CN114411758A - Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization - Google Patents

Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization Download PDF

Info

Publication number
CN114411758A
CN114411758A CN202210133303.5A CN202210133303A CN114411758A CN 114411758 A CN114411758 A CN 114411758A CN 202210133303 A CN202210133303 A CN 202210133303A CN 114411758 A CN114411758 A CN 114411758A
Authority
CN
China
Prior art keywords
cement
shaft
pile
foundation pit
soil slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210133303.5A
Other languages
Chinese (zh)
Inventor
何世鸣
郭凯
李江
蒋凯
王满
陈辉
黄鑫峰
郁河坤
贾城
梁成华
郝雨
洪伟
王海宁
陈鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Building Material Geotechnical Engineering Corp
China Construction Third Bureau Group Beijing Co ltd
Original Assignee
Beijing Building Material Geotechnical Engineering Corp
China Construction Third Bureau Group Beijing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Building Material Geotechnical Engineering Corp, China Construction Third Bureau Group Beijing Co ltd filed Critical Beijing Building Material Geotechnical Engineering Corp
Priority to CN202210133303.5A priority Critical patent/CN114411758A/en
Publication of CN114411758A publication Critical patent/CN114411758A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a construction process of a multi-shaft pressure grouting pile for foundation pit support based on solid waste utilization, which comprises the following steps of: measuring and paying off to determine pile positions; the multi-shaft pile press-filling machine is in place; forced mixer, proportioning machine and ground pump are debugged in place; preparing the cement soil slurry for stirring, and performing slump and fluidity tests; starting the multi-shaft pile press-filling machine to drill until the designed depth is reached, stopping drilling, pumping cement slurry, and lifting the drill rod until the drill rod reaches the orifice; inserting section steel; manufacturing a detachable crown beam; and after the supporting system finishes the function, backfilling the fertilizer tank by using cement-soil slurry in a segmented and layered manner, recovering the anchor head, the waist beam and the anchor rod by layers, and finally recovering the section steel, wherein after the section steel is pulled out, the cavity is filled with the cement-soil slurry. The invention utilizes the characteristic that the multi-shaft pile press-grouting machines are mutually occluded, not only can realize high efficiency of a plurality of piles at one time, but also can realize effective and reliable occlusion between the curtain piles, and ensure no water leakage, thereby better ensuring the water stopping effect of the foundation pit supporting curtain.

Description

Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization
Technical Field
The invention relates to the technical field of foundation pit supporting, in particular to a foundation pit supporting multi-shaft pressure-grouting pile construction process based on solid waste utilization.
Background
At present, the resource utilization of solid wastes in China is more and more emphasized and more common in application, and with the implementation of the policy of encouraging the construction waste treatment, tailings of a construction waste treatment plant are gradually developed and utilized and are firstly processed into cement slurry to carry out the backfill of a construction fertilizer tank, the backfill of a municipal pipe gallery foundation tank, the backfill of a house center, the filling of an underground cavity and the like.
On one hand, however, on the other hand, most of the backfilling of the fertilizer grooves and the like adopts 2:8 lime soil or 3:7 lime soil, for a foundation pit with the depth of dozens of meters, the 2:8 lime soil or 3:7 lime soil is used for filling and tamping layer by layer, a row of reinforced concrete slope protection piles are independently made at the front row, reinforced concrete crown beams are arranged at the pile tops, 5 anchor rods are arranged, reinforcing mesh is woven among the piles for spraying concrete, the fertilizer grooves are backfilled with 2:8 lime soil, one rammer is arranged at 20cm layer by layer, 100 layers of rammers are required to be filled at 20m depth, the reinforced concrete piles and the anchor rods are permanently left underground to occupy underground space, the operation is complicated, and the quality cannot be guaranteed; on the other hand, the existing foundation pit supporting pile construction (for example, the patent number 200510082950.4 is an invention patent of a cement soil pile, the patent number 201210509644.4 is an invention patent named as a foundation pit supporting method of a cement soil type steel pile for manual hole digging, the patent number 201710870705.2 is an invention patent named as a construction method of a structural steel pressure-grouting cement soil curtain supporting pile, and the patent number 201710869952.0 is an invention patent named as a construction method of a rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile) adopts a single-shaft drilling tool for construction, so that the efficiency is low, only one pile can be formed at a time, the occlusion is not reliable when the curtain is made, and water leakage is easy.
Therefore, the technical personnel in the field need to solve the problem of providing an efficient foundation pit supporting multi-shaft pressure-grouting pile construction process based on solid waste utilization.
Disclosure of Invention
In view of the above, the invention provides a foundation pit supporting multi-shaft pressure grouting pile construction process based on solid waste utilization, so that geotechnical engineering construction is efficient, reliable and energy-saving.
In order to achieve the purpose, the invention adopts the following technical scheme:
a foundation pit supporting multi-shaft pressure grouting pile construction process based on solid waste utilization comprises the following steps:
1) measuring and paying off, and determining pile positions;
2) the multi-shaft pile press-filling machine is in place;
3) forced mixer, proportioning machine and ground pump are put in place and debugged, and a dustproof shed is set up;
4) preparing and stirring cement soil slurry: preparing cement soil slurry at a mixing station, transporting the cement soil slurry to the site by a tank truck or mixing the cement soil slurry with a forced mixer at a construction site; and testing slump and fluidity;
5) starting the multi-shaft pile press-filling machine to drill until the designed depth is reached, stopping drilling, pumping cement slurry, and lifting the drill rod until the drill rod reaches the orifice;
6) inserting the profile steel, firstly hoisting the profile steel by adopting a crane and lowering the profile steel by using the self weight of a resonance-free vibration hammer, and starting the vibration hammer to vibrate and lower the profile steel when resistance is met;
7) manufacturing a detachable crown beam;
8) and after the supporting system finishes the function, backfilling the fertilizer tank by using cement-soil slurry in a segmented and layered manner, recovering the anchor head, the waist beam and the anchor rod by layers, and finally recovering the section steel, wherein after the section steel is pulled out, the cavity is filled with the cement-soil slurry.
By adopting the scheme, the invention has the beneficial effects that:
the characteristic that the multi-shaft pile press-grouting machines are mutually occluded is utilized, so that the high efficiency of multiple piles at one time can be realized, the effective and reliable occlusion between the curtain piles can be realized, and the water tightness is ensured, thereby better ensuring the water stop effect of the foundation pit supporting curtain.
Furthermore, the multi-shaft pressure grouting pile machine is a double-shaft or three-shaft or five-shaft or nine-shaft machine.
Furthermore, adjacent helical blades on each drill rod of the multi-shaft pressure grouting pile machine are distributed at intervals, and the helical blades on the adjacent drill rods are distributed in a staggered mode.
The beneficial effect that adopts above-mentioned further technical scheme to produce does, influences each other when avoiding gyration.
Further, the formula for mixing the cement-soil slurry on the construction site is as follows: 50-90 parts of clay or silt, 10-50 parts of sandy soil, 10-15 parts of cement and 70-90 parts of water, wherein the slump is more than 200mm, the fluidity is more than 500mm, the initial setting time is 6-8 hours, the final setting time is 20-24 hours, and the 28-day test block compressive strength is 0.8-3.0 MPa; the formula for preparing the cement soil slurry in the mixing station comprises the following steps: 60-80 parts of construction waste tailings, 20-40 parts of curing agent and 70-90 parts of water, wherein the curing agent can be cement with fly ash and mineral powder or sulfur gypsum with fly ash, mineral powder and cement, the slump is greater than 200mm, the fluidity is greater than 500mm, the initial setting time is 6-8 hours, the final setting time is 16-20 hours, and the test block strength in 28 days is 0.8-3.0 MPa.
Further, in the step 8), the backfill layering number of the fertilizer grooves corresponds to the number of the anchor rod layers.
The beneficial effect that adopts above-mentioned further technical scheme to produce is, be convenient for demolish anchor head, steel waist rail and stock etc..
Therefore, the invention provides a foundation pit supporting multi-shaft pressure grouting pile construction process based on solid waste utilization, compared with the prior art, the process comprises the following steps:
1) the multi-shaft pile press-filling machine is utilized to achieve the effects of high efficiency and reliability;
2) solid wastes are fully utilized, products with high energy consumption and high carbon emission of steel bars and concrete are not used, energy is saved, emission is reduced, and the permanent occupation of an underground space caused by adding an unrecoverable anchor rod to a reinforced concrete pile is overcome;
3) the spray protection among the piles is cancelled, and the direct cost and the pollution during concrete spraying are reduced;
4) the crown beam, the steel waist beam, the anchor head and the profile steel are recycled to the maximum extent, so that the cyclic utilization is realized;
5) the vibration hammer ensures that the section steel is inserted to the designed depth, and underground pipelines of surrounding building structures and the like are not influenced.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
Fig. 1 is a process flow diagram of a foundation pit supporting multi-shaft pressure grouting pile construction process based on solid waste utilization provided by the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Take a foundation pit with a depth of 20m and a perimeter of 1000m as an example:
as shown in fig. 1, the embodiment of the invention discloses a foundation pit support multi-shaft pressure grouting pile construction process based on solid waste utilization, which comprises the following steps:
1) measuring and paying off, and determining pile positions;
2) the multi-shaft pile press-filling machine is in place; in the embodiment, a five-shaft pressure filling pile machine is adopted for pressure filling cement soil slurry;
3) forced mixer, proportioning machine and ground pump are put in place and debugged, and a dustproof shed is set up;
4) preparing and stirring cement soil slurry: preparing cement soil slurry at a mixing station, transporting the cement soil slurry to the site by a tank truck or mixing the cement soil slurry with a forced mixer at a construction site; and testing slump and fluidity; in the embodiment, the field soil taking can be selected according to the situation of the field soil, and can be cohesive soil, silt, sandy soil and the like, the curing agent can be industrial waste such as cement or gypsum (sulfur gypsum, phosphogypsum) and the like, or the curing agent can be conveyed to the field by a tank truck after being stirred by a stirring station, and enters a pressure irrigation drilling machine through a ground pump pipe;
5) starting the multi-shaft pile press-filling machine to drill until the designed depth is reached, stopping drilling, pumping cement slurry, and lifting the drill rod until the drill rod reaches the orifice; in the embodiment, the upper part 6m is designed to be 1:0.3 for slope soil nailing wall support, the lower part 14m is provided with a five-shaft pile press-filling machine for press-filling cement soil slurry, the diameter is 800mm, the occlusion is 200mm, and the length of the cement soil pile is 19m
6) Inserting the profile steel, firstly hoisting the profile steel by adopting a crane and lowering the profile steel by using the self weight of a resonance-free vibration hammer, and starting the vibration hammer to vibrate and lower the profile steel when resistance is met; in the embodiment, the H-shaped steel with the length of 19m, the embedding depth of 5m and the steel section spacing of 1.4m is inserted into the separating piles, wherein the H-shaped steel with the length of 700 x 210 x 13 is inserted into the separating piles;
7) manufacturing a detachable crown beam; in this embodiment, the side of the crown beam near the pit is made of double 25b i-steel, the side of the back pit is made of a 20a channel steel, the site drilling is performed by bolts connected with the profile steel, an anchor rod is arranged on the crown beam, 4 anchor rods are distributed below the crown beam, the horizontal spacing of the anchor rods is 1.4m, the anchor rods are made of pressure dispersion type detachable anchor rods, the process of weaving reinforcing mesh and spraying concrete is cancelled among the piles, the vertical spacing is sequentially 5 anchor rods from the top of the crown beam to the bottom, and the sizes of the steel waist beam are double 25b (2 nd, 3 rd) and 28b (4 th, 5 th) i-steel;
8) after the supporting system finishes the function, the cement soil slurry is used for backfilling the fertilizer groove in a segmented and layered mode, the anchor head, the waist beam and the anchor rod are recovered in a layered mode, finally the section steel is recovered, after the section steel is pulled out, the cavity is filled with the cement soil slurry, in the embodiment, when the fertilizer groove is backfilled, the cement soil slurry is stirred on site, pumping is adopted, the cement soil slurry is used for backfilling in a segmented and layered mode, the backfilling is divided into 6 layers, each layer is stopped when the layer is filled to be 0.5-1.0 m below the steel waist beam of the anchor rod, after the section cement soil slurry is solidified, the anchor head, the steel waist beam and the anchor rod are removed, the cement soil slurry is continuously backfilled until the layer soil slurry is filled to be 1.0m below the crown beam, after the anchor head, the I-beam, the channel steel and the anchor rod are removed, the H-shaped steel is started to be pulled out, and the cavity cement soil slurry is finally filled until the upper portion of the ground surface is filled.
The invention utilizes the characteristic that the multi-shaft pile press-grouting machines are mutually occluded, not only can realize high efficiency of a plurality of piles at one time, but also can realize effective and reliable occlusion between the curtain piles, and ensure no water leakage, thereby better ensuring the water stopping effect of the foundation pit supporting curtain.
Specifically, adjacent helical blades on each drill rod of the multi-shaft pressure grouting pile machine are distributed at intervals, and the helical blades on the adjacent drill rods are distributed in a staggered mode. In this embodiment, press close to the outer pipe wall on even drilling tool and vertically have high-pressure injection thin steel pipe, high-pressure injection thin steel pipe front end has 2 high pressure nozzle, can compensate the not very reliable condition of pressure filling interlock through rotatory stirring injection function, concrete construction adopts "cover to beat the method", five pile machine constructions of pressure filling are pressed to five axles, every (1 preface stake) of beating promptly is five stakes promptly, then jump three, beat second (1 preface stake), then return and beat third (2 preface stakes) time respectively and repeatedly about.
Specifically, the formula for mixing the cement-soil slurry on the construction site is as follows: 50-90 parts of clay or silt, 10-50 parts of sandy soil, 10-15 parts of cement and 70-90 parts of water, wherein the slump is more than 200mm, the fluidity is more than 500mm, the initial setting time is 6-8 hours, the final setting time is 20-24 hours, and the 28-day test block compressive strength is 0.8-3.0 MPa; the formula for preparing the cement soil slurry in the mixing station comprises the following steps: 60-80 parts of construction waste tailings, 20-40 parts of curing agent and 70-90 parts of water, wherein the curing agent can be cement with fly ash and mineral powder or sulfur gypsum with fly ash, mineral powder and cement, the slump is greater than 200mm, the fluidity is greater than 500mm, the initial setting time is 6-8 hours, the final setting time is 16-20 hours, and the test block strength in 28 days is 0.8-3.0 MPa. In this embodiment, the cement-soil slurry is mixed at the construction site, and the formula is as follows: 75 parts of clay or silt, 25 parts of sandy soil, 10 parts of cement, 70 parts of water, more than 200mm of slump, more than 500mm of fluidity, 6 hours of initial setting time, 20 hours of final setting time and 0.8-1.2 MPa of test block strength in 28 days.
Specifically, in the step 8), the number of the backfill layers of the fertilizer groove corresponds to the number of the anchor rod layers, the layers are combined with the underground outdoor wall pasted waterproof protective benzene plate, and when the perimeter of the foundation pit is longer, the steps are performed in sections.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. The device disclosed by the embodiment corresponds to the method disclosed by the embodiment, so that the description is simple, and the relevant points can be referred to the method part for description.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (5)

1. A foundation pit supporting multi-shaft pressure grouting pile construction process based on solid waste utilization is characterized by comprising the following steps:
1) measuring and paying off, and determining pile positions;
2) the multi-shaft pile press-filling machine is in place;
3) forced mixer, proportioning machine and ground pump are put in place and debugged, and a dustproof shed is set up;
4) preparing and stirring cement soil slurry: preparing cement soil slurry at a mixing station, transporting the cement soil slurry to the site by a tank truck or mixing the cement soil slurry with a forced mixer at a construction site; and testing slump and fluidity;
5) starting the multi-shaft pile press-filling machine to drill until the designed depth is reached, stopping drilling, pumping cement slurry, and lifting the drill rod until the drill rod reaches the orifice;
6) inserting the profile steel, firstly hoisting the profile steel by adopting a crane and lowering the profile steel by using the self weight of a resonance-free vibration hammer, and starting the vibration hammer to vibrate and lower the profile steel when resistance is met;
7) manufacturing a detachable crown beam;
8) and after the supporting system finishes the function, backfilling the fertilizer tank by using cement-soil slurry in a segmented and layered manner, recovering the anchor head, the waist beam and the anchor rod by layers, and finally recovering the section steel, wherein after the section steel is pulled out, the cavity is filled with the cement-soil slurry.
2. The construction process of the multi-shaft pressure grouting pile for the foundation pit support based on the solid waste utilization as claimed in claim 1, wherein the multi-shaft pressure grouting pile machine is a double shaft or a triple shaft or a five shaft or a nine shaft.
3. The construction process of the multi-shaft pressure filling pile for the foundation pit support based on the solid waste utilization as claimed in claim 2, wherein the adjacent helical blades on each drill rod of the multi-shaft pressure filling pile machine are distributed at intervals, and the helical blades on the adjacent drill rods are distributed in a staggered mode.
4. The foundation pit support multi-shaft pressure grouting pile construction process based on solid waste utilization according to claim 1, characterized in that the formula for mixing cement-soil slurry at a construction site is as follows: 50-90 parts of clay or silt, 10-50 parts of sandy soil, 10-15 parts of cement and 70-90 parts of water, wherein the slump is more than 200mm, the fluidity is more than 500mm, the initial setting time is 6-8 hours, the final setting time is 20-24 hours, and the 28-day test block compressive strength is 0.8-3.0 MPa; the formula for preparing the cement soil slurry in the mixing station comprises the following steps: 60-80 parts of construction waste tailings, 20-40 parts of curing agent and 70-90 parts of water, wherein the curing agent can be cement with fly ash and mineral powder or sulfur gypsum with fly ash, mineral powder and cement, the slump is greater than 200mm, the fluidity is greater than 500mm, the initial setting time is 6-8 hours, the final setting time is 16-20 hours, and the test block strength in 28 days is 0.8-3.0 MPa.
5. The foundation pit support multi-shaft pressure grouting pile construction process based on solid waste utilization according to claim 1, wherein in the step 8), the number of backfill layers of the fertilizer groove corresponds to the number of anchor rod layers.
CN202210133303.5A 2022-02-09 2022-02-09 Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization Pending CN114411758A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210133303.5A CN114411758A (en) 2022-02-09 2022-02-09 Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210133303.5A CN114411758A (en) 2022-02-09 2022-02-09 Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization

Publications (1)

Publication Number Publication Date
CN114411758A true CN114411758A (en) 2022-04-29

Family

ID=81262263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210133303.5A Pending CN114411758A (en) 2022-02-09 2022-02-09 Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization

Country Status (1)

Country Link
CN (1) CN114411758A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059070A (en) * 2022-05-31 2022-09-16 北京建材地质工程有限公司 Construction method of collapse-free stratum foundation pit supporting pile based on solid waste utilization

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5693778B1 (en) * 2014-09-11 2015-04-01 竜也 近藤 Temporary mountain retaining structure and temporary mountain retaining method
CN107227737A (en) * 2016-03-25 2017-10-03 北京建材地质工程公司 Section-steel Piles pattern foundation pit supporting structure and method for pulling out
CN107653889A (en) * 2017-09-23 2018-02-02 北京建材地质工程有限公司 A kind of shaped steel pressure is poured water the construction method of soil curtain support pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5693778B1 (en) * 2014-09-11 2015-04-01 竜也 近藤 Temporary mountain retaining structure and temporary mountain retaining method
CN107227737A (en) * 2016-03-25 2017-10-03 北京建材地质工程公司 Section-steel Piles pattern foundation pit supporting structure and method for pulling out
CN107653889A (en) * 2017-09-23 2018-02-02 北京建材地质工程有限公司 A kind of shaped steel pressure is poured water the construction method of soil curtain support pile

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
代国忠: "垃圾填埋场防渗新技术", vol. 1, 31 January 2021, 重庆大学出版社, pages: 199 - 201 *
张晓宁 等: "绿色施工综合技术及应用", vol. 1, 31 December 2014, 东南大学出版社, pages: 98 - 102 *
王景军: "桩基支护与降水工程", vol. 1, 31 August 2012, 黑龙江科学技术出版社, pages: 10 - 17 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059070A (en) * 2022-05-31 2022-09-16 北京建材地质工程有限公司 Construction method of collapse-free stratum foundation pit supporting pile based on solid waste utilization

Similar Documents

Publication Publication Date Title
CN101736760B (en) Construction method of prestressed anti-floating anchor rod
CN110185844B (en) Shallow-earthing large-diameter pipe jacking construction method
CN105201513A (en) Shaft construction method for rail transit
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN106049505A (en) Construction method for deep foundation pit supporting and protecting system
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN1067453C (en) Foundation pit slope flat anchor spray net supporting method
CN107700474A (en) A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN206070508U (en) Device for reinforcing foundation
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN110106883A (en) A kind of Real-time Feedback grouting method for correcting subway tunnel horizontal distortion
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN104762957A (en) Construction method for spiral hole forming ram-expanded CFG pile
CN102235008B (en) Engineering pile deviation preventing structure of soft soil foundation and pretreatment method
CN114411758A (en) Foundation pit support multi-shaft pressure-grouting pile construction process based on solid waste utilization
CN210216452U (en) Old excavation supporting system reinforced structure
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN111779004A (en) Construction process for fast supporting high slope of broken rock by strong unloading
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN114251051B (en) Subway tunnel construction technology
RU121274U1 (en) ARTIFICIAL REINFORCED BASIS FOR ESTABLISHED OR RECONSTRUCTED BUILDING
CN213869905U (en) Large-section tunnel base anti-sedimentation structure under loose rock stack stratum
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Room 1008, floor 1, C1, building 1, No. 18, Keyuan Road, economic development zone, Daxing District, Beijing 102600

Applicant after: China Construction Third Bureau Group Beijing Co.,Ltd.

Applicant after: Beijing Building Materials Geological Engineering Co., Ltd

Address before: 102600 floors 8 and 9, building 1, yard 30, Beixing Road, Daxing District, Beijing

Applicant before: China Construction Third Bureau Group Beijing Co.,Ltd.

Applicant before: Beijing Building Materials Geological Engineering Co., Ltd

CB02 Change of applicant information