CN115288175A - Gallery pouring method in steel shell concrete immersed tube section - Google Patents

Gallery pouring method in steel shell concrete immersed tube section Download PDF

Info

Publication number
CN115288175A
CN115288175A CN202211012384.XA CN202211012384A CN115288175A CN 115288175 A CN115288175 A CN 115288175A CN 202211012384 A CN202211012384 A CN 202211012384A CN 115288175 A CN115288175 A CN 115288175A
Authority
CN
China
Prior art keywords
pouring
pump
pump pipe
gallery
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211012384.XA
Other languages
Chinese (zh)
Other versions
CN115288175B (en
Inventor
张文森
王晓东
杨洋
邓懋新
吴宇恒
安凌志
林伟才
邓军
邓世民
薛力源
陈远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Harbor Engineering Co Ltd
No 2 Engineering Co of CCCC Fourth Harbor Engineering Co Ltd
Original Assignee
CCCC Fourth Harbor Engineering Co Ltd
No 2 Engineering Co of CCCC Fourth Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Harbor Engineering Co Ltd, No 2 Engineering Co of CCCC Fourth Harbor Engineering Co Ltd filed Critical CCCC Fourth Harbor Engineering Co Ltd
Priority to CN202211012384.XA priority Critical patent/CN115288175B/en
Publication of CN115288175A publication Critical patent/CN115288175A/en
Application granted granted Critical
Publication of CN115288175B publication Critical patent/CN115288175B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to the field of submarine immersed tubes, in particular to a method for pouring a gallery in a steel shell concrete immersed tube section, which performs skip pouring along the longitudinal two ends of the gallery towards the middle through two pouring machines and comprises the following steps: s1, separating a connecting part between a pouring machine and a pump pipe after two bin lattices are poured; s2, moving the pouring machine to the next pouring station; s3, adding a pump pipe segment between the pouring machine and the pump pipe; s4, after the two pouring machines meet and complete the longitudinal middle bin lattice pouring of the middle gallery, cleaning the pump pipe, separating the connecting part between the pouring machines and the pump pipe, and withdrawing the two pouring machines to corresponding outlet positions respectively; s5, disassembling the pump pipe to form a plurality of pump pipe sections; and S6, the two pouring machines jump the bins again for pouring, and the steps S1-S5 are repeated to finish pouring of all bins of the bottom plate of the middle gallery and recycle all pump pipe segments. The pouring mode of connecting pipes and moving the machine is formed, concrete waste generated by moving the machine and the times of cleaning the pump pipes can be reduced, the construction cost is saved, and the construction period is shortened.

Description

Gallery pouring method in steel shell concrete immersed tube section
Technical Field
The invention relates to the field of submarine immersed pipes, in particular to a gallery pouring method in a steel shell concrete immersed pipe joint.
Background
The steel-shell concrete immersed tube adopts pours self-compaction concrete shaping in steel-shell storehouse check, current steel-shell concrete immersed tube generally has left piping lane, right piping lane and is located the well piping lane between the left and right piping lane, well piping lane is also known as well corridor, its width is littleer about than the piping lane, the laying of auxiliary facilities such as mainly used pipe, line is walked, well corridor bottom plate vertically sets up two rows of storehouse check, every row includes a plurality of independent storehouse check, every storehouse check corresponds and sets up pours the mouth.
The existing immersed tube pipe section bottom plate bin lattice pouring is uniformly carried out in a mode that every row of bin lattices jump a bin and adjacent rows of bin lattices are poured in a staggered mode, in the pouring process, a towing pump is located outside the longitudinal end portion of an immersed tube pipe section and used for receiving concrete conveyed by a concrete tank truck, the towing pump is communicated with a pouring machine through a pump pipe, a gallery is located in the middle of the longitudinal portion of the gallery in the pouring machine in the first pouring process, the two ends of the gallery are poured behind the two ends of the gallery in the length direction, in the pouring process, the pouring machine needs to be moved once every time two bin lattices are poured, as shown in figure 7, the pouring machine moves towards the two ends from the middle of the longitudinal middle of the gallery, at the moment, the pump pipe between the towing pump and the pouring machine is filled with concrete, when the machine is moved, partial pump pipes need to be removed, the removed pump pipe sections are recycling structural members, and in order to avoid pipe blockage caused by time difference when the removed pump pipe sections are used next time, the removed pump pipe sections need to be manually lifted to be cleaned, so that the pump pipe sections are cleaned, and the construction efficiency is low and a lot of concrete is wasted.
Therefore, a technical scheme is urgently needed at present to solve the technical problems that in the existing immersed tube pipe section, a gallery is poured and is detached and moved, the number of times of cleaning a pump pipe is large, the construction efficiency is low, and concrete waste is caused.
Disclosure of Invention
The invention aims to: the method for pouring the gallery in the steel shell concrete immersed tube section is provided aiming at the technical problems that the gallery pouring in the existing immersed tube section adopts a tube dismantling and moving machine, the times of cleaning a pump tube are more, the construction efficiency is low and concrete waste is caused.
In order to achieve the purpose, the invention adopts the technical scheme that:
a gallery pouring method in a steel shell concrete immersed tube pipe section carries out skip pouring along the longitudinal two ends of a gallery towards the middle through two pouring machines and comprises the following steps: s1, separating a connecting part between a pouring machine and a pump pipe after two bin lattices are poured; s2, moving the pouring machine to the next pouring station; s3, adding a pump pipe segment between the pouring machine and the pump pipe; s4, after the two pouring machines meet and complete pouring of the longitudinal middle bin grid of the middle gallery, cleaning the pump pipe, separating the connecting part between the pouring machines and the pump pipe, and moving the two pouring machines back to corresponding outlet positions respectively; s5, disassembling the pump pipe to form a plurality of pump pipe sections; and S6, performing skip pouring by the two pouring machines along the longitudinal two ends of the middle gallery towards the middle again, and circulating S1-S5 to finish pouring of all bin lattices of the bottom plate of the middle gallery and recycle of all pump pipe segments.
According to the gallery pouring method in the steel shell concrete immersed tube section, the two pouring machines move oppositely to carry out skip bin pouring, the pouring machines separate the connecting parts between the pouring machines and the pump pipes when the stations are switched, the pump pipe sections are increased at a new station to form a pouring mode of taking over and moving the machines, concrete waste generated by moving the machines and the times of cleaning the pump pipes can be reduced, the construction cost is saved, the economic benefit is improved, the number of the pouring bin grids of the two pouring machines can be adjusted in real time according to actual conditions, the overall construction period of a gallery in the steel shell concrete immersed tube section is shortened, and the construction progress is accelerated.
As a preferable scheme of the invention, the pouring machine station is positioned at the intersection point of the bin lattices in the adjacent rows for pouring, and the pouring of the two bin lattices positioned at the diagonal positions is completed at each pouring station. The pouring machine finishes pouring of two bin lattices in opposite angle positions at one station, so that the stress of the whole immersed tube joint is balanced, and the deformation is reduced.
As a preferable scheme of the invention, two casting machines are cast in mirror images at the casting station. The gallery is longitudinally and symmetrically poured, the integral stress of the immersed tube pipe joint is further balanced, the deformation is reduced, and meanwhile, when two pouring machines meet, the skip bin pouring can be continuously kept.
In a preferred embodiment of the present invention, in S1, the connection portion between the casting machine and the pump pipe includes a detachable connection through a clamp structure. The pump pipe segment can be disassembled and connected quickly, the machine moving time is shortened, and the machine moving efficiency is improved.
In a preferred embodiment of the present invention, a connection portion is disposed at an end of the pump tube segment, and the clamp structure is provided with a sealing ring engaged with the connection portion. So that the connection between the pump pipe sections is tight.
In a preferable embodiment of the present invention, in S3, the length of the pump pipe segment is equal to the distance between the adjacent bin pouring openings. The length of the pump pipe sections is adapted to the length of the moving machine, and the number of the pump pipe sections is reduced.
In a preferred embodiment of the present invention, in S3, the pump tube segment is pre-wetted by immersion or inner wall sprinkling. The friction between the concrete and the inner wall of the pump pipe can be reduced, the pipe blocking probability of a newly-connected pump pipe section is reduced, and smooth pouring of all stations is guaranteed.
In S4, a sponge ball is placed into an outlet-end pipe opening of the pouring machine, the sponge ball is pushed to move by introducing gas, concrete in the pump pipe is pushed to move towards the side of the trailer pump until the sponge ball is output from the trailer pump, and the inner wall of the pump pipe is cleaned. The pump pipe is disassembled after being cleaned integrally, and the disassembling process is favorably and smoothly carried out.
As a preferable scheme of the present invention, in S5, the disassembling includes in-situ disassembling, where in the in-situ disassembling is to separate a connection portion between adjacent pump pipe segments without moving the pump pipe, place the pump pipe segment in a disassembly position in situ, and wait for reconnection with a casting machine. The handling of pump line segment section is reduced, shortens and moves quick-witted whole time.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
1. by forming a pouring mode of connecting pipes and moving the machine, concrete waste generated by moving the machine and the times of cleaning the pump pipes can be reduced, the construction cost is saved, and the economic benefit is improved;
2. the two pouring machines pour from two ends to the middle, the number of the respective pouring bin lattices of the two pouring machines can be adjusted in real time according to actual conditions, the overall construction period of the middle gallery is shortened, and the construction progress is accelerated;
3. the newly-connected pump pipe segment is wetted in advance, so that friction between concrete and the inner wall of the pump pipe can be reduced, the pipe blocking probability of the newly-connected pump pipe segment is reduced, and smooth pouring of all stations is guaranteed.
Drawings
FIG. 1 is a first schematic plan view of a gallery-cast warehouse of the present embodiment;
FIG. 2 is a schematic plan view of a second gallery compartment for gallery pouring in the present embodiment;
fig. 3 is a schematic plan view of a third cabin poured by a gallery in the embodiment;
fig. 4 is a schematic plan view of a gallery pouring bin in the present embodiment;
FIG. 5 is a schematic structural diagram of the storage compartment and the pump tube in the present embodiment;
FIG. 6 is an enlarged view of a portion A of FIG. 5;
FIG. 7 is a schematic view of a prior art casting machine moving from the longitudinal middle of the center gallery to both ends;
fig. 8 is a schematic view of the present invention casting machine moving from the longitudinal ends of the center gallery to the middle.
Icon:
1-middle gallery, 11-bin lattice, 12-pouring opening, 2-pouring station, 3-pump pipe, 31-pump pipe segment, 32-connecting part, 4-hoop structure and 5-pouring machine.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1
In the method for pouring the gallery in the steel shell concrete immersed tube section, as shown in fig. 1-4, a bottom plate of the gallery 1 is in a checkerboard form to form two rows of bins 11, and a pouring machine 5 stands at the intersection point of the bins 11 in the adjacent rows and finishes pouring of the two bins 11 in the diagonal position at each pouring station 2.
As shown in fig. 1-4 and 8, in the method for pouring the gallery in the steel-shell concrete immersed tube section according to the embodiment, two pouring machines 5 are used for performing skip pouring along the longitudinal two ends of the gallery 1 toward the middle, and the two pouring machines 5 are poured in a mirror image manner at the pouring station 2, so that the immersed tube section is subjected to balanced stress integrally and deformation is reduced.
Further, the method for pouring the gallery in the steel shell concrete immersed tube section comprises the following steps: pouring is started from the longitudinal two ends of the middle gallery 1, and when the pouring of the pouring machine 5 is finished, two bin lattices 11 are separated from the connecting part between the pipe orifice at the inlet end of the pouring machine 5 and the pump pipe 3; moving the casting machine 5 into the middle gallery 1 to a next casting station 2; adding a pump pipe segment 31 between the pouring machine 5 and the pump pipe 3; after the two casting machines 5 meet and complete casting of the middle gallery 1 longitudinal middle bin 11, the pump pipe 4 is cleaned, the connecting part between the inlet end pipe opening of the casting machine and the pump pipe 3 is separated, the two casting machines 5 move back to the corresponding outlet positions respectively, the pump pipe 3 is disassembled to form a plurality of pump pipe sections 31, the two casting machines 5 perform skip bin casting of the rest bin from the two longitudinal ends of the middle gallery 1 to the middle again until meeting again, casting of all the bins 11 of the middle gallery 1 bottom plate is completed, and after cleaning, separation and disassembly of the pump pipe 3, the pump pipe sections 31 are recovered, so that a complete casting mode of symmetrical casting and taking over of the middle gallery of the steel shell concrete immersed pipe section is formed.
Specifically, as shown in fig. 1, two casting machines 5 start casting from two longitudinal ends of the middle gallery 1 until the two casting machines 5 meet in the middle gallery 1 for the first time as shown in fig. 2, at this time, if a middle single cast-free bin lattice 11 as shown in fig. 2 appears, according to actual conditions, any one casting machine 5 is adopted to continuously move forward one station to complete the casting of the single cast-free bin lattice 11; and then, the two casting machines 5 return to the outlet positions at the two ends of the middle corridor 1 respectively, as shown in fig. 3, the two casting machines 5 continue to perform casting on the rest of the bins 11 until the two casting machines meet each other again as shown in fig. 4, and the casting of all the bins 11 is completed in the same manner.
Specifically, the connection position between the casting machine 5 and the pump pipe 3 is detachably connected through the hoop structure 4, so that the pump pipe segment 31 is quickly disassembled and connected, the machine moving time is shortened, the machine moving efficiency is improved, as shown in fig. 6, the end part of the pump pipe segment 31 is provided with the connecting part 32 with the outer annular groove, the inner ring of the hoop structure 4 is provided with the sealing ring matched with the connecting part 32, and when the quick pipe connecting device is used, the quick tight connection or quick separation of the hoop structure 4 and the pump pipe segment 31 is realized through adjusting the fastening bolt on the hoop structure 4, the pipe connecting time is shortened, and the machine moving time is shortened.
It should be noted that, in the process of moving the pipe joint, in this embodiment, by separating the connection between the bottom elbow (i.e. the inlet end pipe orifice) of the pouring machine 5 and the pump pipe 3, one end of the newly-inserted pump pipe segment 31 is connected to the pump pipe 3, and the other end of the newly-inserted pump pipe segment is connected to the bottom elbow of the pouring machine 5, the air segment inside the newly-inserted pump pipe segment 31 is close to the pouring machine 5, is close to the pouring opening 12 of the bin lattice 11, and is located in front of the concrete in the pump pipe 3, and the air segment can be discharged from the bin lattice 11 in advance by adjusting the pumping speed of the concrete, so as to avoid the air segment from affecting the pouring quality of the bin lattice 11.
Further, in order to reduce the friction between the concrete and the inner wall of the pump pipe 3 and reduce the pipe blocking probability of the newly-connected pump pipe segment 31 and ensure the smooth pouring of each station, the inner wall of the newly-connected pump pipe segment 31 is sprayed with water in advance for wetting.
According to the gallery pouring method in the steel shell concrete immersed tube section, two pouring machines 5 move oppositely to carry out skip bin pouring, the pouring machines 5 separate the connecting parts between the inlet end pipe orifices of the pouring machines 5 and the pump tubes 3 when the pouring stations 2 are switched, the pump tube sections 31 are increased at the new pouring stations 2 to form a pouring mode of taking over and moving the pouring machines, no concrete is left in the pump tube sections 31 when the pouring machines 5 are newly connected, concrete waste generated by moving the machines can be reduced, meanwhile, the pump tubes 3 are integrally cleaned after pouring is completed, compared with the prior art that the pump tube sections 31 need to be lifted and cleaned once when the pouring machines 5 move one station, the cleaning frequency is changed from multiple times to one time, the cleaning frequency is obviously reduced, the construction efficiency is improved, the construction cost is saved, the economic benefit is improved, the number of the pouring bin grids 11 of the two pouring machines 5 can be adjusted in real time according to actual conditions, the integral construction period of the gallery is shortened, and the construction progress is accelerated.
Preferably, 3 washing of pump line are for before 3 disassembles of pump line, put into the sponge ball at 5 exit end mouths of pipe of pouring machine, promote the sponge ball through leading-in gas and remove, promote concrete in 3 interior pump lines and to draging the pump side and remove, until the sponge ball is exported from the draging the pump, realize that 3 inner walls of pump line wash.
Preferably, before meeting for the second time after two casting machines 5 meet for the first time, pump line 3 is disassembled including the normal position is disassembled, the normal position is disassembled for under the unmovable pump line circumstances, separates the position of connection between the adjacent pump line segment 31, puts pump line segment 31 normal position in the position of disassembling, waits for and pours 5 reconnection, when making two casting machines 5 jump the storehouse for the second time and pour, still reduced the step of pump line 3 transport for the first time jumps the storehouse and pours, whole construction time is shorter, improves the whole efficiency of construction of immersed tube coupling.
The above description is intended to be illustrative of the preferred embodiment of the present invention and should not be taken as limiting the invention, but rather, the intention is to cover all modifications, equivalents, and alternatives falling within the spirit and scope of the invention.

Claims (9)

1. The method for pouring the gallery in the steel shell concrete immersed tube pipe joint is characterized in that two pouring machines (5) are used for performing skip pouring towards the middle along the longitudinal two ends of the gallery (1), and the method comprises the following steps:
s1, separating a connecting part between a pouring machine (5) and a pump pipe (3) when two bin lattices (11) are poured;
s2, moving the pouring machine (5) to the next pouring station (2);
s3, adding a pump pipe segment (31) between the pouring machine (5) and the pump pipe (3);
s4, after the two pouring machines (5) meet and pouring of the longitudinal middle bin grid (11) of the middle gallery (1) is completed, the pump pipe (3) is cleaned, the connecting part between the pouring machines (5) and the pump pipe (3) is separated, and the two pouring machines (5) are respectively withdrawn to corresponding outlet positions;
s5, disassembling the pump pipe (3) to form a plurality of pump pipe sections (31);
and S6, performing skip pouring by the two pouring machines (5) towards the middle along the longitudinal two ends of the middle gallery (1) again, and circulating S1-S5 to finish pouring of all bin lattices (11) of the bottom plate of the middle gallery (1) and recover all pump pipe sections (31).
2. A method of corridor casting in a steel shell concrete immersed tube section according to claim 1, characterised in that the casting machine (5) is located at the intersection of the bin grids (11) of adjacent rows for casting, and the casting of two bin grids (11) located at diagonal positions is completed at each casting station (2).
3. A method of corridor casting in a steel shell concrete caisson according to claim 1, characterised in that two casting machines (5) are cast in mirror image at the casting station.
4. A method of galley casting in a steel shell concrete caisson according to claim 1, characterised in that in S1 the connection between the casting machine (5) and the pump pipe (3) comprises a detachable connection by means of a clip structure (4).
5. A method of corridor casting in a steel shell concrete sinking pipe section according to claim 4, characterised in that the pump pipe section (31) is provided with a connection portion (32) at its end, and the clamp structure (4) is provided with a sealing ring cooperating with the connection portion (32).
6. A method of gallery pouring in a steel shell concrete sinking pipe section according to claim 1, characterised in that in S3 the length of the pump pipe section (31) is equal to the distance between the pouring openings (12) of the adjacent cells (11).
7. The method for pouring the gallery in the steel shell concrete immersed tube section according to claim 1, wherein in S3, the pump tube section (31) is pre-wetted by soaking water or spraying water on the inner wall.
8. The gallery pouring method in the pipe section of the steel shell concrete immersed pipe according to the claim 1 is characterized in that in S4, the cleaning comprises the steps of placing a sponge ball in a pipe opening at the outlet end of the pouring machine (5), pushing the sponge ball to move by introducing gas, pushing the concrete in the pump pipe (3) to move towards the side of the trailer pump until the sponge ball is output from the trailer pump, and cleaning the inner wall of the pump pipe (3).
9. The method for pouring the gallery in the steel shell concrete immersed tube section as claimed in claim 1, wherein in S5, the disassembling comprises in-situ disassembling, wherein the in-situ disassembling is to separate the connecting parts between the adjacent pump tube sections (31) without moving the pump tube (3), and the pump tube sections (31) are placed in situ in the disassembling position to wait for being connected with the pouring machine (5) again.
CN202211012384.XA 2022-08-23 2022-08-23 Pouring method for gallery in steel shell concrete immersed tube joint Active CN115288175B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211012384.XA CN115288175B (en) 2022-08-23 2022-08-23 Pouring method for gallery in steel shell concrete immersed tube joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211012384.XA CN115288175B (en) 2022-08-23 2022-08-23 Pouring method for gallery in steel shell concrete immersed tube joint

Publications (2)

Publication Number Publication Date
CN115288175A true CN115288175A (en) 2022-11-04
CN115288175B CN115288175B (en) 2023-08-29

Family

ID=83831383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211012384.XA Active CN115288175B (en) 2022-08-23 2022-08-23 Pouring method for gallery in steel shell concrete immersed tube joint

Country Status (1)

Country Link
CN (1) CN115288175B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204491619U (en) * 2015-01-28 2015-07-22 中国葛洲坝集团第六工程有限公司 A kind of overlength inclined shaft concrete conveyance slow descending device
CN108763616A (en) * 2018-03-30 2018-11-06 北京城建集团有限责任公司 Temperature field analysis method and apparatus based on the building for jumping the construction of storehouse method
CN110479708A (en) * 2019-09-19 2019-11-22 广东腾越建筑工程有限公司 A kind of novel air purge pump line technology cleaning device and its cleaning process
CN112796790A (en) * 2020-12-29 2021-05-14 中交第四航务工程局有限公司 Immersed tube tunnel concrete pouring system and method
CN113998958A (en) * 2021-12-08 2022-02-01 中国华西企业股份有限公司 Concrete and ground jumping construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204491619U (en) * 2015-01-28 2015-07-22 中国葛洲坝集团第六工程有限公司 A kind of overlength inclined shaft concrete conveyance slow descending device
CN108763616A (en) * 2018-03-30 2018-11-06 北京城建集团有限责任公司 Temperature field analysis method and apparatus based on the building for jumping the construction of storehouse method
CN110479708A (en) * 2019-09-19 2019-11-22 广东腾越建筑工程有限公司 A kind of novel air purge pump line technology cleaning device and its cleaning process
CN112796790A (en) * 2020-12-29 2021-05-14 中交第四航务工程局有限公司 Immersed tube tunnel concrete pouring system and method
CN113998958A (en) * 2021-12-08 2022-02-01 中国华西企业股份有限公司 Concrete and ground jumping construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
彭英俊等: "深圳至中山跨江通道钢壳沉管施工关键技术", 《武汉理工大学学报》 *

Also Published As

Publication number Publication date
CN115288175B (en) 2023-08-29

Similar Documents

Publication Publication Date Title
CN109352815A (en) Line is deposited in a kind of prefabricated components production line and the production with the prefabricated components production line
CN108149706A (en) A kind of cast-in-place hidden girder and the prefabricated assembled pipe gallery and its construction method of superimposed sheet splicing
CN111231099B (en) Self-compacting concrete pouring method for steel shell concrete immersed tube segment
CN115288175A (en) Gallery pouring method in steel shell concrete immersed tube section
CN104708708A (en) Shield tunnel segment prefabrication method
CN102071953A (en) Method for casting surrounding concrete of lined steel pipe of shield tunnel
CN104786367A (en) Pipe joint prefabricating workshop
CN209408872U (en) A kind of prefabricated components production line
CN107377275A (en) A kind of air-entrained concrete building block production line mould sprays integrated device
CN103692550B (en) A kind of casting method of seabed tunnel immersed tube
CN206086656U (en) Carwash pond
CN215618940U (en) Precast concrete component system of processing
CN115680023A (en) Construction method and design method for steel shell concrete immersed tube pouring
CN110154225B (en) Production method of automatic production line for tubular piles
CN213645390U (en) Steel billet dephosphorization mechanism
CN102287003A (en) Dam concrete cabin surface water accumulation hidden pipe discharge method
CN202896532U (en) Detachable vehicle washing table in engineering construction sites
CN210820156U (en) Concrete prefabricated part production system
CN208375559U (en) Concrete prefabricated element production unit and production line
CN213034912U (en) Concrete pile production system
CN204266125U (en) A kind of device for shifting cast-in-situ box girder ground pump pump line waste water above railway
CN114562224B (en) Pile group foundation slurry circulation purifying system and construction method thereof
CN213593219U (en) PCCP tube core concrete pumping type pouring production line
CN218003193U (en) Manage and use building outer wall infiltration testing arrangement
CN216470076U (en) Construction rubbish transfer car (buggy)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant