CN111962523A - A combined support structure of inclined pipe pile and vertical wedge pile and its construction method - Google Patents

A combined support structure of inclined pipe pile and vertical wedge pile and its construction method Download PDF

Info

Publication number
CN111962523A
CN111962523A CN202010871373.1A CN202010871373A CN111962523A CN 111962523 A CN111962523 A CN 111962523A CN 202010871373 A CN202010871373 A CN 202010871373A CN 111962523 A CN111962523 A CN 111962523A
Authority
CN
China
Prior art keywords
pile
wedge
shaped
piles
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010871373.1A
Other languages
Chinese (zh)
Inventor
郑刚
刘鑫菊
周海祚
何晓佩
郭知一
李松昊
刘照朋
吴小波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN202010871373.1A priority Critical patent/CN111962523A/en
Publication of CN111962523A publication Critical patent/CN111962523A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种倾斜管桩与竖直楔形桩的组合支护结构,包括由管桩和楔形桩交替排列构成的排桩支护结构;所述管桩和所述楔形桩沿基坑边沿内侧设置,在所述管桩和所述楔形桩的桩顶上设有冠梁;所述楔形桩,其轴线垂直于水平面,其横截面的面积从桩顶至桩底依次变小;所述管桩的轴线倾斜于水平面且其下部向基坑内倾斜;所述管桩的桩顶中心连线与所述楔形桩的桩顶中心连线平行或重合。本发明还公开了一种倾斜管桩与竖直楔形桩的组合支护结构的构造方法。本发明可减小桩顶位移,增加开挖深度,降低基坑倾覆破坏可能性,可减小支护桩设计强度以降低造价。

Figure 202010871373

The invention discloses a combined support structure of inclined pipe piles and vertical wedge-shaped piles. The inner side is arranged, and a crown beam is arranged on the top of the pipe pile and the wedge-shaped pile; the axis of the wedge-shaped pile is perpendicular to the horizontal plane, and the area of its cross-section decreases from the top of the pile to the bottom of the pile; the The axis of the pipe pile is inclined to the horizontal plane and the lower part thereof is inclined to the foundation pit; the center line of the pile top of the pipe pile is parallel or coincident with the center line of the pile top of the wedge-shaped pile. The invention also discloses a construction method of the combined support structure of the inclined pipe pile and the vertical wedge pile. The invention can reduce the displacement of the pile top, increase the excavation depth, reduce the possibility of overturning and damage of the foundation pit, and can reduce the design strength of the supporting pile to reduce the construction cost.

Figure 202010871373

Description

一种倾斜管桩与竖直楔形桩的组合支护结构及其构建方法A combined support structure of inclined pipe pile and vertical wedge pile and its construction method

技术领域technical field

本发明涉及一种基坑支护结构及构造方法,特别涉及一种倾斜管桩与竖直楔形桩的组合支护结构及其构建方法。The invention relates to a foundation pit support structure and a construction method, in particular to a combined support structure of an inclined pipe pile and a vertical wedge pile and a construction method thereof.

背景技术Background technique

目前,随着国家城市化进程的推进,地下大面积大长度基坑占我国基坑总面积的80%以上。但是传统的支护方式存在着较大的不足和缺陷:1.对于悬臂基坑支护结构,仅能适用于基坑开挖深度较浅,土质条件较好的基坑工程中;2.对于内支撑支护结构,虽然其可以应用在深基坑中,但是施工复杂,施工工期长,环境污染严重,并且造价高。因此倾斜桩支护结构应运而生,通过将竖直悬臂支护桩向基坑内倾斜一定角度,形成倾斜支护桩,并将倾斜支护桩与竖直支护桩交替布置,便可形成斜直交替支护结构。传统的斜直交替支护桩均采用管桩,在软土地基基础工程中,管桩受力形式大多为摩擦基础桩,而管桩桩身的混凝土强度(C60-C100)很高,但桩体的比表面积(单位混凝土体积与桩身外表面积之比)较小,因此管桩桩身外表与土壤间的作用力远远小于桩身强度,桩身结构强度没有能够得到充分的发挥,造成了混凝土管桩承载力的很大浪费,无法充分发挥支护结构的桩身摩擦力。而支护结构整体支护能力主要靠直桩给予斜桩的拉力来发挥,传统的管桩未能充分发挥此拉力。At present, with the advancement of the country's urbanization process, underground large-area and long-length foundation pits account for more than 80% of the total area of foundation pits in my country. However, the traditional support method has major deficiencies and defects: 1. For the cantilever foundation pit support structure, it can only be applied to the foundation pit engineering with shallow excavation depth and good soil conditions; Although the inner support structure can be used in deep foundation pits, the construction is complicated, the construction period is long, the environmental pollution is serious, and the cost is high. Therefore, the inclined pile support structure came into being. By inclining the vertical cantilever support piles to the foundation pit at a certain angle, the inclined support piles are formed, and the inclined support piles and the vertical support piles are alternately arranged to form the inclined support piles. Straight alternating support structure. The traditional inclined-straight alternate support piles all use pipe piles. In soft soil foundation engineering, the stress form of pipe piles is mostly friction foundation piles. The specific surface area of the pile body (the ratio of the unit concrete volume to the external surface area of the pile body) is small, so the force between the surface of the pipe pile and the soil is far less than the strength of the pile body, and the structural strength of the pile body cannot be fully exerted, resulting in This results in a great waste of the bearing capacity of the concrete pipe pile, and cannot give full play to the friction force of the pile body of the supporting structure. The overall supporting capacity of the supporting structure is mainly exerted by the pulling force given by the straight piles to the inclined piles, and the traditional pipe piles cannot fully exert this pulling force.

发明内容SUMMARY OF THE INVENTION

本发明为解决公知技术中存在的技术问题而提供一种倾斜管桩与竖直楔形桩的组合支护结构及其构建方法。In order to solve the technical problems existing in the known technology, the present invention provides a combined support structure of inclined pipe piles and vertical wedge piles and a construction method thereof.

本发明为解决公知技术中存在的技术问题所采取的技术方案是:一种倾斜管桩与竖直楔形桩的组合支护结构,包括由管桩和楔形桩交替排列构成的排桩支护结构;所述管桩和所述楔形桩沿基坑边沿内侧设置,在所述管桩和所述楔形桩的桩顶上设有冠梁;所述楔形桩,其轴线垂直于水平面,其横截面的面积从桩顶至桩底依次变小;所述管桩的轴线倾斜于水平面且其下部向基坑内倾斜;所述管桩的桩顶中心连线与所述楔形桩的桩顶中心连线平行或重合。The technical scheme adopted by the present invention to solve the technical problems existing in the known technology is: a combined support structure of inclined pipe piles and vertical wedge piles, including a pile row support structure formed by alternately arranging pipe piles and wedge piles ; The pipe pile and the wedge-shaped pile are arranged along the inner side of the edge of the foundation pit, and a crown beam is arranged on the pile top of the pipe pile and the wedge-shaped pile; the axis of the wedge-shaped pile is perpendicular to the horizontal plane, and its cross section is The area of the pipe pile gradually decreases from the top of the pile to the bottom of the pile; the axis of the pipe pile is inclined to the horizontal plane and the lower part of the pipe pile is inclined to the foundation pit; the line connecting the center of the pile top of the pipe pile and the center of the pile top of the wedge-shaped pile parallel or coincident.

进一步地,所述管桩的轴线与所述楔形桩的轴线之间的夹角角度≤30°。Further, the included angle between the axis of the pipe pile and the axis of the wedge-shaped pile is ≤30°.

进一步地,所述管桩或所述楔形桩的桩底深度为2~2.5倍基坑开挖深度。Further, the depth of the pile bottom of the pipe pile or the wedge-shaped pile is 2-2.5 times the excavation depth of the foundation pit.

进一步地,所述管桩桩径为300~600mm;所述楔形桩的桩顶桩径为600~1200mm,所述楔形桩的楔角为5°~15°。Further, the diameter of the pipe pile is 300-600 mm; the diameter of the top of the wedge-shaped pile is 600-1200 mm, and the wedge angle of the wedge-shaped pile is 5°-15°.

进一步地,所述冠梁的宽度方向边缘超出所述管桩和所述楔形桩的桩顶边缘,所述冠梁的高度大于等于管桩桩径的0.6倍或楔形桩平均桩径的0.6倍。Further, the width direction edge of the crown beam exceeds the pile top edge of the pipe pile and the wedge-shaped pile, and the height of the crown beam is greater than or equal to 0.6 times the diameter of the pipe pile or 0.6 times the average pile diameter of the wedge-shaped pile. .

进一步地,所述冠梁的宽度方向边缘单侧超出所述管桩和所述楔形桩的桩顶边缘的尺寸为:1/2管桩的桩径或1/2楔形桩平均桩径。Further, the size of the width direction edge of the crown beam extending beyond the pipe pile and the pile top edge of the wedge pile on one side is: 1/2 the pile diameter of the pipe pile or 1/2 the average pile diameter of the wedge pile.

本发明还提供了一种倾斜管桩与竖直楔形桩的组合支护结构的构造方法,该方法包括:预制管桩和楔形桩;在现场沿基坑边沿内侧布设管桩和楔形桩,使管桩和楔形桩交替排列构成排桩支护结构;使楔形桩的轴线垂直于水平面且其横截面的面积从桩顶至桩底依次变小;使管桩的轴线倾斜于水平面且其下部向基坑内倾斜;使管桩的桩顶中心连线与楔形桩的桩顶中心连线平行或重合,管桩和楔形桩均采用跳桩施工方法,间隔1~2根桩压入下一根预制桩;在管桩的桩顶和楔形桩的桩顶上预制冠梁。The invention also provides a method for constructing a combined support structure of inclined pipe piles and vertical wedge piles, the method comprising: prefabricating pipe piles and wedge piles; Pipe piles and wedge-shaped piles are alternately arranged to form a pile-row support structure; the axis of the wedge-shaped piles is perpendicular to the horizontal plane and the area of its cross-section decreases from the top of the pile to the bottom of the pile; the axis of the pipe piles is inclined to the horizontal plane and its lower part faces toward The foundation pit is inclined; the center line of the pile top of the pipe pile and the center line of the pile top of the wedge pile should be parallel or overlapped. Piles; prefabricated crown beams on the pile tops of pipe piles and wedge piles.

进一步地,在现场布设楔形桩的方法包括如下步骤:Further, the method for laying wedge-shaped piles on site comprises the following steps:

步骤A-1,在目标地基上进行楔形桩成孔作业,使挖成孔径从上至下逐渐变小;Step A-1, carry out the wedge-shaped pile hole forming operation on the target foundation, so that the digging hole diameter gradually becomes smaller from top to bottom;

步骤A-2,成孔后,先在孔底处铺设混凝土垫层;Step A-2, after forming the hole, first lay a concrete cushion at the bottom of the hole;

步骤A-3,楔形桩吊放下沉后,对空心段浇筑混凝土,边浇筑边振捣密实;Step A-3, after the wedge-shaped pile is hoisted and lowered, pour concrete into the hollow section, and vibrate and compact while pouring;

步骤A-4,浇筑完成后,开挖承台基坑,将承台盖板的螺栓孔和注浆孔对应与楔形桩桩顶段的固定螺栓和注浆导管对准,使承台盖板与楔形桩的桩顶及承台基坑的侧壁贴合,回填承台基坑,将边沿填筑紧密;Step A-4, after the pouring is completed, excavate the foundation pit of the cap, and align the bolt holes and grouting holes of the cap cover with the fixing bolts and grouting guides of the top section of the wedge pile, so that the cap cover is aligned. Fit with the pile top of the wedge-shaped pile and the side wall of the cap foundation pit, backfill the cap foundation pit, and fill the edge tightly;

步骤A-5,采用水泥净浆对导管注浆,直至桩侧土层有水泥浆泛出。Step A-5, grouting the conduit with cement slurry until the soil layer on the side of the pile has cement slurry overflowing.

进一步地,设楔形桩长度为L,在楔形桩的桩顶中心连线外侧且距离楔形桩的桩顶中心连线0.2L处设置水泥搅拌桩隔水帷幕;水泥搅拌桩隔水帷幕的构造方法包括如下步骤:Further, set the length of the wedge-shaped pile to be L, and set the cement mixing pile water-proof curtain on the outside of the connection line of the pile top center of the wedge-shaped pile and 0.2L from the center connection line of the pile top of the wedge-shaped pile; the construction method of the cement mixing pile water-proof curtain; It includes the following steps:

步骤B-1,将深层搅拌机到达指定桩位并对中;Step B-1, bring the deep mixer to the designated pile position and center it;

步骤B-2,待深层搅拌机的冷却水循环正常后,启动深层搅拌机,使深层搅拌机沿导向架搅拌切土下沉;Step B-2, after the cooling water circulation of the deep mixer is normal, start the deep mixer, so that the deep mixer stirs and cuts the soil along the guide frame and sinks;

步骤B-3,待深层搅拌机下沉到设定深度时,搅拌水泥浆并将水泥浆倒入集料斗中;Step B-3, when the deep mixer sinks to the set depth, stir the cement slurry and pour the cement slurry into the hopper;

步骤B-4,当深层搅拌机下沉到设计深度后,开启水泥浆泵将水泥浆压入地基中,且边喷浆、边旋转搅拌,同时按照设计确定的提升速度提升深层搅拌机;Step B-4, when the deep mixer sinks to the design depth, turn on the cement slurry pump to press the cement slurry into the foundation, and rotate and stir while spraying, and at the same time lift the deep mixer according to the lifting speed determined by the design;

步骤B-5,深层搅拌机提升至设计深度的顶面标高后,再次将深层搅拌机边旋转搅拌边沉入土中,至设计深度后再将深层搅拌机提升出地面。Step B-5, after the deep mixer is raised to the top surface elevation of the design depth, the deep mixer is sunk into the soil while rotating and stirring again, and the deep mixer is lifted out of the ground after reaching the design depth.

进一步地,在管桩的桩顶和楔形桩的桩顶上预制冠梁的方法包括如下步骤:Further, the method of prefabricating the crown beam on the pile top of the pipe pile and the pile top of the wedge pile includes the following steps:

步骤C-1,冠梁土方采用机械分区开挖,先开挖第一层土方至楔形桩的桩顶标高,清除余土后开始破除桩头浮浆至设计标高,桩芯顶面的混凝土要凿毛处理,清除桩顶浮渣,如设计标高桩头砼强度达不到设计要求,则继续破除直至砼质量达到设计要求;Step C-1, the crown beam earthwork is excavated by mechanical partitions. First, the first layer of earthwork is excavated to the pile top elevation of the wedge-shaped pile. After removing the remaining soil, the pile head floating slurry is removed to the design elevation. The concrete on the top surface of the pile core should be Chisel hair treatment to remove scum at the top of the pile. If the strength of the pile head concrete at the design elevation fails to meet the design requirements, continue to break until the quality of the concrete meets the design requirements;

步骤C-2,桩间土整平至冠梁底标高,并夯填密实;Step C-2, the soil between the piles is leveled to the bottom elevation of the crown beam, and compacted by ramming;

步骤C-3,按冠梁剖面配筋进行钢筋制作;纵筋采用HRB335级或HRB400级钢筋,箍筋采用HPB300级钢筋;拉结筋采用HRB335级钢筋;In step C-3, steel bars are made according to the section reinforcement of the crown beam; the longitudinal bars are HRB335 grade or HRB400 grade steel bars, the stirrups are HPB300 grade steel bars; the tie bars are HRB335 grade steel bars;

步骤C-4,完成混凝土浇筑及养护;混凝土强度等级高于等于C25,排桩主筋锚入冠梁大于等于35倍钢筋桩径。In step C-4, the concrete pouring and curing are completed; the concrete strength grade is higher than or equal to C25, and the main reinforcement of the row pile is anchored into the crown beam larger than or equal to 35 times the diameter of the reinforcement pile.

本发明具有的优点和积极效果是:本发明的一种倾斜管桩与竖直楔形桩的组合支护结构,管桩和楔形桩交替排列构成等高组合支护结构,使楔形桩的轴线垂直于水平面且其横截面的面积从桩顶至桩底依次变小;使管桩的轴线倾斜于水平面且其下部向基坑内倾斜;楔形桩可增大侧摩阻力,从而轴力可充分发挥,给与管桩更大的拉力,很大程度上减小桩顶位移,使设桩后地面变形大大减小,避免对周围环境造成破坏,同时可以减小桩身弯矩,使桩身设计强度降低,从而降低工程造价;本发明可增加开挖深度,并且由于开挖面倾斜,以及楔形桩承载力高,沉降量小,基坑发生倾覆破坏的可能性大大减小,可以保证基坑工程的安全;管桩和楔形桩交替排列构成等高组合支护结构,使原本可能需要采用内撑式支护或拉锚式支护的基坑工程,可仅利用悬臂桩支护就可以满足设计要求,从而使设计施工更加简便,并且节约材料,从而降低工程费用。The advantages and positive effects of the present invention are: a combined support structure of inclined pipe piles and vertical wedge-shaped piles of the present invention, the pipe piles and the wedge-shaped piles are alternately arranged to form an equal-height combined support structure, so that the axis of the wedge-shaped piles is vertical On the horizontal plane and its cross-sectional area decreases from the top of the pile to the bottom of the pile; the axis of the pipe pile is inclined to the horizontal plane and its lower part is inclined to the foundation pit; the wedge-shaped pile can increase the lateral friction resistance, so that the axial force can be fully exerted. Giving the pipe piles greater tensile force can greatly reduce the displacement of the pile top, greatly reduce the ground deformation after the pile is installed, and avoid damage to the surrounding environment. The invention can increase the excavation depth, and because the excavation surface is inclined, the bearing capacity of the wedge-shaped pile is high, and the settlement is small, the possibility of overturning damage of the foundation pit is greatly reduced, and the foundation pit engineering can be guaranteed. Pipe piles and wedge-shaped piles are alternately arranged to form an equal-height composite support structure, so that the foundation pit project that may need to use internal support or anchor support can only be supported by cantilever piles to meet the design requirements. requirements, so as to make the design and construction easier, and save materials, thereby reducing engineering costs.

综上所述,本发明可减小桩顶位移,增加开挖深度,降低基坑倾覆破坏可能性,可减小支护桩设计强度以降低造价的基坑支护工程。To sum up, the present invention can reduce the displacement of the pile top, increase the excavation depth, reduce the possibility of overturning and damage of the foundation pit, and can reduce the design strength of the supporting pile to reduce the cost of foundation pit support engineering.

附图说明Description of drawings

图1为本发明的一种倾斜管桩与竖直楔形桩的组合支护结构的示意图。FIG. 1 is a schematic diagram of a combined support structure of an inclined pipe pile and a vertical wedge pile according to the present invention.

图中:1-冠梁;2-基坑坑底;3-基坑边沿;4-楔形桩;5-管桩。In the picture: 1- crown beam; 2- foundation pit bottom; 3- foundation pit edge; 4- wedge-shaped pile; 5- pipe pile.

图2为本发明的一种倾斜管桩与竖直楔形桩的组合支护结构的剖面示意图。2 is a schematic cross-sectional view of a combined support structure of an inclined pipe pile and a vertical wedge pile according to the present invention.

图中:H1-基坑开挖深度;H2-楔形桩桩长;θ-管桩倾角。In the figure: H 1 - excavation depth of foundation pit; H 2 - length of wedge pile; θ - inclination angle of pipe pile.

具体实施方式Detailed ways

为能进一步了解本发明的发明内容、特点及功效,兹列举以下实施例,并配合附图详细说明如下:In order to further understand the content of the invention, features and effects of the present invention, the following embodiments are listed herewith, and are described in detail as follows in conjunction with the accompanying drawings:

请参见图1至图2,一种倾斜管桩与竖直楔形桩的组合支护结构,包括由管桩5和楔形桩4交替排列构成的排桩支护结构;所述管桩5和所述楔形桩4沿基坑边沿3的内侧设置,在所述管桩5的桩顶和所述楔形桩4的桩顶上设有冠梁1;所述楔形桩4,其轴线垂直于水平面,其横截面的面积从桩顶至桩底依次变小;所述管桩5的轴线倾斜于水平面且其下部向基坑内倾斜;所述管桩5的桩顶中心连线与所述楔形桩4的桩顶中心连线平行或重合。所述管桩5和所述楔形桩4的桩顶位于基坑边沿3的内侧,管桩5和楔形桩4通过冠梁1连接形成一个整体。Please refer to FIGS. 1 to 2 , a combined support structure of inclined pipe piles and vertical wedge-shaped piles, including a pile-row support structure composed of pipe piles 5 and wedge-shaped piles 4 alternately arranged; The wedge-shaped pile 4 is arranged along the inner side of the edge 3 of the foundation pit, and a crown beam 1 is arranged on the pile top of the pipe pile 5 and the pile top of the wedge-shaped pile 4; the wedge-shaped pile 4, its axis is perpendicular to the horizontal plane, The area of its cross section becomes smaller from the top of the pile to the bottom of the pile; the axis of the pipe pile 5 is inclined to the horizontal plane and its lower part is inclined to the foundation pit; the center line of the pile top of the pipe pile 5 and the wedge-shaped pile 4 The lines connecting the center of the pile tops are parallel or coincident. The pile tops of the pipe piles 5 and the wedge-shaped piles 4 are located on the inner side of the edge 3 of the foundation pit, and the pipe piles 5 and the wedge-shaped piles 4 are connected by the crown beam 1 to form a whole.

所述管桩5的桩顶中心连线可位于所述楔形桩4的桩顶中心连线的内侧;相邻管桩5和楔形桩4的桩间距可为2~4倍管桩的桩径或2~4倍楔形桩的平均桩径。The center line of the pile top of the pipe pile 5 can be located on the inner side of the center line of the pile top of the wedge-shaped pile 4; Or 2 to 4 times the average pile diameter of wedge piles.

楔形桩的轴线为垂直于其顶面且与其顶面中心相交的直线,楔形桩的桩径为垂直于其轴线的横截面的4倍面积与周长的比值;楔形桩的横截面的面积从桩顶至桩底依次变小;对应的桩径也从桩顶至桩底依次变小。The axis of the wedge-shaped pile is a straight line perpendicular to its top surface and intersecting the center of its top surface. The diameter of the wedge-shaped pile is the ratio of 4 times the area of the cross-section perpendicular to its axis to the perimeter; the area of the cross-section of the wedge-shaped pile is from The pile top to the pile bottom becomes smaller in turn; the corresponding pile diameter also becomes smaller from the pile top to the pile bottom.

管桩5的轴线相对于楔形桩4的轴线,倾斜角度可大于0°且小于等于30.5°,所述管桩的轴线与所述楔形桩的轴线之间的夹角角度优选≤30°。如图2所示,可将所述管桩的轴线相对于楔形桩的轴线夹角称为管桩倾角θ,管桩倾角θ可≤30°。管桩倾角θ可优选10°、12°、15°、18°、21°、24°。The inclination angle of the axis of the pipe pile 5 relative to the axis of the wedge pile 4 may be greater than 0° and less than or equal to 30.5°, and the included angle between the axis of the pipe pile and the axis of the wedge pile is preferably ≤30°. As shown in FIG. 2 , the included angle between the axis of the pipe pile and the axis of the wedge-shaped pile can be referred to as the pipe pile inclination angle θ, and the pipe pile inclination angle θ can be ≤30°. The pipe pile inclination angle θ may preferably be 10°, 12°, 15°, 18°, 21°, 24°.

所述管桩5或所述楔形桩4的桩底深度可为2~2.5倍基坑开挖深度H1。即所述管桩5或所述楔形桩4的桩底端距离基坑坑底2的高度为2~2.5倍基坑开挖深度H1The depth of the pile bottom of the pipe pile 5 or the wedge pile 4 may be 2 to 2.5 times the excavation depth H 1 of the foundation pit. That is, the height of the pile bottom end of the pipe pile 5 or the wedge pile 4 from the foundation pit bottom 2 is 2 to 2.5 times the foundation pit excavation depth H 1 .

所述管桩桩径可为300~600mm;所述楔形桩的桩顶桩径可为600~1200mm,所述楔形桩的楔角可为5°~15°。所述楔形桩的楔角优选7.5°、9°、12°。The diameter of the pipe pile may be 300-600 mm; the diameter of the pile top of the wedge-shaped pile may be 600-1200 mm, and the wedge angle of the wedge-shaped pile may be 5°-15°. The wedge angle of the wedge pile is preferably 7.5°, 9°, 12°.

在楔形桩4和管桩5上设置冠梁1。冠梁1的宽度可大于与其连接的管桩5及楔形桩4的桩顶桩径,所述冠梁1的宽度方向边缘可超出所述管桩5和所述楔形桩4的桩顶边缘,所述冠梁1的高度可大于等于管桩5桩径的0.6倍或楔形桩4平均桩径的0.6倍。Crown beams 1 are arranged on wedge piles 4 and pipe piles 5 . The width of the crown beam 1 can be larger than the pile diameter of the pipe pile 5 and the wedge pile 4 connected to it, and the width direction edge of the crown beam 1 can exceed the pile top edge of the pipe pile 5 and the wedge pile 4, The height of the crown beam 1 may be greater than or equal to 0.6 times the diameter of the pipe pile 5 or 0.6 times the average diameter of the wedge pile 4 .

进一步地,所述冠梁1的宽度方向边缘单侧超出所述管桩5和所述楔形桩4的桩顶边缘的尺寸可为:1/2管桩5的桩径或1/2楔形桩4的平均桩径。Further, the size of the width direction edge of the crown beam 1 beyond the pipe pile 5 and the pile top edge of the wedge pile 4 can be: 1/2 the pile diameter of the pipe pile 5 or 1/2 the wedge pile. 4 for the average pile diameter.

可设楔形桩长度为L,可在楔形桩的桩顶中心连线外侧且距离楔形桩的桩顶中心连线0.2L处设置水泥搅拌桩隔水帷幕。The length of the wedge-shaped pile can be set to be L, and the cement mixing pile water-proof curtain can be set at the outer side of the connection line of the pile top center of the wedge-shaped pile and 0.2L away from the connection line of the pile top center of the wedge-shaped pile.

本发明还提供了一种倾斜管桩与竖直楔形桩的组合支护结构的构造方法实施例,该方法包括:预制管桩5和楔形桩4;在现场沿基坑边沿内侧布设管桩5和楔形桩4,使管桩5和楔形桩4交替排列构成排桩支护结构;使楔形桩4的轴线垂直于水平面且其横截面的面积从桩顶至桩底依次变小;使管桩5的轴线倾斜于水平面且其下部向基坑内倾斜;使管桩5的桩顶中心连线与楔形桩4的桩顶中心连线平行或重合,管桩5和楔形桩4均采用跳桩施工方法,间隔1~2根桩压入下一根预制桩;在管桩5的桩顶和楔形桩4的桩顶上预制冠梁1。可使所述管桩5的桩顶中心连线位于所述楔形桩4的桩顶中心连线的内侧;可使相邻管桩5和楔形桩4的桩间距为2~4倍管桩的桩径或2~4倍楔形桩的平均桩径。The present invention also provides an embodiment of a method for constructing a combined support structure of inclined pipe piles and vertical wedge-shaped piles. The method includes: prefabricating pipe piles 5 and wedge-shaped piles 4; and wedge-shaped piles 4, so that the pipe piles 5 and wedge-shaped piles 4 are alternately arranged to form a pile-row supporting structure; the axis of the wedge-shaped piles 4 is perpendicular to the horizontal plane and the area of its cross-section decreases from the top of the pile to the bottom of the pile; The axis of 5 is inclined to the horizontal plane and its lower part is inclined to the foundation pit; the center line of the pile top of the pipe pile 5 and the center line of the pile top of the wedge-shaped pile 4 are parallel or coincident, and the pipe pile 5 and the wedge-shaped pile 4 are constructed by jumping piles. Method, 1-2 piles are pressed into the next prefabricated pile; the crown beam 1 is prefabricated on the pile top of the pipe pile 5 and the pile top of the wedge pile 4 . The center line of the pile top of the pipe pile 5 can be located on the inner side of the center line of the pile top of the wedge-shaped pile 4; Pile diameter or 2 to 4 times the average pile diameter of wedge-shaped piles.

进一步地,在现场布设楔形桩4的方法可包括如下步骤:Further, the method for laying the wedge-shaped piles 4 on site may include the following steps:

步骤A-1,在目标地基上进行楔形桩4成孔作业,使挖成孔径从上至下逐渐变小。In step A-1, the wedge-shaped pile 4 is drilled on the target foundation, so that the digging hole diameter gradually becomes smaller from top to bottom.

步骤A-2,成孔后,先在孔底处铺设混凝土垫层。Step A-2, after forming the hole, first lay a concrete cushion at the bottom of the hole.

步骤A-3,楔形桩4吊放下沉后,对空心段浇筑混凝土,边浇筑边振捣密实。In step A-3, after the wedge-shaped pile 4 is hoisted and lowered, concrete is poured into the hollow section, and it is vibrated and compacted while pouring.

步骤A-4,浇筑完成后,开挖承台基坑,将承台盖板的螺栓孔和注浆孔对应与楔形桩4桩顶段的固定螺栓和注浆导管对准,使承台盖板与楔形桩4的桩顶及承台基坑的侧壁贴合,回填承台基坑,将边沿填筑紧密。Step A-4: After the pouring is completed, excavate the foundation pit of the cap, and align the bolt holes and grouting holes of the cap cover with the fixing bolts and grouting guides of the top section of the wedge pile 4 to make the cap cover. The plate is attached to the pile top of the wedge-shaped pile 4 and the side wall of the foundation pit of the cap, backfill the foundation pit of the cap, and fill the edge tightly.

步骤A-5,采用水泥净浆对导管注浆,直至桩侧土层有水泥浆泛出。Step A-5, grouting the conduit with cement slurry until the soil layer on the side of the pile has cement slurry overflowing.

进一步地,可设楔形桩4长度为L,可在楔形桩4的桩顶中心连线外侧且距离楔形桩4的桩顶中心连线0.2L处设置水泥搅拌桩隔水帷幕;水泥搅拌桩隔水帷幕的构造方法可包括如下步骤:Further, the length of the wedge-shaped pile 4 can be set to be L, and the cement mixing pile water-proof curtain can be set at the outer side of the connection line of the pile top center of the wedge-shaped pile 4 and at a distance of 0.2L from the center connection line of the pile top of the wedge-shaped pile 4; The construction method of the water curtain may include the following steps:

步骤B-1,将深层搅拌机到达指定桩位并对中。Step B-1, bring the deep mixer to the designated pile position and center it.

步骤B-2,待深层搅拌机的冷却水循环正常后,启动深层搅拌机,使深层搅拌机沿导向架搅拌切土下沉。Step B-2, after the cooling water circulation of the deep mixer is normal, start the deep mixer, so that the deep mixer stirs and cuts the soil along the guide frame and sinks.

步骤B-3,待深层搅拌机下沉到设定深度时,搅拌水泥浆并将水泥浆倒入集料斗中。Step B-3, when the deep mixer sinks to the set depth, stir the cement slurry and pour the cement slurry into the hopper.

步骤B-4,当深层搅拌机下沉到设计深度后,开启水泥浆泵将水泥浆压入地基中,且边喷浆、边旋转搅拌,同时按照设计确定的提升速度提升深层搅拌机。Step B-4, when the deep mixer sinks to the design depth, turn on the cement slurry pump to press the cement slurry into the foundation, and rotate and mix while spraying, and at the same time lift the deep mixer according to the lifting speed determined by the design.

步骤B-5,深层搅拌机提升至设计深度的顶面标高后,再次将深层搅拌机边旋转搅拌边沉入土中,至设计深度后再将深层搅拌机提升出地面。Step B-5, after the deep mixer is raised to the top surface elevation of the design depth, the deep mixer is sunk into the soil while rotating and stirring again, and the deep mixer is lifted out of the ground after reaching the design depth.

进一步地,在管桩5的桩顶和楔形桩4的桩顶上预制冠梁1的方法可包括如下步骤:Further, the method for prefabricating the crown beam 1 on the pile top of the pipe pile 5 and the pile top of the wedge pile 4 may include the following steps:

步骤C-1,冠梁1土方采用机械分区开挖,先开挖第一层土方至楔形桩4的桩顶标高,清除余土后开始破除桩头浮浆至设计标高,桩芯顶面的混凝土要凿毛处理,清除桩顶浮渣,如设计标高桩头砼强度达不到设计要求,则继续破除直至砼质量达到设计要求。In step C-1, the earthwork of the crown beam 1 is excavated by mechanical partitions. The first layer of earthwork is excavated to the pile top elevation of the wedge pile 4. After removing the remaining soil, the pile head laitance is removed to the design elevation. The concrete should be chiseled to remove the scum at the top of the pile. If the strength of the pile head concrete at the design elevation fails to meet the design requirements, continue to break until the quality of the concrete meets the design requirements.

步骤C-2,桩间土整平至冠梁1底标高,并夯填密实。In step C-2, the soil between the piles is leveled to the bottom elevation of the crown beam 1, and compacted by ramming.

步骤C-3,按冠梁1剖面配筋进行钢筋制作。纵筋采用HRB335级或HRB400级钢筋,箍筋采用HPB300级钢筋;拉结筋采用HRB335级钢筋。Step C-3, according to the section of crown beam 1, the reinforcement is made. Longitudinal bars use HRB335 or HRB400 steel bars, stirrups use HPB300 steel bars, and tie bars use HRB335 steel bars.

步骤C-4,完成混凝土浇筑及养护;混凝土强度等级高于等于C25,排桩主筋锚入冠梁1大于等于35倍钢筋桩径。Step C-4, complete the concrete pouring and curing; the concrete strength grade is higher than or equal to C25, and the main reinforcement of the row pile is anchored into the crown beam 1, which is greater than or equal to 35 times the diameter of the reinforcement pile.

下面以本发明的一个优选实施例来进一步说明本发明的结构、构造方法及工作原理:The structure, construction method and working principle of the present invention are further described below with a preferred embodiment of the present invention:

请参阅图1,一种倾斜管桩与竖直楔形桩的组合支护结构,包括若干个管桩5和若干个楔形桩4,所述管桩5和所述楔形桩4交替排列构成等长组合支护结构;所述楔形桩4,其轴线垂直于水平面,其横截面的面积从桩顶至桩底依次变小;所述管桩5的轴线倾斜于水平面且其下部向基坑内倾斜;所述管桩5的桩顶中心连线与所述楔形桩4的桩顶中心连线平行,所述楔形桩4沿基坑边沿3内侧设置,所述管桩5位于所述楔形桩4的桩顶中心连线的内侧;在所述管桩5的桩顶和所述楔形桩4的桩顶上设有冠梁1。Please refer to FIG. 1, a combined support structure of inclined pipe piles and vertical wedge piles, including several pipe piles 5 and several wedge piles 4, the pipe piles 5 and the wedge piles 4 are alternately arranged to form equal lengths Combined support structure; the axis of the wedge-shaped pile 4 is perpendicular to the horizontal plane, and the area of its cross-section decreases sequentially from the top of the pile to the bottom of the pile; the axis of the pipe pile 5 is inclined to the horizontal plane and its lower part is inclined to the foundation pit; The center line of the pile top of the pipe pile 5 is parallel to the center line of the pile top of the wedge-shaped pile 4 . The inner side of the center line of the pile top; a crown beam 1 is provided on the pile top of the pipe pile 5 and the pile top of the wedge-shaped pile 4 .

所述楔形桩4为竖直支护桩,所述管桩5为内倾支护桩,冠梁1将所有楔形桩和所有管桩连成一体。在所述楔形桩4的桩顶中心连线的外侧设置隔水帷幕。The wedge-shaped piles 4 are vertical support piles, the pipe piles 5 are inclination support piles, and the crown beam 1 connects all the wedge-shaped piles and all the pipe piles into one. A water-proof curtain is arranged on the outer side of the center line of the pile top of the wedge-shaped pile 4 .

本发明的基本原理是:The basic principle of the present invention is:

管桩5和楔形桩4交替排列构成组合支护结构,当竖直支护桩为楔形桩4,内倾支护桩为管桩5时,管桩5和楔形桩4交替排列构成的组合支护结构又称为斜直交替支护结构,管桩5和楔形桩4通过桩顶冠梁1的连接形成一个整体,共同受力。其中,管桩5受压,楔形桩4受拉。通过冠梁1,楔形桩4将自身轴向力提供给管桩5,可以给予管桩5一个向下的拉力,此拉力大小与楔形桩4侧摩阻力的大小相关。The tubular piles 5 and the wedge-shaped piles 4 are alternately arranged to form a combined support structure. When the vertical support piles are the wedge-shaped piles 4 and the inward-inclined support piles are the tubular piles 5, the tubular piles 5 and the wedge-shaped piles 4 are alternately arranged to form a combined support structure. The structure is also known as the inclined-straight alternate support structure. The pipe pile 5 and the wedge-shaped pile 4 form a whole through the connection of the pile top, crown beam 1, and are jointly stressed. Among them, the pipe pile 5 is under compression, and the wedge-shaped pile 4 is under tension. Through the crown beam 1 , the wedge-shaped pile 4 provides its own axial force to the pipe pile 5 , which can give a downward pulling force to the pipe pile 5 .

此拉力可以有效地减小桩体变形,从而减小基坑土体变形,保护周围建筑,增加基坑开挖深度H1,增强基坑稳定性。当竖直支护桩采用楔形桩4进行基坑支护时,由于桩身横截面的面积从桩顶至桩底依次变小,增加了楔形桩与土体尤其是底部较好土层的接触面积,可有效增加侧摩阻力,从而增大楔形桩拉力,进一步控制基坑位移。This tensile force can effectively reduce the deformation of the pile body, thereby reducing the deformation of the soil body of the foundation pit, protecting the surrounding buildings, increasing the excavation depth H 1 of the foundation pit, and enhancing the stability of the foundation pit. When the vertical supporting pile adopts wedge-shaped pile 4 for foundation pit support, since the area of the cross-section of the pile body decreases from the top of the pile to the bottom of the pile, the contact between the wedge-shaped pile and the soil, especially the better soil layer at the bottom is increased. The area can effectively increase the side friction resistance, thereby increasing the wedge pile tension and further controlling the displacement of the foundation pit.

相比较其他支护结构,本发明可有效发挥楔形桩4拉力,因此可以缩短楔形桩桩长H2,增大支护桩的桩间距,缩小支护桩的桩径。施工前需要根据场地条件和计算分析,确定最优的管桩倾斜角度,对楔形桩4及管桩5的桩长与桩身强度进行设计。本发明适用于悬臂桩支护方式。本发明推荐管桩5的倾斜角度大于0°且小于等于30.5°;楔形桩4和管桩5的桩底深度为2~2.5倍基坑开挖深度H1;相邻楔形桩4和管桩5的桩间距为2~2.5倍桩径。管桩5的桩径为300~600mm,楔形桩4的桩头桩径约为600~1200mm,楔形桩4的桩底桩径为300~600mm。Compared with other supporting structures, the present invention can effectively exert the tensile force of the wedge-shaped piles 4, so the length H2 of the wedge-shaped piles can be shortened, the pile spacing of the supporting piles can be increased, and the pile diameter of the supporting piles can be reduced. Before construction, it is necessary to determine the optimal inclination angle of the pipe pile according to the site conditions and calculation analysis, and design the pile length and the strength of the pile body of the wedge pile 4 and the pipe pile 5. The invention is suitable for the support mode of the cantilever pile. The present invention recommends that the inclination angle of the pipe pile 5 is greater than 0° and less than or equal to 30.5°; the depth of the pile bottom of the wedge-shaped pile 4 and the pipe pile 5 is 2 to 2.5 times the excavation depth H 1 of the foundation pit; the adjacent wedge-shaped pile 4 and the pipe pile 5 The pile spacing is 2 to 2.5 times the pile diameter. The pile diameter of the pipe pile 5 is 300-600 mm, the pile head diameter of the wedge-shaped pile 4 is about 600-1200 mm, and the pile bottom pile diameter of the wedge-shaped pile 4 is 300-600 mm.

一种倾斜管桩与竖直楔形桩的组合支护结构的构造方法:A construction method of a combined support structure of inclined pipe piles and vertical wedge piles:

预制等长的管桩5和楔形桩4;在现场布设管桩5和楔形桩4,使管桩5和楔形桩4交替排列;使楔形桩4的轴线垂直于水平面且其横截面的面积从桩顶至桩底依次变小;使管桩5的轴线倾斜于水平面且其下部向基坑内倾斜;使管桩5的桩顶中心连线与楔形桩4的桩顶中心连线平行,使楔形桩4沿基坑边沿3内侧设置,使管桩5位于楔形桩4的桩顶中心连线内侧;管桩5和楔形桩4均采用跳桩施工方法,间隔1~2根桩压入下一根预制桩;在管桩5的桩顶和楔形桩4的桩顶上预制冠梁1。Prefabricate pipe piles 5 and wedge piles 4 of equal length; lay pipe piles 5 and wedge piles 4 on site, so that pipe piles 5 and wedge piles 4 are alternately arranged; make the axis of wedge pile 4 perpendicular to the horizontal plane and the area of its cross section from The top of the pile to the bottom of the pile becomes smaller in turn; the axis of the pipe pile 5 is inclined to the horizontal plane and its lower part is inclined to the foundation pit; The pile 4 is arranged along the inner side of the edge 3 of the foundation pit, so that the pipe pile 5 is located on the inner side of the center line of the pile top of the wedge-shaped pile 4; Root prefabricated pile; prefabricated crown beam 1 on the pile top of the pipe pile 5 and the pile top of the wedge pile 4.

上述楔形桩4的施工方法如下:The construction method of the above-mentioned wedge pile 4 is as follows:

1)在目标地基上进行楔形桩4成孔,挖成孔径从上至下逐渐变小的孔。1) On the target foundation, wedge-shaped piles 4 are formed into holes, and holes with diameters gradually decreasing from top to bottom are dug.

2)成孔后,先在桩端处铺设混凝土垫层。2) After forming the hole, first lay a concrete cushion at the end of the pile.

3)楔形桩4吊放下沉吊装完成后,对空心段浇筑混凝土,边浇筑边振捣密实。3) After the wedge-shaped pile 4 is hoisted and lowered, concrete is poured into the hollow section, and it is vibrated and compacted while pouring.

4)承台拼装:浇筑完成后,开挖承台基坑,将承台盖板的螺栓孔和注浆孔对准桩顶段的固定螺栓和注浆导管,使承台盖板和侧壁与楔形桩4贴合紧密,回填承台基坑,将边沿填筑紧密。4) Cap assembly: After the pouring is completed, excavate the cap foundation pit, and align the bolt holes and grouting holes of the cap plate with the fixing bolts and grouting conduits of the top section of the pile, so that the cap plate and the side walls can be assembled. Fit closely with the wedge-shaped pile 4, backfill the foundation pit of the cap, and fill the edge tightly.

5)导管注浆:安装完成后,采用水泥净浆对导管注浆,直至桩侧土层有水泥浆泛出。5) Conduit grouting: After the installation is completed, use cement slurry to grouting the conduit until the soil layer on the side of the pile has cement grout.

当桩中心距小于等于4倍桩径时,桩较密集,应由中间向两侧对称施打,这样,打桩时土体由四周向两侧挤压,保证施工质量。当桩数较多时,也可采用分区段施打。当桩中心距大于等于4倍边长或桩径时,桩较稀疏,可采用上述施打顺序或采用一侧向单一方向进行施打的方式。When the pile center distance is less than or equal to 4 times the pile diameter, the piles are denser and should be driven symmetrically from the middle to both sides. In this way, the soil body is squeezed from all sides to both sides during pile driving to ensure the construction quality. When the number of piles is large, it can also be applied in sections. When the pile center distance is greater than or equal to 4 times the side length or the pile diameter, the piles are sparse, and the above application sequence or the method of applying one side to a single direction can be used.

设楔形桩4长度为L,在楔形桩4的桩顶中心连线外侧且距离楔形桩4的桩顶中心连线0.2L处设置水泥搅拌桩隔水帷幕;隔水帷幕的搅拌桩桩底标高与楔形桩4桩底标高相同。Let the length of the wedge-shaped pile 4 be L, and set the cement mixing pile water-proof curtain on the outside of the connection line of the pile top center of the wedge-shaped pile 4 and at a distance of 0.2L from the connection line of the pile top center of the wedge-shaped pile 4; It is the same as the bottom elevation of the wedge pile 4.

上述水泥搅拌桩隔水帷幕的施工方法:The construction method of the above-mentioned cement mixing pile waterproof curtain:

1)定位:深层搅拌机到达指定桩位,对中。1) Positioning: The deep mixer reaches the designated pile position and aligns.

2)预搅下沉:待深层搅拌机的冷却水循环正常后,启动搅拌机电机,放松搅拌机吊索使搅拌机沿导向架搅拌切土下沉。2) Pre-mixing and sinking: After the cooling water circulation of the deep mixer is normal, start the motor of the mixer, loosen the sling of the mixer, and let the mixer stir and cut the soil along the guide frame and sink.

3)制备水泥浆:待深层搅拌机下沉到一定深度时,即开始按设计确定的配合比搅拌水泥浆,压浆前将水泥浆倒入集料斗中。3) Preparation of cement slurry: When the deep mixer sinks to a certain depth, it starts to mix the cement slurry according to the mixing ratio determined by the design, and pours the cement slurry into the collecting hopper before grouting.

4)提升喷浆搅拌:深层搅拌机下沉到设计深度后,开启灰浆泵将水泥浆压入地基中,且边喷浆、边旋转,同时严格按照设计确定的提升速度提升深层搅拌机。4) Lifting and mixing: After the deep mixer sinks to the design depth, turn on the mortar pump to press the cement slurry into the foundation, and rotate while spraying, and at the same time lift the deep mixer in strict accordance with the lifting speed determined by the design.

5)重复上、下搅拌:深层搅拌机提升至设计深度的顶面标高时,集料斗中的水泥浆应正好排空。为时软土和水泥浆搅拌均匀,可再次将搅拌机边旋转边沉入土中,至设计加固深度后再将搅拌机提升出地面。5) Repeat up and down mixing: When the deep mixer is lifted to the top elevation of the design depth, the cement slurry in the hopper should be just emptied. In order to mix the soft soil and the cement slurry evenly, the mixer can be sunk into the soil while rotating again, and the mixer can be lifted out of the ground after reaching the designed reinforcement depth.

6)清洗:清洗全部管路中残存的水泥浆,并将粘附在搅拌头的软土清洗干净。6) Cleaning: Clean the remaining cement slurry in all pipelines, and clean the soft soil adhering to the mixing head.

7)移位:将深层搅拌机移至下一桩位,重复上述步骤。7) Shift: Move the deep mixer to the next pile position and repeat the above steps.

在楔形桩4和管桩5的上面设置冠梁1。推荐冠梁1的宽度大于与其连接的管桩5桩径或楔形桩4桩顶桩径,冠梁1的高度可大于等于管桩5桩径的0.6倍或楔形桩4平均桩径的0.6倍。冠梁1沿宽度方向两边各扩出1/2管桩5的桩径或1/2楔形桩4的平均桩径。The crown beam 1 is arranged on the top of the wedge pile 4 and the pipe pile 5 . It is recommended that the width of the crown beam 1 is greater than the diameter of the pipe pile 5 or the top pile diameter of the wedge pile 4. The height of the crown beam 1 can be greater than or equal to 0.6 times the diameter of the pipe pile 5 or 0.6 times the average pile diameter of the wedge pile 4. . The crown beam 1 is expanded by 1/2 of the pile diameter of the pipe pile 5 or 1/2 of the average pile diameter of the wedge-shaped pile 4 on both sides in the width direction.

上述冠梁1的施工方法为:The construction method of the above-mentioned crown beam 1 is:

1)冠梁1土方采用机械分区开挖,先开挖第一层土方至支护桩设计桩顶标高,清除余土后开始破除桩头浮浆至设计标高,桩芯顶面的混凝土要凿毛处理,清除桩顶浮渣,如设计标高桩头砼强度达不到设计要求,须继续破除直至砼质量达到设计要求,不足标高段浇冠梁1砼时一同浇筑成型。1) The earthwork of crown beam 1 is excavated by mechanical partitions. The first layer of earthwork is excavated to the design pile top elevation of the supporting pile. After removing the remaining soil, the pile head floating slurry is removed to the design elevation. The concrete on the top surface of the pile core shall be chiseled. If the strength of the pile head concrete at the design elevation does not meet the design requirements, it must continue to be removed until the quality of the concrete meets the design requirements.

2)桩间土人工整平至冠梁1底标高,并夯填密实。2) The soil between the piles is artificially leveled to the bottom elevation of the crown beam 1, and compacted by ramming.

3)桩头破除后即可按冠梁1剖面配筋进行钢筋制作。钢筋下料、绑扎误差确保满足设计及施工规范要求。3) After the pile head is broken, the reinforcement can be made according to the section 1 of the crown beam. Rebar cutting and binding errors ensure that the design and construction specifications are met.

4)对冠梁1标高进行校核并安装模板。模板支护时须确保模板稳定、牢固,以防浇筑砼时模板变形,模板截面尺寸按冠梁1剖面制作。4) Check the elevation of crown beam 1 and install the formwork. When the formwork is supported, it must be ensured that the formwork is stable and firm to prevent the formwork from being deformed when the concrete is poured.

5)完成钢筋工程。纵筋最好采用HRB335级或HRB400级钢筋,箍筋及拉结筋应采用HPB300级和HRB335级钢筋。5) Complete the reinforcement works. Longitudinal reinforcement is best to use HRB335 or HRB400 steel, stirrups and tie bars should use HPB300 and HRB335 steel.

6)完成混凝土浇筑及养护。混凝土强度等级不应低于C25,排桩主筋锚入冠梁1不应小于35d(d为钢筋桩径)。6) Complete the concrete pouring and curing. The concrete strength grade should not be lower than C25, and the anchoring of the main reinforcement of the row piles into the crown beam 1 should not be less than 35d (d is the diameter of the reinforced pile).

以上所述的实施例仅用于说明本发明的技术思想及特点,其目的在于使本领域内的技术人员能够理解本发明的内容并据以实施,不能仅以本实施例来限定本发明的专利范围,即凡本发明所揭示的精神所作的同等变化或修饰,仍落在本发明的专利范围内。The above-mentioned embodiments are only used to illustrate the technical idea and characteristics of the present invention, and the purpose is to enable those skilled in the art to understand the content of the present invention and implement them accordingly, and the present invention cannot be limited only by the present embodiment. The patent scope, that is, all equivalent changes or modifications made to the spirit disclosed in the present invention, still fall within the patent scope of the present invention.

Claims (10)

1. A combined supporting structure of an inclined pipe pile and a vertical wedge-shaped pile is characterized by comprising a row pile supporting structure formed by alternately arranging pipe piles and wedge-shaped piles; the tubular pile and the wedge-shaped pile are arranged along the inner side of the edge of the foundation pit, and a crown beam is arranged on the pile top of the tubular pile and the wedge-shaped pile; the axis of the wedge-shaped pile is vertical to the horizontal plane, and the area of the cross section of the wedge-shaped pile is sequentially reduced from the pile top to the pile bottom; the axis of the tubular pile is inclined to the horizontal plane, and the lower part of the tubular pile is inclined towards the inside of the foundation pit; and the pile top central connecting line of the tubular pile is parallel to or coincided with the pile top central connecting line of the wedge-shaped pile.
2. The combined supporting structure of an inclined pipe pile and a vertical wedge-shaped pile according to claim 1, wherein an included angle between an axis of the pipe pile and an axis of the wedge-shaped pile is not more than 30 degrees.
3. The combined supporting structure of the inclined tubular pile and the vertical wedge-shaped pile according to claim 1, wherein the depth of the pile bottom of the tubular pile or the wedge-shaped pile is 2-2.5 times of the excavation depth of a foundation pit.
4. The combined supporting structure of the inclined tubular pile and the vertical wedge-shaped pile according to claim 1, wherein the diameter of the tubular pile is 300-600 mm; the pile top diameter of the wedge-shaped pile is 600-1200 mm, and the wedge angle of the wedge-shaped pile is 5-15 degrees.
5. The combined supporting structure of an inclined tubular pile and a vertical wedge-shaped pile according to claim 1, wherein the width direction edge of the crown beam exceeds the tubular pile and the pile top edge of the wedge-shaped pile, and the height of the crown beam is greater than or equal to 0.6 time of the pile diameter of the tubular pile or 0.6 time of the average pile diameter of the wedge-shaped pile.
6. The combined supporting structure of an inclined pipe pile and a vertical wedge-shaped pile according to claim 5, wherein the dimension of the width direction edge of the crown beam beyond the pile top edges of the pipe pile and the wedge-shaped pile on one side is as follows: 1/2 pile diameter or 1/2 wedge pile average pile diameter.
7. A construction method of a combined supporting structure of an inclined pipe pile and a vertical wedge-shaped pile is characterized by comprising the following steps: prefabricating a tubular pile and a wedge-shaped pile; arranging tubular piles and wedge-shaped piles along the inner side of the edge of the foundation pit on site, and enabling the tubular piles and the wedge-shaped piles to be alternately arranged to form a pile arrangement supporting structure; the axis of the wedge-shaped pile is vertical to the horizontal plane, and the area of the cross section of the wedge-shaped pile is reduced from the pile top to the pile bottom in sequence; the axis of the tubular pile is inclined to the horizontal plane, and the lower part of the tubular pile is inclined to the inside of the foundation pit; enabling a pile top central connecting line of the tubular pile and a pile top central connecting line of the wedge-shaped pile to be parallel or coincident, adopting a pile jumping construction method for the tubular pile and the wedge-shaped pile, and pressing a next precast pile at intervals of 1-2 piles; and (4) prefabricating a crown beam on the pile top of the tubular pile and the pile top of the wedge-shaped pile.
8. The construction method of a combined supporting structure of an inclined pipe pile and a vertical wedge-shaped pile according to claim 7, wherein the method for laying the wedge-shaped pile in the field comprises the following steps:
step A-1, performing wedge pile hole forming operation on a target foundation to ensure that the hole diameter of the excavated hole is gradually reduced from top to bottom;
step A-2, after hole forming, paving a concrete cushion layer at the hole bottom;
step A-3, after the wedge-shaped pile is lifted and sunk, pouring concrete into the hollow section, and vibrating and compacting while pouring;
step A-4, after pouring, excavating a bearing platform foundation pit, aligning a bolt hole and a grouting hole of a bearing platform cover plate with a fixing bolt and a grouting guide pipe of a wedge-shaped pile top section correspondingly, attaching the bearing platform cover plate to the pile top of the wedge-shaped pile and the side wall of the bearing platform foundation pit, backfilling the bearing platform foundation pit, and filling the edge tightly;
and step A-5, grouting the guide pipe by adopting cement paste until cement paste is spread out from the soil layer on the side of the pile.
9. The construction method of a combined supporting structure of an inclined tubular pile and a vertical wedge-shaped pile according to claim 7, characterized in that the length of the wedge-shaped pile is set to be L, and a cement mixing pile waterproof curtain is arranged at the position which is outside the center connecting line of the pile tops of the wedge-shaped piles and is 0.2L away from the center connecting line of the pile tops of the wedge-shaped piles; the construction method of the waterproof curtain of the cement mixing pile comprises the following steps:
b-1, enabling the deep layer stirrer to reach the designated pile position and centering;
b-2, after the cooling water circulation of the deep layer stirrer is normal, starting the deep layer stirrer to enable the deep layer stirrer to stir along the guide frame, cut soil and sink;
step B-3, when the deep layer stirrer sinks to a set depth, stirring cement paste and pouring the cement paste into a collecting hopper;
step B-4, after the deep layer stirrer sinks to the designed depth, starting a cement slurry pump to press cement slurry into the foundation, spraying the cement slurry and rotating and stirring the cement slurry, and simultaneously lifting the deep layer stirrer according to the lifting speed determined by the design;
and step B-5, after the deep layer stirring machine is lifted to the top surface elevation of the designed depth, the deep layer stirring machine is sunk into the soil while rotating and stirring, and the deep layer stirring machine is lifted out of the ground after the design depth.
10. The construction method of a combined supporting structure of an inclined pipe pile and a vertical wedge-shaped pile according to claim 7, wherein the method of prefabricating a crown beam on the pile top of the pipe pile and the pile top of the wedge-shaped pile comprises the steps of:
c-1, excavating the earthwork of the crown beam in a mechanical partition mode, excavating a first layer of earthwork to reach the pile top elevation of the wedge-shaped pile, removing residual soil, then beginning to remove pile head floating slurry to reach the designed elevation, chiseling the concrete on the top surface of the pile core, removing the pile top floating slurry, and continuing to remove the pile head floating slurry until the concrete quality reaches the designed requirement if the pile head concrete strength at the designed elevation does not reach the designed requirement;
c-2, leveling the soil between the piles to the elevation of the bottom of the crown beam, and compacting by tamping;
c-3, manufacturing steel bars according to the cross section reinforcements of the crown beam; the longitudinal bars adopt HRB335 grade or HRB400 grade steel bars, and the stirrups adopt HPB300 grade steel bars; the tie bars are HRB 335-grade steel bars;
c-4, completing concrete pouring and curing; the concrete strength grade is higher than or equal to C25, and the main reinforcement of the row pile is anchored into the crown beam and is more than or equal to 35 times of the diameter of the reinforced pile.
CN202010871373.1A 2020-08-26 2020-08-26 A combined support structure of inclined pipe pile and vertical wedge pile and its construction method Pending CN111962523A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010871373.1A CN111962523A (en) 2020-08-26 2020-08-26 A combined support structure of inclined pipe pile and vertical wedge pile and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010871373.1A CN111962523A (en) 2020-08-26 2020-08-26 A combined support structure of inclined pipe pile and vertical wedge pile and its construction method

Publications (1)

Publication Number Publication Date
CN111962523A true CN111962523A (en) 2020-11-20

Family

ID=73390501

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010871373.1A Pending CN111962523A (en) 2020-08-26 2020-08-26 A combined support structure of inclined pipe pile and vertical wedge pile and its construction method

Country Status (1)

Country Link
CN (1) CN111962523A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2254417C1 (en) * 2003-12-15 2005-06-20 Басиев Асхар Николаевич Method and anchor system for securing pit bordering
CN208563346U (en) * 2018-07-10 2019-03-01 中冶集团武汉勘察研究院有限公司 A kind of large span band angle brace prestressing force Double-row Piles Support system
CN109440778A (en) * 2018-11-24 2019-03-08 天津大学 Active two-way inclined pile foundation pit support method
CN208618421U (en) * 2018-06-08 2019-03-19 常州大学怀德学院 A kind of combined support structure of high and low double row inclined straight foundation pit
CN109594578A (en) * 2018-12-27 2019-04-09 河南省信息咨询设计研究有限公司 A kind of small micro- communication base station pile foundation mechanism of the 5G of tower cabinet
CN111287193A (en) * 2020-02-19 2020-06-16 天津大学 Foundation pit support structure using steel sheet piles and precast concrete piles and its support method
CN212506308U (en) * 2020-08-26 2021-02-09 天津大学 A combined support structure of inclined pipe piles and vertical wedge piles

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2254417C1 (en) * 2003-12-15 2005-06-20 Басиев Асхар Николаевич Method and anchor system for securing pit bordering
CN208618421U (en) * 2018-06-08 2019-03-19 常州大学怀德学院 A kind of combined support structure of high and low double row inclined straight foundation pit
CN208563346U (en) * 2018-07-10 2019-03-01 中冶集团武汉勘察研究院有限公司 A kind of large span band angle brace prestressing force Double-row Piles Support system
CN109440778A (en) * 2018-11-24 2019-03-08 天津大学 Active two-way inclined pile foundation pit support method
CN109594578A (en) * 2018-12-27 2019-04-09 河南省信息咨询设计研究有限公司 A kind of small micro- communication base station pile foundation mechanism of the 5G of tower cabinet
CN111287193A (en) * 2020-02-19 2020-06-16 天津大学 Foundation pit support structure using steel sheet piles and precast concrete piles and its support method
CN212506308U (en) * 2020-08-26 2021-02-09 天津大学 A combined support structure of inclined pipe piles and vertical wedge piles

Similar Documents

Publication Publication Date Title
CN111287193A (en) Foundation pit support structure using steel sheet piles and precast concrete piles and its support method
CN109440778B (en) Active two-way inclined pile foundation pit support method
CN103510510B (en) A kind of enhancement mode long auger cast-with-pressure concrete pile and construction method
CN112323777A (en) Hollow precast pile for rock embedding and rock embedding construction method using precast pile
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN208136903U (en) A kind of precast prestressed formula diaphram wall
CN107326898B (en) I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof
CN111962522A (en) A combined support structure of inclined wedge piles and vertical pipe piles and construction method thereof
CN111535334B (en) Construction method of double-core expanded pile anchor foundation pit supporting structure
CN212506308U (en) A combined support structure of inclined pipe piles and vertical wedge piles
CN212506305U (en) Combined support structure of inclined wedge piles and vertical wedge piles
CN212506306U (en) A combined support structure of inclined wedge piles and vertical pipe piles
CN111962521A (en) Combined support structure of inclined wedge pile and vertical wedge pile and its construction method
CN111287194A (en) Recyclable foundation pit support structure using inclined steel sheet piles and its support method
CN109440781B (en) Active inclined double-row pile foundation pit support method
CN212506307U (en) A combined support structure of inclined pipe piles and vertical bamboo piles
CN212248261U (en) Foundation pit support structure using steel sheet piles and precast concrete piles
CN212506310U (en) A combined support structure of inclined bamboo piles and vertical pipe piles
CN212506309U (en) Combined Supporting Structure of Inclined Bamboo Pile and Vertical Bamboo Pile
CN117364789A (en) Soft soil deep foundation pit supporting structure for building construction and supporting construction method thereof
CN207160041U (en) Anchor rod type artificial digging pile
CN113585336B (en) Quick construction method of sinking type concrete mixing station in soft foundation environment
CN117027027A (en) Construction method of locking steel pipe pile cofferdam for rock-socketed anchoring
CN212248262U (en) Recyclable foundation pit support structure using inclined steel sheet piles
CN111962523A (en) A combined support structure of inclined pipe pile and vertical wedge pile and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination