CN115125840A - Construction method of modified high-strength concrete corrugated roof combined bridge deck - Google Patents

Construction method of modified high-strength concrete corrugated roof combined bridge deck Download PDF

Info

Publication number
CN115125840A
CN115125840A CN202210599946.9A CN202210599946A CN115125840A CN 115125840 A CN115125840 A CN 115125840A CN 202210599946 A CN202210599946 A CN 202210599946A CN 115125840 A CN115125840 A CN 115125840A
Authority
CN
China
Prior art keywords
concrete
bridge deck
parts
strength concrete
modified high
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210599946.9A
Other languages
Chinese (zh)
Inventor
赵永辉
白志强
代钊
范光辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Third Highway Engineering Co Ltd
Original Assignee
CCCC SHEC Third Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Third Highway Engineering Co Ltd filed Critical CCCC SHEC Third Highway Engineering Co Ltd
Priority to CN202210599946.9A priority Critical patent/CN115125840A/en
Publication of CN115125840A publication Critical patent/CN115125840A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B40/00Processes, in general, for influencing or modifying the properties of mortars, concrete or artificial stone compositions, e.g. their setting or hardening ability
    • C04B40/02Selection of the hardening environment
    • C04B40/024Steam hardening, e.g. in an autoclave
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Toxicology (AREA)
  • Health & Medical Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种改性高强混凝土波形顶板组合式桥面板的施工方法,包括有以下工艺步骤:S1,铺设压型钢板,当前期的桥面板、中支点两侧腹板内衬以及端横梁支撑处的混凝土养护完成后,先在钢箱梁的悬臂、箱间分别铺设开口型压型钢板,再将开口型压型钢板的端部安装堵头板;S2,安装钢筋、锚垫板和预应力孔道;S3,浇筑改性高强混凝土,侧模板安装完成后浇筑改性高强混凝土;S4,养护混凝土,混凝土浇筑完成后,通过蒸汽管道通入45~55℃的蒸汽进行养护6~12h,气压控制在1.0~1.2Mpa。本发明的波形顶板和混凝土结构层之间联结可靠,降低了钢桥面板疲劳开裂可能性,明显改善桥面板的施工质量。

Figure 202210599946

The invention relates to a construction method of a modified high-strength concrete corrugated roof composite bridge deck, which includes the following process steps: S1, laying profiled steel plates, the current bridge deck, the web lining on both sides of the middle fulcrum, and the end beam support After the concrete curing is completed, firstly lay open profiled steel plates between the cantilevers and boxes of the steel box girder, and then install plug plates at the ends of the open profiled steel plates; S2, install steel bars, anchor pads and pre- Stress tunnel; S3, pouring the modified high-strength concrete, pouring the modified high-strength concrete after the installation of the side formwork; S4, curing the concrete, after the concrete pouring is completed, pass the steam at 45-55 ℃ through the steam pipe for curing for 6-12 hours, and the air pressure Controlled at 1.0 ~ 1.2Mpa. The corrugated roof and the concrete structure layer of the invention are reliable in connection, reduce the fatigue cracking possibility of the steel bridge deck, and obviously improve the construction quality of the bridge deck.

Figure 202210599946

Description

一种改性高强混凝土波形顶板组合式桥面板的施工方法A kind of construction method of modified high-strength concrete corrugated roof composite bridge deck

技术领域technical field

本发明涉及桥面结构施工领域,尤其是涉及一种改性高强混凝土波形顶板组合式桥面板的施工方法。The invention relates to the field of bridge deck structure construction, in particular to a construction method of a modified high-strength concrete corrugated roof composite bridge deck.

背景技术Background technique

钢桥面板具有自重轻、承载力高、便于制造、施工便捷等优点,被广泛应用于大、中跨桥梁工程中,但正交异性钢桥面板作为纵向与横向受力性能和局部刚度均存在显著差异的薄Steel bridge decks have the advantages of light weight, high bearing capacity, easy manufacture, and convenient construction, and are widely used in large and medium-span bridge projects. Significant difference in thinness

壁板结构,在往复轮载作用下部分焊接构造细节因应力集中而承受较高的应力幅值,不可避免的初始焊接缺陷、焊接残余应力和制造加工误差等不利因素进一步加剧了钢桥面板发生疲劳开裂的风险,已成为制约钢结构桥梁可持续发展的关键技术难题。The wall plate structure, under the action of the reciprocating wheel load, part of the welded structure details are subjected to high stress amplitude due to stress concentration, and the inevitable initial welding defects, welding residual stress and manufacturing and processing errors and other unfavorable factors further aggravate the occurrence of steel bridge decks. The risk of fatigue cracking has become a key technical problem restricting the sustainable development of steel structure bridges.

在现有技术中,钢桥面板受到轮载作用下钢桥面板的局部变形较大,铺装层和黏结层均存在较高的局部应力,在往复轮载和高温、高湿等环境因素的耦合作用下,钢桥面板铺装层易发生开裂、车辙、脱层和拥包等病害,不仅显著降低了桥梁结构的服役质量、大幅增加了运营与维护成本,而且进一步加剧了钢桥面板发生疲劳开裂的风险。In the prior art, the local deformation of the steel bridge deck under the action of wheel load is relatively large, and both the paving layer and the bonding layer have high local stress. Under the coupling action, the steel bridge deck pavement is prone to cracking, rutting, delamination and wrapping, which not only significantly reduces the service quality of the bridge structure, greatly increases the operation and maintenance costs, but also further aggravates the occurrence of steel bridge decks. Risk of fatigue cracking.

为此,亟需研发设计一种波形顶板组合桥面结构及施工工法,以解决钢桥面板疲劳开裂和桥面铺装易损两大难题,进一步提高组合桥面结构的施工质量。Therefore, it is urgent to develop and design a corrugated roof composite bridge deck structure and construction method to solve the two major problems of fatigue cracking of steel bridge deck and vulnerable deck pavement, and further improve the construction quality of composite bridge deck structure.

发明内容SUMMARY OF THE INVENTION

针对现有技术存在的问题,本发明的目的是提供一种波形顶板组合桥面结构及施工工法,波形顶板和混凝土结构层之间联结可靠,降低了钢桥面板疲劳开裂可能性,明显改善桥面板的施工质量。In view of the problems existing in the prior art, the purpose of the present invention is to provide a corrugated roof deck combined bridge deck structure and construction method, the connection between the corrugated roof and the concrete structure layer is reliable, the possibility of fatigue cracking of the steel bridge deck is reduced, and the bridge deck is obviously improved. Construction quality of the panels.

本发明的上述目的是通过以下技术方案得以实现的:Above-mentioned purpose of the present invention is achieved through the following technical solutions:

一种改性高强混凝土波形顶板组合式桥面板的施工方法,包括有以下工艺步骤:A construction method of a modified high-strength concrete corrugated roof composite bridge deck, comprising the following process steps:

S1,铺设压型钢板,当前期的桥面板、中支点两侧腹板内衬以及端横梁支撑处的混凝土养护完成后,先在钢箱梁的悬臂、箱间分别铺设开口型压型钢板,再将开口型压型钢板的端部安装堵头板;S1, laying profiled steel plates. After the current bridge deck, the web lining on both sides of the mid-fulcrum and the concrete curing at the end beam supports are completed, firstly lay open profiled steel plates between the cantilevers and boxes of the steel box girder. Then install the plug plate at the end of the open profiled steel plate;

S2,安装钢筋、锚垫板和预应力孔道,具体分为操作步骤:S2, install steel bars, anchor plates and prestressed tunnels, which are divided into operation steps:

(1)先在开口型压型钢板四周弹出钢筋骨架的边线,并采用钢筋定位胎架控制钢筋的间距,然后将钢筋安装绑扎于开口型压型钢板内;(1) First pop out the edge of the steel bar frame around the open profiled steel plate, and use the steel bar positioning frame to control the spacing of the steel bars, and then install and bind the steel bars in the open profiled steel plate;

(2)在钢筋骨架片安装过程中,按照预定位置安装锚垫板,保证锚垫板的安装位置要求;(2) During the installation of the reinforced skeleton sheet, install the anchor plate according to the predetermined position to ensure the installation position requirements of the anchor plate;

(3)预应力孔道选用波纹管,锚固端上安装的预埋锚环顶板应垂直与预应力孔道的中心线,预应力孔道上设置压浆孔和排气孔;(3) Corrugated pipes are used for the prestressed tunnel, the top plate of the embedded anchor ring installed on the anchoring end should be perpendicular to the center line of the prestressed tunnel, and grouting holes and exhaust holes are set on the prestressed tunnel;

S3,浇筑改性高强混凝土,侧模板安装完成后浇筑后期的桥面板、端横梁、墩顶连续处和中支点两侧的混凝土,三辊轴混凝土摊铺机以30~40m/h的布料速度进行施工,布料前喷水湿润箱梁的表面;S3, pouring the modified high-strength concrete. After the side formwork is installed, pour the bridge deck, end beam, pier top continuous and both sides of the middle fulcrum. The three-roller concrete paver is placed at a speed of 30-40m/h. For construction, spray water to wet the surface of the box girder before fabricating;

S4,养护混凝土,混凝土浇筑完成后,通过蒸汽管道通入45~55℃的蒸汽进行养护6~12h,气压控制在1.0~1.2Mpa,直至桥面板、端横梁、墩顶连续处和中支点两侧的混凝土养护达到设计标准。S4, curing the concrete. After the concrete is poured, the steam at 45-55°C is introduced through the steam pipe for curing for 6-12 hours, and the air pressure is controlled at 1.0-1.2Mpa until the bridge deck, end beam, pier top continuous and middle pivot point. The concrete curing on the side reaches the design standard.

更进一步地,所述改性高强混凝土由以下重量份的组分制成:水泥35~45份、细砂8~10份、碎石20~25份、水50~60份、改性沥青5.5~7.5份、偏高岭土8~10份、粉煤灰3~5份、流平剂0.6~0.8份。Further, the modified high-strength concrete is made of the following components in parts by weight: 35-45 parts of cement, 8-10 parts of fine sand, 20-25 parts of crushed stone, 50-60 parts of water, and 5.5 parts of modified asphalt ~7.5 parts, 8-10 parts of metakaolin, 3-5 parts of fly ash, 0.6-0.8 part of leveling agent.

更进一步地,所述改性沥青由以下重量份的组分充分混合制成:基质沥青60~80份,赤泥10~15份,胶粉5~7份,SBS改性剂2.5~5.5份,消石灰5~7份,白泥8~10份,硅酸盐材料0.3~1.6份。Further, the modified asphalt is made by fully mixing the following components by weight: 60-80 parts of base asphalt, 10-15 parts of red mud, 5-7 parts of rubber powder, and 2.5-5.5 parts of SBS modifier , 5 to 7 parts of slaked lime, 8 to 10 parts of white mud, and 0.3 to 1.6 parts of silicate materials.

更进一步地,所述预应力孔道的一端为压浆端,压浆端与压浆泵相连接,预应力孔道的另一端为吸浆端,吸浆端分支连接有废浆容器、储浆桶,储浆桶还连接有真空泵。Further, one end of the prestressed channel is the grouting end, the grouting end is connected with the grouting pump, the other end of the prestressed channel is the suction end, and the suction end is branched with a waste slurry container and a slurry storage bucket. , the slurry barrel is also connected with a vacuum pump.

更进一步地,将所述预应力孔道进行抽真空处理,直至真空压力达到-0.06~-0.1Mpa范围,然后通过压浆泵将浆体压入预应力孔道内,压浆压力控制在0.5~0.7Mpa。Further, vacuumize the prestressed channel until the vacuum pressure reaches the range of -0.06~-0.1Mpa, and then press the slurry into the prestressed channel through a grouting pump, and the grouting pressure is controlled at 0.5~0.7 Mpa.

更进一步地,所述钢箱梁的梁顶铺设有波形顶板,波形顶板的凹槽与钢筋相定位配合。Further, the top of the steel box beam is covered with a corrugated top plate, and the grooves of the corrugated top plate are positioned and matched with the steel bars.

更进一步地,所述三辊轴混凝土摊铺机的三根辊轴的长度为3.5m,直径为219mm,布料高度高出轨道2cm。Further, the length of the three rollers of the three-roller concrete paver is 3.5m, the diameter is 219mm, and the height of the material is 2cm higher than the track.

更进一步地,所述波纹管的每个顶点位置均设有排气孔,每个低点位置均设有排水孔,每个顶点和两端部均设有检查孔,排气孔、排水孔分别对应连接有排气管和排水管。Further, each vertex position of the bellows is provided with an exhaust hole, each low point position is provided with a drainage hole, each vertex and both ends are provided with inspection holes, exhaust holes and drainage holes. Correspondingly, an exhaust pipe and a drain pipe are connected.

更进一步地,所述蒸汽管道连接有电加热蒸汽发生器,电加热蒸汽发生器包括供水系统、自控系统、加热系统和安全保护系统,电加热蒸汽发生器产生的蒸汽通过蒸汽管道输入至桥面板的混凝土。Further, the steam pipeline is connected with an electric heating steam generator, the electric heating steam generator includes a water supply system, an automatic control system, a heating system and a safety protection system, and the steam generated by the electric heating steam generator is input to the bridge deck through the steam pipeline concrete.

更进一步地,所述高强混凝土浇筑完成后,静放时间为4~6h,静放环境温度不低于10℃;待高强度混凝土达到初期强度后,通入蒸汽对混凝土进行升温养生,升温速度不大于8℃/h。Further, after the high-strength concrete is poured, the standing time is 4 to 6 hours, and the ambient temperature is not lower than 10°C; after the high-strength concrete reaches the initial strength, steam is introduced to heat up the concrete. Not more than 8℃/h.

与现有技术相比,本发明至少包括以下有益技术效果:Compared with the prior art, the present invention at least includes the following beneficial technical effects:

1.本发明的施工方法采用高弹性模量、高抗拉压强度的改性高强混凝土材料作为桥面结构层,通过改进其中混凝土的组分配比以及掺杂改性沥青,实现混凝土浇筑完成后免蒸养目的,该改性混凝土的使用可大幅降低结构层的厚度和自重,并提升组合桥面板耐久性。本发明采用与波形腹板同样方式将波形顶板轧制,并代替顶板U肋焊接,大幅减少焊缝数量,实现所有焊缝均机械化焊接,提高制造效率并控制焊接质量。本发明将原有PBL剪力连接件进行优化,采用两端自由开口的剪力连接件作为钢筋布置、限位结构结构,剪力连接件的开口形状利于钢筋布置,同时具备优良的力学与疲劳性能,可有效提升桥梁使用寿命。1. The construction method of the present invention adopts the modified high-strength concrete material of high elastic modulus and high tensile and compressive strength as the bridge deck structure layer, and realizes that after the concrete pouring is completed, the component distribution ratio of the concrete and the doped modified asphalt are improved. For the purpose of no steam curing, the use of the modified concrete can greatly reduce the thickness and self-weight of the structural layer, and improve the durability of the composite bridge deck. The invention adopts the same method as the corrugated web to roll the corrugated top plate, and replaces the U-rib welding of the top plate, greatly reduces the number of welding seams, realizes mechanized welding of all welding seams, improves the manufacturing efficiency and controls the welding quality. The invention optimizes the original PBL shear connector, and adopts the shear connector with free openings at both ends as the reinforcement arrangement and limit structure structure. performance, which can effectively improve the service life of the bridge.

2.本发明的施工方法具体步骤分为:铺设压型钢板步骤、安装钢筋、锚垫板和预应力孔道步骤、浇筑改性高强混凝土步骤、养护混凝土步骤,混凝土浇筑分为桥面板混凝土、端横梁细石子混凝土、墩顶连续处、中支点两侧混凝土,桥面板混凝土分两次浇筑工序,混凝土浇筑完成后及时进行蒸汽养护,从而保证桥面板的施工质量。混凝土浇筑过程中随时进行预拱度检测,预拱度变化过大则及时采取措施进行调整,以保证钢箱梁的施工质量。2. The specific steps of the construction method of the present invention are divided into: the step of laying profiled steel plates, the step of installing steel bars, anchor plates and prestressed tunnels, the step of pouring modified high-strength concrete, and the step of curing concrete. The fine stone concrete of the beam, the continuous part of the top of the pier, the concrete on both sides of the middle fulcrum, and the concrete of the bridge deck are poured in two steps. After the concrete is poured, steam curing is carried out in time to ensure the construction quality of the bridge deck. Pre-camber detection should be carried out at any time during the concrete pouring process. If the pre-camber changes too much, measures should be taken to adjust it in time to ensure the construction quality of the steel box girder.

3.本发明采用真空辅助压浆工艺进行孔道压浆时,所有预应力孔道均在每个顶点设排气孔,在每个低点设排水孔,在每顶点和两端设检查孔,待预应力孔道内真空压力达到并稳定在-0.06~-0.1MPa范围时,采用低档慢速将浆体压入预应力孔道,压浆压力控制在0.5~0.7MPa,从而可以实时监控孔道内的气密性情况,保证波纹管与各个管道连接的密封性和连接强度满足要求。3. When the vacuum-assisted grouting process is used in the present invention to perform grouting, all prestressed ducts are provided with exhaust holes at each vertex, drainage holes at each low point, and inspection holes at each vertex and both ends. When the vacuum pressure in the prestressed channel reaches and stabilizes in the range of -0.06~-0.1MPa, the slurry is pressed into the prestressed channel at low speed and slow speed, and the grouting pressure is controlled at 0.5~0.7MPa, so that the gas in the channel can be monitored in real time. To ensure that the tightness and connection strength of the connection between the bellows and each pipeline meet the requirements.

4.本发明的改性高强混凝土浇筑施工完毕后,在其覆盖土工布并撒适量温水养护,混凝土表面布设蒸汽管道,保证混凝土的养护温度满足要求,并有效避免高温蒸汽可能对涂层的影响,混凝土在养护过程采用搭设整体棚架进行保温,外侧包裹保温篷布,养护时记录养护温度及湿度,并检测第三天、第四天、第五天混凝土及弹模强度,确定养护周期,从而保证混凝土的养护质量。4. After the construction of the modified high-strength concrete of the present invention is completed, cover it with a geotextile and sprinkle an appropriate amount of warm water for curing, and arrange a steam pipeline on the surface of the concrete to ensure that the curing temperature of the concrete meets the requirements, and effectively avoid the influence of high-temperature steam on the coating. , In the curing process of concrete, an overall scaffold is used for thermal insulation, and the outer side is wrapped with thermal insulation tarpaulin. The curing temperature and humidity are recorded during curing, and the strength of concrete and elastic mold on the third, fourth and fifth days is tested to determine the curing cycle. So as to ensure the quality of concrete curing.

附图说明Description of drawings

图1是本发明的工艺流程示意图。Fig. 1 is the process flow schematic diagram of the present invention.

图2是本发明的桥面板的结构示意图。FIG. 2 is a schematic structural diagram of the bridge deck of the present invention.

图3是本发明的开口型压型钢板布置示意图。Fig. 3 is a schematic diagram of the arrangement of the open profiled steel plate of the present invention.

图4是本发明的桥面板的混凝土浇筑示意图。Fig. 4 is a schematic diagram of concrete pouring of the bridge deck of the present invention.

图5是本发明的真空辅助压浆示意图。Fig. 5 is a schematic diagram of the vacuum-assisted grouting of the present invention.

图中附图标记:1、钢箱梁;2、悬臂;3、开口型压型钢板;4、端横梁支撑处的混凝土;5、压浆泵;6、排气阀;7、预应力孔道;8、储浆桶;9、真空泵;10、废浆容器;11、压浆端;12、吸浆端;13、桥面板;13-a、桥面板前期浇筑的混凝土;13-b、桥面板后期浇筑的混凝土。Reference symbols in the figure: 1. Steel box girder; 2. Cantilever; 3. Open profiled steel plate; 4. Concrete at the end beam support; 5. Grouting pump; 6. Exhaust valve; 7. Prestressed tunnel ;8, slurry tank; 9, vacuum pump; 10, waste slurry container; 11, grouting end; 12, suction end; 13, bridge deck; 13-a, pre-cast concrete for bridge deck; 13-b, bridge Panel post poured concrete.

具体实施方式Detailed ways

以下结合附图对本发明作进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings.

参照图1和图2,本实施例公开了一种改性高强混凝土波形顶板组合式桥面板的施工方法,包括有以下工艺步骤:1 and 2, the present embodiment discloses a construction method of a modified high-strength concrete corrugated roof composite bridge deck, which includes the following process steps:

S1,铺设压型钢板,参照图3,当前期的桥面板13、中支点两侧腹板内衬以及端横梁支撑处的混凝土4养护完成后,先在钢箱梁1的悬臂2、箱间分别铺设开口型压型钢板3,再将开口型压型钢板3的端部安装堵头板,钢箱梁1的梁顶铺设有波形顶板,波形顶板的凹槽与钢筋相定位配合。S1, laying profiled steel plates, referring to Figure 3, after the current bridge deck 13, the web linings on both sides of the middle fulcrum and the concrete 4 at the end beam supports are cured, first install the cantilever 2 of the steel box girder 1, between the boxes Lay the open profiled steel plates 3 respectively, and then install the plug plates at the ends of the open profiled steel plates 3. The beam top of the steel box girder 1 is laid with a corrugated top plate, and the grooves of the corrugated top plate are positioned and matched with the steel bars.

S2,安装钢筋、锚垫板和预应力孔道7,具体分为操作步骤:S2, install reinforcing bars, anchor plates and prestressed tunnels 7, which are divided into operation steps:

(1)先在开口型压型钢板3四周弹出钢筋骨架的边线,并采用钢筋定位胎架控制钢筋的间距,然后将钢筋安装绑扎于开口型压型钢板3内;(1) First pop out the edge of the steel bar frame around the open profiled steel plate 3, and use the steel bar positioning frame to control the spacing of the steel bars, and then install and bind the steel bars in the open profiled steel plate 3;

(2)在钢筋骨架片安装过程中,按照预定位置安装锚垫板,保证锚垫板的安装位置要求;(2) During the installation of the reinforced skeleton sheet, install the anchor plate according to the predetermined position to ensure the installation position requirements of the anchor plate;

(3)预应力孔道7选用波纹管,锚固端上安装的预埋锚环顶板应垂直与预应力孔道7的中心线,预应力孔道7上设置压浆孔和排气孔;(3) Corrugated pipes are used for the prestressed channel 7. The top plate of the embedded anchor ring installed on the anchoring end should be perpendicular to the center line of the prestressed channel 7. The prestressed channel 7 is provided with grouting holes and exhaust holes;

S3,浇筑改性高强混凝土,参照图4,三辊轴混凝土摊铺机的三根辊轴的长度为3.5m,直径为219mm,布料高度高出轨道2cm。侧模板安装完成后浇筑后期的桥面板13、端横梁、墩顶连续处和中支点两侧的混凝土,三辊轴混凝土摊铺机以30~40m/h的布料速度进行施工,布料前喷水湿润箱梁的表面;S3, pouring modified high-strength concrete, referring to Figure 4, the length of the three rollers of the three-roller concrete paver is 3.5m, the diameter is 219mm, and the height of the material is 2cm higher than the track. After the side formwork is installed, the bridge deck 13, the end beams, the concrete at the continuous part of the pier top and the two sides of the middle fulcrum are poured in the later stage. Wet the surface of the box girder;

S4,养护混凝土,混凝土浇筑完成后,通过蒸汽管道通入45~55℃的蒸汽进行养护6~12h,气压控制在1.0~1.2Mpa,直至桥面板13、端横梁、墩顶连续处和中支点两侧的混凝土养护达到设计标准。蒸汽管道连接有电加热蒸汽发生器,电加热蒸汽发生器包括供水系统、自控系统、加热系统和安全保护系统,电加热蒸汽发生器产生的蒸汽通过蒸汽管道输入至桥面板13的混凝土。高强混凝土浇筑完成后,静放时间为4~6h,静放环境温度不低于10℃;待高强度混凝土达到初期强度后,通入蒸汽对混凝土进行升温养生,升温速度不大于8℃/h。S4, curing the concrete. After the concrete is poured, the steam at 45-55°C is passed through the steam pipe for curing for 6-12 hours, and the air pressure is controlled at 1.0-1.2Mpa until the bridge deck 13, the end beam, the pier top continuous and the middle fulcrum The concrete curing on both sides reaches the design standard. The steam pipeline is connected with an electric heating steam generator. The electric heating steam generator includes a water supply system, an automatic control system, a heating system and a safety protection system. The steam generated by the electric heating steam generator is input to the concrete of the bridge deck 13 through the steam pipeline. After the high-strength concrete is poured, the standing time is 4 to 6 hours, and the ambient temperature is not lower than 10 °C; after the high-strength concrete reaches the initial strength, the concrete is heated and cured with steam, and the heating rate is not more than 8 °C/h .

本实施例中,改性高强混凝土由以下重量份的组分制成:水泥40份、细砂9份、碎石22份、水55份、改性沥青6.5份、偏高岭土9份、粉煤灰4份、流平剂0.7份。改性沥青由以下重量份的组分充分混合制成:基质沥青70份,赤泥12份,胶粉6份,SBS改性剂4份,消石灰6份,白泥9份,硅酸盐材料0.9份。In this embodiment, the modified high-strength concrete is made from the following components by weight: 40 parts of cement, 9 parts of fine sand, 22 parts of crushed stone, 55 parts of water, 6.5 parts of modified asphalt, 9 parts of metakaolin, and pulverized coal. 4 parts of ash, 0.7 part of leveling agent. Modified asphalt is made by fully mixing the following components by weight: 70 parts of base asphalt, 12 parts of red mud, 6 parts of rubber powder, 4 parts of SBS modifier, 6 parts of slaked lime, 9 parts of white mud, silicate material 0.9 servings.

参照图5,预应力孔道7的一端为压浆端11,压浆端11与压浆泵5相连接,预应力孔道7的另一端为吸浆端12,吸浆端12分支连接有废浆容器10、储浆桶8,储浆桶8还连接有真空泵9,压浆端11、吸浆端12均设有排气阀6。将预应力孔道7进行抽真空处理,直至真空压力达到-0.06~-0.1Mpa范围,然后通过压浆泵5将浆体压入预应力孔道7内,压浆压力控制在0.5~0.7Mpa。Referring to Figure 5, one end of the prestressed hole 7 is the grouting end 11, the grouting end 11 is connected to the grouting pump 5, the other end of the prestressed hole 7 is the suction end 12, and the suction end 12 is branched and connected with waste pulp The container 10, the slurry storage barrel 8, the slurry storage barrel 8 is also connected with a vacuum pump 9, and the slurry pressing end 11 and the slurry suction end 12 are provided with an exhaust valve 6. The prestressed channel 7 is vacuumed until the vacuum pressure reaches -0.06~-0.1Mpa, and then the slurry is pressed into the prestressed channel 7 by the grouting pump 5, and the grouting pressure is controlled at 0.5~0.7Mpa.

波纹管的每个顶点位置均设有排气孔,每个低点位置均设有排水孔,每个顶点和两端部均设有检查孔,排气孔、排水孔分别对应连接有排气管和排水管,压浆管、排气管和排水管为最小内径为20mm的标准管或适配的塑性管。Each vertex of the bellows is provided with an exhaust hole, each low point is provided with a drainage hole, each vertex and both ends are provided with inspection holes, and the exhaust holes and the drainage holes are respectively connected with exhaust holes. Pipe and drain pipes, grouting pipes, exhaust pipes and drain pipes are standard pipes or suitable plastic pipes with a minimum inner diameter of 20mm.

本实施例公开的改性高强混凝土波形顶板组合式桥面板13的施工方法的工作原理如下:施工方法分为铺设压型钢板步骤、安装钢筋、锚垫板和预应力孔道7步骤、浇筑改性高强混凝土步骤、养护混凝土步骤,混凝土浇筑分为桥面板13混凝土、端横梁细石子混凝土、墩顶连续处、中支点两侧混凝土,桥面板13混凝土分两次浇筑工序,混凝土浇筑完成后及时进行蒸汽养护,从而保证桥面板13的施工质量。混凝土浇筑过程中随时进行预拱度检测,预拱度变化过大则及时采取措施进行调整,以保证钢箱梁1的施工质量。The working principle of the construction method of the modified high-strength concrete corrugated roof composite bridge deck 13 disclosed in this embodiment is as follows: the construction method is divided into the steps of laying profiled steel plates, installing steel bars, anchor plates and prestressed tunnels 7 steps, pouring modification The high-strength concrete step and the curing concrete step, the concrete pouring is divided into the bridge deck 13 concrete, the end beam fine stone concrete, the continuous part of the pier top, and the concrete on both sides of the middle fulcrum. The bridge deck 13 concrete is poured in two steps. Steam curing, so as to ensure the construction quality of the bridge deck 13. During the concrete pouring process, the pre-camber detection should be carried out at any time. If the pre-camber changes too much, measures should be taken to adjust it in time to ensure the construction quality of the steel box girder 1.

另外,该施工方法采用高弹性模量、高抗拉压强度的改性高强混凝土材料作为桥面结构层,通过改进其中混凝土的组分配比以及掺杂改性沥青,实现混凝土浇筑完成后免蒸养目的,该改性混凝土的使用可大幅降低结构层的厚度和自重,并提升组合桥面板13耐久性。本发明采用与波形腹板同样方式将波形顶板轧制,并代替顶板U肋焊接,大幅减少焊缝数量,实现所有焊缝均机械化焊接,提高制造效率并控制焊接质量。In addition, the construction method adopts the modified high-strength concrete material with high elastic modulus and high tensile and compressive strength as the bridge deck structure layer. For maintenance purposes, the use of the modified concrete can greatly reduce the thickness and self-weight of the structural layer, and improve the durability of the composite bridge deck 13 . The invention adopts the same method as the corrugated web to roll the corrugated top plate, and replaces the U-rib welding of the top plate, greatly reduces the number of welding seams, realizes mechanized welding of all welding seams, improves the manufacturing efficiency and controls the welding quality.

本具体实施方式的实施例均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The embodiments of this specific embodiment are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore: all equivalent changes made according to the structure, shape and principle of the present invention should be covered in within the protection scope of the present invention.

Claims (10)

1.一种改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于,包括有以下工艺步骤:1. a construction method of modified high-strength concrete corrugated roof composite bridge deck, is characterized in that, comprises following processing steps: S1,铺设压型钢板,当前期的桥面板(13)、中支点两侧腹板内衬以及端横梁支撑处的混凝土(4)养护完成后,先在钢箱梁(1)的悬臂(2)、箱间分别铺设开口型压型钢板(3),再将开口型压型钢板(3)的端部安装堵头板;S1, laying profiled steel plates, the current bridge deck (13), the web linings on both sides of the middle fulcrum, and the concrete (4) at the end beam supports are cured, first install the cantilever (2) of the steel box girder (1). ) and between the boxes respectively lay open profiled steel plates (3), and then install plug plates on the ends of the open profiled steel plates (3); S2,安装钢筋、锚垫板和预应力孔道(7),具体分为操作步骤:S2, install reinforcing bars, anchor plates and prestressed tunnels (7), which are divided into operation steps: (1)先在开口型压型钢板(3)四周弹出钢筋骨架的边线,并采用钢筋定位胎架控制钢筋的间距,然后将钢筋安装绑扎于开口型压型钢板(3)内;(1) First pop out the edge of the steel frame around the open profiled steel plate (3), and use the steel bar to locate the frame to control the spacing of the steel bars, and then install and bind the steel bars in the open profiled steel plate (3); (2)在钢筋骨架片安装过程中,按照预定位置安装锚垫板,保证锚垫板的安装位置要求;(2) During the installation of the reinforced skeleton sheet, install the anchor plate according to the predetermined position to ensure the installation position requirements of the anchor plate; (3)预应力孔道(7)选用波纹管,锚固端上安装的预埋锚环顶板应垂直与预应力孔道(7)的中心线,预应力孔道(7)上设置压浆孔和排气孔;(3) Corrugated pipes are used for the prestressed tunnel (7). The top plate of the embedded anchor ring installed on the anchoring end should be perpendicular to the centerline of the prestressed tunnel (7). The prestressed tunnel (7) is provided with grouting holes and exhaust. hole; S3,浇筑改性高强混凝土,侧模板安装完成后浇筑后期的桥面板(13)、端横梁、墩顶连续处和中支点两侧的混凝土,三辊轴混凝土摊铺机以30~40m/h的布料速度进行施工,布料前喷水湿润箱梁的表面;S3, pouring the modified high-strength concrete, pouring the bridge deck (13) in the later stage, the end beams, the continuous part of the pier top and the concrete on both sides of the middle fulcrum after the installation of the side formwork, the three-roller concrete paver runs at 30-40m/h The construction is carried out at a high speed of distribution, and the surface of the box girder is wetted by spraying water before the distribution; S4,养护混凝土,混凝土浇筑完成后,通过蒸汽管道通入45~55℃的蒸汽进行养护6~12h,气压控制在1.0~1.2Mpa,直至桥面板(13)、端横梁、墩顶连续处和中支点两侧的混凝土养护达到设计标准。S4, curing the concrete. After the concrete is poured, the steam at 45-55°C is introduced through the steam pipe for curing for 6-12 hours, and the air pressure is controlled at 1.0-1.2Mpa until the bridge deck (13), the end beam, the pier top continuous and The concrete curing on both sides of the central fulcrum reaches the design standard. 2.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:所述改性高强混凝土由以下重量份的组分制成:水泥35~45份、细砂8~10份、碎石20~25份、水50~60份、改性沥青5.5~7.5份、偏高岭土8~10份、粉煤灰3~5份、流平剂0.6~0.8份。2. The construction method of modified high-strength concrete corrugated roof composite bridge deck according to claim 1, characterized in that: the modified high-strength concrete is made of the following components by weight: 35-45 parts of cement, fine 8-10 parts of sand, 20-25 parts of gravel, 50-60 parts of water, 5.5-7.5 parts of modified asphalt, 8-10 parts of metakaolin, 3-5 parts of fly ash, and 0.6-0.8 parts of leveling agent. 3.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:所述改性沥青由以下重量份的组分充分混合制成:基质沥青60~80份,赤泥10~15份,胶粉5~7份,SBS改性剂2.5~5.5份,消石灰5~7份,白泥8~10份,硅酸盐材料0.3~1.6份。3. The construction method of modified high-strength concrete corrugated roof composite bridge deck according to claim 1, characterized in that: the modified asphalt is made by fully mixing the following components by weight: 60-80 parts of base asphalt , 10 to 15 parts of red mud, 5 to 7 parts of rubber powder, 2.5 to 5.5 parts of SBS modifier, 5 to 7 parts of slaked lime, 8 to 10 parts of white mud, and 0.3 to 1.6 parts of silicate materials. 4.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:所述预应力孔道(7)的一端为压浆端(11),压浆端(11)与压浆泵(5)相连接,预应力孔道(7)的另一端为吸浆端(12),吸浆端(12)分支连接有废浆容器(10)、储浆桶(8),储浆桶(8)还连接有真空泵(9)。4. The construction method of modified high-strength concrete corrugated roof composite bridge deck according to claim 1, characterized in that: one end of the prestressed tunnel (7) is a grouting end (11), and the grouting end (11) ) is connected with the grouting pump (5), the other end of the prestressed hole (7) is the suction end (12), and the suction end (12) is branched with a waste slurry container (10) and a slurry storage bucket (8) , the slurry storage barrel (8) is also connected with a vacuum pump (9). 5.根据权利要求4所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:将所述预应力孔道(7)进行抽真空处理,直至真空压力达到-0.06~-0.1Mpa范围,然后通过压浆泵(5)将浆体压入预应力孔道(7)内,压浆压力控制在0.5~0.7Mpa。5. The construction method of the modified high-strength concrete corrugated roof composite bridge deck according to claim 4, wherein the prestressed tunnel (7) is subjected to vacuum treatment until the vacuum pressure reaches -0.06~-0.1 Mpa range, and then press the slurry into the prestressed hole (7) through the grouting pump (5), and the grouting pressure is controlled at 0.5-0.7Mpa. 6.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:所述钢箱梁(1)的梁顶铺设有波形顶板,波形顶板的凹槽与钢筋相定位配合。6. The construction method of modified high-strength concrete corrugated roof composite bridge deck according to claim 1, characterized in that: the beam top of the steel box girder (1) is laid with a corrugated roof, and the grooves of the corrugated roof and the steel bars Matching positioning. 7.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:所述三辊轴混凝土摊铺机的三根辊轴的长度为3.5m,直径为219mm,布料高度高出轨道2cm。7. The construction method of modified high-strength concrete corrugated roof composite bridge deck according to claim 1, characterized in that: the length of the three rollers of the three-roller concrete paver is 3.5m, and the diameter is 219mm, The height of the fabric is 2cm higher than the track. 8.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于:所述波纹管的每个顶点位置均设有排气孔,每个低点位置均设有排水孔,每个顶点和两端部均设有检查孔,排气孔、排水孔分别对应连接有排气管和排水管。8. The construction method of the modified high-strength concrete corrugated roof composite bridge deck according to claim 1, wherein each vertex position of the corrugated pipe is provided with an exhaust hole, and each low point position is provided with an exhaust hole. There are drainage holes, each vertex and both ends are provided with inspection holes, and the exhaust holes and the drainage holes are respectively connected with an exhaust pipe and a drainage pipe. 9.根据权利要求1所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于,所述蒸汽管道连接有电加热蒸汽发生器,电加热蒸汽发生器包括供水系统、自控系统、加热系统和安全保护系统,电加热蒸汽发生器产生的蒸汽通过蒸汽管道输入至桥面板(13)的混凝土。9. The construction method of modified high-strength concrete corrugated roof composite bridge deck according to claim 1, wherein the steam pipeline is connected with an electric heating steam generator, and the electric heating steam generator comprises a water supply system, an automatic control system , heating system and safety protection system, the steam generated by the electric heating steam generator is input to the concrete of the bridge deck (13) through the steam pipeline. 10.根据权利要求1~9任一项所述的改性高强混凝土波形顶板组合式桥面板的施工方法,其特征在于,所述高强混凝土浇筑完成后,静放时间为4~6h,静放环境温度不低于10℃;待高强度混凝土达到初期强度后,通入蒸汽对混凝土进行升温养生,升温速度不大于8℃/h。10. The construction method of the modified high-strength concrete corrugated roof composite bridge deck according to any one of claims 1 to 9, wherein after the high-strength concrete is poured, the standing time is 4-6 hours, and the standing time is 4-6 hours. The ambient temperature is not lower than 10°C; after the high-strength concrete reaches the initial strength, the concrete is heated and cured by passing in steam, and the heating rate is not more than 8°C/h.
CN202210599946.9A 2022-05-29 2022-05-29 Construction method of modified high-strength concrete corrugated roof combined bridge deck Pending CN115125840A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210599946.9A CN115125840A (en) 2022-05-29 2022-05-29 Construction method of modified high-strength concrete corrugated roof combined bridge deck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210599946.9A CN115125840A (en) 2022-05-29 2022-05-29 Construction method of modified high-strength concrete corrugated roof combined bridge deck

Publications (1)

Publication Number Publication Date
CN115125840A true CN115125840A (en) 2022-09-30

Family

ID=83378135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210599946.9A Pending CN115125840A (en) 2022-05-29 2022-05-29 Construction method of modified high-strength concrete corrugated roof combined bridge deck

Country Status (1)

Country Link
CN (1) CN115125840A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102490262A (en) * 2011-11-30 2012-06-13 中铁五局集团建筑工程有限责任公司 Steam curing construction method for ballastless track plate
KR20140102842A (en) * 2013-02-15 2014-08-25 우경기술주식회사 Bridge construction method using steel I girder with increased compression resistance
CN107268445A (en) * 2017-07-18 2017-10-20 上海宝冶集团有限公司 Large-span cast-in-situ concrete box girder post-tension of pre-stress construction under complex environment
CN208183547U (en) * 2018-04-26 2018-12-04 中交一公局桥隧工程有限公司 Box girder pre-stressed hole path pressure grouting experimental rig
CN109133739A (en) * 2018-08-25 2019-01-04 太和县鑫泰高科新型建筑材料有限公司 A kind of preparation method of rubber powder-metakaolin modified high-strength concrete
CN109972512A (en) * 2019-04-17 2019-07-05 浙江省交通规划设计研究院有限公司 A cast-in-place construction method for a profiled steel plate-concrete composite bridge deck
CN110156397A (en) * 2019-05-07 2019-08-23 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of high-strength and high-toughness self-leveling lightweight aggregate concrete and its preparation method
CN111877156A (en) * 2020-07-28 2020-11-03 长安大学 Half-opening shear connector used in corrugated steel combined bridge deck
CN112266623A (en) * 2020-10-29 2021-01-26 山东大学 Red mud-based composite modified asphalt cement paste, modified asphalt mixture, and preparation methods and applications thereof
CN112706267A (en) * 2020-12-30 2021-04-27 保利长大工程有限公司 Novel concrete curing mode
CN113416040A (en) * 2021-07-12 2021-09-21 江苏东曌建筑产业创新发展研究院有限公司 High-performance concrete

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102490262A (en) * 2011-11-30 2012-06-13 中铁五局集团建筑工程有限责任公司 Steam curing construction method for ballastless track plate
KR20140102842A (en) * 2013-02-15 2014-08-25 우경기술주식회사 Bridge construction method using steel I girder with increased compression resistance
CN107268445A (en) * 2017-07-18 2017-10-20 上海宝冶集团有限公司 Large-span cast-in-situ concrete box girder post-tension of pre-stress construction under complex environment
CN208183547U (en) * 2018-04-26 2018-12-04 中交一公局桥隧工程有限公司 Box girder pre-stressed hole path pressure grouting experimental rig
CN109133739A (en) * 2018-08-25 2019-01-04 太和县鑫泰高科新型建筑材料有限公司 A kind of preparation method of rubber powder-metakaolin modified high-strength concrete
CN109972512A (en) * 2019-04-17 2019-07-05 浙江省交通规划设计研究院有限公司 A cast-in-place construction method for a profiled steel plate-concrete composite bridge deck
CN110156397A (en) * 2019-05-07 2019-08-23 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of high-strength and high-toughness self-leveling lightweight aggregate concrete and its preparation method
CN111877156A (en) * 2020-07-28 2020-11-03 长安大学 Half-opening shear connector used in corrugated steel combined bridge deck
CN112266623A (en) * 2020-10-29 2021-01-26 山东大学 Red mud-based composite modified asphalt cement paste, modified asphalt mixture, and preparation methods and applications thereof
CN112706267A (en) * 2020-12-30 2021-04-27 保利长大工程有限公司 Novel concrete curing mode
CN113416040A (en) * 2021-07-12 2021-09-21 江苏东曌建筑产业创新发展研究院有限公司 High-performance concrete

Similar Documents

Publication Publication Date Title
CN104652210B (en) Assembled concrete traffic pavement and construction method thereof
CN104594210B (en) A kind of concrete prefabricated board and its preparation method and application
CN113586084A (en) Superposed prefabricated double-layer duct piece structure
CN107447676B (en) Prefabricated construction method of steel-ultra-high performance concrete composite beam based on folded steel plate closed ribs
CN209722630U (en) Prefabricated asphalt blocks and their paving structures
CN112813794B (en) Solid-web arch bridge system and construction method using UHPC prefabrication
CN115125840A (en) Construction method of modified high-strength concrete corrugated roof combined bridge deck
CN118548110A (en) Underground gas storage sealing structure and construction method
CN204475099U (en) A kind of assembly concrete traffic
CN218756968U (en) Seamless expansion joint structure based on spring rib
CN108589758A (en) A kind of foundation structure and construction method of acid-resistance infiltration
CN111549690A (en) A low-cost, high-performance rainwater tank-culvert combined structure and its construction method
CN117988295A (en) A steel face rockfill dam
CN203783600U (en) Bonding steel reinforcement device for highway tunnel lining surface
CN218062324U (en) A Multilayer Composite Shield Tunnel Segment Based on Fiber Concrete
CN107447675B (en) Cast-in-situ construction method of steel-ultra high performance concrete composite beam based on folded steel plate closed rib
CN214363658U (en) Seamless waterproof structure of prestressed anchor rod reverse construction method
CN112813858B (en) An open type corrugated steel culvert structure and construction method thereof
CN112962537A (en) Integrated pouring method for self-compacting rock-fill concrete dam body
CN209907695U (en) An integrated steel-concrete composite floor based on I-beam
CN108589765B (en) Cold box foundation structure adopting pearly-lustre sand concrete precast slabs and construction method thereof
CN218952105U (en) Underwater crack defect repairing structure of concrete panel dam
CN217976235U (en) A reinforced structure for railway tunnel
CN221291779U (en) Auxiliary device of prefabricated prestressed CFRP reinforced concrete pipeline structure
CN117166674B (en) Waterproof roof laminated slab, waterproof structure using same and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination