CN115288427A - Method for erecting framework structure settlement joint formwork - Google Patents

Method for erecting framework structure settlement joint formwork Download PDF

Info

Publication number
CN115288427A
CN115288427A CN202210904584.XA CN202210904584A CN115288427A CN 115288427 A CN115288427 A CN 115288427A CN 202210904584 A CN202210904584 A CN 202210904584A CN 115288427 A CN115288427 A CN 115288427A
Authority
CN
China
Prior art keywords
formwork
template
frame structure
settlement joint
erecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210904584.XA
Other languages
Chinese (zh)
Inventor
周忠祥
张国祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202210904584.XA priority Critical patent/CN115288427A/en
Publication of CN115288427A publication Critical patent/CN115288427A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0651One-piece elements
    • E04G17/0654One-piece elements remaining completely or partially embedded in the cast material

Abstract

The invention provides a method for erecting a settlement joint template of a frame structure, which comprises the following steps of: setting out for the first time, and setting out the beam column of the frame structure; modeling, namely erecting a template in the area where the lofting is finished; firstly, casting a component, and casting concrete in the modeled area; and removing the formwork at one time, and removing the formwork at the side after the pouring member is finished. The invention has the advantages of eliminating the quality hidden trouble of the settlement joint structure of the frame structure, improving the quality management benefit, putting an end to the quality problems of mold expansion, honeycomb pitted surface and the like at the settlement joint, saving the labor and material cost for later repair and grinding of the concrete appearance, and effectively improving the economic benefit. The method enables the construction process of the frame structure settlement joint to be more convenient and faster.

Description

Method for erecting framework structure settlement joint formwork
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a method for erecting a settlement joint formwork of a frame structure.
Background
In a frame residential building, because the length span of an underground garage is large, settlement joints are arranged at proper positions, the net width of the settlement joints of more than five layers of buildings is not less than 120mm according to the foundation design Specification for building foundations (GB 5007-2011), and the width of the settlement joints of the high-rise residential buildings is generally 200-300 mm at present. Because the space between the building elements at the settlement joint is small. The conventional formwork can not be erected and dismantled, the quality of the building component at the settlement joint is difficult to guarantee in actual construction, and certain quality hidden danger is brought to the structural safety and the appearance quality of a building.
Disclosure of Invention
The invention aims to provide a method for erecting a formwork of a settlement joint of a frame structure, which is particularly suitable for erecting the formwork of the settlement joint of the frame structure.
In order to solve the technical problems, the invention adopts the technical scheme that:
a method for framing structure sinker formwork erection, the method comprising, on one side of the framing structure:
lofting for the first time, wherein the lofting is carried out on the beam column of the frame structure;
modeling, namely erecting a template in the area where the lofting is finished;
firstly, casting a component, and casting concrete in the modeled area;
and removing the formwork at one time, and removing the formwork at the side after the pouring member is finished.
Further, on the other side of the frame structure:
secondary lofting, namely lofting the beam column of the frame structure;
a rear pouring member, wherein concrete is poured into the modeled area;
and removing the formwork for the second time, and removing the formwork on the side after the pouring member is finished.
Furthermore, the template is provided with a template fixing part for fixing the template.
Further, the formwork fixing member includes a steel pipe and a plurality of battens for reinforcing the formwork, and split bolts for locking the formwork,
the battens are vertically arranged between the steel pipe and the template according to the short sides, and the split bolts and the nuts are embedded in the pouring area.
Further, the widths of the template, the steel pipe, the batten and the split bolt and nut are recorded to be H, D, H and D in sequence, and H + D + H + D is regulated to be less than or equal to 200mm.
Further, when the modeling step is performed on one side of the frame structure, the templates are simultaneously arranged on the other side of the frame structure, and the templates on the two sides are tied through the split bolts.
Further, after the step of secondary form removal, the method further comprises the following steps:
and filling gaps, removing the split bolts, polishing the settlement joints, and leveling filling mortar.
The invention has the advantages and positive effects that: by adopting the technical scheme, the quality hidden danger of the settlement joint structure of the frame structure is eliminated, the quality management benefit is improved, the quality problems of mold expansion, honeycomb pitted surface and the like at the settlement joint are avoided, the labor and material cost for later repair and grinding of the concrete appearance is saved, and the economic benefit is effectively improved. The method enables the construction process of the frame structure settlement joint to be more convenient and faster.
Drawings
Fig. 1 is a schematic view of a method for formwork erection of a settlement joint of a frame structure according to an embodiment of the present invention.
Fig. 2 is a schematic view of a 1-1 way sinker beam configuration according to an embodiment of the present invention.
Figure 3 is a schematic view of a 2-2 way settling leg configuration according to one embodiment of the present invention.
In the figure:
1. split bolt 2, steel pipe 3, flitch
4. Template 5 and butterfly nut
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are illustrative and intended to be illustrative of the invention and are not to be construed as limiting the invention.
In the prior art, a settlement joint construction method comprises the following steps:
(1) firstly, pouring a component to paste the foam board:
and constructing the column and beam members on one side and then constructing the column and beam members on the other side. And (3) erecting a template at the construction part according to a conventional method, after pouring concrete and removing the template, sticking foam plates with the same thickness and width as the settlement joints on the settlement joint sides of the columns and the beams to be used as side templates for constructing the settlement joints of the columns and the beams, binding reinforcing steel bars and erecting an internal mold.
The method comprises the following steps:
a. the formwork expanding phenomenon is easy to occur due to the fact that the formwork supporting component cannot be provided with the split bolts and the inner side formwork is relatively difficult to reinforce;
b. because the foam board replaces the template to use, when the concrete vibrates, smash the foam board to pieces easily, garrulous foam board gets into in post, the roof beam easily and the concrete easily flows into the subsiding crack, brings the quality hidden danger for the engineering. It is difficult to ensure the quality of the appearance.
c. The bottom die is a wood template, one side close to the settlement joint is a foam board, the splicing of the template at the joint of two different materials is difficult, slurry leakage at the splicing joint is easy to occur, and the quality is affected.
d. The foam board sticking has the disadvantages of great labor input, high material cost and corresponding increase of construction cost.
(2) Flitch side top
And constructing the column and beam members on one side and then constructing the column and beam members on the other side. And (3) erecting a template at the constructed part according to a conventional method, and after pouring concrete and dismantling the template. And (3) processing battens with slightly longer lengths according to the width of the settlement joint (minus the thickness of the formwork) on the side formwork of the settlement joint of the column and the beam which are constructed after being laid down, and smashing the settlement joint into a wooden hammer to serve as the side top of the side formwork.
The method comprises the following steps:
a. the batten side-top mode causes the stress of the template to be too concentrated and uneven, and the template at the interval part of the batten and the batten is easy to expand and deform.
b. The problem of lateral stress in the die is only solved by the side top of the batten, and the joint of the bottom die and the side die is easy to explode.
(3) Steel-wood combined template
When the column and beam components on one side are constructed firstly, the steel templates of the column and the beam on the other side are fixed by screws after the back ridges and the steel pipes on one side. After the member poured firstly is finished, the template is not dismantled. The fixed steel template is used as a side mold for casting a side column and a beam.
The method comprises the following steps:
a. and the pouring of the components on the two sides is completed, and the middle template of the settlement joint is difficult to remove.
b. The steel form needs special processing customization because each architectural design settlement joint width is different, and the steel form needs special customization, and the commonality is not strong.
c. The steel form is difficult to dismantle, and the damage rate is high in the forced dismantling process. The turnover frequency of the same project is low. In addition, the cost for customizing the steel template is high, and the economic benefit is lower.
To distinguish from the prior art solutions, as shown in fig. 1-3, which show construction diagrams in an embodiment of the present invention, the embodiment of the present invention relates to a method for framing structure settlement joint formwork erection, the method comprising, on one side of the framing structure:
s1: lofting for the first time, wherein the lofting is carried out on the beam column of the frame structure;
s2: modeling, namely erecting a template 4 in the lofting area;
s3: firstly, casting a component, and casting concrete in a modeling area;
s4: and removing the side template 4 after the casting component is finished.
Further elaboration of this solution is that on the other side of the frame structure:
s5: secondary lofting, namely lofting the other side of the beam column of the frame structure;
s6: a rear pouring member, which is used for pouring concrete in the modeling area;
s7: and (5) secondary form removal, and removing the side form 4 after the cast component is completed.
It is mainly noted that in the above steps of the method, only one modeling operation is needed to be performed on two ends of a beam column of the framework structure after lofting, and repeated modeling is not needed, in the process of one modeling, templates 4 need to be supported at two ends of the framework structure at the same time, the supports of the templates 4 at the two ends are kept symmetrical and parallel as much as possible, and template fixing members are arranged at the edges of the templates 4.
Wherein, above-mentioned template mounting includes: a butterfly nut 5 that is used for consolidating steel pipe 2 and a plurality of flitch 3 of template 4, and be used for locking template 4 to the stay bolt 1, a plurality of flitches 3 are according to the vertical setting of minor face between steel pipe 2 and template 4, thereby it produces certain construction gap to be used for raising up template 4, thereby stay bolt 1 is used for drawknot two templates 4, it needs to notice be, in this embodiment, a butterfly nut that is used for locking stay bolt 1 is pre-buried in pouring the region earlier, and need not take out, then pour the region and be used for locking the butterfly nut of stay bolt 1 and lock through the mode of hammering, can shelter from the cover with the nut of pouring the region afterwards for pleasing to the eye.
In the embodiment of the invention, the widths of the template 4, the steel pipe 2, the batten 3 and the split bolt butterfly nut 5 need to be recorded as H, D, H and D in sequence, and the H + D + H + D is regulated to be less than or equal to 200mm, and it can be understood that the design specification requirement of the settlement joint of the high-rise dwelling house is 200mm-300mm at present, so when the template is arranged in the settlement joint of the frame structure, the sum of the thicknesses of the template and other fixing devices does not exceed the width requirement, otherwise, pouring cannot be carried out.
At the end of this scheme, at S7: after the step of secondary form removal, the method also comprises the following steps:
s8: filling gaps, removing the split bolts 1, polishing the settlement joints, filling mortar, and trowelling, wherein the split bolts 1 are taken out after the settlement joint structure is completed, the split bolts 1 can be mechanically cut off or the handheld electric grinder is used for polishing, antirust paint is smeared inside the settlement joints, and trowelling is carried out through waterproof mortar.
The embodiments of the present invention have been described in detail, but the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.

Claims (7)

1. A method for framing structure sinker seam formwork erection, characterized in that it comprises, on one of the sides of the framing structure:
setting out for the first time, and setting out the beam column of the frame structure;
modeling, namely erecting a template in the area where the lofting is finished;
firstly, casting a component, and casting concrete in the modeled area;
and removing the formwork at one time after the pouring member is finished.
2. A method for framing structure sinker seam template bracing according to claim 1, wherein at the other side of the framing structure:
secondary lofting, namely lofting the beam column of the frame structure;
a rear pouring member for pouring concrete in the modeled area;
and removing the formwork for the second time, and removing the formwork on the side after the pouring member is finished.
3. The method for framing structure sinker seam template bracing according to claim 2, wherein said templates are provided with template fasteners for fastening said templates.
4. The method for framing structure sinker seam template bracing according to claim 3, wherein the template fixing members include steel pipes and battens for reinforcing the templates, and split bolts for locking the templates,
the battens are vertically arranged between the steel pipe and the template according to the short sides, and the split bolts and the nuts are embedded in the pouring area.
5. The method for erecting the settlement joint formwork of the frame structure as claimed in claim 4, wherein the widths of the formwork, the steel pipe, the batten and the split bolt and nut are recorded as H, D, H and D in sequence, and H + D + H + D is regulated to be less than or equal to 200mm.
6. The method for erecting the formwork for the settlement joint of the frame structure as claimed in claim 4 or 5, wherein when the modeling step is performed on one side of the frame structure, the formwork is simultaneously arranged on the other side of the frame structure, and the formworks on the two sides are pulled and connected through the split bolts.
7. The method for framing structure sinker seam template bracing according to claim 4, further comprising, after said step of secondary form removal:
and filling joints, removing the split bolts, polishing the settlement joints, and leveling the filling mortar.
CN202210904584.XA 2022-07-29 2022-07-29 Method for erecting framework structure settlement joint formwork Pending CN115288427A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210904584.XA CN115288427A (en) 2022-07-29 2022-07-29 Method for erecting framework structure settlement joint formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210904584.XA CN115288427A (en) 2022-07-29 2022-07-29 Method for erecting framework structure settlement joint formwork

Publications (1)

Publication Number Publication Date
CN115288427A true CN115288427A (en) 2022-11-04

Family

ID=83825819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210904584.XA Pending CN115288427A (en) 2022-07-29 2022-07-29 Method for erecting framework structure settlement joint formwork

Country Status (1)

Country Link
CN (1) CN115288427A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817376A (en) * 2012-08-07 2012-12-12 中国建筑第六工程局有限公司 Settlement joint template system for big-volume slabstone concrete and settlement joint construction method
CN102953546A (en) * 2012-08-28 2013-03-06 中联世纪建设集团有限公司 Construction method for mounting deformation joint template at double walls
CN103321257A (en) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN108571166A (en) * 2017-03-10 2018-09-25 五冶集团上海有限公司 A kind of deformation joint formwork construction method
CN210105298U (en) * 2019-05-16 2020-02-21 江西国金建设集团有限公司 Deformation joint department wall body formwork system
CN211850804U (en) * 2019-09-24 2020-11-03 中冶天工集团有限公司 Shear force wall settlement joint steel wood combines template to prop up establishes device
CN212478538U (en) * 2020-06-08 2021-02-05 中冶天工集团天津有限公司 Deformation joint wall body erecting structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817376A (en) * 2012-08-07 2012-12-12 中国建筑第六工程局有限公司 Settlement joint template system for big-volume slabstone concrete and settlement joint construction method
CN102953546A (en) * 2012-08-28 2013-03-06 中联世纪建设集团有限公司 Construction method for mounting deformation joint template at double walls
CN103321257A (en) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN108571166A (en) * 2017-03-10 2018-09-25 五冶集团上海有限公司 A kind of deformation joint formwork construction method
CN210105298U (en) * 2019-05-16 2020-02-21 江西国金建设集团有限公司 Deformation joint department wall body formwork system
CN211850804U (en) * 2019-09-24 2020-11-03 中冶天工集团有限公司 Shear force wall settlement joint steel wood combines template to prop up establishes device
CN212478538U (en) * 2020-06-08 2021-02-05 中冶天工集团天津有限公司 Deformation joint wall body erecting structure

Similar Documents

Publication Publication Date Title
US20140223851A1 (en) Prefabricated reinforced concrete wall panel and installation method
CN110158951B (en) Construction method of all-wood template with frame structure
JP2004528497A (en) Reinforced building panels and triangular columns
CN111962675A (en) Construction method of large-span special-shaped cast-in-place reinforced concrete open-web truss
CN111218983A (en) Lattice formula structure concrete frame house
US20090121373A1 (en) Method and Apparatus for Construction
CN111778990A (en) Permanent-temporary combined assembly type inner support system and construction method
CN115288427A (en) Method for erecting framework structure settlement joint formwork
CN212506301U (en) Support system in combination assembled forever
CN209907936U (en) Integrated template system of cast-in-situ overhanging window board with secondary structure
CN214117507U (en) Convenient ring beam template system is dismantled in installation
CN114541809A (en) Supporting system for building structure pouring and construction process
CN113090013A (en) Construction method for simultaneously constructing deformation joint shear wall without supporting wood formwork
KR20030040687A (en) panel for external underground wall of building, structure and construction method using the same
JPH0657710A (en) Construction of concrete main tower
AU2005287894B2 (en) Method and apparatus for construction
CN218148907U (en) Full-assembly full-turnover assembly type building capable of being built quickly
CN212316990U (en) Lining wall template structure in circular shaft of ultradeep
CN215519925U (en) Arc shear force wall pouring template system
JP7389634B2 (en) Building construction method
CN212957182U (en) Assembled anti-cracking and disassembly-free template, floor bearing plate and cast-in-place construction and disassembly-free floor
JP2797023B2 (en) Construction method of beam
JPH1121860A (en) Construction method for wall-form concrete structure
KR100607904B1 (en) Hanging type formwork for non-supporting formwork system for top down construction and concrete structure construction method using the same
CN115822313A (en) Brick wall reinforcing structure and manufacturing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination