CN115162355A - Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit - Google Patents

Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit Download PDF

Info

Publication number
CN115162355A
CN115162355A CN202210856523.0A CN202210856523A CN115162355A CN 115162355 A CN115162355 A CN 115162355A CN 202210856523 A CN202210856523 A CN 202210856523A CN 115162355 A CN115162355 A CN 115162355A
Authority
CN
China
Prior art keywords
foundation pit
shallow
construction
precast tubular
deep
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210856523.0A
Other languages
Chinese (zh)
Inventor
刘建雄
暨雷庭
石相美
张瑞泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal Jiangnan Construction Development Group Co ltd
Original Assignee
China Coal Jiangnan Construction Development Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Coal Jiangnan Construction Development Group Co ltd filed Critical China Coal Jiangnan Construction Development Group Co ltd
Priority to CN202210856523.0A priority Critical patent/CN115162355A/en
Publication of CN115162355A publication Critical patent/CN115162355A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of foundation pit bracing, and discloses a foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit, which comprises the following steps of S1, construction preparation; s2: treatment on a construction site; s3, pre-burying the tubular pile; s4, mounting a support protection plate; s5, reinforcing the junction of the shallow foundation pit and the deep foundation pit; s6, finishing enclosure. According to the invention, the embedded rod is arranged at the bottom of the precast tubular pile, so that the precast tubular pile can be conveniently embedded, the first barb and the second barb are arranged outside the precast tubular pile, so that the installation stability of the precast tubular pile is better, and the construction efficiency of the precast tubular pile is effectively improved.

Description

Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit
Technical Field
The invention relates to the technical field of foundation pit bracing, in particular to a foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit.
Background
In the building construction process, the original underground foundation is often changed due to the adjustment of the functions of the underground structure, for example, due to the change of the structural functions, the underground structure needs to be expanded from a deep foundation pit to a shallow foundation pit, so that the axis of the underground structure, a pile foundation of a bearing platform, the deep foundation pit and the shallow foundation pit need to be enclosed on the basis of the original enclosure of the foundation pit.
The Chinese patent discloses a foundation pit enclosure method for expanding construction from a deep foundation pit to a shallow foundation pit (with the publication number of CN 110284506A), in the technical construction process of the patent, piling, pore-forming and pore-forming grouting can be almost simultaneously carried out, compared with a mode of directly drilling and pouring a pile, the method has the effects of quickly forming a pile groove, facilitating quality control of the pile groove, shortening the construction period and improving the construction efficiency, but the method can play a role of enclosure, but the stability of the tubular pile during installation is poor, and more devices are used, and the operation is troublesome. Therefore, those skilled in the art provide a foundation pit enclosure method for extended construction from a deep foundation pit to a shallow foundation pit to solve the problems in the background art.
Disclosure of Invention
The invention aims to provide a foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit, which aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme:
a foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit comprises the following steps:
s1, construction preparation: transporting machinery required for construction to a construction site, and simultaneously mixing and stirring concrete in advance at the construction site:
s2: and (3) treatment on a construction site: cleaning the junction of the shallow foundation pit and the deep foundation pit, and reasonably placing the construction equipment and tools prepared in the step S1 so as to be convenient for constructors to quickly take;
s3, embedding the tubular pile: the method comprises the following steps that mechanical equipment is utilized to uniformly and alternately arrange the precast tubular piles at the junction of a shallow foundation pit and a deep foundation pit, the tail ends of the precast tubular piles are inserted into the deep foundation pit, and meanwhile first barbs symmetrically arranged on the outer portions of the precast tubular piles are also inserted into the deep foundation pit, so that the precast tubular piles form a pile foundation;
s4, installing a supporting protection plate: installing a support protection plate between the two precast tubular piles pre-buried in the step S3, and inserting a first inserted rod arranged at the bottom of the support protection plate into the deep foundation pit;
s5, reinforcing the junction of the shallow foundation pit and the deep foundation pit: pouring concrete into the interior of the support protection plate after installation, thereby ensuring the support strength of the junction of the shallow foundation pit and the deep foundation pit;
s6, completing enclosure: and repeating the steps in the operations S3, S4 and S5, thereby completing the formation of the foundation pit enclosure.
As a still further scheme of the invention: the mechanical equipment used in the step S3 is a pile driver, the depth of the precast tubular pile entering the deep foundation pit is 20-30 meters, and an embedded rod is arranged at the bottom of the precast tubular pile.
As a still further scheme of the invention: the distance between the precast tubular piles in the step S3 is 2-4 m, and the precast tubular piles are PHC tubular piles.
As a still further scheme of the invention: in step S3, the first barbs are arranged in a rectangular shape, and the included angle between the first barbs and the precast tubular pile is 30-50 degrees.
As a still further scheme of the invention: in step S3, the outside of the precast tubular pile can be set to be a disc-shaped second barb, and the second barb is at least provided with five groups in the outside of the precast tubular pile.
As a still further scheme of the invention: and in the step S4, the bottom end of the first inserted bar is arranged in a conical shape, and the first inserted bar is inserted into the deep foundation pit to a depth of at least more than 3 m.
As a still further scheme of the invention: and in the step S4, a second inserted bar symmetrically penetrates through one side of the supporting protection plate, one end of the second inserted bar is connected with a connecting disc, and the other end of the second inserted bar is inserted into the shallow foundation pit.
As a still further scheme of the invention: the tail end of the second inserted bar is arranged in a conical shape, and the second inserted bar is inserted into the shallow foundation pit by at least more than 2 meters.
As a still further scheme of the invention: and in the step S5, concrete is poured into the supporting and protecting plate through the concrete pump and the guide pipe, so that the supporting and protecting plate forms a protecting pile wall, and the integral strength of the protecting pile wall is improved.
Compared with the prior art, the invention has the beneficial effects that: according to the invention, the embedded rod is arranged at the bottom of the precast tubular pile, so that the precast tubular pile can be conveniently embedded, the first barb and the second barb are arranged outside the precast tubular pile, so that the installation stability of the precast tubular pile is better, and the construction efficiency of the precast tubular pile is effectively improved.
Drawings
FIG. 1 is a schematic structural diagram of a foundation pit bracing method for extended construction from a deep foundation pit to a shallow foundation pit;
FIG. 2 is an enlarged view of portion A of FIG. 1;
FIG. 3 is a schematic structural diagram of a second inserted link in a foundation pit bracing method for extended construction from a deep foundation pit to a shallow foundation pit;
FIG. 4 is a schematic structural diagram of a first barb in a foundation pit bracing method for extended construction from a deep foundation pit to a shallow foundation pit;
fig. 5 is a schematic structural diagram of a second barb in the foundation pit bracing method for extended construction from a deep foundation pit to a shallow foundation pit.
In the figure: 1. prefabricating a tubular pile; 2. supporting the protection plate; 3. shallow foundation pits; 4. a first plunger; 5. a deep foundation pit; 6. a connecting disc; 7. a second plunger; 8. an embedded rod; 9. a first barb; 10. a second barb.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, an embodiment of the invention
A foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit comprises the following steps:
s1, construction preparation: the machinery that will be under construction needs transports to the job site, mixes and stirs the concrete in advance at the job site simultaneously:
s2: and (3) treatment on a construction site: cleaning the junction of the shallow foundation pit 3 and the deep foundation pit 5, and reasonably placing the construction equipment and tools prepared in the step S1 so as to be convenient for constructors to quickly take;
s3, embedding the tubular pile: uniformly arranging the precast tubular piles 1 at the junctions of the shallow foundation pits 3 and the deep foundation pit 5 at intervals by using mechanical equipment, inserting the tail ends of the precast tubular piles 1 into the deep foundation pit 5, and simultaneously inserting first barbs 9 symmetrically arranged outside the precast tubular piles 1 into the deep foundation pit 5 so that the precast tubular piles 1 form a pile foundation;
the mechanical equipment used in the step S3 is a pile driver, the depth of the precast tubular pile 1 entering the deep foundation pit 5 is 20 meters, and the bottom of the precast tubular pile 1 is provided with an embedded rod 8; in the step S3, the distance between the precast tubular piles 1 is 2 meters, and the precast tubular piles 1 are PHC tubular piles; in the step S3, the first barbs 9 are arranged in a rectangular shape, and the included angle between the first barbs 9 and the precast tubular pile 1 is 30 degrees;
s4, installing a supporting protection plate 2: installing a support protection plate 2 between the two precast tubular piles 1 pre-buried in the step S3, and inserting a first inserted link 4 arranged at the bottom of the support protection plate 2 into the deep foundation pit 5;
in the step S4, the bottom end of the first inserted link 4 is arranged in a conical shape, and the first inserted link 4 is inserted into the deep foundation pit 5 to a depth of at least more than 3 m; in the step S4, a second inserted link 7 is symmetrically arranged on one side of the supporting and protecting plate 2 in a penetrating manner, one end of the second inserted link 7 is connected with a connecting disc 6, the other end of the second inserted link 7 is inserted into the shallow foundation pit 3, the tail end of the second inserted link 7 is arranged in a conical manner, the length of the second inserted link 7 inserted into the shallow foundation pit 3 is at least more than 2 m,
s5, reinforcing the junction of the shallow foundation pit 3 and the deep foundation pit 5: pouring concrete into the interior of the support protection plate 2 after installation, so as to ensure the support strength of the junction of the shallow foundation pit 3 and the deep foundation pit 5;
in the step S5, concrete is poured into the supporting and protecting plate 2 through a concrete pump and a guide pipe, so that the supporting and protecting plate 2 forms a protecting pile wall, and the overall strength of the protecting pile wall is improved;
s6, finishing enclosure: and repeating the steps in the operations S3, S4 and S5, thereby completing the formation of the foundation pit enclosure.
Example two
A foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit comprises the following steps:
s1, construction preparation: the machinery that will be under construction needs transports to the job site, mixes and stirs the concrete in advance at the job site simultaneously:
s2: and (3) treatment on a construction site: cleaning the junction of the shallow foundation pit 3 and the deep foundation pit 5, and reasonably placing the construction equipment and tools prepared in the step S1 so as to be convenient for constructors to quickly take;
s3, embedding the tubular pile: uniformly arranging the precast tubular piles 1 at the junctions of the shallow foundation pit 3 and the deep foundation pit 5 at intervals by using mechanical equipment, inserting the tail ends of the precast tubular piles 1 into the deep foundation pit 5, and simultaneously inserting first barbs 9 symmetrically arranged outside the precast tubular piles 1 into the deep foundation pit 5 so that the precast tubular piles 1 form a pile foundation;
the mechanical equipment used in the step S3 is a pile driver, the depth of the precast tubular pile 1 entering the deep foundation pit 5 is 20 meters, and the bottom of the precast tubular pile 1 is provided with an embedded rod 8; in the step S3, the distance between the precast tubular piles 1 is 2 meters, and the precast tubular piles 1 are PHC tubular piles; in the step S3, the exterior of the precast tubular pile 1 can also be provided with a second reversed thorn 10 in a disc shape, and the second reversed thorn 10 is provided with at least five groups outside the precast tubular pile 1;
s4, installing a supporting protection plate 2: installing a support protection plate 2 between the two precast tubular piles 1 pre-buried in the step S3, and inserting a first inserted rod 4 arranged at the bottom of the support protection plate 2 into the deep foundation pit 5;
in the step S4, the bottom end of the first inserted link 4 is arranged in a conical shape, and the first inserted link 4 is inserted into the deep foundation pit 5 to a depth of at least more than 3 m; in the step S4, a second inserted link 7 is symmetrically arranged on one side of the supporting and protecting plate 2 in a penetrating manner, one end of the second inserted link 7 is connected with a connecting disc 6, the other end of the second inserted link 7 is inserted into the shallow foundation pit 3, the tail end of the second inserted link 7 is arranged in a conical manner, the length of the second inserted link 7 inserted into the shallow foundation pit 3 is at least more than 2 m,
s5, reinforcing the junction of the shallow foundation pit 3 and the deep foundation pit 5: pouring concrete into the interior of the support protection plate 2 after installation, so as to ensure the support strength of the junction of the shallow foundation pit 3 and the deep foundation pit 5;
in the step S5, concrete is poured into the supporting and protecting plate 2 through a concrete pump and a guide pipe, so that the supporting and protecting plate 2 forms a protecting pile wall, and the integral strength of the protecting pile wall is improved;
s6, completing enclosure: and repeating the steps in the operations S3, S4 and S5, thereby completing the formation of the foundation pit enclosure.
EXAMPLE III
A foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit comprises the following steps:
s1, construction preparation: the machinery that will be under construction needs transports to the job site, mixes and stirs the concrete in advance at the job site simultaneously:
s2: and (3) treatment on a construction site: cleaning the junction of the shallow foundation pit 3 and the deep foundation pit 5, and reasonably placing the construction equipment and tools prepared in the step S1 so as to be convenient for constructors to quickly take;
s3, embedding the tubular pile: uniformly arranging the precast tubular piles 1 at the junctions of the shallow foundation pits 3 and the deep foundation pit 5 at intervals by using mechanical equipment, inserting the tail ends of the precast tubular piles 1 into the deep foundation pit 5, and simultaneously inserting first barbs 9 symmetrically arranged outside the precast tubular piles 1 into the deep foundation pit 5 so that the precast tubular piles 1 form a pile foundation;
the mechanical equipment used in the step S3 is a pile driver, the depth of the precast tubular pile 1 entering the deep foundation pit 5 is 30 meters, and the bottom of the precast tubular pile 1 is provided with an embedded rod 8; in the step S3, the distance between the precast tubular piles 1 is 4 meters, and the precast tubular piles 1 are PHC tubular piles; in the step S3, the first barbs 9 are arranged in a rectangular shape, and the included angle between the first barbs 9 and the precast tubular pile 1 is 50 degrees;
s4, installing a supporting protection plate 2: installing a support protection plate 2 between the two precast tubular piles 1 pre-buried in the step S3, and inserting a first inserted rod 4 arranged at the bottom of the support protection plate 2 into the deep foundation pit 5;
in the step S4, the bottom end of the first inserted link 4 is arranged in a conical shape, and the first inserted link 4 is inserted into the deep foundation pit 5 to a depth of at least more than 3 m; in the step S4, a second inserted link 7 is symmetrically arranged on one side of the supporting and protecting plate 2 in a penetrating manner, one end of the second inserted link 7 is connected with a connecting disc 6, the other end of the second inserted link 7 is inserted into the shallow foundation pit 3, the tail end of the second inserted link 7 is arranged in a conical manner, the length of the second inserted link 7 inserted into the shallow foundation pit 3 is at least more than 2 m,
s5, reinforcing the junction of the shallow foundation pit 3 and the deep foundation pit 5: pouring concrete into the interior of the support protection plate 2 after installation, so as to ensure the support strength of the junction of the shallow foundation pit 3 and the deep foundation pit 5;
in the step S5, concrete is poured into the supporting and protecting plate 2 through a concrete pump and a guide pipe, so that the supporting and protecting plate 2 forms a protecting pile wall, and the overall strength of the protecting pile wall is improved;
s6, finishing enclosure: and repeating the steps in the operations S3, S4 and S5, thereby completing the formation of the foundation pit enclosure.
According to the invention, the embedded rod 8 is arranged at the bottom of the precast tubular pile 1, so that the precast tubular pile 1 can be conveniently embedded, the first barb 9 and the second barb 10 are arranged outside the precast tubular pile 1, so that the installation stability of the precast tubular pile 1 is better, and the construction efficiency is effectively improved, the support and protection plate 2 is arranged between the two precast tubular piles 1, the connection stability of the support and protection plate 2 and the shallow foundation pit 5 and the shallow foundation pit 3 can be improved by using the first insertion rod 4 and the second insertion rod 7, and meanwhile, mortar is poured into the support and protection plate 2, so that a good support and maintenance effect can be provided for the junction of the shallow foundation pit 3 and the deep foundation pit 5, the arrangement can effectively improve the working efficiency, the used equipment is fewer, the energy consumption is reduced, the operation is convenient, and the support and maintenance effect is better.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (9)

1. A foundation pit enclosure method for expanding construction from a deep foundation pit to a shallow foundation pit is characterized by comprising the following steps:
s1, construction preparation: the machinery that will be under construction needs transports to the job site, mixes and stirs the concrete in advance at the job site simultaneously:
s2: and (3) treatment on a construction site: cleaning the junction of the shallow foundation pit (3) and the deep foundation pit (5), and reasonably placing the construction equipment and tools prepared in the step S1 so as to be convenient for constructors to quickly take;
s3, embedding the tubular pile: the method comprises the following steps that mechanical equipment is utilized to uniformly and alternately arrange precast tubular piles (1) at the junction of a shallow foundation pit (3) and a deep foundation pit (5), the tail ends of the precast tubular piles (1) are inserted into the deep foundation pit (5), and meanwhile first barbs (9) symmetrically arranged on the outer portion of the precast tubular piles (1) are also inserted into the deep foundation pit (5), so that the precast tubular piles (1) form a pile foundation;
s4, installing a supporting protection plate (2): installing a supporting protection plate (2) between the two precast tubular piles (1) pre-buried in the step S3, and inserting a first insertion rod (4) arranged at the bottom of the supporting protection plate (2) into the deep foundation pit (5);
s5, reinforcing the junction of the shallow foundation pit (3) and the deep foundation pit (5): pouring concrete into the interior of the supporting and protecting plate (2) after installation, thereby ensuring the supporting strength of the junction of the shallow foundation pit (3) and the deep foundation pit (5);
s6, completing enclosure: and repeating the steps in the operations S3, S4 and S5, thereby completing the formation of the foundation pit enclosure.
2. A method for enclosing a foundation pit for extended construction from a deep foundation pit to a shallow foundation pit according to claim 1, wherein the mechanical equipment used in step S3 is a pile driver, and the depth of the precast tubular pile (1) entering the deep foundation pit (5) is 20 m-30 m, and the bottom of the precast tubular pile (1) is provided with an embedded rod (8).
3. The method for enclosing a foundation pit for extended construction from a deep foundation pit to a shallow foundation pit according to claim 1, wherein the distance between the precast tubular piles (1) in the step S3 is 2 m to 4 m, and the precast tubular piles (1) are PHC tubular piles.
4. The foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit according to claim 1, wherein the first barb (9) is rectangular in step S3, and an included angle between the first barb (9) and the precast tubular pile (1) is 30-50 degrees.
5. The method for enclosing a foundation pit for extended construction from a deep foundation pit to a shallow foundation pit according to claim 1, wherein the exterior of the precast tubular pile (1) in step S3 is further provided with a second barb (10) of a disc type, and the second barb (10) is provided with at least five groups on the exterior of the precast tubular pile (1).
6. The method for enclosing a foundation pit for extended construction of a deep foundation pit into a shallow foundation pit according to claim 1, wherein the bottom end of the first inserting rod (4) is tapered in step S4, and the first inserting rod (4) is inserted into the deep foundation pit (5) to a depth of at least 3 m or more.
7. The foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit according to claim 1, wherein a second inserted bar (7) symmetrically penetrates through one side of the supporting and protecting plate (2) in the step S4, one end of the second inserted bar (7) is connected with the connecting disc (6), and the other end of the second inserted bar (7) is inserted into the shallow foundation pit (3).
8. The method for enclosing a foundation pit for expanding construction from a deep foundation pit to a shallow foundation pit according to claim 7, wherein the end of the second inserting rod (7) is arranged in a conical shape, and the second inserting rod (7) is inserted into the shallow foundation pit (3) by at least 2 meters.
9. The foundation pit bracing method for expanding construction from a deep foundation pit to a shallow foundation pit according to claim 1, wherein concrete is poured into the supporting and protecting plate (2) through a concrete pump and a guide pipe in the step S5, so that the supporting and protecting plate (2) forms a protecting pile wall to improve the overall strength.
CN202210856523.0A 2022-07-21 2022-07-21 Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit Pending CN115162355A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210856523.0A CN115162355A (en) 2022-07-21 2022-07-21 Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210856523.0A CN115162355A (en) 2022-07-21 2022-07-21 Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit

Publications (1)

Publication Number Publication Date
CN115162355A true CN115162355A (en) 2022-10-11

Family

ID=83494501

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210856523.0A Pending CN115162355A (en) 2022-07-21 2022-07-21 Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit

Country Status (1)

Country Link
CN (1) CN115162355A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0941363A (en) * 1995-08-02 1997-02-10 Kajima Corp Method of simple underground construction
JPH09279573A (en) * 1996-04-18 1997-10-28 Kodama Concrete Kogyo Kk Steel framed bottom enlarged pile using existing pile
CN203594037U (en) * 2013-11-28 2014-05-14 杭州江润科技有限公司 Foundation pit fencing structure of prestress hollow tube piles
CN104499478A (en) * 2014-12-25 2015-04-08 山东八闽建筑工程有限公司 Prefabricated concrete supporting anchored pile
CN105544525A (en) * 2015-12-11 2016-05-04 陈明 Uplift pile with unfolding barb and construction method thereof
CN107740426A (en) * 2017-10-13 2018-02-27 南京工业大学 A kind of assembled arcading wall base pit supporting construction and construction technology
CN208235536U (en) * 2018-02-02 2018-12-14 江苏工程职业技术学院 A kind of modified H profile steel anchor pole composite pile-prefabricated board wall deep footing groove enclosing structure
CN110284506A (en) * 2019-05-22 2019-09-27 上海港城建筑安装工程有限公司 A kind of foundation pit enclosure method for the expansion construction that deep basal pit is cheated to shallow foundation
CN212077965U (en) * 2020-04-28 2020-12-04 中铁十二局集团第二工程有限公司 Deep basal pit excavation inter-pile assembled supporting construction
CN112195928A (en) * 2020-10-09 2021-01-08 中煤长江生态环境科技有限公司 Pile plate composite structure for foundation pit support
CN113585239A (en) * 2021-09-02 2021-11-02 中庆建设有限责任公司 Prestressed anchor pile
CN215290152U (en) * 2021-05-19 2021-12-24 山西工程技术学院 Novel assembled foundation pit retaining structure

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0941363A (en) * 1995-08-02 1997-02-10 Kajima Corp Method of simple underground construction
JPH09279573A (en) * 1996-04-18 1997-10-28 Kodama Concrete Kogyo Kk Steel framed bottom enlarged pile using existing pile
CN203594037U (en) * 2013-11-28 2014-05-14 杭州江润科技有限公司 Foundation pit fencing structure of prestress hollow tube piles
CN104499478A (en) * 2014-12-25 2015-04-08 山东八闽建筑工程有限公司 Prefabricated concrete supporting anchored pile
CN105544525A (en) * 2015-12-11 2016-05-04 陈明 Uplift pile with unfolding barb and construction method thereof
CN107740426A (en) * 2017-10-13 2018-02-27 南京工业大学 A kind of assembled arcading wall base pit supporting construction and construction technology
CN208235536U (en) * 2018-02-02 2018-12-14 江苏工程职业技术学院 A kind of modified H profile steel anchor pole composite pile-prefabricated board wall deep footing groove enclosing structure
CN110284506A (en) * 2019-05-22 2019-09-27 上海港城建筑安装工程有限公司 A kind of foundation pit enclosure method for the expansion construction that deep basal pit is cheated to shallow foundation
CN212077965U (en) * 2020-04-28 2020-12-04 中铁十二局集团第二工程有限公司 Deep basal pit excavation inter-pile assembled supporting construction
CN112195928A (en) * 2020-10-09 2021-01-08 中煤长江生态环境科技有限公司 Pile plate composite structure for foundation pit support
CN215290152U (en) * 2021-05-19 2021-12-24 山西工程技术学院 Novel assembled foundation pit retaining structure
CN113585239A (en) * 2021-09-02 2021-11-02 中庆建设有限责任公司 Prestressed anchor pile

Similar Documents

Publication Publication Date Title
CN104863131A (en) Polygonal cement-soil stirring pile and formation method thereof
CN102635120A (en) Supportless construction structure and supportless construction method for round deep base pit
CN109914472B (en) Soft soil area assembled comprehensive pipe gallery and construction method thereof
CN204662426U (en) Cement mixing method
CN204780874U (en) Insert many drilling rods cement mixing method of prefabricated section bar
CN110777802A (en) Deep foundation pit high-low span supporting structure and construction method thereof
CN113309132A (en) Construction method based on steel trestle bridge anchoring pile
CN203080551U (en) Vertical building envelope comprising occlusive cast-in-place piles and mixing piles
KR101187170B1 (en) Application of under pinning method in remodeling
KR20080034424A (en) A constructing method of underground structure with supporting beam for steel pipe
CN105002895A (en) Multiple-drill-rod cement-soil mixing pile inserting prefabricated profiles
CN112281828A (en) Novel composite pile structure and construction method
CN105672329B (en) The large size prefabricated building enclosure of deep basal pit and construction method
CN115162355A (en) Foundation pit enclosure method for expanding construction from deep foundation pit to shallow foundation pit
CN105714832A (en) Deep-foundation-pit large-sized precast building envelope and construction method
CN215977295U (en) Foundation pit supporting structure
KR20040031451A (en) Prestressed scaffolding method
CN202139604U (en) Cast-in-situ abnormal reinforced concrete pile core cement soil underground continuous wall for retaining and protection for foundation excavation
CN115262614A (en) Embedded rock-socketed pile foundation and construction method
CN114411758A (en) Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization
CN102505698A (en) Soil mass supporting structure and construction method thereof
CN102677679A (en) Cement-soil diaphragm wall with cast-in-situ special-shaped reinforced concrete pile cores for construction of foundation pits
CN113026801A (en) Construction method for reinforcing steel pipe pile of construction elevator foundation
CN216920329U (en) Simple precast pile and positioning device thereof
CN216891934U (en) Steel trestle bridge anchoring pile for hard stratum of sea area tidal zone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20221011