推移将水化收缩或老化开裂,易产生缝隙,仍会导致渗漏,最终造成地下室外墙及地下室各层楼板钢筋锈蚀等不利现象。In the foundation pit excavation and underground structure construction, in order to speed up the construction progress and shorten the construction period, when supporting the slanting braces, the key parts such as the outer wall of the basement and the floor slabs of each floor of the basement are often constructed at the same time, and then demolished after the concrete strength meets the requirements. Diagonal throwing braces. At this time, large holes are left at the intersections of the diagonal throwing braces and the basement exterior wall and the floor slabs of each floor in the basement, which may easily cause surface water or groundwater to leak. Usually, waterproof materials are used to seal holes and other anti-leakage methods to deal with it. However, as time goes by, the sealing materials will hydrate, shrink or age and crack, which will easily produce gaps, which will still lead to leakage, and eventually cause the basement exterior walls and basements to be damaged. Unfavorable phenomena such as corrosion of steel bars on the floor slab.
发明内容Contents of the invention
(一)要解决的技术问题(1) Technical problems to be solved
鉴于现有技术的上述缺点、不足,本发明提供一种地下室外墙无缝防漏的施工方法,其解决了斜抛撑拆卸所产生的地下室外墙渗漏的技术问题。In view of the above-mentioned shortcomings and deficiencies of the prior art, the present invention provides a seamless leak-proof construction method for the outer wall of the basement, which solves the technical problem of leakage of the outer wall of the basement caused by the disassembly of the oblique caster brace.
(二)技术方案(2) Technical solution
为了达到上述目的,本发明采用的主要技术方案包括:In order to achieve the above object, the main technical solutions adopted in the present invention include:
一种地下室外墙无缝防漏的施工方法,包括以下步骤:A construction method for seamless leak-proofing of basement exterior walls, comprising the following steps:
S1、由上至下依次安装多排用于支撑基坑坑壁的斜抛撑,安装每排斜抛撑后,清除与该排斜抛撑对应的反压土;S1. Install multiple rows of diagonal braces for supporting the foundation pit wall from top to bottom. After installing each row of diagonal braces, remove the back pressure soil corresponding to the row of diagonal braces;
其中,安装每排斜抛撑前,在该排斜抛撑对应的反压土上开设用于安装斜抛撑的安装槽;Wherein, before installing each row of inclined throwing braces, an installation groove for installing diagonal throwing braces is opened on the counter pressure soil corresponding to the row of inclined throwing braces;
S2、清除所述基坑内剩余的反压土,由底部向上依次对各楼层进行施工;S2. Remove the remaining back pressure soil in the foundation pit, and construct each floor sequentially from the bottom up;
每层楼层的外墙施工前,拆除所述楼层对应的斜抛撑,已经施工完成的楼层的底板上留有对应的斜抛撑孔;Before the construction of the outer wall of each floor, remove the corresponding slanting bracing of the floor, and leave the corresponding slanting bracing hole on the bottom plate of the floor that has been constructed;
对应的斜抛撑是指斜抛撑穿过该楼层的外墙;The corresponding diagonal brace means that the diagonal brace passes through the outer wall of the floor;
对拆除斜抛撑后的楼层的上一层进行施工时,用混凝土对斜抛撑孔进行填补。When constructing the upper floor of the floor after the oblique throwing braces have been removed, the holes of the diagonal throwing braces are filled with concrete.
优选地,在步骤S1中,采用盆式挖土的方式得到所述基坑和多层所述反压土。Preferably, in step S1, the foundation pit and the multi-layer back pressure soil are obtained by using pot excavation.
优选地,在步骤S1中安装所述斜抛撑之前,沿所述基坑坑壁浇筑多个咬合桩,所述咬合桩沿上下方向延伸布置,沿所述咬合桩从上至下依次浇筑多个连接梁,所述连接梁沿水平方向布置,所述斜抛撑的顶端与所述连接梁相连接,所述斜抛撑的底部与所述基坑的底部相连接。Preferably, before installing the slanted castor brace in step S1, a plurality of occlusal piles are poured along the wall of the foundation pit, and the occlusal piles are arranged along the vertical direction, and multiple occlusal piles are poured sequentially from top to bottom along the occlusal piles. A connecting beam, the connecting beam is arranged along the horizontal direction, the top of the diagonal brace is connected with the connecting beam, and the bottom of the diagonal brace is connected with the bottom of the foundation pit.
优选地,所述斜抛撑包括上支墩和下支墩,所述上支墩与下支墩之间设有钢支撑。Preferably, the diagonal throwing brace includes an upper pier and a lower pier, and a steel support is provided between the upper pier and the lower pier.
优选地,所述上支墩与所述连接梁采用钢筋混凝土整体浇筑,所述下支墩与最底层楼层的底板采用钢筋混凝土整体浇筑,所述钢支撑与所述上支墩和所述下支墩相抵接。Preferably, the upper pier and the connecting beam are integrally poured with reinforced concrete, the lower pier and the floor of the bottom floor are integrally poured with reinforced concrete, and the steel support is integrated with the upper pier and the lower pier. The buttresses touch each other.
优选地,所述上支墩与所述钢支撑的接触面为第一连接面,所述下支墩与所述钢支撑的接触面为第二连接面,所述第一连接面与所述第二连接面相互平行,所述第一连接面与所述第二连接面相对应。Preferably, the contact surface between the upper pier and the steel support is a first connection surface, the contact surface between the lower pier and the steel support is a second connection surface, and the first connection surface and the The second connection surfaces are parallel to each other, and the first connection surface corresponds to the second connection surface.
优选地,所述上支墩与所述连接梁之间设有钢锚板。Preferably, a steel anchor plate is provided between the upper pier and the connecting beam.
优选地,每层楼层施工时,依次对该楼层的底板、用于支撑底部的换撑梁和外墙进行浇筑,外墙浇注前需先拆除所述楼层对应的斜抛撑。Preferably, during the construction of each floor, the bottom plate of the floor, the brace beams used to support the bottom and the outer wall are poured in sequence, and the diagonal braces corresponding to the floors need to be removed before pouring the outer wall.
优选地,清除所述基坑内所有的反压土后,对所述基坑内底部进行夯实,并在所述基坑内底部浇筑混凝土,以做为传力垫层,最底层楼层的底板浇筑于所述传力垫层的顶部。Preferably, after removing all the back pressure soil in the foundation pit, tamp the inner bottom of the foundation pit, and pour concrete at the inner bottom of the foundation pit as a force transmission cushion, and pour the bottom plate of the bottom floor on the bottom of the foundation pit. The top of the force-transmitting cushion described above.
优选地,拆除斜抛撑时,当受空间限制,钢支撑无法拆除时,可将钢支撑分割成多段后再进行拆除。Preferably, when dismantling the oblique brace, when the steel support cannot be dismantled due to space constraints, the steel support can be divided into multiple sections before dismantling.
(三)有益效果(3) Beneficial effects
本发明的有益效果是:(1)本发明通过预留的反压土对基坑坑壁进行支撑,防止基坑坑壁变形。The beneficial effects of the present invention are: (1) The present invention supports the wall of the foundation pit through the reserved back pressure soil to prevent deformation of the wall of the foundation pit.
(2)本发明安装多层斜抛撑时,由上至下依次清除多层反压土,清除每层反压土的同时安装斜抛撑,使未清除的反压土和已安装的斜抛撑共同支撑基坑坑壁,保持基坑的稳定;多层斜抛撑同时进行安装,缩短安装斜抛撑的时间,以缩短施工周期。(2) When the present invention is installed with multi-layer diagonal throwing braces, the multi-layer backpressure soil is removed successively from top to bottom. The throwing braces support the wall of the foundation pit together to maintain the stability of the foundation pit; multi-layer diagonal throwing braces are installed at the same time, shortening the time for installing the diagonal throwing braces, so as to shorten the construction period.
(3)本发明通过先拆除斜抛撑,再进行外墙的施工,以防止外墙上留有斜抛撑孔,保证外墙结构的整体性,以达到防止渗漏的效果。(3) The present invention removes the slanting brace first, and then carries out the construction of the outer wall, to prevent the slanting brace hole from being left on the outer wall, to ensure the integrity of the outer wall structure, and to achieve the effect of preventing leakage.
附图说明Description of drawings
图1为本发明的实施例中的方法流程框图;Fig. 1 is a method block diagram in the embodiment of the present invention;
图2为本发明的实施例中的斜抛撑的安装示意图;Fig. 2 is the installation schematic diagram of the oblique cast brace in the embodiment of the present invention;
图3为图2中斜抛撑的左视图与各楼层的组合视图。Fig. 3 is the left side view and the combination view of each floor in Fig. 2 for the diagonal throwing brace.
【附图标记说明】[Description of Reference Signs]
1:冠梁;2:安装槽;3:下支墩;4:上层反压土;5:下层反压土;6:上斜抛撑;7:腰梁;8:咬合桩;9:下斜抛撑;10:上支墩;11:负一层;12:负二层;13:负三层。1: crown beam; 2: installation groove; 3: lower pier; 4: upper backpressure soil; 5: lower backpressure soil; 10: upper pier; 11: negative first floor; 12: negative second floor; 13: negative third floor.
具体实施方式detailed description
为了更好的解释本发明,以便于理解,下面结合附图,通过具体实施方式,对本发明作详细描述。In order to better explain the present invention and facilitate understanding, the present invention will be described in detail below through specific embodiments in conjunction with the accompanying drawings.
实施例Example
如图1~3所示,一种地下室外墙无缝防漏的施工方法,包括以下步骤:As shown in Figures 1 to 3, a construction method for seamless leak-proofing of basement exterior walls includes the following steps:
S1、由上至下依次安装多排用于支撑基坑坑壁的斜抛撑,安装每排斜抛撑后,清除与该排斜抛撑对应的反压土;S1. Install multiple rows of diagonal braces for supporting the foundation pit wall from top to bottom. After installing each row of diagonal braces, remove the back pressure soil corresponding to the row of diagonal braces;
其中,安装每排斜抛撑前,在该排斜抛撑对应的反压土上开设用于安装斜抛撑的安装槽2。Wherein, before installing each row of inclined throwing braces, an
由于基坑是具有一定的长度和宽度的,每排斜抛撑包括多个斜抛撑,安装每排斜抛撑需要一定的时间,所以安装每排斜抛撑时,只要斜抛撑安装完成后,即可清除与该斜抛撑对应的反压土。Since the foundation pit has a certain length and width, and each row of diagonal braces includes multiple diagonal braces, it takes a certain amount of time to install each row of diagonal braces, so when installing each row of diagonal braces, as long as the installation of diagonal braces is completed After that, the backpressure soil corresponding to the diagonal throw can be removed.
地下室包括多层楼层,每层楼层包括外墙、底板和支撑底板的换撑梁。The basement includes multiple floors, each floor including exterior walls, a floor, and braced beams supporting the floor.
如图2~3所示,本实施例中,基坑深度为12.6m,咬合桩直径为1m,相邻咬合桩间的间距为1m,所要建造的地下室有三层楼层,由上至下依次为负一层11、负二层12和负三层13。预设安装两层斜抛撑,分别为上排斜抛撑和下排斜抛撑。基坑内对应设有两层反压土,分别为上层反压土4和下层反压土5。As shown in Figures 2-3, in this embodiment, the depth of the foundation pit is 12.6m, the diameter of the occlusal piles is 1m, and the distance between adjacent occlusal piles is 1m. The basement to be built has three floors, and the order from top to bottom is Negative
当然本方案的地下室不限于三层楼层,可以为两层、四层或五层,本方案的斜抛撑和反压土也不限于两层,可以为一层、三层或四层。Certainly the basement of this program is not limited to three floors, can be two floors, four floors or five floors, and the diagonal throwing brace and back pressure soil of this program are not limited to two floors, can be one floor, three floors or four floors.
如图2所示,本实施例中,由左向右依次清除上层反压土4,安装上排斜抛撑,上排斜抛撑包括多个上斜抛撑6,同时由左至右依次清除下层反压土5,安装下排斜抛撑,下排斜抛撑包括多个下斜抛撑9,多个下斜抛撑9与多个上斜抛撑6一一对应。为了缩短施工周期,上排斜抛撑和下排斜抛撑可同时进行安装,即,只要上斜抛撑6安装完成后,即可安装与其对应的下斜抛撑9。图2中的箭头方向为清除上层反压土4和下层反压土5的方向,及安装上斜抛撑6和下斜抛撑9的方向。As shown in Figure 2, in this embodiment, the upper layer of
为了充分利用反压土对基坑坑壁的支撑作用,安装斜抛撑时,可先在预设的安装斜抛撑的位置对应的反压土上开设安装槽2,待斜抛撑安装完成后再清理反压土。In order to make full use of the supporting effect of the anti-pressure soil on the wall of the foundation pit, when installing the oblique throw brace, you can first open the
如图2所示,具体地,本实施例中安装上排斜抛撑时,先在上层反压土4上开设用于安装上斜抛撑的安装槽2,上斜抛撑6安装完成后,再清理该上斜抛撑6对应的上层反压土4。同理,安装下排斜抛撑时,先在下层反压土5上开设用于安装下斜抛撑9的安装槽2,下斜抛撑9安装完成后,可再清理该下斜抛撑9对应的下层反压土5,或者所有的下斜抛撑9安装完成后,再清理下层反压土5。As shown in Figure 2, specifically, when installing the upper row of inclined throwing braces in this embodiment, an
S11、采用盆式挖土的方式挖取基坑,以使基坑坑壁覆盖多层反压土,反压土沿基坑坑壁四周布置,反压土能够对基坑的所有坑壁进行支撑,防止基坑坑壁变形或坍塌。S11. The foundation pit is excavated by basin excavation, so that the wall of the foundation pit is covered with multiple layers of back pressure soil, and the back pressure soil is arranged around the walls of the foundation pit, and the back pressure soil can Support to prevent the deformation or collapse of the foundation pit wall.
S12、安装所述斜抛撑之前,沿基坑坑壁浇筑多个咬合桩,咬合桩沿上下方向延伸布置,沿咬合桩最上层的连接梁,连接梁沿水平方向布置,斜抛撑的顶端与连接梁相连接,斜抛撑的底部与基坑的底部相连接。S12. Before installing the slanting braces, pour a plurality of occlusal piles along the wall of the foundation pit. The occlusal piles are arranged along the vertical direction, and the connecting beams on the uppermost layer of the occlusal piles are arranged along the horizontal direction. It is connected with the connecting beam, and the bottom of the diagonal brace is connected with the bottom of the foundation pit.
斜抛撑包括上支墩10和下支墩3,上支墩10与下支墩3之间设有钢支撑。The oblique cast support includes an
本实施例中,沿咬合桩8高度方向上安装两层连接梁,分别为冠梁1和腰梁7,冠梁1置于咬合桩8的顶部,腰梁7置于咬合桩的中部。冠梁1和腰梁7分别对应连接上排斜抛撑和下排斜抛撑。本实施例中先浇筑冠梁1。In this embodiment, two layers of connecting beams are installed along the height direction of the
S13、对预设的浇筑下支墩3的位置进行夯实,并铺设100mm厚的C20细石混凝土,以做为传力垫层,在传力垫层上浇筑最底层楼层的底板,在最底层楼层的底板的顶部浇注下支墩3,在最上层的连接梁的预设位置上浇筑上支墩10。S13. Tamp the preset position of the pouring
上支墩10与连接梁相连接,下支墩3与最底层楼层的底板相连接。本实施例中,上支墩10与连接梁采用钢筋混凝土整体浇筑而成,下支墩与最底层楼层的底板采用钢筋混凝土整体浇筑而成。The
上支墩10和下支墩3浇注前,采用多点激光测距法进行测量,以确定上支墩10和下支墩3的位置。上支墩10与钢支撑的接触面为第一连接面,下支墩3与钢支撑的接触面为第二连接面,第一连接面与第二连接面相互平行,第一连接面与第二连接面相对应。Before the upper buttress 10 and the lower buttress 3 are poured, a multi-point laser ranging method is used for measurement to determine the positions of the upper buttress 10 and the lower buttress 3 . The contact surface between the
为了增大连接梁的受力面积,防止连接梁局部受力过大,连接梁与上支墩10之间设有钢锚板。In order to increase the stressed area of the connecting beam and prevent the connecting beam from being overstressed locally, a steel anchor plate is provided between the connecting beam and the
本实施例中,上排斜抛撑的上支墩10与冠梁1通过混凝土相连接,上排斜抛撑的下支墩3通过混凝土与负三层13的底板相连接。上排斜抛撑的上支墩10与负二层12相对应,即下排斜抛撑与负一层11相对应。In this embodiment, the
S14、用于安装最上层的斜抛撑的上支墩10和下支墩3的强度达到预设后,即浇筑上支墩10和下支墩3的混凝土凝固,且其强度达到预设值后,安装最上层的钢支撑,钢支撑的顶端与上支墩10相抵接,钢支撑的底端与下支墩3相抵接。S14. After the strength of the upper buttress 10 and the lower buttress 3 used to install the uppermost diagonal cast support reaches the preset value, the concrete poured on the upper buttress 10 and the lower buttress 3 is solidified, and its strength reaches the preset value Finally, the uppermost steel support is installed, the top of the steel support abuts against the
具体地,先将活络头安装于钢支撑的底部,并将活络头固定于钢支撑内,使用起重机将钢支撑安装于预设位置,将活络头拉出,使活络头的底端与下支墩3相抵接,钢支撑的顶端与上支墩10相抵接。Specifically, firstly install the active head on the bottom of the steel support, and fix the active head in the steel support, use a crane to install the steel support at the preset position, pull out the active head, and make the bottom end of the active head and the lower branch The
钢支撑放置完成后,需及时通过液压千斤顶对钢支撑施加预应力,以使钢支撑的两端分别与上支墩10和下支墩3相抵接。After the steel support is placed, it is necessary to apply prestress to the steel support in time through the hydraulic jack, so that the two ends of the steel support are in contact with the
S15、依次安装其余各层的斜抛撑,直到所有的斜抛撑安装完成。S15. Install the diagonal braces of the remaining layers in sequence until all the diagonal braces are installed.
本实施例中,下排斜抛撑的上支墩10与负二层12相对应,即下排斜抛撑与负二层12相对应。In this embodiment, the upper buttresses 10 of the lower row of oblique braces correspond to the negative
S2、清除基坑内剩余的反压土,由基坑底部向上依次对各楼层进行施工;S2. Remove the remaining back pressure soil in the foundation pit, and construct each floor sequentially from the bottom of the foundation pit upwards;
每层楼层的外墙施工前,拆除该楼层对应的斜抛撑,已经施工完成的楼层的底板上留有对应的斜抛撑孔;Before the construction of the exterior wall of each floor, remove the corresponding slanting braces of the floor, and leave the corresponding slanting brace holes on the bottom plate of the floors that have been constructed;
对应的斜抛撑是指设计方案中的斜抛撑穿过该楼层的外墙;The corresponding diagonal brace means that the diagonal brace in the design scheme passes through the outer wall of the floor;
对拆除斜抛撑后的楼层的上一层进行施工时,用混凝土对斜抛撑孔进行填补。When constructing the upper floor of the floor after the oblique throwing braces have been removed, the holes of the diagonal throwing braces are filled with concrete.
S21、清除基坑内所有的反压土,浇筑剩余的最底层楼层的底板,完成整个最底层楼层的底板的浇筑,浇筑最底层楼层的外墙。最底层楼层的底板即为基坑的底板传力垫层上的底板。S21. Clear all the back pressure soil in the foundation pit, pour the remaining floor of the bottom floor, complete the pouring of the bottom floor of the entire bottom floor, and pour the outer wall of the bottom floor. The base plate of the lowest floor is the base plate on the base plate force transmission cushion of the foundation pit.
由于安装完所有的斜抛撑后,就开始浇筑最底层楼层的施工,所以本实施例中,最底层楼层不设置对应的斜抛撑,即下排斜抛撑9的上支墩10的高度高于负三层13楼层的高度。After installing all the slanting struts, the construction of the bottom floor is started, so in this embodiment, the bottom floor is not provided with corresponding slanting struts, that is, the height of the
S22、依次对其余各楼层进行施工,对其余各楼层施工时,先浇筑用于支撑该楼层的底板的换撑梁,再浇筑该楼层的底板,拆除该楼层对应的斜抛撑,浇筑该楼层的外墙,同时填补已施工的楼层的底板上的斜抛撑孔。S22. Carry out construction on the remaining floors in turn. When constructing the remaining floors, first pour the supporting beams for supporting the bottom slab of the floor, then pour the bottom slab of the floor, remove the corresponding diagonal braces of the floor, and pour the floor At the same time, fill the oblique cast holes on the floor of the constructed floor.
拆除斜抛撑过程中,需随时观察基坑变形的情况,先对斜抛撑进行试拆,如果基坑坑壁没有沉降变形,或沉降变形极小,即可拆除斜抛撑。In the process of dismantling the diagonal braces, it is necessary to observe the deformation of the foundation pit at any time, and first perform a trial demolition of the diagonal braces. If the foundation pit wall has no settlement deformation, or the settlement deformation is very small, the diagonal throw braces can be removed.
拆除钢支撑过程中,如果不易将整个钢支撑取出,可将钢支撑切割成多段后进行拆除。During the removal of the steel support, if it is not easy to take out the entire steel support, the steel support can be cut into multiple sections and then removed.
本实施例中,先对负三层13的换撑梁、底板和外墙进行浇筑,再浇筑负二层12的换撑梁和负二层12的底板。拆除下排斜抛撑,浇筑负二层12的外墙、负一层11的底板的换撑梁、负一层11的底板和负二层12的底板上的斜抛撑孔。拆除上排斜抛撑,浇筑负一层11的外墙、负一层11的顶板的换撑梁、负一层11的顶板、负二层12底板上的斜抛撑孔和负一层11底板上的斜抛撑孔。In the present embodiment, the supporting beams, base plates and outer walls of the third
在本发明的描述中,需要理解的是,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In the description of the present invention, it should be understood that the terms "first" and "second" are used for description purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly indicating the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features. In the description of the present invention, "plurality" means two or more, unless otherwise specifically defined.
在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连;可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise clearly specified and limited, terms such as "installation", "connection", "connection" and "fixation" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection , or integrated; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary; it can be the internal communication of two elements or the interaction relationship between two elements. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention according to specific situations.
在本发明中,除非另有明确的规定和限定,第一特征在第二特征“上”或“下”,可以是第一和第二特征直接接触,或第一和第二特征通过中间媒介间接接触。而且,第一特征在第二特征“之上”、“上方”和“上面”,可以是第一特征在第二特征正上方或斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”,可以是第一特征在第二特征正下方或斜下方,或仅仅表示第一特征水平高度低于第二特征。In the present invention, unless otherwise clearly specified and limited, the first feature is "on" or "under" the second feature, which may be that the first and second features are in direct contact, or the first and second features pass through an intermediary indirect contact. Moreover, the first feature being "above", "above" and "above" the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the level of the first feature is higher than that of the second feature . "Below", "below" and "under" the first feature may mean that the first feature is directly below or obliquely below the second feature, or it just means that the first feature is lower in level than the second feature.
在本说明书的描述中,术语“一个实施例”、“一些实施例”、“实施例”、“示例”、“具体示例”或“一些示例”等的描述,是指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不必须针对的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任一个或多个实施例或示例中以合适的方式结合。此外,在不相互矛盾的情况下,本领域的技术人员可以将本说明书中描述的不同实施例或示例以及不同实施例或示例的特征进行结合和组合。In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" refers to the A particular feature, structure, material, or characteristic is described as included in at least one embodiment or example of the invention. In this specification, the schematic representations of the above terms are not necessarily directed to the same embodiment or example. Furthermore, the described specific features, structures, materials or characteristics may be combined in any suitable manner in any one or more embodiments or examples. In addition, those skilled in the art can combine and combine different embodiments or examples and features of different embodiments or examples described in this specification without conflicting with each other.
尽管上面已经示出和描述了本发明的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本发明的限制,本领域的普通技术人员在本发明的范围内可以对上述实施例进行改动、修改、替换和变型。Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present invention, those skilled in the art can make the above-mentioned The embodiments are subject to alterations, modifications, substitutions and variations.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211086276.7A CN115506419A (en) | 2022-09-06 | 2022-09-06 | Seamless leakage-proof construction method for basement exterior wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211086276.7A CN115506419A (en) | 2022-09-06 | 2022-09-06 | Seamless leakage-proof construction method for basement exterior wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115506419A true CN115506419A (en) | 2022-12-23 |
Family
ID=84503014
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211086276.7A Pending CN115506419A (en) | 2022-09-06 | 2022-09-06 | Seamless leakage-proof construction method for basement exterior wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115506419A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116575480A (en) * | 2023-07-13 | 2023-08-11 | 中国建筑第六工程局有限公司 | Construction method for supporting steel pipe of deep foundation pit penetrating through basement floor slab |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101886392A (en) * | 2010-06-30 | 2010-11-17 | 济南鼎汇土木工程技术有限公司 | Supporting design and construction method of foundation pit supporting system |
CN103603359A (en) * | 2013-11-14 | 2014-02-26 | 明业建设集团有限公司 | Deep foundation pit diagonal bracing support structure demolition method |
CN205134327U (en) * | 2015-11-10 | 2016-04-06 | 中天建设集团有限公司 | Concrete diclinic props row -pile support system |
JP2016216975A (en) * | 2015-05-19 | 2016-12-22 | 鹿島建設株式会社 | How to place an earth anchor |
CN109667273A (en) * | 2018-12-22 | 2019-04-23 | 广州市天作建筑规划设计有限公司 | A kind of construction method of deep foundation pit supporting structure |
CN210395371U (en) * | 2019-07-02 | 2020-04-24 | 中建八局第四建设有限公司 | Water stopping measure for foundation pit supporting steel pipe inclined strut penetrating bottom plate and basement outer wall |
CN111395353A (en) * | 2019-12-07 | 2020-07-10 | 中冶天工集团有限公司 | Foundation pit supporting device and method based on combination of steel sheet piles and vertical inclined struts |
CN114197481A (en) * | 2021-12-01 | 2022-03-18 | 中国五冶集团有限公司 | Supporting structure for foundation pit supporting by using inclined strut and construction method |
CN114457847A (en) * | 2022-02-21 | 2022-05-10 | 江苏扬建集团有限公司 | Basement exterior wall formwork dismantling-free supporting system and construction method thereof |
CN114575356A (en) * | 2022-04-15 | 2022-06-03 | 中国建筑第二工程局有限公司 | Foundation pit supporting structure, supporting pile transaction processing method and basement construction method |
-
2022
- 2022-09-06 CN CN202211086276.7A patent/CN115506419A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101886392A (en) * | 2010-06-30 | 2010-11-17 | 济南鼎汇土木工程技术有限公司 | Supporting design and construction method of foundation pit supporting system |
CN103603359A (en) * | 2013-11-14 | 2014-02-26 | 明业建设集团有限公司 | Deep foundation pit diagonal bracing support structure demolition method |
JP2016216975A (en) * | 2015-05-19 | 2016-12-22 | 鹿島建設株式会社 | How to place an earth anchor |
CN205134327U (en) * | 2015-11-10 | 2016-04-06 | 中天建设集团有限公司 | Concrete diclinic props row -pile support system |
CN109667273A (en) * | 2018-12-22 | 2019-04-23 | 广州市天作建筑规划设计有限公司 | A kind of construction method of deep foundation pit supporting structure |
CN210395371U (en) * | 2019-07-02 | 2020-04-24 | 中建八局第四建设有限公司 | Water stopping measure for foundation pit supporting steel pipe inclined strut penetrating bottom plate and basement outer wall |
CN111395353A (en) * | 2019-12-07 | 2020-07-10 | 中冶天工集团有限公司 | Foundation pit supporting device and method based on combination of steel sheet piles and vertical inclined struts |
CN114197481A (en) * | 2021-12-01 | 2022-03-18 | 中国五冶集团有限公司 | Supporting structure for foundation pit supporting by using inclined strut and construction method |
CN114457847A (en) * | 2022-02-21 | 2022-05-10 | 江苏扬建集团有限公司 | Basement exterior wall formwork dismantling-free supporting system and construction method thereof |
CN114575356A (en) * | 2022-04-15 | 2022-06-03 | 中国建筑第二工程局有限公司 | Foundation pit supporting structure, supporting pile transaction processing method and basement construction method |
Non-Patent Citations (2)
Title |
---|
刘俊岩等: "深基坑工程", vol. 2001, 31 August 2001, pages: 308 - 309 * |
刘燕等: "济南恒隆广场深基坑斜撑支护体系分段先拆后撑施工技术", 施工技术, vol. 40, no. 344, pages 1 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116575480A (en) * | 2023-07-13 | 2023-08-11 | 中国建筑第六工程局有限公司 | Construction method for supporting steel pipe of deep foundation pit penetrating through basement floor slab |
CN116575480B (en) * | 2023-07-13 | 2023-10-10 | 中国建筑第六工程局有限公司 | Construction method for supporting steel pipe of deep foundation pit penetrating through basement floor slab |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106193141A (en) | A kind of earthquake impaired pier footing method for reinforcing | |
CN202787055U (en) | Pier fixed connection structure of steel structure overhead bridge | |
CN201972155U (en) | Topdown-construction-method foundation pit supporting structure of steel plate pile | |
CN111502691B (en) | Anti-slip tunnel structure and construction method thereof | |
CN115506419A (en) | Seamless leakage-proof construction method for basement exterior wall | |
CN209855277U (en) | Conversion layer structure for underground added layer of existing building | |
CN108385693A (en) | A kind of waiting for anchor rod support method and support system for basement supporting by stages | |
CN105442457B (en) | Construction structure and method for extending bridge floor plate bridge filled with fine sand | |
CN110158602A (en) | A kind of Soft Clay deep foundation pit support excavation construction structure and construction method | |
CN110685287A (en) | Double-row pile foundation pit supporting system with drainage ditch and retaining wall and construction method | |
CN111472363A (en) | Construction method of foundation pit enclosure structure located in underground space of existing building | |
CN203960878U (en) | A kind of construction formwork of retaining engineering | |
CN207727604U (en) | A kind of prefabricated open caisson elevator pit | |
CN104612174A (en) | Ultrasoft soil brick molding bed auxiliary bearing platform structure and construction method thereof | |
CN106522576B (en) | Old City Wall door opening reinforcement means and ruggedized construction | |
CN205676899U (en) | A kind of foundation ditch permanent support structure based on double bored concrete pile | |
CN212506308U (en) | A combined support structure of inclined pipe piles and vertical wedge piles | |
CN212506305U (en) | Combined support structure of inclined wedge piles and vertical wedge piles | |
CN111962521A (en) | Combined support structure of inclined wedge pile and vertical wedge pile and its construction method | |
CN221094826U (en) | Cantilever type sidewalk construction system for bridge | |
CN117822640B (en) | Combined grouting steel pipe pile unit, steel pipe pile foundation and construction method | |
CN218090938U (en) | A New Steel Tube-Concrete Composite Tower Crane Foundation | |
CN118704490B (en) | A construction method for foundation pit support structure | |
CN212561604U (en) | A Novel Assembled Cantilever Retaining Wall Structure | |
CN219508628U (en) | Permanent open caisson for preventing pavement from subsidence |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20221223 |
|
RJ01 | Rejection of invention patent application after publication |