CN115456424A - Project supervision management method, system, terminal equipment and storage medium - Google Patents

Project supervision management method, system, terminal equipment and storage medium Download PDF

Info

Publication number
CN115456424A
CN115456424A CN202211132641.3A CN202211132641A CN115456424A CN 115456424 A CN115456424 A CN 115456424A CN 202211132641 A CN202211132641 A CN 202211132641A CN 115456424 A CN115456424 A CN 115456424A
Authority
CN
China
Prior art keywords
information
construction
task
responsible person
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211132641.3A
Other languages
Chinese (zh)
Inventor
高莉华
刘玉峰
申宁
赵小斐
史志强
刘劲松
邓志远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Shanfeng Construction Technology Co ltd
Original Assignee
Henan Shanfeng Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Shanfeng Construction Technology Co ltd filed Critical Henan Shanfeng Construction Technology Co ltd
Priority to CN202211132641.3A priority Critical patent/CN115456424A/en
Publication of CN115456424A publication Critical patent/CN115456424A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • G06Q10/0875Itemisation or classification of parts, supplies or services, e.g. bill of materials
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Primary Health Care (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to a project supervision management method, a system, terminal equipment and a storage medium, belonging to the technical field of project supervision, wherein the method comprises the following steps: acquiring engineering task information of an engineering task and construction leader information of a construction leader, and associating the engineering task information with the construction leader information; acquiring a construction material list based on the engineering task information; distributing target construction materials based on a preset information identification module and the construction material list; acquiring material use information of the target construction material; and analyzing based on the material use information and the construction material list to obtain material use abnormal information. The method has the effects of facilitating effective management of building construction materials and screening abnormal reasons of material use.

Description

Project supervision management method, system, terminal equipment and storage medium
Technical Field
The present application relates to the field of engineering supervision, and in particular, to a method, a system, a terminal device, and a storage medium for managing engineering supervision.
Background
The project supervision activity is a service activity that construction project supervision units are entrusted by construction units, the quality, the cost and the progress of construction projects are controlled in the construction stage according to laws and regulations, construction standards, survey design files and contracts, the contracts and information are managed, the relationship of relevant parties of the construction projects is coordinated, and the legal obligations of the safety production management of the construction projects are fulfilled.
When the facility is built, the construction materials are various and are dispersed in position, the construction material management is very difficult, and the project supervision personnel can not take into account all aspects in the construction process, so that the situations of material waste, loss and the like in the construction process are difficult to avoid, the use of the construction materials is excessive, the construction cost budget is increased, and the follow-up accountability is difficult.
Disclosure of Invention
In order to effectively manage the building construction materials and screen the causes of abnormal use of the materials, the application provides a project supervision management method, a system, terminal equipment and a storage medium.
In a first aspect, the present application provides a project supervision management method, which adopts the following technical scheme:
a project supervision management method comprises the following steps:
acquiring engineering task information of an engineering task and construction leader information of a construction leader, and associating the engineering task information with the construction leader information;
acquiring a construction material list based on the engineering task information;
distributing target construction materials based on a preset information identification module and the construction material list;
acquiring material use information of the target construction material;
and analyzing based on the material use information and the construction material list to obtain material use abnormal information.
By adopting the technical scheme, the engineering task information is associated with the construction responsible person information, and the engineering task responsible by the construction responsible person can be determined through the construction responsible person information, so that the method is convenient; the using condition of the construction materials of the engineering project can be estimated through the construction material list, and the condition that the construction materials are used indiscriminately and abused in the construction process can be reduced by taking the construction material list as a standard; after the information identification module identifies the information of the construction responsible person, the construction material is distributed for the construction responsible person, so that the construction material is more reliable, and the condition of falsely claiming the construction material is reduced; the material use information is obtained in the construction process, so that the use condition of the material in the construction process can be known; and analyzing according to the material use information and the construction material list to obtain the abnormal use condition of the construction material, and determining a construction responsible person according to the construction responsible person information so as to facilitate follow-up accountability.
Optionally, the associating the engineering task information with the information of the construction person in charge includes:
storing the engineering task information and the construction responsible person information into a preset engineering information base;
associating the construction responsible person information with the engineering task information in the engineering information base;
and configuring an information identifier for the construction responsible person, wherein the construction responsible person information can be obtained based on the information identifier.
By adopting the technical scheme, the engineering task information can be acquired through the information of the construction responsible person, and the method is reliable.
Optionally, the engineering task information includes a BIM building model, and the obtaining of the construction bill of materials based on the engineering task information includes:
acquiring a construction material list based on the BIM building model;
storing the construction bill of materials into the engineering information base;
and associating the construction bill of materials with the construction responsible person information in the engineering information base.
By adopting the technical scheme, the construction bill of materials of the corresponding engineering project can be obtained through the information of the construction responsible person, and the situations of faking and disorderly collar are reduced.
Optionally, the information identification module is configured to identify the construction responsible person information of the construction responsible person, and the allocating the target construction material based on the preset information identification module and the construction material list includes:
identifying the construction responsible person information based on the information identification module;
acquiring a construction material list in the engineering information base based on a preset material management platform and the construction responsible person information;
distributing target construction materials for the construction responsible person based on the construction bill of materials and the materials management platform.
By adopting the technical scheme, the accuracy of construction material distribution can be improved.
Optionally, the obtaining material usage information of the target construction material includes:
acquiring stage task information based on the engineering task information, and acquiring a stage bill of materials based on the stage task information;
executing the stage task based on the stage task information to obtain material consumption information;
after the stage task is finished, material allowance information is obtained;
comparing and analyzing the material consumption information with the stage material list to obtain excess material information;
taking the material consumption information, the material allowance information and the material excess information as stage task material use information, and taking all the stage material use information as material use information of the engineering task;
and storing the material use information into the engineering information base, and associating the material use information with the construction responsible person information.
By adopting the technical scheme, the construction method can directly correspond to a construction responsible person according to the material use information, and is convenient for solving the follow-up problem disputes.
Optionally, the comparing and analyzing the material consumption information and the phase bill of materials, and the obtaining of the excess material information includes:
analyzing based on the material consumption information and the phase bill of materials, and judging whether the material consumption information exceeds the range of the phase bill of materials:
and if the excess is not exceeded, acquiring the excess type, the excess quantity and the excess factor of the material as the excess information of the material.
By adopting the technical scheme, the construction materials which are excessively used are conveniently recorded, and follow-up exploration is facilitated.
Optionally, the analyzing based on the material usage information and the construction bill of materials, and obtaining the material usage abnormal information includes:
obtaining a bill of material usage based on the material usage information;
performing comparative analysis based on the material use list and the construction material list, acquiring an abnormal task with abnormal material use and the excess material information corresponding to the abnormal task, and acquiring the construction responsible person information corresponding to the abnormal task;
and taking the abnormal task, the material excess information and the construction responsible person information as material use abnormal information.
By adopting the technical scheme, abnormal tasks and construction responsible persons with abnormal material use can be directly positioned, and responsibility tracing is facilitated.
In a second aspect, the present application provides an engineering supervision management system, which adopts the following technical solutions:
an engineering supervision management system comprising:
the system comprises an acquisition module, a construction data storage module and a data processing module, wherein the acquisition module is used for acquiring engineering task information of an engineering task and construction responsible person information of a construction responsible person, associating the engineering task information with the construction responsible person information and acquiring a construction bill based on the engineering task information;
the distribution module is used for distributing target construction materials based on a preset information identification module and the construction material list;
the recording module is used for acquiring material use information of the target construction material;
and the analysis module is used for analyzing based on the material use information and the construction material list to obtain material use abnormal information.
By adopting the technical scheme, the engineering task information is associated with the construction responsible person information, and the engineering task responsible by the construction responsible person can be determined through the construction responsible person information, so that the method is convenient; the using condition of the construction materials of the engineering project can be estimated through the construction material list, and the condition that the construction materials are used indiscriminately and abused in the construction process can be reduced by taking the construction material list as a standard; after the information identification module identifies the information of the construction responsible person, the construction material is distributed for the construction responsible person, so that the construction material distribution is reliable, and the condition that the construction material is falsely led is reduced; the material use information is obtained in the construction process, so that the use condition of the material in the construction process can be known; and analyzing according to the material use information and the construction material list to obtain the abnormal use condition of the construction material, and determining a construction responsible person according to the construction responsible person information so as to facilitate follow-up accountability.
In a third aspect, the present application provides a terminal device, which adopts the following technical solution:
a terminal device comprises a memory, a processor and a computer program which is stored in the memory and can run on the processor, wherein when the processor loads and executes the computer program, the project supervision management method is adopted.
By adopting the technical scheme, the computer program is generated by the engineering supervision management method and stored in the memory to be loaded and executed by the processor, so that the terminal equipment is manufactured according to the memory and the processor, and the use is convenient.
In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solutions:
a computer-readable storage medium, in which a computer program is stored, which, when loaded and executed by a processor, employs an above-mentioned project supervision management method.
By adopting the technical scheme, the project supervision management method generates the computer program, and stores the computer program in the computer readable storage medium so as to be loaded and executed by the processor, and the computer program can be conveniently read and stored through the computer readable storage medium.
Drawings
Fig. 1 is a schematic overall flow chart of a project supervision management method according to an embodiment of the present application.
Fig. 2 is a schematic flowchart illustrating steps S201 to S203 in a project supervision and management method according to an embodiment of the present application.
Fig. 3 is a schematic flowchart illustrating steps S301 to S303 in a project supervision management method according to an embodiment of the present application.
Fig. 4 is a schematic flowchart illustrating steps S401 to S403 in a project supervision management method according to an embodiment of the present application.
Fig. 5 is a flowchart illustrating steps S501 to S506 in a project supervision management method according to an embodiment of the present application.
Fig. 6 is a flowchart illustrating steps S601-S602 in a project supervision management method according to an embodiment of the present application.
Fig. 7 is a flowchart illustrating steps S701 to S703 in a project supervision management method according to an embodiment of the present application.
Detailed Description
The present application is described in further detail below with reference to the attached drawings.
The embodiment of the application discloses a project supervision management method, which comprises the following steps of referring to fig. 1:
s101, acquiring engineering task information of an engineering task and construction leader information of a construction leader, and associating the engineering task information with the construction leader information;
s102, acquiring a construction material list based on the engineering task information;
s103, distributing target construction materials based on a preset information identification module and a construction material list;
s104, acquiring material use information of the target construction material;
and S105, analyzing based on the material use information and the construction material list to obtain material use abnormal information.
In the building industry, there are many factors involved, and a construction project can be divided into a plurality of project projects, for example, building construction needs to be divided into building construction, heating engineering, ventilation engineering, lighting engineering, thermal equipment and installation engineering, electrical equipment and installation engineering, and the like. And under each project, a plurality of project tasks can be divided, for example, the building project can include a foundation project task, a main structure project task, a building decoration project task, a water supply and drainage project task and the like, and each project task also needs a construction responsible person for management.
Step S101, in this embodiment, first, engineering task information of an engineering task is obtained, where the engineering task information includes engineering task content, engineering task period, purchasing budget, and a BIM building model, and the BIM building model refers to a method and a technology for performing information management by applying a model and a digital technology means in a full life cycle of a construction project asset. Its application covers the full life cycle of a building from planning design, project and initial design, construction drawing design, construction build, as built delivery, asset operation and maintenance and final demolition.
After the engineering task information is obtained, the construction responsible person information of the construction responsible person of the engineering task is obtained, wherein the construction responsible person information comprises personal basic information, contact information and the like of the construction responsible person, and the construction responsible person information can also comprise the engineering completion condition of the historical responsibility of the construction responsible person.
After acquiring the construction responsible person, associating the construction responsible person information with the engineering task information, referring to fig. 2, specifically including:
s201, storing the project task information and the construction responsible person information into a preset project information base;
s202, associating the construction responsible person information with the engineering task information in an engineering information base;
s203, configuring an information identifier for the construction responsible person, and acquiring the construction responsible person information based on the information identifier.
In this embodiment, a project platform may be configured for the project, a project information base is preset in the project platform, and the project, the project responsible person, the project task information, and the construction responsible person information of each project task are associated and stored in the project information base. Meanwhile, information identification is configured for the project responsible person and the construction responsible person, and identity information of the project responsible person or the construction responsible person can be identified through the information identification.
For example, information with a single identifier, such as facial identification information and fingerprint identification information of the construction person in charge, may be acquired as the information identifier, and the project smart card may be distributed to the construction person in charge, and the construction person in charge information may be stored in the project smart card, and the information identification module may identify the facial identification information, fingerprint identification information, or project smart card of the construction person in charge and retrieve the construction person in charge information.
Step S102, a construction material list is obtained according to the engineering task information, specifically, the construction material list is obtained through a BIM building model and represents information such as the type and the quantity of the planned construction materials which need to be used when the engineering task is executed, and the quantity of the construction materials in the construction material list is slightly higher than the quantity of the strictly planned construction materials so as to be suitable for the material using condition under special conditions. For example, the construction list includes the types of materials such as steel bars, cement, lime, sand, steel materials, and the corresponding amount of materials, for example, 500 tons. Referring to fig. 3, step S102 includes:
s301, acquiring a construction material list based on the BIM building model;
s302, storing the construction material list into an engineering information base;
and S303, associating the construction material list with the construction responsible person information in the engineering information base.
And storing the obtained construction bill of materials into an engineering information base, and associating the construction bill of materials with a construction responsible person.
Through the arrangement, the engineering task and the construction bill of materials responsible for the construction responsible person can be obtained only by identifying the construction responsible person information of the construction responsible person.
In step S103, after the construction material list is obtained, the construction material may be distributed to the construction person in charge according to the construction material list. Referring to fig. 4, the method specifically includes:
s401, identifying information of a construction responsible person based on an information identification module;
s402, acquiring a construction material list in an engineering information base based on a preset material management platform and construction responsible person information;
and S403, distributing target construction materials for the construction responsible person based on the construction material list and the material management platform.
In this embodiment, still be provided with the material management platform for the project platform matching, the material management platform is connected with the engineering information base, and the material management platform possesses purchase and delivery function, and the material management platform can be the APP on the cell phone terminal, also can be the software platform of computer end, and purchasing personnel or responsible person can purchase the construction material and carry out the delivery according to construction responsible person's request.
The material management platform is configured with an information identification module, the information identification module is used for identifying construction responsible person information of a construction responsible person, the information identification module can be a verification module in an APP, when the construction responsible person sends a construction material request to the material management platform, the construction responsible person information can be identified through the information identification module, and an engineering task and a corresponding construction material list which are responsible for the construction responsible person are obtained from an engineering information base.
After the material management platform obtains the construction material list, construction materials are purchased and distributed for a construction responsible person according to the construction material list and the request of the construction responsible person, if the construction materials exceed the quantity specified in the construction material list, an early warning signal is sent to the construction responsible person and a project responsible person, and the construction responsible person and the project responsible person are reminded that the use of the construction materials exceeds the expected limit.
Step S104, in order to facilitate management of the construction material, in the construction process, the material usage information of the construction material is acquired in real time, and referring to fig. 5, the method specifically includes:
s501, acquiring stage task information based on the engineering task information, and acquiring a stage bill of materials based on the stage task information;
s502, executing the stage task based on the stage task information to obtain material consumption information;
s503, after the stage task is finished, material allowance information is obtained;
s504, comparing and analyzing the material consumption information with the stage material list to obtain excess material information;
s505, using the material consumption information, the material allowance information and the material excess information as stage task material use information, and using all the stage material use information as material use information of the engineering task;
and S506, storing the material use information into an engineering information base, and associating the material use information with the information of a construction responsible person.
During actual construction, the engineering task is divided into a plurality of stage tasks, stage task information is obtained, and a construction responsible person can configure a stage bill of materials for the stage tasks according to the stage task information and the BIM building model. For example, the architectural decoration engineering task can be divided into the stage tasks of outer wall decoration, inner wall decoration, floor decoration and the like. The stage task information includes stage task content, stage task completion period, stage task material type, and the like.
In addition, the stage material list can be obtained through historical use experience, for example, in combination with the historical use experience of the coating, 1 ton of coating can be coated on a wall surface with the square of about 1000, and the quantity of the required coating can be calculated according to the area of the construction wall surface.
Of course, task responsible persons can be allocated to tasks in each stage, the processing mode of the information of the task responsible persons is the same as that of the information of the construction responsible persons, and the task responsible persons can also claim construction materials through the material management platform. Therefore, the task responsible person needs to report the stage task completion condition to the construction responsible person, and the construction responsible person needs to report the project task completion condition to the project responsible person for hierarchical management.
When a task responsible person executes a stage task, recording material consumption information, material allowance information and material excess information of construction materials, for example, in the indoor decoration process, 20 tons of coatings are specified in a stage material list, 18 tons of coatings are consumed in the construction process, the rest 2 tons of coatings are obtained, wherein the 18 tons of coatings are material consumption information, and the 2 tons of coatings are material allowance information. For another example, 20 tons of paint are specified in the phase bill of materials, 22 tons are used in the construction process, and 2 tons can be used as one item of data in the material excess information.
In addition, the material excess information also needs to know the material excess type and the material excess factor, and referring to fig. 6, the obtaining of the material excess information includes:
s601, analyzing based on the material consumption information and the phase bill of materials, and judging whether the material consumption information exceeds the range of the phase bill of materials:
s602, if the material is exceeded, acquiring the material excess type, the material excess quantity and the material excess factor as material excess information.
Comparing the material consumption information with the stage material list, if the consumed construction material exceeds the content of the stage material list, determining that the construction material is excessive, and recording the material excess type, the material excess quantity and the material excess factor by a task responsible person as material excess information.
The acquired material consumption information, material allowance information and material excess information are used as stage task material use information, and the engineering task is divided into a plurality of stage tasks, so that the acquired all-stage task material use information is used as the material use information of the engineering task. And after the material use information is acquired, the material use information is stored in an engineering information base and is also associated with the information of a construction responsible person so as to facilitate the resolution and accountability of subsequent disputes.
In step S105, after the material usage information is obtained, the material usage information and the construction material list are analyzed, so that the specific usage condition of the material can be obtained. Referring to fig. 7, the method specifically includes:
s701, acquiring a material use list based on the material use information;
s702, comparing and analyzing the material use list and the construction material list to obtain abnormal tasks with abnormal material use and excess material information corresponding to the abnormal tasks and obtain construction responsible person information corresponding to the abnormal tasks;
and S703, taking the abnormal task, the excess material information and the construction responsible person information as material use abnormal information.
After the engineering task is finished, a material use list is generated according to the material use information, the material use list and the construction material list are compared and analyzed, the fact that the use of some construction materials exceeds the range of the construction material list can be known, the corresponding engineering task can be directly obtained from the engineering information base and serves as an abnormal task, the material excess information in the abnormal task and a construction responsible person corresponding to the task are obtained at the same time, then the abnormal task, the material excess information and the corresponding construction responsible person serve as the material use abnormal information and are recorded in an engineering information base, the reason of the material excess can be known subsequently, and the corresponding construction responsible person is asked for.
The implementation principle of the project supervision management method in the embodiment of the application is as follows: the engineering task information is associated with the construction responsible person information, and the engineering task responsible by the construction responsible person can be determined through the construction responsible person information, so that convenience is brought; the using condition of the construction materials of the engineering project can be estimated through the construction material list, and the condition that the construction materials are used indiscriminately and abused in the construction process can be reduced by taking the construction material list as a standard; after the information identification module identifies the information of the construction responsible person, the construction material is distributed for the construction responsible person, so that the construction material is more reliable, and the condition of falsely claiming the construction material is reduced; the material use information is obtained in the construction process, so that the use condition of the material in the construction process can be known; and analyzing according to the material use information and the construction material list to obtain the abnormal use condition of the construction material, and determining a construction responsible person according to the construction responsible person information so as to facilitate follow-up accountability.
The embodiment of the application also discloses an engineering supervision management system, which comprises an acquisition module, a distribution module, a recording module and an analysis module, wherein the acquisition module is used for acquiring the engineering task information of an engineering task and the construction responsible person information of a construction responsible person, associating the engineering task information with the construction responsible person information, and acquiring a construction material list based on the engineering task information; the distribution module is used for distributing target construction materials based on a preset information identification module and the construction material list; the recording module is used for acquiring material use information of the target construction material; and the analysis module is used for analyzing based on the material use information and the construction material list to obtain material use abnormal information.
The specific implementation of the project supervision management system in the embodiment of the present application is the same as the specific implementation of the project supervision management method, and therefore, details are not described herein again.
The embodiment of the application further discloses a terminal device, which comprises a memory, a processor and a computer program which is stored in the memory and can run on the processor, wherein when the processor executes the computer program, the engineering supervision management method in the embodiment is adopted.
The terminal device may adopt a computer device such as a desktop computer, a notebook computer, or a cloud server, and the terminal device includes but is not limited to a processor and a memory, for example, the terminal device may further include an input/output device, a network access device, a bus, and the like.
The processor may be a Central Processing Unit (CPU), and of course, according to an actual use situation, other general processors, digital Signal Processors (DSPs), application Specific Integrated Circuits (ASICs), field Programmable Gate Arrays (FPGAs) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, and the like may also be used, and the general processor may be a microprocessor or any conventional processor, and the present application does not limit the present invention.
The memory may be an internal storage unit of the terminal device, for example, a hard disk or a memory of the terminal device, or an external storage device of the terminal device, for example, a plug-in hard disk, a smart card memory (SMC), a secure digital card (SD) or a flash memory card (FC) equipped on the terminal device, and the memory may also be a combination of the internal storage unit of the terminal device and the external storage device, and the memory is used for storing a computer program and other programs and data required by the terminal device, and the memory may also be used for temporarily storing data that has been output or will be output, which is not limited in this application.
The project supervision management method in the embodiment is stored in a memory of the terminal device through the terminal device, and is loaded and executed on a processor of the terminal device, so that the terminal device is convenient to use.
The embodiment of the application also discloses a computer readable storage medium, and the computer readable storage medium stores a computer program, wherein when the computer program is executed by a processor, the project supervision management method in the above embodiment is adopted.
The computer program may be stored in a computer readable medium, the computer program includes computer program code, the computer program code may be in a source code form, an object code form, an executable file or some intermediate form, and the like, the computer readable medium includes any entity or device capable of carrying the computer program code, a recording medium, a usb disk, a removable hard disk, a magnetic disk, an optical disk, a computer memory, a Read Only Memory (ROM), a Random Access Memory (RAM), an electrical carrier signal, a telecommunication signal, a software distribution medium, and the like, and the computer readable medium includes but is not limited to the above components.
The engineering supervision management method in the above embodiment is stored in the computer-readable storage medium through the computer-readable storage medium, and is loaded and executed on the processor, so as to facilitate storage and application of the method.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: equivalent changes in structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. A project supervision management method is characterized by comprising the following steps:
acquiring engineering task information of an engineering task and construction leader information of a construction leader, and associating the engineering task information with the construction leader information;
acquiring a construction material list based on the engineering task information;
distributing target construction materials based on a preset information identification module and the construction material list;
acquiring material use information of the target construction material;
and analyzing based on the material use information and the construction material list to obtain material use abnormal information.
2. The project supervision management method according to claim 1, wherein the associating the project task information with the construction leader information comprises:
storing the engineering task information and the construction responsible person information into a preset engineering information base;
associating the construction responsible person information with the engineering task information in the engineering information base;
and configuring an information identifier for the construction responsible person, and acquiring the construction responsible person information based on the information identifier.
3. The project supervision management method according to claim 2, wherein the project task information includes a BIM building model, and the obtaining of the construction bill of materials based on the project task information includes:
acquiring a construction material list based on the BIM building model;
storing the construction bill of materials into the engineering information base;
and associating the construction bill of materials with the construction responsible person information in the engineering information base.
4. The project supervision and management method according to claim 2, wherein the information identification module is configured to identify the construction leader information of the construction leader, and the allocating target construction materials based on the preset information identification module and the construction materials list comprises:
identifying the construction responsible person information based on the information identification module;
acquiring a construction material list in the engineering information base based on a preset material management platform and the construction responsible person information;
distributing target construction materials for the construction responsible person based on the construction bill of materials and the materials management platform.
5. The project supervision management method according to claim 1, wherein the acquiring of the material usage information of the target construction material comprises:
acquiring stage task information based on the engineering task information, and acquiring a stage bill of materials based on the stage task information;
executing the stage task based on the stage task information to obtain material consumption information;
after the stage task is finished, material allowance information is obtained;
comparing and analyzing the material consumption information with the stage material list to obtain excess material information;
taking the material consumption information, the material allowance information and the material excess information as stage task material use information, and taking all the stage material use information as material use information of the engineering task;
and storing the material use information into the engineering information base, and associating the material use information with the construction responsible person information.
6. The project supervision management method according to claim 5, wherein the comparing and analyzing the material consumption information and the phase bill of materials, and the obtaining of the excess material information comprises:
analyzing based on the material consumption information and the phase bill of materials, and judging whether the material consumption information exceeds the range of the phase bill of materials:
and if the excess is not exceeded, acquiring the excess type, the excess quantity and the excess factor of the material as the excess information of the material.
7. The project supervision and management method according to claim 6, wherein the analyzing based on the material usage information and the construction bill of materials, and obtaining the material usage abnormal information comprises:
obtaining a bill of material usage based on the material usage information;
performing comparative analysis based on the material use list and the construction material list, acquiring an abnormal task with abnormal material use and the excess material information corresponding to the abnormal task, and acquiring the construction responsible person information corresponding to the abnormal task;
and taking the abnormal task, the excess material information and the construction responsible person information as material use abnormal information.
8. An engineering supervision management system, comprising:
the system comprises an acquisition module, a construction material list acquisition module and a construction task management module, wherein the acquisition module is used for acquiring engineering task information of an engineering task and construction responsible person information of a construction responsible person, associating the engineering task information with the construction responsible person information and acquiring the construction material list based on the engineering task information;
the distribution module is used for distributing target construction materials based on a preset information identification module and the construction material list;
the recording module is used for acquiring material use information of the target construction material;
and the analysis module is used for analyzing based on the material use information and the construction material list to obtain material use abnormal information.
9. A terminal device comprising a memory, a processor and a computer program stored in the memory and being executable on the processor, characterized in that the method of any of claims 1-7 is used when the computer program is loaded and executed by the processor.
10. A computer-readable storage medium, in which a computer program is stored, which, when loaded and executed by a processor, carries out the method of any one of claims 1 to 7.
CN202211132641.3A 2022-09-17 2022-09-17 Project supervision management method, system, terminal equipment and storage medium Pending CN115456424A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211132641.3A CN115456424A (en) 2022-09-17 2022-09-17 Project supervision management method, system, terminal equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211132641.3A CN115456424A (en) 2022-09-17 2022-09-17 Project supervision management method, system, terminal equipment and storage medium

Publications (1)

Publication Number Publication Date
CN115456424A true CN115456424A (en) 2022-12-09

Family

ID=84304799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211132641.3A Pending CN115456424A (en) 2022-09-17 2022-09-17 Project supervision management method, system, terminal equipment and storage medium

Country Status (1)

Country Link
CN (1) CN115456424A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116342076A (en) * 2023-05-30 2023-06-27 山东建筑大学设计集团有限公司 Engineering information management system and management method
CN116681377A (en) * 2023-05-24 2023-09-01 天津瑞利通科技有限公司 Tool management method, system, electronic device and readable storage medium
CN117575518A (en) * 2023-11-20 2024-02-20 浙江建友工程咨询有限公司 Method, device, equipment and medium for digital management of whole engineering construction process

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116681377A (en) * 2023-05-24 2023-09-01 天津瑞利通科技有限公司 Tool management method, system, electronic device and readable storage medium
CN116681377B (en) * 2023-05-24 2024-02-27 天津瑞利通科技有限公司 Tool management method, system, electronic device and readable storage medium
CN116342076A (en) * 2023-05-30 2023-06-27 山东建筑大学设计集团有限公司 Engineering information management system and management method
CN116342076B (en) * 2023-05-30 2023-08-01 山东建筑大学设计集团有限公司 Engineering information management system and management method
CN117575518A (en) * 2023-11-20 2024-02-20 浙江建友工程咨询有限公司 Method, device, equipment and medium for digital management of whole engineering construction process

Similar Documents

Publication Publication Date Title
CN115456424A (en) Project supervision management method, system, terminal equipment and storage medium
US11557009B2 (en) System and method for generating financial assessments based on construction site images
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
US11481853B2 (en) Selective reporting of construction errors
CN111242543B (en) Concrete material management system and method
CN112561487B (en) Method, device and equipment for calculating construction progress and readable storage medium
WO2019159115A1 (en) System and method for processing of construction site images
CN116823191B (en) Intelligent construction engineering management platform based on EMPC mode
CN110363319A (en) Resource allocation methods, server, resource claim method and client
US20070094038A1 (en) Franchising business method
CN113256108A (en) Human resource allocation method, device, electronic equipment and storage medium
CN112651583A (en) Fixed asset checking method and device, mobile terminal and storage medium
CN116562715B (en) Index data monitoring method, device, computer equipment and storage medium
Framinan et al. Available-to-promise systems in the semiconductor industry: A review of contributions and a preliminary experiment
CN108647847A (en) Material management system in work progress and method
CN116630082A (en) Method and device for allocating production resources, electronic equipment and storage medium
CN115689030A (en) Digital lean construction management method, system, electronic device and storage medium
CN115564381A (en) Information control method for construction progress of fabricated building
CN113487290A (en) System for monitoring house decoration progress and monitoring method thereof
CN113128876A (en) Image-based object management method, device and computer-readable storage medium
CN113988804A (en) Digital management method, device, equipment and storage medium for whole engineering construction process
CN110838003A (en) Management system, method, device and readable medium for shared office
CN117391638A (en) Management platform for building engineering based on network technology
CN117910686A (en) Power supply management method and system
CN114943566A (en) Evaluation method and recall method for lost commercial tenant, electronic equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination