CN115045268A - 超深超厚地下连续墙施工方法 - Google Patents
超深超厚地下连续墙施工方法 Download PDFInfo
- Publication number
- CN115045268A CN115045268A CN202210799740.0A CN202210799740A CN115045268A CN 115045268 A CN115045268 A CN 115045268A CN 202210799740 A CN202210799740 A CN 202210799740A CN 115045268 A CN115045268 A CN 115045268A
- Authority
- CN
- China
- Prior art keywords
- ultra
- reinforcement cage
- support
- pouring
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210799740.0A CN115045268B (zh) | 2022-07-08 | 2022-07-08 | 超深超厚地下连续墙施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210799740.0A CN115045268B (zh) | 2022-07-08 | 2022-07-08 | 超深超厚地下连续墙施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115045268A true CN115045268A (zh) | 2022-09-13 |
CN115045268B CN115045268B (zh) | 2023-09-05 |
Family
ID=83165115
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210799740.0A Active CN115045268B (zh) | 2022-07-08 | 2022-07-08 | 超深超厚地下连续墙施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115045268B (zh) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03212508A (ja) * | 1990-01-17 | 1991-09-18 | Nippon Steel Corp | 連続地中壁構築方法および連続地中壁用鉄筋籠 |
KR20030016815A (ko) * | 2001-08-22 | 2003-03-03 | 주식회사 동우 이앤씨 건축사사무소 | Pc부재를 이용한 지하연속벽 시공방법 |
CN104120712A (zh) * | 2013-04-28 | 2014-10-29 | 杨哲 | 一种地下连续墙的施工方法 |
CN107700478A (zh) * | 2017-09-30 | 2018-02-16 | 国网福建省电力有限公司 | 输电线路工程灌注桩单桩基础一次成型施工方法 |
CN109930591A (zh) * | 2019-02-25 | 2019-06-25 | 安徽省公路桥梁工程有限公司 | 地下连续墙及其施工方法 |
CN110042855A (zh) * | 2019-04-25 | 2019-07-23 | 倡创(上海)咨询管理事务所 | 混凝土防渗墙及施工方法 |
CN110387874A (zh) * | 2019-07-30 | 2019-10-29 | 杭州江润科技有限公司 | 地下连续墙及施工方法 |
CN212026263U (zh) * | 2020-01-06 | 2020-11-27 | 中建三局第三建设工程有限责任公司 | 可拆卸装配式地下连续墙超灌混凝土防绕流装置 |
CN112376612A (zh) * | 2020-12-08 | 2021-02-19 | 安徽省路桥工程集团有限责任公司 | 大断面多舱室现浇综合管廊顶板模板施工体系及施工方法 |
-
2022
- 2022-07-08 CN CN202210799740.0A patent/CN115045268B/zh active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03212508A (ja) * | 1990-01-17 | 1991-09-18 | Nippon Steel Corp | 連続地中壁構築方法および連続地中壁用鉄筋籠 |
KR20030016815A (ko) * | 2001-08-22 | 2003-03-03 | 주식회사 동우 이앤씨 건축사사무소 | Pc부재를 이용한 지하연속벽 시공방법 |
CN104120712A (zh) * | 2013-04-28 | 2014-10-29 | 杨哲 | 一种地下连续墙的施工方法 |
CN107700478A (zh) * | 2017-09-30 | 2018-02-16 | 国网福建省电力有限公司 | 输电线路工程灌注桩单桩基础一次成型施工方法 |
CN109930591A (zh) * | 2019-02-25 | 2019-06-25 | 安徽省公路桥梁工程有限公司 | 地下连续墙及其施工方法 |
CN110042855A (zh) * | 2019-04-25 | 2019-07-23 | 倡创(上海)咨询管理事务所 | 混凝土防渗墙及施工方法 |
CN110387874A (zh) * | 2019-07-30 | 2019-10-29 | 杭州江润科技有限公司 | 地下连续墙及施工方法 |
CN212026263U (zh) * | 2020-01-06 | 2020-11-27 | 中建三局第三建设工程有限责任公司 | 可拆卸装配式地下连续墙超灌混凝土防绕流装置 |
CN112376612A (zh) * | 2020-12-08 | 2021-02-19 | 安徽省路桥工程集团有限责任公司 | 大断面多舱室现浇综合管廊顶板模板施工体系及施工方法 |
Non-Patent Citations (2)
Title |
---|
余剑锋;: "超深超厚近海地下连续墙施工关键技术", 广东土木与建筑, no. 08 * |
车申;杨德新;: "地下连续墙施工探讨", 湖南农机, no. 07 * |
Also Published As
Publication number | Publication date |
---|---|
CN115045268B (zh) | 2023-09-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11280055B1 (en) | Construction device and method for lateral bracing in ultra-deep foundation pit with silt | |
KR100694503B1 (ko) | 지하층의 1방향 보 및 데크 슬래브 시공을 위한 하향 골조타설 시스템 및 방법 | |
CN102587286A (zh) | 桥梁上部结构简支变连续施工方法 | |
CN111749140A (zh) | 一种桁架整体提升式桥梁高墩爬模装置及施工方法 | |
CN113148893A (zh) | 一种液压顶升承重支架及其安装方法 | |
CN107829408B (zh) | 矩形渡槽施工钢模台车 | |
CN102677624A (zh) | U型渡槽仿真试验装置及方法 | |
CN112431407A (zh) | 一种建筑主体悬挑结构支模施工方法 | |
CN114775622B (zh) | 紧邻建构筑物施工空间受限异形深基坑施工方法 | |
CN217268350U (zh) | 一种大跨度异形钢混柱 | |
CN115045268A (zh) | 超深超厚地下连续墙施工方法 | |
CN215164712U (zh) | 用于大跨径钢管混凝土拱施工的移动式平台系统 | |
CN215167163U (zh) | 剪力结构与维护结构一体化的预制吊装墙板单元 | |
CN217758718U (zh) | 超深超厚地下连续墙 | |
CN104532952A (zh) | 短角钢连接的钢筋混凝土装配整体式框架及其施工方法 | |
CN210256628U (zh) | 一种用于混凝土预制的自适应外模系统 | |
CN210289267U (zh) | 一种装配式站台雨棚 | |
CN202559291U (zh) | U型渡槽仿真试验装置 | |
CN111622347A (zh) | 一种装配式框架结构十字型节点连接结构及其施工方法 | |
CN213204202U (zh) | 一种板墙分离的预制装配式挡土墙 | |
CN205063369U (zh) | 超深基坑螺旋下降物料快速运输通道 | |
CN115233655B (zh) | 地铁车站围护结构半截墙施工方法 | |
CN114837137B (zh) | 混凝土闸墩滑模液压施工方法 | |
CN219690578U (zh) | 一种独立柱墩式双层板施工升降机混凝土基础结构 | |
CN214459662U (zh) | 一种用于双柱式桥墩的施工作业平台 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Sun Deming Inventor after: Zhou Bo Inventor after: Liu Fenghua Inventor after: Xia Nengwu Inventor after: Zhu Lingsheng Inventor after: Yang Zemin Inventor after: Chen Yihua Inventor after: Wu Xianbin Inventor after: Zhang Gaofeng Inventor after: Yue Xiaoqiang Inventor before: Zhou Bo Inventor before: Zhang Gaofeng Inventor before: Sun Deming Inventor before: Liu Fenghua Inventor before: Xia Nengwu Inventor before: Zhu Lingsheng Inventor before: Yang Zemin Inventor before: Chen Yihua Inventor before: Wu Xianbin Inventor before: Yue Xiaoqiang |
|
GR01 | Patent grant | ||
GR01 | Patent grant |