CN115199041A - Construction method for inserting basement roof in advance - Google Patents

Construction method for inserting basement roof in advance Download PDF

Info

Publication number
CN115199041A
CN115199041A CN202210934181.XA CN202210934181A CN115199041A CN 115199041 A CN115199041 A CN 115199041A CN 202210934181 A CN202210934181 A CN 202210934181A CN 115199041 A CN115199041 A CN 115199041A
Authority
CN
China
Prior art keywords
post
pouring
concrete
grouting
cast strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210934181.XA
Other languages
Chinese (zh)
Inventor
曾维晓
罗匡懿
史宗亮
余伟伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202210934181.XA priority Critical patent/CN115199041A/en
Publication of CN115199041A publication Critical patent/CN115199041A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to a basement roof advanced insertion construction method, which belongs to the technical field of building construction and comprises the following steps of determining a reserved pouring opening spacing distance and a self-compacting concrete mix proportion according to a field grouting pouring experiment, pouring a prefabricated concrete plate, installing a post-cast strip template, treating construction joints and clearing concrete residues, finishing post-cast strip steel bar binding, sealing a post-cast strip by adopting the prefabricated concrete plate and well performing waterproof construction, performing high-pressure grouting after the grouting condition of the post-cast strip is achieved, performing concrete moisturizing maintenance on the post-cast strip, and removing the post-cast strip template to finish construction after the concrete strength meets the requirement. According to the invention, the cast-in-place prefabricated concrete slabs are adopted to be sealed in advance, and the pouring openings are reserved on the post-pouring strip templates for grouting and pouring, so that the condition that an owner template house and a garden display area are open is met, the construction of a waterproof protective layer and backfilling is carried out in advance, and the effects of saving energy and land, shortening the whole progress of the project and increasing the economic benefit are achieved.

Description

Construction method for inserting basement roof in advance
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a construction method for inserting a top plate of a basement in advance.
Background
The post-settlement casting belt can be cast for more than 60 days after the main building structure is closed or longer according to design requirements, and the construction time of top plate backfill of the top plate earthing garage is also limited by the casting time of the post-settlement casting belt, so that the construction site is narrow, the transportation site is difficult to arrange, and the site expense and the construction period loss are increased; generally, the basement has a large area, a plurality of post-cast strips need to be arranged vertically and horizontally for control such as settlement, the post-cast strips are constructed for the second time, construction joints exist between the post-cast strips and surrounding top plates, leakage is easy to cause due to carelessness, grouting treatment is needed, maintenance is difficult, cost is high, and the influence on construction period and quality is large.
Disclosure of Invention
In order to solve the problems in the prior art, the invention provides a construction method for inserting a basement roof in advance, which is characterized in that a cast-in-place prefabricated concrete plate is adopted to be closed in advance, a pouring opening is reserved in a post-pouring strip template for grouting and pouring, the opening of an owner template house and a garden display area is met, the construction of a waterproof and waterproof protective layer and backfilling is carried out in advance, and the effects of saving energy and land, shortening the integral progress of a project and increasing the economic benefit are achieved.
The purpose of the invention can be realized by the following technical scheme:
a construction method for inserting a top plate of a basement in advance comprises the following steps:
firstly, performing a grouting pouring experiment on site, determining the spacing distance of the preformed holes and the mixing proportion of self-compacting concrete, and optimizing a construction scheme;
step two, casting the prefabricated concrete plate in situ: the prefabricated concrete slab pouring reinforcing bars are double-layer and bidirectional, round steel lifting rings are embedded in the prefabricated concrete slab pouring reinforcing bars, and round corners are formed on two sides parallel to the post-pouring belt;
step three, post-pouring strip template installation and construction joint treatment: the supporting system of the post-cast strip is independently built, the template of the post-cast strip is tightly attached to the top plate, a plurality of vertical rods are arranged below the top plate, wood beams are arranged between the top plate and the vertical rods, the vertical rods are connected into a whole through a plurality of horizontal rods, and the position of a construction joint is roughened;
step four, binding post-cast steel bars: finishing the steel bars, straightening, regulating and fully fastening and binding;
step five, closing the prefabricated concrete plate of the post-cast strip and reserving a pouring opening on the template of the post-cast strip: before laying the precast concrete slabs, transversely building a layer of lime-sand bricks along the edges of the two sides of the post-cast strip by using cement mortar, ensuring the upper surfaces of the lime-sand bricks to be flat and straight, and laying the precast concrete slabs after the building of the lime-sand bricks is completed for 48 hours;
the pouring openings are preferentially arranged on a floor slab on the negative layer of the basement, and the distance between the pouring openings at the bottom of the post-cast strip formwork can be determined according to the thickness of concrete slabs, reinforcements in the concrete slabs, self-compacting concrete and the actual pressure characteristics of a grouting machine;
step six, base layer treatment: after the prefabricated concrete plate is installed, checking the internal corners at the root part of the prefabricated concrete plate, the external corners at the top part of the prefabricated concrete plate, the internal corners of the sand lime brick and the like, and performing fillet plastering treatment by using waterproof cement mortar;
step seven, waterproof layer construction: when the base layer is processed and dried to reach waterproof construction conditions, adhering mortar bricks at the root parts of the prefabricated concrete slabs, arranging foamed polyethylene rods, carrying out waterproof construction on joints such as male and female corner lap joints, stubble throwing, additional layers and the like, sealing by adopting waterproof coiled materials, and adding the additional layers at the tops of the prefabricated concrete slabs after sealing is finished;
step eight, pouring concrete in the post-pouring belt by grouting: the method comprises the following steps that a pouring opening and an exhaust opening are formed in a post-pouring belt template, pipelines of grouting equipment and secondary pressurization equipment are connected with the pouring opening and the exhaust opening respectively, the length of a grouting pipe is measured actually, a pressure gauge and a grouting pump are debugged, grout is poured into the pouring opening under the condition that the structure pressure range is not exceeded, and after grouting of the grouting equipment is finished, secondary pressurization is carried out on the inner portion of grouting through a high-pressure grouting machine after the grout is initially set;
step nine, concrete curing and pouring opening sealing: temporarily sealing and curing a pouring opening by adopting plastic cloth or a film within 12 hours after the concrete pouring is finished, and spraying water into gaps of a post-pouring strip template, wherein the concrete is maintained for at least 14 days;
step ten, dismantling the post-cast strip template: and (3) dismantling the post-cast strip template when the concrete strength of the post-cast strip reaches 100% of that of the original structure, wherein the concrete dismantling time is determined according to the test result of the test block under the same condition of the post-cast strip.
And further, in the third step, concrete residues are removed from the base layer before the post-cast strip template is installed, and cement mortar is coated as an interface treating agent and washed clean.
Furthermore, in the fifth step, before the precast concrete slabs are laid, setting out lines according to a laying drawing to mark the edge line of each precast slab, paving a layer of cement mortar on the originally laid sand-lime bricks during laying, squeezing the precast concrete slabs tightly, and keeping the edges of the precast concrete slabs on the same post-pouring belt on the same straight line.
Further, in the fifth step, after the prefabricated concrete plate is paved for 48 hours, the levelness, the verticality and the like of the prefabricated concrete plate are corrected, the joint filling treatment is carried out on the joint by using waterproof mortar, and the gap between the prefabricated concrete plate and the top plate is sealed by adopting a foamed polyethylene rod.
And further, in the seventh step, after the waterproof layer is constructed, artificial backfill is carried out between the prefabricated concrete plates and within 2 meters on two sides of the prefabricated concrete plates, and the prefabricated concrete plates cannot be disturbed.
Further, in the eighth step, when grout is poured, pouring is performed gradually from one side of the post-pouring strip to the other side of the post-pouring strip according to the setting sequence of the positions of the pouring openings, when grouting is performed on each pouring opening, a mode of multiple supplementary grouting is adopted, grouting is stopped until the pressure change of grouting is relatively smooth and stable, a valve on a grouting pipe is closed, and adjacent pouring openings are re-poured.
The beneficial effects of the invention are as follows:
(1) The post-cast strip after sedimentation is sealed in advance by adopting a cast-in-place prefabricated concrete plate, and concrete is poured by grouting in a preformed hole of a template at the bottom of the post-cast strip, so that the requirements of opening an owner template house and a garden display area are met, and the requirements of construction of a waterproof protective layer and backfilling are met in advance.
(2) The post-pouring belt after settlement is sealed at the top of a main building structure, self-compacting concrete is adopted for post-pouring after settlement difference between the underground garage and the main building is eliminated, vibration is not needed, closed maintenance is conducted, and the quality of the concrete is guaranteed.
(3) The on-site space utilization problem caused by the post-pouring belt pouring and roof earthing backfill time is solved, and the effects of saving energy and land, shortening the whole progress of the project and increasing the economic benefit are achieved.
Drawings
In order to facilitate understanding for those skilled in the art, the present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a construction structure view of a post-settlement casting strip according to the present invention;
figure 2 is a side sectional view of the precast concrete slab of the present invention;
FIG. 3 is a schematic view of the top plate form of the present invention;
description of the main element symbols:
in the figure: 1. prefabricating a concrete slab; 2. lime-sand bricks; 3. an additional layer; 4. a top plate; 5. post-pouring a strip template; 6. pouring a mouth; 7. wood purlin; 8. erecting a rod; 9. a horizontal bar; 10. waterproof coiled materials; 11. a hoisting ring; 12. and (4) rounding the corners.
Detailed Description
To further illustrate the technical means and effects of the present invention adopted to achieve the predetermined objects, the following detailed description of the embodiments, structures, characteristics and effects according to the present invention will be made with reference to the accompanying drawings and preferred embodiments.
Referring to fig. 1-3, a construction method for inserting a top plate of a basement in advance includes the following steps:
firstly, performing a grouting pouring experiment on site, determining the spacing distance of the preformed holes and the mixing proportion of self-compacting concrete, and optimizing a construction scheme;
step two, casting the prefabricated concrete plate 1 in situ: the precast concrete slab 1 is poured and reinforced with steel bars in a double-layer bidirectional A10@150 mode, the concrete grade is C30, a steel bar protective layer is 15mm, the structural size is 1100mm x 900mm x 200mm, an A8 round steel hanging ring 11 is embedded in advance, and two sides parallel to a post-pouring belt are provided with R =50mm round corners 12;
step three, installing a post-cast strip template 5 and treating a construction joint: a supporting system of the post-cast strip is independently built, a template 5 of the post-cast strip is tightly attached to a top plate 4, a plurality of vertical rods 8 are arranged below the top plate 4, the distance between the vertical rods 8 is 900mm, the step pitch is 1200mm, wood beams 7 are arranged between the top plate 4 and the vertical rods 8, the vertical rods 8 are connected into a whole through a plurality of horizontal rods 9, and the construction joint is roughened;
step four, binding post-cast steel bars: finishing the steel bars, straightening, regulating and fully fastening and binding;
step five, closing the post-cast strip precast concrete plate 1 and reserving a pouring opening 6 on a post-cast strip template 5: before laying the precast concrete plate 1, transversely laying a layer of lime-sand bricks 2 by cement mortar along the edges of two sides of the post-cast strip by 2-3cm, ensuring the upper surfaces of the lime-sand bricks 2 to be flat and straight, and laying the precast concrete plate 1 after the lime-sand bricks 2 are laid for 48 hours;
the pouring openings 6 are preferentially arranged on a floor slab on the negative layer of the basement, the horizontal flowing distance of self-sealing concrete from a discharging point is not more than 10m, in order to ensure the plate thickness and the concrete compactness of the post-cast strip, the distance between the pouring openings 6 at the bottom of the post-cast strip template 5 is not more than 2400mm, and the distance between the pouring openings 6 can be determined according to the plate thickness of the concrete, the arrangement of reinforcements in the concrete plate, the self-sealing concrete and the pressure actual characteristics of a grouting machine;
step six, base layer treatment: after the prefabricated concrete plate 1 is installed, checking the positions of the internal corner at the root of the prefabricated concrete plate 1, the external corner at the top of the prefabricated concrete plate 1, the internal corner of the sand lime brick 2 and the like, and performing treatment of smearing a fillet D by using waterproof cement mortar to be more than or equal to 50 mm;
step seven, waterproof layer construction: when the base layer is processed and dried to reach the waterproof construction condition, setting 50 foamed polyethylene rods on the lime sand bricks 2 adhered to the roots of the prefabricated concrete slabs 1, carrying out waterproof construction on nodes such as the internal and external corner lap joint, stubble throwing, an additional layer 3 and the like, sealing by adopting a waterproof coiled material 10, and adding the additional layer 3 on the top of the prefabricated concrete slabs 1 after sealing;
step eight, pouring the post-cast strip concrete by grouting: a pouring opening 6 and an exhaust opening are formed in the post-pouring belt template 5, pipelines of grouting equipment and secondary pressurization equipment are respectively connected with the pouring opening 6 and the exhaust opening, the length of a grouting pipe is actually measured, a pressure gauge and a grouting pump are debugged, grout is poured into the pouring opening 6 under the condition that the structure compression range is not exceeded, and after grouting of the grouting equipment is finished, secondary pressurization is carried out on the interior of grouting through a high-pressure grouting machine after the grout is initially set;
step nine, concrete curing and pouring opening 6 is closed: temporarily sealing and maintaining the pouring opening 6 by adopting plastic cloth or a film within 12 hours after the concrete pouring is finished, and spraying water into the gap of the post-pouring strip template 5 at the same time, wherein the concrete is maintained for at least 14 days in a moisture-preserving manner;
step ten, dismantling the post-cast strip template 5: and the post-cast strip template 5 can be dismantled when the concrete strength of the post-cast strip reaches 100% of that of the original structure, and the concrete dismantling time is determined according to the test result of the test block under the same condition of the post-cast strip.
And further, in the third step, concrete residues are removed from the base layer before the post-cast strip template 5 is installed, and cement mortar is coated as an interface treating agent and washed clean.
Furthermore, in the fifth step, before the precast concrete slabs 1 are laid, the lines are laid according to the laying drawing to mark the edge lines of each precast slab, a layer of cement mortar is laid on the originally laid sand lime bricks 2, the precast concrete slabs 1 are tightly squeezed, and the edges of the precast concrete slabs 1 on the same post-cast strip are on the same straight line.
Further, in the fifth step, after the prefabricated concrete plate 1 is paved for 48 hours, the levelness, the verticality and the like of the prefabricated concrete plate 1 are corrected, the joint filling treatment is carried out on the joint by using waterproof mortar, and the gap between the prefabricated concrete plate 1 and the top plate 4 is sealed by adopting a foamed polyethylene rod.
And further, in the seventh step, after the waterproof layer is constructed, backfilling the backfilled soil between the prefabricated concrete plates 1 and within 2 meters of two sides of the prefabricated concrete plates 1 manually, wherein the disturbance cannot be caused to the prefabricated concrete plates 1, and the compaction coefficient of the backfilled soil is more than or equal to 0.94.
Further, in the eighth step, when grout is poured, pouring is gradually carried out from one side of the post-pouring zone to the other side of the post-pouring zone according to the arrangement sequence of the positions of the pouring openings 6, when each pouring opening 6 is grouted, the pouring pressure is 0.5-1.6mpa, the grouting is stopped by adopting a mode of multiple supplementary grouting until the grouting pressure changes smoothly and stably, a valve on a grouting pipe is closed, and the adjacent pouring openings 6 are grouted again.
According to the invention, the grout is subjected to secondary pressurization inside the grouting after initial setting, so that a certain pressure can be always applied to the grouting material in a period from the beginning of grouting to the initial setting of the grout, and the compactness of the grouting material and the compactness of horizontal joints of upper and lower structures are ensured.
According to the invention, the post-cast strip can be timely used for waterproofing and finishing the protective layer after being sealed in advance, so that sundries can be prevented from falling in and rainwater can be prevented from flowing in, a good condition is created for basement construction, reinforcing steel bars can be prevented from being corroded to weaken the structural strength, a good site space and a good transportation condition are provided for construction, the site material stacking is effectively ensured under the conditions of short construction period, large reinforcing steel bar amount, large templates and more turnover materials waiting for entering the site, the smooth insertion of decoration in advance is ensured, the construction progress is accelerated overall, and the operation cost is reduced.
The working principle and the using process of the invention are as follows:
a technician determines the spacing distance of reserved pouring ports 6 and the mix proportion of self-compacting concrete according to a field grouting pouring experiment, pours a prefabricated concrete plate 1, installs a post-pouring strip template 5, processes construction joints and cleans concrete residues, finishes post-pouring strip steel bar binding, closes a post-pouring strip by adopting the prefabricated concrete plate 1 and performs waterproof construction, performs high-pressure grouting after the grouting condition of the post-pouring strip is met, performs concrete moisturizing and curing on the post-pouring strip, and can dismantle the post-pouring strip template 5 after the strength of the concrete meets the requirement.
The invention relates to an assembly type temporary pipeline comprehensive arrangement structure, which combines a temporary assembly type drainage ditch and a temporary pipeline in a construction site, is constructed in an assembly type mode, is convenient and fast to operate, not only ensures construction drainage in the construction site, but also has better protection effect on the temporary pipeline, greatly reduces the breakage rate of the temporary pipeline, improves the turnover rate of the temporary pipeline, can recycle and reuse the prefabricated concrete drainage ditch components in the later period, saves materials, time and labor, saves construction cost and is environment-friendly.
Although the present invention has been described with reference to the preferred embodiments, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the scope of the present invention.

Claims (6)

1. A construction method for inserting a basement roof in advance is characterized in that: the method comprises the following steps:
firstly, performing a grouting pouring experiment on site, determining the spacing distance of reserved pouring openings (6) and the mixing proportion of self-compacting concrete, and optimizing a construction scheme;
step two, cast-in-situ precast concrete slab (1): the precast concrete plate (1) is poured with reinforcing bars in double-layer bidirectional mode, round steel hanging rings (11) are embedded in the precast concrete plate, and round corners (12) are formed on two sides parallel to the post-pouring belt;
step three, mounting the post-cast strip template (5) and treating a construction joint: the supporting system of the post-cast strip is independently built, a template (5) of the post-cast strip is tightly attached to a top plate (4), a plurality of vertical rods (8) are arranged below the top plate (4), wood purlins (7) are arranged between the top plate (4) and the vertical rods (8), the vertical rods (8) are connected into a whole through a plurality of horizontal rods (9), and the construction joint is roughened;
step four, binding post-cast steel bars: finishing the steel bars, straightening, regulating and fully fastening and binding;
step five, sealing the post-cast strip precast concrete plate (1) and reserving a pouring opening (6) on the post-cast strip template (5): before laying the precast concrete plate (1), transversely laying a layer of lime-sand bricks (2) along the edges of the two sides of the post-cast strip by cement mortar, ensuring the upper surfaces of the lime-sand bricks (2) to be flat and straight, and laying the precast concrete plate (1) after the lime-sand bricks (2) are laid for 48 hours;
the pouring openings (6) are preferentially arranged on a floor slab on the negative layer of the basement, and the distance between the pouring openings (6) at the bottom of the post-pouring strip template (5) can be determined according to the thickness of concrete slab, the internal arrangement of reinforcement of the concrete slab, self-compacting concrete and the pressure actual characteristics of a grouting machine;
step six, base layer treatment: after the prefabricated concrete plate (1) is installed, checking positions such as the root internal corner of the prefabricated concrete plate (1), the top external corner of the prefabricated concrete plate (1), the internal corner of the sand lime brick (2) and the like, and performing fillet plastering treatment by using waterproof cement mortar;
step seven, waterproof layer construction: when the base layer is processed and dried to reach the waterproof construction condition, setting a foamed polyethylene rod by adhering a lime sand brick (2) to the root of the prefabricated concrete plate (1), carrying out node waterproof construction such as female and male corner lapping, stubble throwing, an additional layer (3) and the like, sealing by adopting a waterproof coiled material (10), and adding the additional layer (3) at the top of the prefabricated concrete plate (1) after sealing is finished;
step eight, pouring the post-cast strip concrete by grouting: a pouring opening (6) and an exhaust opening are formed in the post-pouring belt template (5), pipelines of grouting equipment and secondary pressurization equipment are respectively connected with the pouring opening (6) and the exhaust opening, the length of a grouting pipe is actually measured, a pressure gauge and a grouting pump are debugged, grout is poured into the pouring opening (6) under the condition that the structure compression range is not exceeded, and after grouting of the grouting equipment is finished, secondary pressurization is carried out on the inside of grouting through a high-pressure grouting machine after the grout is initially set;
step nine, concrete curing and pouring opening (6) is closed: temporarily sealing and maintaining the pouring opening (6) by adopting plastic cloth or a film within 12 hours after the concrete pouring is finished, and spraying water into the gap of the post-pouring strip template (5) at the same time, wherein the concrete is maintained for not less than 14 days in a moisture-preserving manner;
step ten, dismantling the post-cast strip template (5): and (3) dismantling the post-cast strip template (5) when the concrete strength of the post-cast strip reaches 100% of that of the original structure, wherein the concrete dismantling time is determined according to the test result of the post-cast strip test block under the same condition.
2. The construction method for inserting the top plate of the basement in advance as claimed in claim 1, wherein the construction method comprises the following steps: in the third step, concrete residues are removed from the base layer before the post-cast strip template (5) is installed, and cement mortar is coated as an interface treating agent and is washed clean.
3. The construction method for inserting the top plate of the basement in advance as claimed in claim 1, wherein the construction method comprises the following steps: and fifthly, before the precast concrete plates (1) are laid, paying off according to a laying drawing to mark the edge line of each precast plate, laying a layer of cement mortar on the originally laid sand lime bricks (2), squeezing the precast concrete plates (1), and keeping the edges of the precast concrete plates (1) on the same post-cast strip on the same straight line.
4. The construction method for inserting the top plate of the basement in advance as claimed in claim 3, wherein the construction method comprises the following steps: and fifthly, after the prefabricated concrete plate (1) is paved for 48 hours, correcting levelness, verticality and the like of the prefabricated concrete plate (1), performing joint filling treatment on the joint by using waterproof mortar, and sealing the gap between the prefabricated concrete plate (1) and the top plate (4) by using a foamed polyethylene rod.
5. The construction method for inserting the top plate of the basement in advance as claimed in claim 1, wherein the construction method comprises the following steps: and seventhly, after the waterproof layer is constructed, manually backfilling the space between the prefabricated concrete plates (1) and within 2 meters of the two sides of the prefabricated concrete plates, wherein the prefabricated concrete plates (1) cannot be disturbed.
6. The construction method for inserting the top plate of the basement in advance as claimed in claim 1, wherein the construction method comprises the following steps: and step eight, gradually pouring the grout from one side of the post-pouring belt to the other side of the post-pouring belt according to the setting sequence of the positions of the pouring openings (6) during pouring, stopping grouting after the pressure change of grouting is relatively smooth and stable by adopting a mode of multiple supplementary grouting when each pouring opening (6) is grouted, closing a valve on a grouting pipe, and re-pouring the adjacent pouring openings (6).
CN202210934181.XA 2022-08-04 2022-08-04 Construction method for inserting basement roof in advance Pending CN115199041A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210934181.XA CN115199041A (en) 2022-08-04 2022-08-04 Construction method for inserting basement roof in advance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210934181.XA CN115199041A (en) 2022-08-04 2022-08-04 Construction method for inserting basement roof in advance

Publications (1)

Publication Number Publication Date
CN115199041A true CN115199041A (en) 2022-10-18

Family

ID=83586809

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210934181.XA Pending CN115199041A (en) 2022-08-04 2022-08-04 Construction method for inserting basement roof in advance

Country Status (1)

Country Link
CN (1) CN115199041A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790436A (en) * 2015-04-16 2015-07-22 中国二十二冶集团有限公司 High-rise building basement roof settlement post-pouring joint advanced water stop construction method
CN105350581A (en) * 2015-10-10 2016-02-24 中建二局第二建筑工程有限公司 Advanced sealing structure for basement top slab settlement post-cast strips
CN108396783A (en) * 2018-05-17 2018-08-14 中冶天工集团天津有限公司 A kind of pre- closure grouting devices and methods therefor of basement roof pouring after settlement
CN113585351A (en) * 2021-09-08 2021-11-02 中建五局第三建设有限公司 Soil covering plane settlement post-cast strip prefabrication advanced reverse order closed construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790436A (en) * 2015-04-16 2015-07-22 中国二十二冶集团有限公司 High-rise building basement roof settlement post-pouring joint advanced water stop construction method
CN105350581A (en) * 2015-10-10 2016-02-24 中建二局第二建筑工程有限公司 Advanced sealing structure for basement top slab settlement post-cast strips
CN108396783A (en) * 2018-05-17 2018-08-14 中冶天工集团天津有限公司 A kind of pre- closure grouting devices and methods therefor of basement roof pouring after settlement
CN113585351A (en) * 2021-09-08 2021-11-02 中建五局第三建设有限公司 Soil covering plane settlement post-cast strip prefabrication advanced reverse order closed construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
俞黎明: "覆土顶板沉降后浇带先封闭后浇筑施工技术", 城市住宅, no. 7, pages 108 - 111 *
韩佳彤等: "城市轨道交通建设工程明挖法施工技术指南", 31 July 2020, 北京理工大学出版社, pages: 144 - 145 *

Similar Documents

Publication Publication Date Title
CN205653820U (en) Basement post -cast strip advances plugging device
CN209723052U (en) The prefabricated plate advanced water-stopping of poured band of outer wall of basement backfills structure
CN101818539A (en) Assembled integral building and construction method thereof
CN213952303U (en) Basement outer wall post-cast strip assembled protection wall construction structures
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN109853625B (en) Integrated concrete comprehensive pipe gallery connected and assembled in mixed mode
CN111058631A (en) Concrete construction method for large-gradient inclined roof
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN109610665A (en) Oil depot assembled fire wall construction method
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN209989847U (en) Shear force wall post-cast strip prefabricated plate closing device
CN112112295A (en) Reinforcing construction method for post-cast strip of post-sealed outer wall
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN115030556B (en) Repairing and reinforcing method for exposed wall old building of brick
CN217758964U (en) Basement outer wall post-cast strip closed structure
CN216615981U (en) Basement outer wall post-cast strip precast slab reinforced structure
CN115199041A (en) Construction method for inserting basement roof in advance
CN214090002U (en) Basement outer wall post-cast strip is enclosed construction in advance
CN210288465U (en) Assembled retaining wall post-cast strip plugging member
CN206768879U (en) A kind of poured band of outer wall of basement structure
CN218148527U (en) Subside post-cast strip structure sealed in advance
CN219973299U (en) Prefabricated assembled basement roof post-cast strip advanced sealing structure
CN211816452U (en) Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination