CN115288427B - Method for supporting frame structure settlement joint template - Google Patents

Method for supporting frame structure settlement joint template Download PDF

Info

Publication number
CN115288427B
CN115288427B CN202210904584.XA CN202210904584A CN115288427B CN 115288427 B CN115288427 B CN 115288427B CN 202210904584 A CN202210904584 A CN 202210904584A CN 115288427 B CN115288427 B CN 115288427B
Authority
CN
China
Prior art keywords
frame structure
formwork
settlement joint
pouring
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210904584.XA
Other languages
Chinese (zh)
Other versions
CN115288427A (en
Inventor
周忠祥
张国祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202210904584.XA priority Critical patent/CN115288427B/en
Publication of CN115288427A publication Critical patent/CN115288427A/en
Application granted granted Critical
Publication of CN115288427B publication Critical patent/CN115288427B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0651One-piece elements
    • E04G17/0654One-piece elements remaining completely or partially embedded in the cast material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a method for erecting a settlement joint template of a frame structure, which comprises the following steps of: setting out the sample at one time, and setting out the beam column of the frame structure; modeling, namely erecting a template in the region where the lofting is completed; firstly pouring a member, and pouring concrete into the modeled area; and removing the die plate at the side after the pouring member is completed. The invention has the beneficial effects of eliminating the hidden quality trouble of the structure of the settlement joint of the frame structure, improving the quality management benefit, avoiding the quality problems of the expansion of the settlement joint, honeycomb pitting surface and the like, saving the labor and material cost for later repair and polishing the appearance of the concrete and effectively improving the economic benefit. The method ensures that the construction process of the settlement joint of the frame structure is more convenient and quicker.

Description

Method for supporting frame structure settlement joint template
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a method for supporting a settlement joint template of a frame structure.
Background
In a frame residential building, as the length span size of an underground garage is large, a settlement joint is arranged at a proper position, and the clear width of the settlement joint of more than five layers of residences is not less than 120mm according to the building foundation base design Specification (GB 5007-2011), and the current settlement joint width of a high-rise residence is generally 200-300 mm. Due to the small space between the building elements at the settlement joint. The conventional formwork can not be supported and dismantled, and in actual construction, the quality of building components at the settlement joint is difficult to ensure, so that certain quality hidden trouble is brought to the structural safety and appearance quality of the building.
Disclosure of Invention
The invention aims to provide a method for supporting a frame structure settlement joint template, which is particularly suitable for supporting the frame structure settlement joint template.
In order to solve the technical problems, the invention adopts the following technical scheme:
A method for formwork erection of a frame structure, the method comprising, at one side of the frame structure:
setting out the sample at one time, and setting out the beam column of the frame structure;
modeling, namely erecting a template in the region where the lofting is completed;
Firstly pouring a member, and pouring concrete into the modeled area;
and removing the die plate at the side after the pouring member is completed.
Further, on the other side of the frame structure:
Secondarily lofting, namely lofting the beam column of the frame structure;
a post-pouring member for pouring concrete into the modeled region;
And (5) secondarily removing the die, and removing the die plate at the side after the pouring member is finished.
Further, a template fixing piece for fixing the template is arranged on the template.
Further, the template fixing piece comprises a steel pipe and a plurality of battens for reinforcing the template and split bolts for locking the template,
The timber is vertically arranged between the steel pipe and the template according to the short sides, and the split bolt nuts are pre-buried in the pouring area.
Further, the widths of the template, the steel pipe, the batten and the split bolt and nut are H, D, H and D in sequence, and H+D+h+d is specified to be less than or equal to 200mm.
Further, when the modeling step is performed on one side of the frame structure, the templates are simultaneously arranged on the other side of the frame structure, and the templates on two sides are tied through the split bolts.
Further, after the step of secondarily removing the mold, the method further comprises the steps of:
and (3) caulking, namely removing the split bolts, polishing the settlement joint, and filling mortar for trowelling.
The invention has the advantages and positive effects that: by adopting the technical scheme, the quality hidden trouble of the structure of the settlement joint of the frame structure is eliminated, the quality management benefit is improved, the quality problems of the settlement joint, the mold expanding, the honeycomb pitting surface and the like are completely eradicated, the labor and material cost for later repair and polishing of the appearance of the concrete are saved, and the economic benefit is effectively improved. The method ensures that the construction process of the settlement joint of the frame structure is more convenient and quicker.
Drawings
FIG. 1 is a schematic illustration of a method for formwork erection for a frame structure sinker slit according to an embodiment of the invention.
FIG. 2 is a schematic view of a 1-way settling slit beam construction of an embodiment of the present invention.
FIG. 3 is a schematic view of a 2-way sinker loop column configuration according to one embodiment of the present invention.
In the figure:
1. split bolt 2, steel pipe 3, and square
4. Template 5, butterfly nut
Detailed Description
Embodiments of the present invention are described in detail below, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to like or similar elements or elements having like or similar functions throughout. The embodiments described below by referring to the drawings are illustrative and intended to explain the present invention and should not be construed as limiting the invention.
In the prior art, the construction method of the settlement joint comprises the following steps:
① Firstly, pouring a component to paste a foam board:
The column and the beam member on one side are firstly constructed, and then the column and the beam member on the other side are constructed. And (3) erecting the formwork according to a conventional method at the constructed position, after the concrete is poured and the formwork is removed, pasting foam plates with the thickness the same as the width of the settlement joint on the settlement joint sides of the column and the beam, taking the foam plates as side formworks of the settlement joint of the post and the beam, binding reinforcing steel bars and erecting an inner formwork.
The defects are as follows:
a. The formwork supporting component is difficult to reinforce due to the fact that the split bolts cannot be arranged after the construction method, and the formwork expansion phenomenon is easy to occur;
b. Because the foam board is used as a template, when concrete vibrates, the foam board is easy to smash, the smashed foam board easily enters the columns and the beams, and concrete easily flows into the settlement joint, so that the quality hidden trouble is brought to the engineering. It is difficult to secure the appearance quality.
C. The bottom die is a wood die plate, one side close to the settlement joint is a foam plate, the joint of the die plates of two different materials is difficult, and slurry leakage at the joint is easy to occur, so that the quality is influenced.
D. the pasting foam board has large labor and material cost, and the construction cost can be correspondingly increased.
② Side roof of wood square
Firstly, constructing a column and a beam component on one side, and then constructing a column and a beam component on the other side. And (3) erecting the template according to a conventional method at the site where the construction is performed, and removing the template after the concrete is poured. And (3) processing a side template of the post and beam settlement joint constructed after putting down, namely, a wood square with a slightly longer length according to the width of the settlement joint (the thickness of the subtracted template), and using a wood hammer to smash into the settlement joint to serve as a side top of the side template.
The defects are as follows:
a. The side-propping mode of the battens causes too concentrated stress and uneven stress of the templates, and the templates at the intervals between the battens are easy to expand and deform.
B. the side roof of the wood only solves the problem of side stress in the die, and the junction of the bottom die and the side die is easy to burst.
③ Steel-wood combined template
When the column and beam components on one side are constructed, the steel template of the column and beam on the other side is fixed by a screw after the back edge and the steel pipe on one side are constructed. And after the pouring of the component is finished, the template is not dismantled. And the fixed steel template is used as a side mould for pouring a side column and a beam.
The defects are as follows:
a. and the pouring of the two side components is completed, and the middle template of the settlement joint is difficult to remove.
B. The steel forms are required to be specially processed and customized, and because the settlement joint widths of all building designs are different, the steel forms are required to be specially customized, and the universality is not strong.
C. The steel form is difficult to disassemble, and the damage rate is high in the forced disassembling process. The turnover number of the same project is low. In addition, the cost of customizing the steel template is high, and the economic benefit is low.
In order to distinguish from the prior art, as shown in fig. 1-3, there is shown a construction diagram in an embodiment of the present invention, which relates to a method for setting up a settlement joint formwork of a frame structure, the method comprising, on one side of the frame structure:
s1: setting out the sample at one time, and setting out the beam column of the frame structure;
s2: modeling, namely supporting a template 4 in a region where lofting is completed;
S3: firstly pouring a member, and pouring concrete into the modeled area;
s4: and (5) removing the mold once, and removing the side mold plate 4 after the pouring of the component is completed.
Further perfecting this scheme, namely, on the other side of the frame structure:
S5: secondarily lofting, namely lofting the other side of the beam column of the frame structure;
S6: pouring a member, namely pouring concrete into the modeled area;
S7: and (5) removing the die secondarily, and removing the side die plate 4 after the poured component is finished.
It is mainly noted that in the above method steps, only one modeling operation is required to be performed at two ends of a beam column of a frame structure after lofting, and repeated modeling is not required, in the process of one modeling, the templates 4 are supported at two ends of the frame structure at the same time, the templates 4 at two ends are supported to be as symmetrical and parallel as possible, and the template fixing pieces are arranged at the edges of the templates 4.
Wherein, foretell template mounting includes: the steel pipe 2 and the battens 3 for reinforcing the formwork 4 and the split bolt 1 for locking the formwork 4 are vertically arranged between the steel pipe 2 and the formwork 4 according to the short sides, and are used for cushioning the formwork 4 to generate a certain construction gap, the split bolt 1 is used for tying the two formworks 4, and it is noted that in the embodiment, the butterfly nut for locking the split bolt 1 is pre-buried in a pouring area before the butterfly nut is not taken out, the butterfly nut 5 for locking the split bolt 1 is locked in a hammering manner in the pouring area after the butterfly nut is not taken out, and the nut shielding of the pouring area after the butterfly nut is covered for attractive appearance.
In the embodiment of the invention, the widths of the template 4, the steel pipe 2, the batten 3 and the split bolt butterfly nut 5 are required to be recorded as H, D, H and D in sequence, and the rule H+D+h+d is less than or equal to 200mm, and it can be understood that the design specification requirement of the settlement joint of the high-rise residence is 200mm-300mm at present, so that the sum of the thicknesses of the template and other fixing devices cannot exceed the width requirement when the template is supported in the settlement joint of the frame structure, otherwise pouring cannot be implemented.
At the end of this scheme, it is necessary to: after the step of secondary demolding, the method further comprises the following steps:
S8: and (3) caulking, removing the split bolt 1, polishing the settlement joint, trowelling the filling mortar, taking out the split bolt 1 after finishing the settlement joint structure, mechanically cutting off the split bolt 1 or polishing by a handheld electric grinder, smearing antirust paint in the settlement joint, and trowelling by waterproof mortar.
The foregoing describes the embodiments of the present invention in detail, but the description is only a preferred embodiment of the present invention and should not be construed as limiting the scope of the invention. All equivalent changes and modifications within the scope of the present invention are intended to be covered by the present invention.

Claims (5)

1. A method for formwork erection of a settlement joint of a frame structure, the method comprising, on one side of the frame structure:
setting out the sample at one time, and setting out the beam column of the frame structure;
modeling, namely erecting a template in the region where the lofting is completed; when one side of the frame structure is subjected to the modeling step, the templates are simultaneously arranged on the other side of the frame structure, and the templates on the two sides are tied through split bolts;
Firstly pouring a member, and pouring concrete into the modeled area;
removing the mold once, and removing the mold plate at the side after the pouring member is finished;
on the other side of the frame structure:
Secondarily lofting, namely lofting the beam column of the frame structure;
a post-pouring member for pouring concrete into the modeled region;
And (5) secondarily removing the die, and removing the die plate at the side after the pouring member is finished.
2. A method for formwork erection of a frame structure settlement joint according to claim 1, wherein a formwork fixing member for fixing the formwork is provided on the formwork.
3. A method for formwork erection for a frame structure according to claim 2, wherein the formwork fastener comprises steel pipes and battens for reinforcing the formwork, and split bolts for locking the formwork,
The timber is vertically arranged between the steel pipe and the template according to the short sides, and the split bolt nuts are pre-buried in the pouring area.
4. A method for formwork bracing for a settlement joint of a frame structure according to claim 3, wherein the widths of the formwork, the steel pipe, the batten and the split bolt and nut are H, D, H and D in sequence, and h+d+h+d is specified to be less than or equal to 200mm.
5. A method for formwork erection of a settlement joint for a frame structure as claimed in claim 3, further comprising, after the step of secondarily removing the formwork, the steps of:
and (3) caulking, namely removing the split bolts, polishing the settlement joint, and filling mortar for trowelling.
CN202210904584.XA 2022-07-29 2022-07-29 Method for supporting frame structure settlement joint template Active CN115288427B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210904584.XA CN115288427B (en) 2022-07-29 2022-07-29 Method for supporting frame structure settlement joint template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210904584.XA CN115288427B (en) 2022-07-29 2022-07-29 Method for supporting frame structure settlement joint template

Publications (2)

Publication Number Publication Date
CN115288427A CN115288427A (en) 2022-11-04
CN115288427B true CN115288427B (en) 2024-06-07

Family

ID=83825819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210904584.XA Active CN115288427B (en) 2022-07-29 2022-07-29 Method for supporting frame structure settlement joint template

Country Status (1)

Country Link
CN (1) CN115288427B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817376A (en) * 2012-08-07 2012-12-12 中国建筑第六工程局有限公司 Settlement joint template system for big-volume slabstone concrete and settlement joint construction method
CN102953546A (en) * 2012-08-28 2013-03-06 中联世纪建设集团有限公司 Construction method for mounting deformation joint template at double walls
CN103321257A (en) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN108571166A (en) * 2017-03-10 2018-09-25 五冶集团上海有限公司 A kind of deformation joint formwork construction method
CN207988490U (en) * 2018-01-10 2018-10-19 中天建设集团有限公司 A kind of easy device that deformation joint shear wall formwork installs
CN210105298U (en) * 2019-05-16 2020-02-21 江西国金建设集团有限公司 Deformation joint department wall body formwork system
CN211850804U (en) * 2019-09-24 2020-11-03 中冶天工集团有限公司 Shear force wall settlement joint steel wood combines template to prop up establishes device
CN212478538U (en) * 2020-06-08 2021-02-05 中冶天工集团天津有限公司 Deformation joint wall body erecting structure
CN114109030A (en) * 2021-06-01 2022-03-01 上海宝冶集团有限公司 Construction method of special-shaped structure of bare concrete diaphragm wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817376A (en) * 2012-08-07 2012-12-12 中国建筑第六工程局有限公司 Settlement joint template system for big-volume slabstone concrete and settlement joint construction method
CN102953546A (en) * 2012-08-28 2013-03-06 中联世纪建设集团有限公司 Construction method for mounting deformation joint template at double walls
CN103321257A (en) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN108571166A (en) * 2017-03-10 2018-09-25 五冶集团上海有限公司 A kind of deformation joint formwork construction method
CN207988490U (en) * 2018-01-10 2018-10-19 中天建设集团有限公司 A kind of easy device that deformation joint shear wall formwork installs
CN210105298U (en) * 2019-05-16 2020-02-21 江西国金建设集团有限公司 Deformation joint department wall body formwork system
CN211850804U (en) * 2019-09-24 2020-11-03 中冶天工集团有限公司 Shear force wall settlement joint steel wood combines template to prop up establishes device
CN212478538U (en) * 2020-06-08 2021-02-05 中冶天工集团天津有限公司 Deformation joint wall body erecting structure
CN114109030A (en) * 2021-06-01 2022-03-01 上海宝冶集团有限公司 Construction method of special-shaped structure of bare concrete diaphragm wall

Also Published As

Publication number Publication date
CN115288427A (en) 2022-11-04

Similar Documents

Publication Publication Date Title
CN111502247B (en) Wall form bottom plugging device, form supporting system and form supporting construction method
CN206616862U (en) Formwork root bracing means
CN106320691A (en) Aluminum-wood formwork construction method
CN105926942A (en) Construction method of combined aluminum/steel frame wood-plastic formwork system
CN210396134U (en) Reinforcing tool for controlling horizontal joint quality of shear wall
CN110863590A (en) Mold device for manufacturing + type cavity concrete module and using method thereof
CN111663770B (en) Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN115288427B (en) Method for supporting frame structure settlement joint template
CN212866852U (en) Wall form bottom plugging device and form support system
CN113152893A (en) Template for building construction and using method
CN202831624U (en) Template for deformation joint of shear wall
CN217079684U (en) Split type form removal-free concrete hollow structure
CN210289132U (en) Cross-shaped constructional column combined type aluminum alloy template assembly
CN215889453U (en) Temporary support for two sides of post-cast strip of building floor
CN111236647A (en) Constructional column oblique split bolt and construction method of fixed template thereof
CN104975715A (en) Formwork sealing method for walls or columns
CN214245382U (en) Stainless steel-wood combined template applied to bare concrete
CN211973582U (en) Basement template system
CN209907936U (en) Integrated template system of cast-in-situ overhanging window board with secondary structure
CN112727083A (en) Formwork erecting method for reserved hole
CN110863589A (en) Mold device for manufacturing L-shaped cavity concrete module and using method thereof
CN111005558A (en) Mould for manufacturing basic cavity concrete mould and using method thereof
CN111622263A (en) Comprehensive pipe gallery construction method based on composite material combined type template system
CN110700586A (en) Refined construction method for formwork at near-empty part
CN221142761U (en) Prefabricated tubular pile cap template device capable of being rapidly assembled and disassembled

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant