CN114988310A - A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof - Google Patents

A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof Download PDF

Info

Publication number
CN114988310A
CN114988310A CN202210656874.7A CN202210656874A CN114988310A CN 114988310 A CN114988310 A CN 114988310A CN 202210656874 A CN202210656874 A CN 202210656874A CN 114988310 A CN114988310 A CN 114988310A
Authority
CN
China
Prior art keywords
core tube
outer frame
floor
hoisting
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210656874.7A
Other languages
Chinese (zh)
Inventor
董军业
高继贵
刘腾
赵晓娟
王苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202210656874.7A priority Critical patent/CN114988310A/en
Publication of CN114988310A publication Critical patent/CN114988310A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66DCAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
    • B66D3/00Portable or mobile lifting or hauling appliances
    • B66D3/04Pulley blocks or like devices in which force is applied to a rope, cable, or chain which passes over one or more pulleys, e.g. to obtain mechanical advantage
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/14Slings with hooks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种爬模下核心筒内部钢梁倒运安装系统及其施工方法,涉及建筑施工大型材料调运及安装设备技术领域,技术方案为,包括起重吊装机构、方向转换机构以及吊装钢丝绳和挂钩;起重吊装机构设置在外框楼板上,起重吊装机构包括方形框底座和卷扬机。本发明的有益效果是:该装置通过合理布置核心筒外框及核心筒内水平结构施工顺序,同时在核心筒外框布置起重吊装机构、通过两个滑轮转向机构将吊装钢丝绳引入核心筒内部,通过该系统和方法可以实现在超高层核心筒采用全封闭爬模或者顶升平台体系先行施工核心筒剪力墙工况下爬模底部的钢梁等大型材料的倒运和安装,进而提高核心筒内部水平结构的施工速度。

Figure 202210656874

The invention discloses a system and a construction method for the reverse transportation and installation of steel beams inside a core tube under a climbing formwork, and relates to the technical field of large-scale material transportation and installation equipment for construction. and hooks; the hoisting and hoisting mechanism is arranged on the outer frame floor, and the hoisting and hoisting mechanism includes a square frame base and a hoist. The beneficial effects of the invention are: the device reasonably arranges the construction sequence of the outer frame of the core tube and the horizontal structure in the core tube, at the same time arranges a hoisting and hoisting mechanism on the outer frame of the core tube, and introduces the hoisting wire rope into the interior of the core tube through two pulley steering mechanisms Through the system and method, it is possible to realize the reverse transportation and installation of large materials such as steel beams at the bottom of the climbing formwork under the condition that the super high-rise core tube adopts a fully enclosed climbing formwork or a jacking platform system to construct the core tube shear wall first, thereby improving the core The construction speed of the horizontal structure inside the cylinder.

Figure 202210656874

Description

一种爬模下核心筒内部钢梁倒运安装系统及其施工方法A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof

技术领域technical field

本发明涉及建筑施工大型材料调运及安装设备技术领域,特别涉及一种爬模下核心筒内部钢梁倒运安装系统及其施工方法。The invention relates to the technical field of large-scale material transportation and installation equipment for construction, in particular to a system for reverse transportation and installation of steel beams inside a core tube under a climbing formwork and a construction method thereof.

背景技术Background technique

超高层建筑结构形式常采用“核心筒+外框钢结构”形式,且多数利用爬模或施工平台体系先行施工核心筒剪力墙结构,核心筒水平结构及外框水平结构后滞施工。The structural form of super high-rise buildings often adopts the form of "core tube + outer frame steel structure", and most of them use climbing formwork or construction platform system to construct the core tube shear wall structure first, and the core tube horizontal structure and the outer frame horizontal structure lag construction.

为适应超高层水平结构快速施工要求,水平楼板常设计成组合式楼板,通过采用压型钢板及型钢梁作为永久模板及支撑,可实现水平结构较快施工,该种模式下外框结构施工时钢梁及其他大型材料可通过核心筒上上部的塔吊实现吊装,而由于核心筒上部结构采用全封闭爬模或施工平台体系,导致塔吊吊钩无法通过爬模进入到爬模下部核心筒区域,导致下部水平结构时无法利用塔吊将材料调运至水平结构作业面,核心筒内水平楼板钢梁等大型材料调运安装困难。In order to meet the requirements of rapid construction of super high-rise horizontal structures, horizontal floor slabs are often designed as combined floor slabs. By using profiled steel plates and profiled steel beams as permanent formwork and supports, faster construction of horizontal structures can be achieved. In this mode, the outer frame structure is constructed. At the same time, steel beams and other large materials can be hoisted by the tower crane on the upper part of the core tube, but because the upper structure of the core tube adopts a fully enclosed climbing formwork or construction platform system, the tower crane hook cannot enter the core tube area below the climbing formwork through the climbing formwork. As a result, the tower crane cannot be used to transport materials to the working surface of the horizontal structure when the lower horizontal structure is used, and it is difficult to transport and install large materials such as horizontal floor steel beams in the core tube.

发明内容SUMMARY OF THE INVENTION

为了实现上述发明目的,针对上述技术问题,本发明提供一种爬模下核心筒内部钢梁倒运安装系统及其施工方法。In order to achieve the above purpose of the invention, in view of the above technical problems, the present invention provides an installation system for backward transport of steel beams inside a core tube under a climbing formwork and a construction method thereof.

其技术方案为,包括起重吊装机构、方向转换机构以及吊装钢丝绳和挂钩;The technical scheme includes a hoisting and hoisting mechanism, a direction converting mechanism, a hoisting wire rope and a hook;

位于爬模下方的核心筒外框结构第N层施工完成后,所述起重吊装机构设置在第N-M层核心筒外框结构的外框楼板上,起重吊装机构包括方形框底座和通过机械连接方式固定设置在所述方形框底座上的卷扬机。After the construction of the Nth floor of the outer frame structure of the core tube located under the climbing formwork is completed, the hoisting and hoisting mechanism is set on the outer frame floor of the outer frame structure of the core tube on the N-Mth floor. The hoisting and hoisting mechanism includes a square frame base and a mechanical The connection mode is fixedly arranged on the hoist on the base of the square frame.

卷扬机根据所需吊装材料的重量选择合适型号,作为卷扬机底座的方形框底座采用4根10#槽钢两两焊接组成方形框结构。The hoist selects the appropriate model according to the weight of the hoisting material required. The square frame base as the hoist base is welded with four 10# channel steels to form a square frame structure.

所述方形框底座的每条边均开设两个螺栓孔,方形框底座通过膨胀螺栓固定在所述核心筒外框结构的外框楼板上,所述方形框底座上设置有若干个限位钢筋,所述卷扬机固定于所述限位钢筋内部。Each side of the square frame base is provided with two bolt holes, the square frame base is fixed on the outer frame floor of the core tube outer frame structure through expansion bolts, and a number of limit steel bars are arranged on the square frame base , the hoist is fixed inside the limit steel bar.

膨胀螺栓的型号及数量需结合钢梁重量进行确定,以保证卷扬机的稳定性,同时在方形框底座四个连接位置设置限位钢筋,进一步保证卷扬机的稳定性。The type and number of expansion bolts should be determined in combination with the weight of the steel beam to ensure the stability of the winch. At the same time, limit steel bars are set at the four connection positions of the square frame base to further ensure the stability of the winch.

所述方向转换机构包括一级转向滑轮、二级转向滑轮、固定钢梁、滑轮定位钢丝绳以及橡胶垫。The direction conversion mechanism includes a primary diverting pulley, a secondary diverting pulley, a fixed steel beam, a pulley positioning wire rope and a rubber pad.

所述固定钢梁设置在所述外框楼板上,所述滑轮定位钢丝绳通过卡扣固定在所述固定钢梁上,所述滑轮定位钢丝绳和固定钢梁的连接位置处设置橡胶垫,所述二级转向滑轮设置在滑轮定位钢丝绳上;The fixed steel beam is arranged on the outer frame floor, the pulley positioning wire rope is fixed on the fixed steel beam through a buckle, a rubber pad is provided at the connection position of the pulley positioning wire rope and the fixed steel beam, and the The secondary steering pulley is arranged on the pulley positioning wire rope;

所述一级转向滑轮设置在所述外框楼板上。The primary diverting pulley is arranged on the outer frame floor.

所述固定钢梁设置在第N层所述外框楼板上,所述滑轮定位钢丝绳设置在第N层所述外框楼板的高度上;The fixed steel beam is arranged on the outer frame floor of the Nth layer, and the pulley positioning wire rope is arranged at the height of the outer frame floor of the Nth layer;

所述一级转向滑轮设置在第N-M层所述外框楼板上。The first-level diverting pulleys are arranged on the outer frame floors of the N-M layers.

现场施工时,由于核心筒外框结构起重吊装施工方便,因此可安排核心筒外框结构的施工提前于核心筒内框水平结构的施工,在施工核心筒内框水平结构时,可在核心筒内框水平结构所需施工区域的上部5到10层外框楼板上布置固定钢梁和滑轮定位钢丝绳,同时为减小滑轮定位钢丝绳和固定钢梁的摩擦,在其连接位置布置橡胶垫。During on-site construction, due to the convenience of lifting and hoisting of the outer frame structure of the core tube, the construction of the outer frame structure of the core tube can be arranged in advance of the construction of the horizontal structure of the inner frame of the core tube. Fixed steel beams and pulley positioning wire ropes are arranged on the upper 5 to 10 floors of the construction area required for the horizontal structure of the inner frame of the cylinder. At the same time, in order to reduce the friction between the pulley positioning wire rope and the fixed steel beam, rubber pads are arranged at the connection positions.

所述吊装钢丝绳一端连接所述卷扬机,另一端依次经过一级转向滑轮和二级转向滑轮后连接所述挂钩。One end of the hoisting wire rope is connected to the hoist, and the other end is connected to the hook after passing through the primary diverting pulley and the secondary diverting pulley in sequence.

在布置有起重吊装机构的外框楼板与核心筒连接的连梁位置安装一级转向滑轮,一级转向滑轮将吊装钢丝绳从外框楼板导入至核心筒内部;在滑轮定位钢丝绳中间位置安装二级转向滑轮,二级转向滑轮完成吊装钢丝绳竖直方向的转换;吊装钢丝绳从二级转向滑轮引出后连接挂钩,实现下部分段钢梁的吊装施工。Install the first-level steering pulley at the position of the connecting beam connecting the outer frame floor with the hoisting mechanism and the core tube, and the first-level steering pulley guides the hoisting wire rope from the outer frame floor to the inside of the core cylinder; The secondary steering pulley completes the conversion of the vertical direction of the hoisting wire rope; the hoisting wire rope is drawn out from the secondary steering pulley and then connected to the hook to realize the hoisting construction of the lower section steel beam.

方向转换机构的作用主要在于将吊装钢丝绳需从核心筒外框结构楼板进入核心筒内部的同时,完成吊装钢丝绳横向到竖向的方向转换。The function of the direction conversion mechanism is mainly to convert the hoisting wire rope from the horizontal to the vertical direction of the hoisting wire rope while entering the core tube from the outer frame structure floor of the core tube.

N-M为核心筒内楼板需施工层,M为所述外框楼板与核心筒内楼板的层高差,外框楼板作业面高于核心筒内框。N-M is the floor to be constructed in the core tube inner floor, M is the floor height difference between the outer frame floor slab and the core tube inner floor slab, and the working surface of the outer frame floor slab is higher than the inner frame of the core tube.

基于爬模下核心筒内部钢梁倒运安装系统的施工方法,包括以下步骤:Based on the construction method of the inverted transport installation system for the inner steel beam of the core tube under the climbing formwork, the following steps are included:

S1、核心筒外框结构第N层施工完成后,利用塔吊将核心筒内水平楼板的钢梁等大型材料调运至第N-M层外框楼板上;S1. After the construction of the Nth floor of the outer frame structure of the core tube is completed, use the tower crane to transfer large materials such as steel beams of the horizontal floor slabs in the core tube to the outer frame floor slabs of the N-M layers;

S2、在第N-M层外框楼板上布置所述起重吊装机构及所述一级转向滑轮;S2. Arrange the hoisting mechanism and the first-level steering pulley on the outer frame floor of the N-Mth floor;

S3、在第N层外框楼板上布置固定钢梁以及滑轮定位钢丝绳,并安装二级转向滑轮以及吊装钢丝绳和挂钩;S3. Arrange fixed steel beams and pulley positioning wire ropes on the outer frame floor of the Nth floor, and install secondary steering pulleys, hoisting wire ropes and hooks;

S4、下放吊装钢丝绳至第N-M层位置,并将钢梁从N-M层核心筒外框位置调运至核心筒内作业面;为保证钢梁在调运过程中的稳定,在调运过程中,需安排工人在第N-M层位置利用揽风绳向内移送钢梁,使其保持稳定慢慢进入核心筒内部。S4. Lower the hoisting wire rope to the position of the N-M layer, and transfer the steel beam from the position of the outer frame of the core tube on the N-M layer to the inner working surface of the core tube; in order to ensure the stability of the steel beam during the transfer and transportation process, it is necessary to arrange workers during the transfer and transportation process At the position of the N-M layer, use the wind rope to move the steel beam inward to keep it stable and slowly enter the core tube.

本发明实施例提供的技术方案带来的有益效果是:本发明的目的就在于研发一种适用于爬模下方区域塔吊无法进入到爬模下部工况下的钢梁等大型材料调运及安装系统及其施工方法,该装置通过合理布置核心筒外框及核心筒内水平结构施工顺序,同时在核心筒外框布置起重吊装机构、通过两个滑轮转向机构将吊装钢丝绳引入核心筒内部,通过该系统和方法可以实现在超高层核心筒采用全封闭爬模或者顶升平台体系先行施工核心筒剪力墙工况下爬模底部的钢梁等大型材料的倒运和安装,进而提高核心筒内部水平结构的施工速度,有效解决传统的核心筒内部水平结构施工效率低,施工速度慢的难题。The beneficial effects brought by the technical solutions provided by the embodiments of the present invention are as follows: the purpose of the present invention is to develop a large-scale material transportation and installation system, such as steel beams, which is suitable for the area below the climbing form where the tower crane cannot enter the lower part of the climbing form. and its construction method. The device reasonably arranges the construction sequence of the outer frame of the core tube and the horizontal structure in the core tube, and at the same time arranges a hoisting and hoisting mechanism on the outer frame of the core tube, and introduces the lifting wire rope into the core tube through two pulley steering mechanisms. The system and method can realize the reverse transportation and installation of large-scale materials such as steel beams at the bottom of the climbing formwork under the condition that the super-high-rise core tube adopts a fully enclosed climbing formwork or a jacking platform system to construct the core tube shear wall first, thereby improving the interior of the core tube. The construction speed of the horizontal structure effectively solves the problems of low construction efficiency and slow construction speed of the traditional horizontal structure inside the core tube.

附图说明Description of drawings

图1为本发明实施例核心筒和核心筒外框结构的结构示意图。FIG. 1 is a schematic structural diagram of a core tube and an outer frame structure of the core tube according to an embodiment of the present invention.

图2为本发明实施例的整体结构示意图。FIG. 2 is a schematic diagram of the overall structure of an embodiment of the present invention.

图3为图2的A局部放大图。FIG. 3 is an enlarged view of part A of FIG. 2 .

图4为图2的B局部放大图。FIG. 4 is an enlarged view of part B of FIG. 2 .

图5为图2的C局部放大图。FIG. 5 is an enlarged view of part C of FIG. 2 .

其中,附图标记为:1、起重吊装机构;2、方向转换机构;3、吊装钢丝绳;4、挂钩;5、核心筒;6、核心筒外框结构;7、外框楼板;8、塔吊;9、爬模;101、卷扬机;102、方形框底座;103、膨胀螺栓;104、限位钢筋;201、一级转向滑轮;202、二级转向滑轮;203、固定钢梁;204、滑轮定位钢丝绳;205、橡胶垫。Wherein, the reference signs are: 1, hoisting and hoisting mechanism; 2, direction conversion mechanism; 3, hoisting wire rope; 4, hook; 5, core tube; 6, outer frame structure of core tube; 7, outer frame floor; 8, Tower crane; 9. Climbing formwork; 101, hoist; 102, square frame base; 103, expansion bolt; 104, limit steel bar; 201, first-level steering pulley; 202, second-level steering pulley; 203, fixed steel beam; 204, Pulley positioning wire rope; 205, rubber pad.

具体实施方式Detailed ways

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。当然,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. Of course, the specific embodiments described herein are only used to explain the present invention, but not to limit the present invention.

需要说明的是,在不冲突的情况下,本发明创造中的实施例及实施例中的特征可以相互组合。It should be noted that the embodiments of the present invention and the features of the embodiments may be combined with each other under the condition of no conflict.

在本发明创造的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明创造和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明创造的限制。此外,术语“第一”、“第二”等仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”等的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明创造的描述中,除非另有说明,“多个”的含义是两个或两个以上。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "horizontal", "top", "bottom", "front", "rear", "left", "right", The orientation or positional relationship indicated by "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention The description is created and simplified rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore should not be construed as limiting the invention. In addition, the terms "first", "second", etc. are used for descriptive purposes only, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first", "second", etc., may expressly or implicitly include one or more of that feature. In the description of the present invention, unless otherwise specified, "plurality" means two or more.

在本发明创造的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以通过具体情况理解上述术语在本发明创造中的具体含义。In the description of the present invention, it should be noted that, unless otherwise expressly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection or a connectable connection. Detachable connection, or integral connection; may be mechanical connection or electrical connection; may be direct connection, or indirect connection through an intermediate medium, or internal communication between two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood through specific situations.

实施例1Example 1

参见图1至图5,本发明提供一种爬模下核心筒内部钢梁倒运安装系统及其施工方法,包括起重吊装机构1、方向转换机构2以及吊装钢丝绳3和挂钩4;Referring to FIGS. 1 to 5 , the present invention provides a system for inverting and installing steel beams in a core tube under a climbing formwork and a construction method thereof, including a hoisting and hoisting mechanism 1 , a direction converting mechanism 2 , a hoisting wire rope 3 and a hook 4 ;

位于爬模9下方的核心筒外框结构6第N层施工完成后,起重吊装机构1设置在第N-M层核心筒外框结构6的外框楼板7上,起重吊装机构1包括方形框底座102和通过机械连接方式固定设置在方形框底座102上的卷扬机101。After the construction of the Nth floor of the core tube outer frame structure 6 under the climbing formwork 9 is completed, the hoisting and hoisting mechanism 1 is arranged on the outer frame floor 7 of the core tube outer frame structure 6 on the N-Mth floor, and the hoisting and hoisting mechanism 1 includes a square frame. The base 102 and the hoisting machine 101 fixed on the square frame base 102 by means of mechanical connection.

卷扬机101根据所需吊装材料的重量选择合适型号,作为卷扬机底座的方形框底座102采用4根10#槽钢两两焊接组成方形框结构。The hoist 101 selects an appropriate model according to the weight of the hoisting material required. The square frame base 102 as the hoist base is formed by welding four 10# channel steels in pairs to form a square frame structure.

方形框底座102的每条边均开设两个螺栓孔,方形框底座102通过膨胀螺栓103固定在核心筒外框结构6的外框楼板7上,方形框底座102上设置有若干个限位钢筋104,卷扬机101固定于限位钢筋104内部。Each side of the square frame base 102 is provided with two bolt holes, the square frame base 102 is fixed on the outer frame floor 7 of the core tube outer frame structure 6 through expansion bolts 103, and a number of limit steel bars are arranged on the square frame base 102 104 , the hoist 101 is fixed inside the limit steel bar 104 .

膨胀螺栓103的型号及数量需结合钢梁重量进行确定,以保证卷扬机101的稳定性,同时在方形框底座102四个连接位置设置限位钢筋104,进一步保证卷扬机101的稳定性。The type and quantity of the expansion bolts 103 need to be determined in combination with the weight of the steel beam to ensure the stability of the winch 101 .

方向转换机构2包括一级转向滑轮201、二级转向滑轮202、固定钢梁203、滑轮定位钢丝绳204以及橡胶垫205。The direction conversion mechanism 2 includes a primary diverting pulley 201 , a secondary diverting pulley 202 , a fixed steel beam 203 , a pulley positioning wire rope 204 and a rubber pad 205 .

固定钢梁203设置在外框楼板7上,滑轮定位钢丝绳204通过卡扣固定在固定钢梁203上,滑轮定位钢丝绳204和固定钢梁203的连接位置处设置橡胶垫205,二级转向滑轮202设置在滑轮定位钢丝绳204上;The fixed steel beam 203 is set on the outer frame floor 7, the pulley positioning wire rope 204 is fixed on the fixed steel beam 203 by the buckle, the rubber pad 205 is set at the connection position of the pulley positioning wire rope 204 and the fixed steel beam 203, and the secondary steering pulley 202 is set on the pulley positioning wire rope 204;

一级转向滑轮201设置在外框楼板7上。The primary diverting pulley 201 is provided on the outer frame floor 7 .

固定钢梁203设置在第N层外框楼板7上,滑轮定位钢丝绳204设置在第N层外框楼板7的高度上;The fixed steel beam 203 is arranged on the outer frame floor 7 of the Nth layer, and the pulley positioning wire rope 204 is arranged on the height of the outer frame floor 7 of the Nth layer;

一级转向滑轮201设置在第N-M层外框楼板7上。The primary diverting pulley 201 is arranged on the outer frame floor 7 of the N-Mth floor.

现场施工时,由于核心筒外框结构6起重吊装施工方便,因此可安排核心筒外框结构6的施工提前于核心筒5内框水平结构的施工,在施工核心筒5内框水平结构时,可在核心筒5内框水平结构所需施工区域的上部5到10层外框楼板7上布置固定钢梁203和滑轮定位钢丝绳204,同时为减小滑轮定位钢丝绳204和固定钢梁203的摩擦,在其连接位置布置橡胶垫205。During on-site construction, due to the convenience of lifting and hoisting construction of the outer frame structure 6 of the core tube, the construction of the outer frame structure 6 of the core tube can be arranged in advance of the construction of the horizontal structure of the inner frame of the core tube 5. , the fixed steel beam 203 and the pulley positioning wire rope 204 can be arranged on the upper 5 to 10 layers of the outer frame floor 7 in the required construction area of the inner frame horizontal structure of the core tube 5, and at the same time, in order to reduce the distance between the pulley positioning wire rope 204 and the fixed steel beam 203 For friction, rubber pads 205 are arranged at their connection locations.

吊装钢丝绳3一端连接卷扬机101,另一端依次经过一级转向滑轮201和二级转向滑轮202后连接挂钩4。One end of the hoisting wire rope 3 is connected to the hoist 101 , and the other end is connected to the hook 4 after passing through the primary diverting pulley 201 and the secondary diverting pulley 202 in sequence.

在布置有起重吊装机构1的外框楼板7与核心筒5连接的连梁位置安装一级转向滑轮201,一级转向滑轮201将吊装钢丝绳3从外框楼板7导入至核心筒5内部;在滑轮定位钢丝绳204中间位置安装二级转向滑轮202,二级转向滑轮202完成吊装钢丝绳3竖直方向的转换;吊装钢丝绳3从二级转向滑轮202引出后连接挂钩4,实现下部分段钢梁的吊装施工。A first-level diverting pulley 201 is installed at the connecting beam position where the outer frame floor 7 of the hoisting and hoisting mechanism 1 is connected to the core tube 5, and the first-level diverting pulley 201 guides the hoisting wire rope 3 from the outer frame floor 7 to the core tube 5; The secondary diverting pulley 202 is installed in the middle of the pulley positioning wire rope 204, and the secondary diverting pulley 202 completes the conversion of the vertical direction of the hoisting wire rope 3; hoisting construction.

方向转换机构2的作用主要在于将吊装钢丝绳3需从核心筒外框结构6楼板进入核心筒5内部的同时,完成吊装钢丝绳3横向到竖向的方向转换。The function of the direction conversion mechanism 2 is mainly to convert the hoisting wire rope 3 from the horizontal to the vertical direction when the hoisting wire rope 3 needs to enter the core tube 5 from the floor slab of the outer frame structure 6 of the core tube.

N-M为核心筒5内楼板需施工层,M为外框楼板7与核心筒5内楼板的层高差,外框楼板7作业面高于核心筒5内框。N-M is the floor to be constructed in the core tube 5, M is the floor height difference between the outer frame floor 7 and the inner frame of the core tube 5, and the working surface of the outer frame floor 7 is higher than the inner frame of the core tube 5.

基于爬模下核心筒内部钢梁倒运安装系统的施工方法,包括以下步骤:Based on the construction method of the inverted transport installation system for the inner steel beam of the core tube under the climbing formwork, the following steps are included:

S1、核心筒外框结构6第N层施工完成后,利用塔吊8将核心筒5内水平楼板的钢梁等大型材料调运至第N-M层外框楼板7上;S1. After the construction of the Nth floor of the outer frame structure 6 of the core tube is completed, the tower crane 8 is used to transfer large materials such as steel beams of the horizontal floor slab in the core tube 5 to the outer frame floor slab 7 of the N-Mth floor;

S2、在第N-M层外框楼板7上布置起重吊装机构1及一级转向滑轮201;S2. Arrange the hoisting mechanism 1 and the first-level diverting pulley 201 on the outer frame floor 7 of the N-M layer;

S3、在第N层外框楼板7上布置固定钢梁203以及滑轮定位钢丝绳204,并安装二级转向滑轮202以及吊装钢丝绳3和挂钩4;S3. Arrange fixed steel beams 203 and pulley positioning wire ropes 204 on the Nth layer outer frame floor 7, and install secondary steering pulleys 202, hoisting wire ropes 3 and hooks 4;

S4、下放吊装钢丝绳3至第N-M层位置,并将钢梁从N-M层核心筒5外框位置调运至核心筒5内作业面;为保证钢梁在调运过程中的稳定,在调运过程中,需安排工人在第N-M层位置利用揽风绳向内移送钢梁,使其保持稳定慢慢进入核心筒5内部。S4. Lower the hoisting wire rope 3 to the position of the N-M layer, and transfer the steel beam from the position of the outer frame of the core tube 5 of the N-M layer to the inner working surface of the core tube 5; It is necessary to arrange workers to move the steel beam inward by using the wind rope at the position of the N-M layer, so that it can keep stable and slowly enter the core tube 5.

以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection of the present invention. within the range.

Claims (8)

1.一种爬模下核心筒内部钢梁倒运安装系统,其特征在于,包括起重吊装机构(1)、方向转换机构(2)以及吊装钢丝绳(3)和挂钩(4);1. A system for reverse transporting and installing steel beams inside a core tube under a climbing formwork, characterized in that it comprises a hoisting and hoisting mechanism (1), a direction conversion mechanism (2), a hoisting wire rope (3) and a hook (4); 位于爬模(9)下方的核心筒外框结构(6)第N层施工完成后,所述起重吊装机构(1)设置在第N-M层核心筒外框结构(6)的外框楼板(7)上,起重吊装机构(1)包括方形框底座(102)和通过机械连接方式固定设置在所述方形框底座(102)上的卷扬机(101)。After the construction of the Nth floor of the core tube outer frame structure (6) located under the climbing formwork (9) is completed, the hoisting mechanism (1) is arranged on the outer frame floor ( 7) On, the hoisting mechanism (1) includes a square frame base (102) and a hoist (101) fixed on the square frame base (102) by mechanical connection. 2.根据权利要求1所述的爬模下核心筒内部钢梁倒运安装系统,其特征在于,所述方形框底座(102)的每条边均开设两个螺栓孔,方形框底座(102)通过膨胀螺栓(103)固定在所述核心筒外框结构(6)的外框楼板(7)上,所述方形框底座(102)上设置有若干个限位钢筋(104),所述卷扬机(101)固定于所述限位钢筋(104)内部。2. The installation system for reverse transportation of steel beams inside the core tube under the climbing formwork according to claim 1, characterized in that, each side of the square frame base (102) is provided with two bolt holes, and the square frame base (102) It is fixed on the outer frame floor (7) of the core tube outer frame structure (6) by means of expansion bolts (103), and the square frame base (102) is provided with a number of limit steel bars (104). (101) is fixed inside the limiting steel bar (104). 3.根据权利要求1所述的爬模下核心筒内部钢梁倒运安装系统,其特征在于,所述方向转换机构(2)包括一级转向滑轮(201)、二级转向滑轮(202)、固定钢梁(203)、滑轮定位钢丝绳(204)以及橡胶垫(205)。3. The installation system for reverse transportation of steel beams inside the core tube under the climbing formwork according to claim 1, wherein the direction conversion mechanism (2) comprises a primary steering pulley (201), a secondary steering pulley (202), Fix the steel beam (203), the pulley positioning wire rope (204) and the rubber pad (205). 4.根据权利要求3所述的爬模下核心筒内部钢梁倒运安装系统,其特征在于,所述固定钢梁(203)设置在所述外框楼板(7)上,所述滑轮定位钢丝绳(204)通过卡扣固定在所述固定钢梁(203)上,所述滑轮定位钢丝绳(204)和固定钢梁(203)的连接位置处设置橡胶垫(205),所述二级转向滑轮(202)设置在滑轮定位钢丝绳(204)上;4. The installation system for reverse transportation of steel beams inside the core tube under the climbing formwork according to claim 3, wherein the fixed steel beam (203) is arranged on the outer frame floor (7), and the pulley locates the wire rope (204) is fixed on the fixed steel beam (203) by snaps, a rubber pad (205) is provided at the connection position of the pulley positioning wire rope (204) and the fixed steel beam (203), and the secondary steering pulley (202) is arranged on the pulley positioning wire rope (204); 所述一级转向滑轮(201)设置在所述外框楼板(7)上。The primary diverting pulley (201) is arranged on the outer frame floor (7). 5.根据权利要求4所述的爬模下核心筒内部钢梁倒运安装系统,其特征在于,所述固定钢梁(203)设置在第N层所述外框楼板(7)上,所述滑轮定位钢丝绳(204)设置在第N层所述外框楼板(7)的高度上;5. The installation system for backward transporting and installing steel beams inside the core tube under the climbing formwork according to claim 4, wherein the fixed steel beams (203) are arranged on the outer frame floor (7) of the Nth floor, and the The pulley positioning wire rope (204) is arranged at the height of the outer frame floor (7) of the Nth layer; 所述一级转向滑轮(201)设置在第N-M层所述外框楼板(7)上。The first-level diverting pulley (201) is arranged on the outer frame floor (7) of the N-Mth floor. 6.根据权利要求3所述的爬模下核心筒内部钢梁倒运安装系统,其特征在于,所述吊装钢丝绳(3)一端连接所述卷扬机(101),另一端依次经过一级转向滑轮(201)和二级转向滑轮(202)后连接所述挂钩(4)。6. The installation system for reverse transportation of steel beams inside the core tube under the climbing formwork according to claim 3, characterized in that, one end of the hoisting wire rope (3) is connected to the hoist (101), and the other end passes through a first-level diverting pulley ( 201) and the secondary diverting pulley (202) are connected to the hook (4). 7.根据权利要求1所述的爬模下核心筒内部钢梁倒运安装系统,其特征在于,N-M为核心筒(5)内楼板需施工层,M为所述外框楼板(7)与核心筒(5)内楼板的层高差,第N层外框楼板(7)作业面高于核心筒(5)内框楼板,第N-M层外框楼板(7)与核心筒(5)内框需施工的最底层楼板位于同一层。7. The installation system for backward transportation and installation of steel beams inside the core tube under the climbing formwork according to claim 1, characterized in that, N-M is the required construction layer of the inner floor slab of the core tube (5), and M is the outer frame floor slab (7) and the core The floor height difference of the inner floor of the tube (5), the working surface of the outer frame floor (7) of the Nth floor is higher than the inner frame floor of the core tube (5), the outer frame floor of the N-M layer (7) and the inner frame of the core tube (5) The lowest floor slab to be constructed is on the same level. 8.基于权利要求1所述的爬模下核心筒内部钢梁倒运安装系统的施工方法,其特征在于,包括以下步骤:8. based on the construction method of the lower core tube inner steel beam installation system of climbing formwork according to claim 1, is characterized in that, comprises the following steps: S1、核心筒外框结构(6)第N层施工完成后,利用塔吊(8)将核心筒(5)内水平楼板的钢梁等大型材料调运至第N-M层外框楼板(7)上;S1. After the construction of the Nth floor of the outer frame structure of the core tube (6) is completed, use the tower crane (8) to transfer large materials such as steel beams of the horizontal floor slabs in the core tube (5) to the outer frame floor slabs (7) of the N-M layers; S2、在第N-M层外框楼板(7)上布置所述起重吊装机构(1)及所述一级转向滑轮(201);S2. Arrange the hoisting mechanism (1) and the first-level diverting pulley (201) on the outer frame floor (7) of the N-M layers; S3、在第N层外框楼板(7)上布置固定钢梁(203)以及滑轮定位钢丝绳(204),并安装二级转向滑轮(202)以及吊装钢丝绳(3)和挂钩(4);S3. Arrange fixed steel beams (203) and pulley positioning wire ropes (204) on the Nth layer outer frame floor slab (7), and install secondary steering pulleys (202), hoisting wire ropes (3) and hooks (4); S4、下放吊装钢丝绳(3)至第N-M层位置,并将钢梁从N-M层核心筒(5)外框位置调运至核心筒(5)内作业面;为保证钢梁在调运过程中的稳定,在调运过程中,需安排工人在第N-M层位置利用揽风绳向内移送钢梁,使其保持稳定慢慢进入核心筒(5)内部。S4. Lower the hoisting wire rope (3) to the position of the N-M layer, and transfer the steel beam from the outer frame position of the core tube (5) of the N-M layer to the inner working surface of the core tube (5); in order to ensure the stability of the steel beam during the transfer and transportation process , During the transfer process, it is necessary to arrange workers to use the wind rope to move the steel beam inward at the position of the N-M layer to keep it stable and slowly enter the core tube (5).
CN202210656874.7A 2022-06-10 2022-06-10 A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof Pending CN114988310A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210656874.7A CN114988310A (en) 2022-06-10 2022-06-10 A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210656874.7A CN114988310A (en) 2022-06-10 2022-06-10 A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof

Publications (1)

Publication Number Publication Date
CN114988310A true CN114988310A (en) 2022-09-02

Family

ID=83033672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210656874.7A Pending CN114988310A (en) 2022-06-10 2022-06-10 A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof

Country Status (1)

Country Link
CN (1) CN114988310A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492387A (en) * 2022-09-15 2022-12-20 中建八局第一建设有限公司 Creeping formwork integrated material hoisting system and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006348691A (en) * 2005-06-20 2006-12-28 Shimizu Corp Construction system for building outer wall
CN204983692U (en) * 2015-07-29 2016-01-20 中建八局第四建设有限公司 Concrete panel's hoist device
CN206538126U (en) * 2017-03-17 2017-10-03 北京建工博海建设有限公司 The large-scale overweight equipment handling constructing device of Super High
KR20180000019U (en) * 2016-06-23 2018-01-03 김량호 Transporting goods elevator for workplace
CN110359674A (en) * 2019-07-17 2019-10-22 中航建设集团有限公司 A kind of vertical duct well casing pipeline construction method of skyscraper small space
CN113502924A (en) * 2021-07-31 2021-10-15 中冶(上海)钢结构科技有限公司 Method for constructing steel beam in high-rise closed core cylinder
CN214462706U (en) * 2020-11-10 2021-10-22 精工工业建筑系统有限公司 Device for quickly installing roof purlines
CN215248971U (en) * 2021-07-15 2021-12-21 中建一局华江建设有限公司 Hoisting construction device for large-scale overweight electromechanical equipment of high-rise and super high-rise building
CN216127449U (en) * 2021-04-20 2022-03-25 浙江交工集团股份有限公司西南分公司 Small box girder core mold drawing winch fixing seat assembly

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006348691A (en) * 2005-06-20 2006-12-28 Shimizu Corp Construction system for building outer wall
CN204983692U (en) * 2015-07-29 2016-01-20 中建八局第四建设有限公司 Concrete panel's hoist device
KR20180000019U (en) * 2016-06-23 2018-01-03 김량호 Transporting goods elevator for workplace
CN206538126U (en) * 2017-03-17 2017-10-03 北京建工博海建设有限公司 The large-scale overweight equipment handling constructing device of Super High
CN110359674A (en) * 2019-07-17 2019-10-22 中航建设集团有限公司 A kind of vertical duct well casing pipeline construction method of skyscraper small space
CN214462706U (en) * 2020-11-10 2021-10-22 精工工业建筑系统有限公司 Device for quickly installing roof purlines
CN216127449U (en) * 2021-04-20 2022-03-25 浙江交工集团股份有限公司西南分公司 Small box girder core mold drawing winch fixing seat assembly
CN215248971U (en) * 2021-07-15 2021-12-21 中建一局华江建设有限公司 Hoisting construction device for large-scale overweight electromechanical equipment of high-rise and super high-rise building
CN113502924A (en) * 2021-07-31 2021-10-15 中冶(上海)钢结构科技有限公司 Method for constructing steel beam in high-rise closed core cylinder

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李宁宁;郑峰;宋磊;何鼎晶;包科;: "武汉绿地中心顶模下方核心筒内钢结构施工关键技术", 施工技术, no. 15, pages 104 - 107 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492387A (en) * 2022-09-15 2022-12-20 中建八局第一建设有限公司 Creeping formwork integrated material hoisting system and construction method thereof
CN115492387B (en) * 2022-09-15 2023-08-11 中建八局第一建设有限公司 Climbing form integrated material hoisting system and construction method thereof

Similar Documents

Publication Publication Date Title
CN106698208B (en) A kind of hanging device and hanging method for being transported outside high-rise building
CN114988310A (en) A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN208039864U (en) The attached lift-type discharging platform of Guiding Support Elevating Scaffold
CN216920365U (en) Intelligent climbing type steel formwork and operation platform integrated equipment for ultra-deep foundation pit
CN202347846U (en) Simple lifting setting stair steel moulding plate
CN216840692U (en) Construction device for super high-rise building
CN115583584A (en) Unequal-height double-fulcrum full-rotation type light truss hoisting device and construction method
CN115559414A (en) Construction method of cantilever steel truss on top layer of building
CN211998555U (en) Construction structure of super high-rise inner climbing tower crane
CN215291319U (en) Multi-point elevator shaft construction lifting platform
CN109989590A (en) For the auxiliary fixing device of roof overlength steel girder erection and the hanging method of girder steel
CN214329956U (en) Ring rail hoisting device for curtain wall installation
CN109138398B (en) Assembled suspension steel platform and construction method thereof
CN111196566A (en) Construction structure and construction method of super high-rise inner climbing tower crane
CN113494127A (en) Construction method for layered lifting of large-span open-web corridor steel platform
CN218933662U (en) Space unconstrained special-shaped unsupported spiral staircase
CN218114742U (en) Carrying pole beam hoisting system and carrying pole beam hoisting system
CN214942442U (en) Super high-rise horizontal structure construction is with hanging mould platform device
CN218668607U (en) A perpendicular transfer system of indoor material for floor is reformed transform
CN216766245U (en) High-rise large-span steel concrete beam connection structure
CN113718654B (en) Installation structure for ropeless beam section of bridge tower area
CN219794710U (en) Cantilever type unloading platform
CN115492387B (en) Climbing form integrated material hoisting system and construction method thereof
CN222498464U (en) Light vertical lifting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220902