CN107285200A - A kind of high large-span truss integral translation construction method for hanging - Google Patents
A kind of high large-span truss integral translation construction method for hanging Download PDFInfo
- Publication number
- CN107285200A CN107285200A CN201710540236.8A CN201710540236A CN107285200A CN 107285200 A CN107285200 A CN 107285200A CN 201710540236 A CN201710540236 A CN 201710540236A CN 107285200 A CN107285200 A CN 107285200A
- Authority
- CN
- China
- Prior art keywords
- truss
- crane
- lifting
- hanging
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention provides a kind of high large-span truss integral translation construction method for hanging, utilize two identical or different parameters large-scale cranes, two ends Heave Here is hung, two cranes are distributed in truss two ends, track route according to having proposed before pre- is walked unhurriedly lifting, to be lifted to arrive certain altitude, two cranes assist synchronously slowly to move to the lower section of structures installation position, then integral lifting is in place.The construction method of the present invention can greatly reduce crane it is in place after weld job workload, it is ensured that the resistance to overturning and truss rigidity of overall truss, while the hanging method of the present invention is easy to operate, speed of application is fast, can effectively improve truss installa-tion duty cycle.
Description
Technical field
The present invention relates to the installation Technology in a kind of building construction process, more particularly to a kind of high large-span truss are whole
Body translates construction method for hanging.
Background technology
At present, high large-span truss lifting operation typically makes processing using in structure factory, and burst is transported to job site
Install in place pre- lifting region, the installation position that structures are finally lifted to using the crane of relevant parameter.The construction method is constructed
There is no problem for the not high steel structure installation of general span low height, but construction large span, the truss construction of height superelevation have three
Big defect:First, fabricating yard is needed to carry out carry out rationalization partition orderly in a organized way, each preassembling component is identified, to hanging
The tissue difficulty for pretending industry is larger.Second, each pre-splicing connection member weld job when top is installed requires high, substantial amounts of to connect
The quality of head is difficult to ensure that, larger in high aerial inspection from sample difficulty simultaneously for first-order weld, if in the weldering of upper detection part
Seam is unqualified to be had weld defect and is difficult to do over again, influence steel truss integral rigidity and stability.3rd, because of most splicing work
Work be in hoisting process complete, its lifting operation it is long in time limit, while security risk increase.
The content of the invention
To solve the above problems, the present invention provides a kind of high large-span truss integral translation construction method for hanging, two are utilized
Platform is identical or large-scale cranes of different parameters, has hung two ends Heave Here, two cranes are distributed in truss two ends, before pre-
The track route proposed is walked unhurriedly lifting, to be lifted to arrive certain altitude, and two cranes assist synchronous slowly to move to structures peace
The lower section at dress position, then integral lifting are in place.
A kind of high large-span truss integral translation construction method for hanging of the present invention, Specific construction step is as follows:
(1) construction technology prepares:If two crane performance parameters are different, that every crane need to undertake should be calculated in advance
Lift heavy amount, and after truss lifting two ends difference of height and angle.
(2) crane track route figure is lifted according to the high large-span truss integral translation of Steel Structural Design drawing compilation;
(3) truss fabrication and transport:Make and weld in the assembly of structure factory, check welding quality and carry out flaw detection experiment,
Ensure that weldquality is qualified;Derusting anti-corrosive construction is carried out to component;The high large-span truss for making qualified is transported to job site
Lifting operation region;
(4) crane walking roadshow is carried out before formal lifting, it is ensured that crane smooth running in hoisting process;
(5) leveling is carried out to pre-installation truss structure base and pre-treatment is installed;
(6) steel wire rope of two crane lifting truss is hung on to the Heave Here of the steel truss of pre- lifting;
(7) by the crane track route figure woven, lifted slowly after truss lifting certain altitude, then by two cranes
Travel to the lower section of structures truss installa-tion;
(8) truss lifting is in place, and truss integral lifting exceeds the top of mounting seat, and adjustment is installed on base;
(9) truss and base are consolidated and are connected.
Further, the piece of smooth land, the piece of smooth land after hardening in crane travel region are hardened according to step (2) crane track route figure
Except compacting factor experiment need to be done;While carrying out post training to crane operator and telling somebody what one's real intentions are in detail.
Further, in (7) two crane walking processes of step, two cranes remain a constant speed forward, steel wire rope part side
Notice that crane collaboration moves pendulum into swing, it is ensured that steel wire rope and truss integral translation.
Further, when step (8) lifting is in place, if two crane performance parameters are different, need the big one end of load-bearing first
In place, then the other end can be slowly in place.
Compared with prior art, the construction method advantage of the invention is:
1) construction method of the invention greatly reduce lifting it is in place after weld job workload, it is ensured that overall truss it is whole
Body stability and truss rigidity;
2) construction method of the invention is easy to operate, and speed of application is fast, can effectively improve truss installa-tion duty cycle.
Brief description of the drawings
Fig. 1 is a kind of process chart of high large-span truss integral translation construction method for hanging of the present invention.
Embodiment
Invention is further described with reference to Figure of description.
As shown in Fig. 1 process chart, a kind of high large-span truss integral translation lifting of the invention
Construction method, Specific construction step is as follows:
(1) construction technology prepares:If two crane performance parameters are different, that every crane need to undertake should be calculated in advance
Lift heavy amount, and after truss lifting two ends difference of height and angle.
(2) crane track route figure is lifted according to the high large-span truss integral translation of Steel Structural Design drawing compilation;
(3) truss fabrication and transport:Make and weld in the assembly of structure factory, check welding quality and carry out flaw detection experiment,
Ensure that weldquality is qualified;Derusting anti-corrosive construction is carried out to component;The high large-span truss for making qualified is transported to job site
Lifting operation region;
(4) crane walking roadshow is carried out before formal lifting, it is ensured that crane smooth running in hoisting process;
(5) leveling is carried out to pre-installation truss structure base and pre-treatment is installed;
(6) steel wire rope of two crane lifting truss is hung on to the Heave Here of the steel truss of pre- lifting;
(7) by the crane track route figure woven, lifted slowly after truss lifting certain altitude, then by two cranes
Travel to the lower section of structures truss installa-tion;
(8) truss lifting is in place, and truss integral lifting exceeds the top of mounting seat, and adjustment is installed on base;
(9) truss and base are consolidated and are connected.
In above-described embodiment, the piece of smooth land in crane travel region is hardened according to step (2) crane track route figure, after hardening
The piece of smooth land, which is removed, need to do compacting factor experiment;While carrying out post training to crane operator and telling somebody what one's real intentions are in detail.
In (7) two crane walking processes of step, two cranes remain a constant speed it is forward, steel wire rope local direction swing in note
Crane collaboration of anticipating moves pendulum, it is ensured that steel wire rope and truss integral translation.
When step (8) lifting is in place, if two crane performance parameters are different, the one end for needing load-bearing big is first in place, then
The other end can be slowly in place.
In work progress, note also:
1st, must be according to the actual crane track route figure for lifting condition establishment in place, two crane walkings of hardening before constructing
The roadbed of circuit.
2nd, calculate every crane load-bearing, and after truss lifting two ends difference of height and angle, while to crane operation people
Member carries out post training and told somebody what one's real intentions are in detail, the crane smooth-ride after lifting, and control lifting at the uniform velocity, keeps purlin during lifting
The relative quiescent lifting of frame two ends, the angle allowed band that its truss two ends can not be calculated beyond it, this is that high large-span truss is whole
The key point that body shifting method is successfully lifted.
3rd, treat that truss two ends are effectively connected the errorless detachable steel wire rope in rear of confirmation with base by design drawing requirement.
Claims (4)
1. a kind of high large-span truss integral translation construction method for hanging, it is characterised in that Specific construction step is as follows:
(1) construction technology prepares:If two crane performance parameters are different, the lift heavy that every crane need to undertake should be calculated in advance
Amount, and after truss lifting two ends difference of height and angle.
(2) crane track route figure is lifted according to the high large-span truss integral translation of Steel Structural Design drawing compilation;
(3) truss fabrication and transport:Make and weld in the assembly of structure factory, check welding quality and carry out flaw detection experiment, it is ensured that
Weldquality is qualified;Derusting anti-corrosive construction is carried out to component;The high large-span truss for making qualified is transported to hanging for job site
Fill operating area;
(4) crane walking roadshow is carried out before formal lifting, it is ensured that crane smooth running in hoisting process;
(5) leveling is carried out to pre-installation truss structure base and pre-treatment is installed;
(6) steel wire rope of two crane lifting truss is hung on to the Heave Here of the steel truss of pre- lifting;
(7) by the crane track route figure woven, slow traveling is lifted after truss lifting certain altitude, then by two cranes
To the lower section of structures truss installa-tion;
(8) truss lifting is in place, and truss integral lifting exceeds the top of mounting seat, and adjustment is installed on base;
(9) truss and base are consolidated and are connected.
2. a kind of high large-span truss integral translation construction method for hanging according to claim 1, it is characterized in that according to step
Suddenly (2) crane track route figure hardens the piece of smooth land in crane travel region, and the piece of smooth land after hardening, which is removed, need to do compacting factor experiment;And
Post training is carried out to crane operator simultaneously and told somebody what one's real intentions are in detail.
3. a kind of high large-span truss integral translation construction method for hanging according to claim 1, it is characterized in that step (7)
In two crane walking processes, two cranes remain a constant speed it is forward, steel wire rope local direction swing in note crane collaboration move pendulum,
Ensure steel wire rope and truss integral translation.
4. a kind of high large-span truss integral translation construction method for hanging according to claim 1, it is characterized in that step (8)
When lifting by crane in place, if two crane performance parameters are different, the one end for needing load-bearing big is first in place, and then the other end can slowly
Position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710540236.8A CN107285200A (en) | 2017-07-05 | 2017-07-05 | A kind of high large-span truss integral translation construction method for hanging |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710540236.8A CN107285200A (en) | 2017-07-05 | 2017-07-05 | A kind of high large-span truss integral translation construction method for hanging |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107285200A true CN107285200A (en) | 2017-10-24 |
Family
ID=60100186
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710540236.8A Pending CN107285200A (en) | 2017-07-05 | 2017-07-05 | A kind of high large-span truss integral translation construction method for hanging |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107285200A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112575900A (en) * | 2020-11-13 | 2021-03-30 | 中建四局第六建设有限公司 | Double-layer synchronous hoisting construction method for large-span precast beam of assembled industrial factory building |
CN113774808A (en) * | 2021-09-30 | 2021-12-10 | 安徽省公路桥梁工程有限公司 | Urban-rail dual-purpose double-layer large-span steel truss and arch cooperation system bridge construction method |
CN115234009A (en) * | 2022-09-05 | 2022-10-25 | 中国十七冶集团有限公司 | Construction method of integral hoisting system of grid unit truss |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202004021050U1 (en) * | 2004-04-23 | 2006-10-05 | Werdin, Walerij | Twin-handled brick lifter comprises two identical shaped devices with angled handles and hand protectors and interchangeable gripper arms to carry and lay bricks |
CN101324146A (en) * | 2008-08-11 | 2008-12-17 | 河北建工集团有限责任公司 | Construction method for hanging wide span arcuated open-web beam |
-
2017
- 2017-07-05 CN CN201710540236.8A patent/CN107285200A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202004021050U1 (en) * | 2004-04-23 | 2006-10-05 | Werdin, Walerij | Twin-handled brick lifter comprises two identical shaped devices with angled handles and hand protectors and interchangeable gripper arms to carry and lay bricks |
CN101324146A (en) * | 2008-08-11 | 2008-12-17 | 河北建工集团有限责任公司 | Construction method for hanging wide span arcuated open-web beam |
Non-Patent Citations (1)
Title |
---|
林新强: "73m大跨度钢管桁架组双机吊装施工技术", 《钢结构》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112575900A (en) * | 2020-11-13 | 2021-03-30 | 中建四局第六建设有限公司 | Double-layer synchronous hoisting construction method for large-span precast beam of assembled industrial factory building |
CN113774808A (en) * | 2021-09-30 | 2021-12-10 | 安徽省公路桥梁工程有限公司 | Urban-rail dual-purpose double-layer large-span steel truss and arch cooperation system bridge construction method |
CN115234009A (en) * | 2022-09-05 | 2022-10-25 | 中国十七冶集团有限公司 | Construction method of integral hoisting system of grid unit truss |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101613990B (en) | Construction method of railway steel truss girder T-shaped stiffening rib orthotropic slab bridge deck | |
CN106087752B (en) | Multispan cable-carried arch bridge construction method | |
CN111335178B (en) | Small-curve-radius steel box girder bridge girder erection machine and erection construction method | |
CN107285200A (en) | A kind of high large-span truss integral translation construction method for hanging | |
CN103882812A (en) | Construction method for midspan main beams of cable-stayed bridge | |
CN104652827A (en) | Three-stage-relay hoisting construction method for large-span arc-shaped truss | |
CN106758828A (en) | The application process of fixed asymmetric bridge girder cantilever assembly equipment | |
CN107060349A (en) | A kind of large-span steel girder upper air installing system in place and its construction | |
CN101537965B (en) | Step chain installation device and method thereof | |
CN104863374B (en) | Large-span steel slipping mechanism and its gliding method | |
CN106758872A (en) | Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution | |
CN106544959A (en) | The construction method of the lifting sections of the king-tower containing saddle and bridge main tower saddle | |
CN105274976B (en) | Steel platform prefabricated construction method in water | |
CN102226497B (en) | Manufacturing method of large rubber rolling curtain sealed dry-type gas holder | |
CN105776011A (en) | Mounting method for crane beam on blast furnace top | |
CN108952002B (en) | Oversized and ultra-wide double-spliced combined I-shaped steel beam and sectional division and installation method thereof | |
CN104775363B (en) | The spelling method of upper king-post strut reinforcing bar sections | |
CN201390584Y (en) | Step chain mounting device | |
CN106120573A (en) | Multispan cable-carried arch bridge self-balancing button over strait hangs construction method | |
CN107881926B (en) | Combined hanging basket with full-rotation crane and construction method thereof | |
CN102259794B (en) | Method for installing overall combined type crane beam | |
CN206736726U (en) | The device of the prefabricated arch ring of nose girder auxiliary erection | |
CN107366232A (en) | Steel box-girder chooses the embedding section of mending of arm decorative panel and integrally faces upward dress method | |
CN107893377A (en) | The on-site consolidation method of Cable-stayed Bridges loop wheel machine bottom basket system | |
CN107285209A (en) | A kind of Novel U-shaped erection equipment and its operating method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171024 |
|
WD01 | Invention patent application deemed withdrawn after publication |