CN115234009A - Construction method of integral hoisting system of grid unit truss - Google Patents

Construction method of integral hoisting system of grid unit truss Download PDF

Info

Publication number
CN115234009A
CN115234009A CN202211076728.3A CN202211076728A CN115234009A CN 115234009 A CN115234009 A CN 115234009A CN 202211076728 A CN202211076728 A CN 202211076728A CN 115234009 A CN115234009 A CN 115234009A
Authority
CN
China
Prior art keywords
grid unit
unit truss
hoisting
construction
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211076728.3A
Other languages
Chinese (zh)
Inventor
蒋福生
岳杰
李欢欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202211076728.3A priority Critical patent/CN115234009A/en
Publication of CN115234009A publication Critical patent/CN115234009A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/142Means in or on the elements for connecting same to handling apparatus

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a construction method of a grid unit truss integral hoisting system, and relates to the technical field of constructional engineering. The construction method of the grid unit truss integral hoisting system comprises the following specific operations: s1, configuring grid unit truss materials with corresponding sizes according to the requirements of design drawings, prefabricating a grid unit truss structure in a segmented mode through factory, and delivering the grid unit truss structure to a construction site after the grid unit truss structure is qualified through inspection. The construction method of the integral hoisting system of the grid unit truss is mainly applied to the development and introduction of a roof support system of a steel structure factory building. In the installation process, a mode of synchronously hoisting the integral structure system of the grid unit truss and the main frame beam structure is adopted, and construction processes such as connection of the grid unit truss and the main frame beam structure are completed on the ground, so that the overhead working time of the process is reduced, the construction process is improved to a greater extent, and the construction safety is further improved.

Description

Construction method of integral hoisting system of grid unit truss
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a construction method of an integral hoisting system of a grid unit truss.
Background
The traditional roof support system construction is usually carried out by adopting an overhead splicing or welding mode, the hoisting operation is high in danger, the labor intensity is high, the requirements on the quality, the constitution, the technology and the like of operating personnel are high, the overhead operation time is long, and the potential safety hazard is large.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a construction method of an integral hoisting system of a grid unit truss, which solves the problems that the construction of the traditional roof support system is generally carried out in a high-altitude splicing or welding mode, the hoisting operation is high in danger and labor intensity, the requirements on the quality, constitution, technology and the like of operating personnel are high, the high-altitude operation time is long, and the potential safety hazard is large.
(II) technical scheme
In order to realize the purpose, the invention is realized by the following technical scheme: a construction method for a grid unit truss integral hoisting system comprises the following specific operations:
s1, configuring grid unit truss materials with corresponding sizes according to the requirements of design drawings, prefabricating a grid unit truss structure in a segmented mode through factory, and delivering the grid unit truss structure to a construction site after the grid unit truss structure is qualified through inspection;
s2, hoisting the structural beam and the grid unit truss structure to corresponding positions in a segmented manner according to a construction drawing, and assembling the grid unit truss structure into a grid unit truss finished product on the ground of the site in a segmented manner;
s3, determining the connection position of the grid unit truss, and sequentially connecting the grid unit truss with an H-shaped steel structural beam through a connecting piece, a high-strength bolt, a connecting plate and a short column support, wherein the high-strength bolt is in threaded connection with the connecting plate, and the connecting piece, the connecting plate and the short column support are all in welded connection;
s4, completing the process through one connection point, and repeating other connection points according to the method;
s5, after detail processing such as polishing, rust prevention, corrosion prevention and the like, checking and accepting;
s6, after the acceptance is qualified, hoisting by adopting a double-machine synchronous hoisting method, wherein the double-machine synchronous hoisting method comprises the following steps: two cranes are adopted to simultaneously lift the grid unit truss integral structure system;
s7, before the hoisting connector is installed, the internal bolt device is placed in place, the steel wire rope is placed in the rope threading track, the steel wire rope is exposed after two ends of the steel wire rope are connected through rope braking control, the steel wire rope penetrates out through the balance limiting device and is sequentially connected in place, wherein the rope threading track and the rope braking control are linked with the steel wire rope, a set of variable frequency speed regulation test system is adopted, the trigger speed detection in an idle load state can be completed, the hoisting connector and the balance limiting device are connected into a whole to facilitate the overall balance, and the number of the balance limiting device can be increased according to the actual hoisting requirement;
s8, trial debugging, namely checking the connection condition of each part in the cable, the braking control efficiency of the cable and the overall operation condition to ensure limited use;
s9, installing a hoisting connector corresponding to the position of equipment according to different hoisting equipment;
s10, hoisting the light grid unit truss member, adjusting the balance limiting device, and checking the hoisting, braking and connecting conditions again;
s11, formally hoisting, wherein when the hoisting grid unit truss member is large, the lower part of the steel wire rope can be connected with a tray base;
s12, after the grid unit truss integral structure system is firmly fixed, the steel wire rope is put down, the hanging ring is detached, and the hanging is finished.
(III) advantageous effects
The invention provides a construction method of an integral hoisting system of a grid unit truss. The method has the following beneficial effects:
the construction method of the integral hoisting system of the grid unit truss is mainly applied to the development introduction of a roof supporting system of a steel structure factory building. In the installation process, the mode of synchronously hoisting the grid unit truss integral structure system and the main body frame beam structure is adopted, the construction processes such as connection of the grid unit truss and the main body frame beam structure and the like are all completed on the ground, the overhead working time of the process is reduced, the construction process is improved to a greater extent, and the construction safety is further improved. The connection quality of the structural surface is effectively improved in the process, the quality control in the construction process is facilitated, the integral connection accuracy is improved, and the method is safe and reliable, and is beneficial to batch construction and standardized application.
Drawings
FIG. 1 is a schematic diagram of a connection node of a construction method of a grid unit truss integral hoisting system;
FIG. 2 is a connection front view of a construction method of an integral grid unit truss hoisting system;
fig. 3 is a schematic diagram of a hoisting node by a double-machine synchronous lifting method.
In the figure: 1 grid unit truss, 2 connecting pieces, 3 high-strength bolts, 4 connecting plates, 5 short column supports, 6H-shaped steel, 7 hoisting connectors, 8 bolt devices, 9 threading rails, 10 rope brake controls, 11 balance limiting devices and 12 steel wire ropes.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a construction method for a grid unit truss integral hoisting system comprises the following specific operations:
s1, configuring grid unit truss materials with corresponding sizes according to the requirements of design drawings, prefabricating a grid unit truss structure in a segmented mode through factory, and delivering the grid unit truss structure to a construction site after the grid unit truss structure is qualified through inspection;
s2, hoisting the structural beam and the grid unit truss structure to corresponding positions in a segmented manner according to a construction drawing, and assembling the grid unit truss structure into a grid unit truss 1 finished product on the ground of the site in a segmented manner;
s3, determining the connecting position of the grid unit truss 1, and sequentially connecting the grid unit truss 1 with an H-shaped steel 6 structural steel beam through a connecting piece 2, a high-strength bolt 3, a connecting plate 4 and a short column support 5, wherein the high-strength bolt 3 is in threaded connection with the connecting plate 4, and the connecting piece 2, the connecting plate 4 and the short column support 5 are all in welded connection;
s4, completing the process through one connection point, and repeating other connection points according to the method;
s5, after detail treatment such as polishing, rust prevention, corrosion prevention and the like, checking and accepting;
s6, after the acceptance is qualified, hoisting by adopting a double-machine synchronous hoisting method, wherein the double-machine synchronous hoisting method comprises the following steps: two cranes are adopted to simultaneously lift the grid unit truss integral structure system;
s7, before the hoisting connector 7 is installed, the internal bolt device 8 is placed in place, the steel wire rope 12 is placed in the rope threading track 9, the steel wire rope 12 is exposed after two ends of the steel wire rope are connected through the rope brake control 10, the steel wire rope 12 penetrates out through the balance limiting device 11 and is sequentially connected in place, wherein the rope threading track 9 and the rope brake control 10 are linked with the steel wire rope 12, a set of variable frequency speed regulation test system is adopted, the trigger speed detection in an idle state can be completed, the safety braking or deceleration function is realized when the load is over-speed, the hoisting connector 7 and the balance limiting device 11 are connected into a whole, the overall balance is facilitated, and the number of the balance limiting devices 11 can be increased according to the actual hoisting requirement;
s8, debugging in a trial mode, and checking the connection condition of each part in the rope brake control system, the efficiency of the rope brake control system 10 and the overall operation condition to ensure limited use;
s9, installing a hoisting connector 7 corresponding to the position of equipment according to different hoisting equipment;
s10, hoisting the components of the light grid unit truss 1, adjusting the balance limiting device 11, and checking the hoisting, braking and connecting conditions again;
s11, formally hoisting, wherein when the hoisting grid unit truss 1 is large, the lower part of the steel wire rope 12 can be connected with a tray base;
s12, after the grid unit truss integral structure system is firmly fixed, the steel wire rope is put down, the hanging ring is detached, and the hoisting is finished.
In conclusion, the construction method of the grid unit truss integral hoisting system can effectively improve the connection quality of the structural surface, is beneficial to quality control in the construction process, improves the integral connection accuracy, is safe and reliable, and is beneficial to batch construction and standardized application. The construction method of the grid unit truss integral hoisting system is realized as follows: the construction method of the integral hoisting system of the grid unit truss is characterized in that all connection procedures of the grid unit truss and a main body beam are completed on the ground, the overhead working time of the procedures is reduced, the construction process is improved to a greater extent, and the construction safety is further improved. The connection quality of the structural surface is effectively improved in the process, the quality control in the construction process is facilitated, the integral connection accuracy is improved, and the method is safe, reliable, convenient to operate and high in practicability.
The construction method of the integral hoisting system of the grid unit truss is mainly applied to the development and introduction of a roof support system of a steel structure factory building. In the installation process, the mode of synchronously hoisting the grid unit truss integral structure system and the main body frame beam structure is adopted, the construction processes such as connection of the grid unit truss and the main body frame beam structure and the like are all completed on the ground, the overhead working time of the process is reduced, the construction process is improved to a greater extent, and the construction safety is further improved. The connection quality of the structural surface is effectively improved in the process, the quality control in the construction process is facilitated, the integral connection accuracy is improved, and the method is safe and reliable, and is beneficial to batch construction and standardized application.
It should be noted that, in this document, relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (1)

1. A construction method of a grid unit truss integral hoisting system is characterized by comprising the following steps: the specific operation is as follows:
s1, configuring grid unit truss materials with corresponding sizes according to the requirements of a design drawing, segmenting through an industrial prefabricated grid unit truss structure, and delivering the grid unit truss materials to a construction site after the grid unit truss structure is inspected to be qualified;
s2, hoisting the structural beam and the grid unit truss structure to corresponding positions in a segmented manner according to a construction drawing, and assembling the grid unit truss structure into a grid unit truss (1) finished product on the ground of the site in a segmented manner;
s3, determining the connection position of the grid unit truss (1), and sequentially connecting the grid unit truss with a structural steel beam of H-shaped steel (6) through a connecting piece (2), a high-strength bolt (3), a connecting plate (4) and a short column support (5), wherein the high-strength bolt (3) is in threaded connection with the connecting plate (4), and the connecting piece (2), the connecting plate (4) and the short column support (5) are in welded connection;
s4, completing the process through one connection point, and repeating other connection points according to the method;
s5, after detail processing such as polishing, rust prevention, corrosion prevention and the like, checking and accepting;
s6, after the acceptance is qualified, hoisting by adopting a double-machine synchronous hoisting method, wherein the double-machine synchronous hoisting method comprises the following steps: two cranes are adopted to simultaneously lift the grid unit truss integral structure system;
s7, before the hoisting connector (7) is installed, the internal bolt device (8) is placed in place, the steel wire rope (12) is placed in the rope threading track (9), two ends of the rope threading track are connected through the rope braking control device (10), the steel wire rope (12) is exposed, the steel wire rope (12) penetrates out through the balance limiting device (11), and the balance limiting device (11) and the steel wire rope (12) are sequentially connected in place, wherein the rope threading track (9) and the rope braking control device (10) are linked with each other, a set of variable frequency speed regulation test system is adopted, the triggering speed detection in an idle state can be completed, the safety braking or deceleration function is realized when the load exceeds the speed, the hoisting connector (7) and the balance limiting device (11) are connected into a whole, the overall balance is facilitated, and the number of the balance limiting device (11) can be increased according to the actual hoisting requirement;
s8, debugging in a trial mode, and checking the connection condition of each part in the rope brake control device, the efficiency of the rope brake control device (10) and the overall operation condition to ensure limited use;
s9, installing a hoisting connector (7) corresponding to the position of equipment according to different hoisting equipment;
s10, hoisting a light grid unit truss (1) component, adjusting a balance limiting device (11), and checking hoisting, braking and connecting conditions again;
s11, formally hoisting, wherein when the hoisting grid unit truss (1) member is large, the lower part of the steel wire rope (12) can be connected with a tray base;
s12, after the grid unit truss integral structure system is firmly fixed, the steel wire rope is put down, the hanging ring is detached, and the hanging is finished.
CN202211076728.3A 2022-09-05 2022-09-05 Construction method of integral hoisting system of grid unit truss Pending CN115234009A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211076728.3A CN115234009A (en) 2022-09-05 2022-09-05 Construction method of integral hoisting system of grid unit truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211076728.3A CN115234009A (en) 2022-09-05 2022-09-05 Construction method of integral hoisting system of grid unit truss

Publications (1)

Publication Number Publication Date
CN115234009A true CN115234009A (en) 2022-10-25

Family

ID=83681565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211076728.3A Pending CN115234009A (en) 2022-09-05 2022-09-05 Construction method of integral hoisting system of grid unit truss

Country Status (1)

Country Link
CN (1) CN115234009A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107285200A (en) * 2017-07-05 2017-10-24 中国十七冶集团有限公司 A kind of high large-span truss integral translation construction method for hanging
CN114673364A (en) * 2022-03-17 2022-06-28 中国十七冶集团有限公司 Method for installing pipeline by using hollow structure of European truss

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107285200A (en) * 2017-07-05 2017-10-24 中国十七冶集团有限公司 A kind of high large-span truss integral translation construction method for hanging
CN114673364A (en) * 2022-03-17 2022-06-28 中国十七冶集团有限公司 Method for installing pipeline by using hollow structure of European truss

Similar Documents

Publication Publication Date Title
CN106437178B (en) A kind of multi-storey steel structure vestibule construction method for lifting whole and device
CN105443871B (en) A kind of new suspension and support and construction technology for the connection of horizontal multi-pipeline counterpart
CN204983613U (en) Hoist and mount system of cell board curtain installation
CN106193618B (en) A kind of aerial steel structure truss construction of Long span
CN114873497B (en) Vertical lifting installation device and method for variable-diameter unbalanced load equipment
CN205501837U (en) Steel case roof beam becomes bridge welding simple platform
CN109372243A (en) A kind of hanging basket system for the installation of steel construction metal Roof bottom plate
CN204531469U (en) A kind of steel work overhanging component temporary support of tool-type and discharge mechanism
CN110306782A (en) Reactor building shell dome template and its assembling and construction method
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN113666284B (en) Hydraulic lifting construction method for outdoor truss steel structure
CN115234009A (en) Construction method of integral hoisting system of grid unit truss
CN104153586A (en) Construction method for installing purline through suspension cable cranes
CN110255331A (en) A kind of building hoist testing stand
CN103743581B (en) Internal-climbing tower crane test platform device and test method
CN109378767A (en) A kind of lifting engineering method of hoist engine to skyscraper electricity well inner cable
CN220645136U (en) Lifting platform special for chimney steel beam construction
CN108545629A (en) Utilize the construction method of tower crane lifting girder truss
CN212154097U (en) Overhead pipeline high-altitude operation platform device
CN207144533U (en) The horizontal protective of building hoist basis conversion
CN210002233U (en) Hoisting system suitable for suspension bridge steel structure bridge deck system
CN110386543B (en) Method for hoisting cable-stayed suspension type tubular bus
CN104806001A (en) Safety operation platform for sliding and lifting of elevator shaft guide rail and construction method
CN102041784B (en) Horizontal rotation construction technology of oversized, overweight and special-shaped construction member through multipoint hoisting and horizontal rotation hanger
CN112456348A (en) Heat absorber hoisting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20221025

RJ01 Rejection of invention patent application after publication