CN114753315B - Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels - Google Patents

Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels Download PDF

Info

Publication number
CN114753315B
CN114753315B CN202210407590.4A CN202210407590A CN114753315B CN 114753315 B CN114753315 B CN 114753315B CN 202210407590 A CN202210407590 A CN 202210407590A CN 114753315 B CN114753315 B CN 114753315B
Authority
CN
China
Prior art keywords
glass fiber
layer glass
reinforcement
rib
bottom layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210407590.4A
Other languages
Chinese (zh)
Other versions
CN114753315A (en
Inventor
余万龙
谢小东
代江
胡应洪
李林涛
姚江涛
鄢锐
李佐武
邓捍东
刘传军
李文超
赵四海
李秋菊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 2 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 2 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 2 Engineering Co Ltd filed Critical China Gezhouba Group No 2 Engineering Co Ltd
Priority to CN202210407590.4A priority Critical patent/CN114753315B/en
Publication of CN114753315A publication Critical patent/CN114753315A/en
Application granted granted Critical
Publication of CN114753315B publication Critical patent/CN114753315B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/07Reinforcing elements of material other than metal, e.g. of glass, of plastics, or not exclusively made of metal
    • E04C5/073Discrete reinforcing elements, e.g. fibres
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a construction method for a dam panel by adopting glass fiber reinforced plastic to replace steel bars, which solves the problems of low installation speed, poor crack resistance and high cost of the traditional hot rolled ribbed steel bars adopted by the dam panel of a reservoir, and utilizes a truck crane to horizontally transport the glass fiber reinforced plastic to a temporary storage yard of the dam top steel bars for stacking, and adopts a 5T winch to pull a steel bar trolley to transport to a binding part. The slope is erected and inserted with reinforcing steel bars, two layers of phi 22mm 1 st and 2 nd horizontal sample frame reinforcing steel bars are welded on the inserted reinforcing steel bars, the 1 st bottom layer glass fiber reinforced bar is connected with the 2 nd horizontal sample frame reinforcing steel bars through binding wires, the longitudinal 1 st bottom layer glass fiber reinforced bar is connected with the transverse 2 nd bottom layer glass fiber reinforced bar through binding wires, after the 1 st and 2 nd bottom layer glass fiber reinforced bars are bound, the 2 nd surface layer glass fiber reinforced bar is bound with the upper layer 1 st horizontal sample frame reinforcing steel bar, the transverse 1 st surface layer glass fiber reinforced bar is bound on the upper portion after the longitudinal 2 nd surface layer glass fiber reinforced bar is installed, and the 2 nd surface layer glass fiber reinforced bar is bound with the 1 st surface layer glass fiber reinforced bar.

Description

Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels
Technical Field
The glass fiber reinforcement is mainly used for replacing reinforcement in the dam panel of the hydro-electric hydraulic engineering, and can be used for replacing reinforcement in the dam panel construction.
Background
The conventional reservoir dam panels all adopt common hot rolled ribbed steel bars, the conventional steel bars have large quality, slow installation progress, more manpower and poor cracking resistance.
Disclosure of Invention
The invention aims to provide a construction method for a dam panel with easy field installation, improved crack resistance, lower cost and less manpower resources, wherein glass fiber ribs are adopted to replace steel bars.
The object of the invention is achieved in that:
The dam panel adopts glass fiber reinforcement to replace the construction method of reinforcing steel bars, the glass fiber reinforcement is horizontally transported by a truck crane to a temporary storage yard of dam roof reinforcement for stacking, a winch is used for traction of a reinforcing steel bar trolley to a binding position, a reinforcing steel bar 1 is erected on a slope and is perpendicular to the slope, the reinforcing steel bar 1 forms a network consisting of longitudinal and transverse lines with the same spacing on the slope, the reinforcing steel bar 1 is positioned at four corners of a grid of 2x 2m, the reinforcing steel bar 1 penetrates through solid slope mortar to enter cushion materials for 35 cm to 45cm, an upper layer of reinforcing steel bar 3 and a lower layer of reinforcing steel bar 2 are welded on the reinforcing steel bar 1, the reinforcing steel bar 3 and the reinforcing steel bar 2 of the 1 st horizontal sample frame are positioned in the transverse direction of the slope, the outer leakage part of the reinforcing steel bar 1 is flush with the surface of the reinforcing steel bar 3 of the upper layer of the 1 st horizontal sample frame, the 1 st and the 2 glass fiber reinforcement 4 and 5 are bound, the 1 st and 2 bottom layer of the reinforcing steel bar 4 and 5 are respectively positioned in the longitudinal and transverse directions of the slope, firstly binding a 1 st bottom layer glass fiber reinforced bar 4, connecting the 1 st bottom layer glass fiber reinforced bar 4 with a 2 nd horizontal sample frame reinforced bar 2 through binding wires, after the 1 st bottom layer glass fiber reinforced bar 4 is bound, connecting a longitudinal 1 st bottom layer glass fiber reinforced bar 4 with a transverse 2 nd bottom layer glass fiber reinforced bar 5 through binding wires, binding the intersection position of the 1 st bottom layer glass fiber reinforced bar 4 and the 2 nd bottom layer glass fiber reinforced bar 5 by binding wires, binding intersection points of two rows of 1 st bottom layer glass fiber reinforced bars and 2 nd bottom layer glass fiber reinforced bars close to the periphery of a network, binding intersection points of the 1 st bottom layer glass fiber reinforced bars and 2 nd bottom layer glass fiber reinforced bars at the rest of the network according to 50 percent of intersection points, after the 1 st bottom layer glass fiber reinforced bar 4 and 2 nd bottom layer glass fiber reinforced bar 5 are bound, constructing 1 st surface layer glass fiber reinforced bars 6 and 7, arranging the 1 st surface layer glass fiber reinforced bars 6 and 2 surface layer 7 transversely and longitudinally respectively, the 2 nd surface layer glass fiber reinforced bar 7 is bound and connected with the upper layer 1 st horizontal sample frame reinforced bar 3, the longitudinal 2 nd surface layer glass fiber reinforced bar 7 is bound and connected with the 1 st surface layer glass fiber reinforced bar 6 by the transverse 1 st surface layer glass fiber reinforced bar 6 after being installed.
The 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 and the 1 st and 2 nd surface layer glass fiber ribs 6 and 7 are formed by overlapping a plurality of glass fibers, the overlapping length of two adjacent glass fibers is not less than 40 cm, and the binding wire adopts No. 12 iron wires.
And the slope surface inserted steel bar 1 is welded and connected with the steel bars of the 1 st horizontal sample frame and the 2 nd horizontal sample frame after finishing.
The glass fiber manufacturing lengths are different, so that the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 and the 1 st and 2 nd surface layer glass fiber ribs 6 and 7 are not bound and connected on the same section.
The construction method for the dam panel by adopting glass fiber reinforced plastic to replace steel bars comprises the following steps:
⑴ Glass fiber reinforcement manufacturing and transporting
The surface of the fiber rib should be clean, the surface stain should be cleaned before use, and if the surface of the material is polluted by certain substances or reagents, the fiber rib can be wiped by a solvent. The glass fiber ribs are made of brittle materials, and throwing and collision are avoided during loading, unloading and transportation; and the transverse stay bars are adopted for loading, hanging and transporting, so that the material is prevented from being bent and broken due to overweight. All the glass fiber reinforcements need to be numbered, 18T crane is used for transporting the glass fiber reinforcements to a temporary storage yard of dam crest reinforcements horizontally for stacking, 25T crane is used for placing the processed and formed fiber reinforcements on a slope reinforcement trolley according to the number, 5T winch is used for towing the reinforcement trolley, 1T fiber reinforcements are transported to a mounting working surface each time, and the fiber reinforcements are manually mounted on site,
⑵ Laying slope surface inserted steel bar
The total station is adopted for measuring and lofting, grid lines are piled and arranged, phi 25mm screw steel is adopted for inserting steel bars, the interval distance is 2 multiplied by 2m, the steel bars are manually driven into cushion materials by using hammers for 40cm, personnel use a crawling ladder to go up and down, and binding safety ropes are adopted, the outer leakage part of the inserted steel bars is flush with the surface of the steel bars of the upper horizontal sample frame, the design positions of the 1 st sample frame steel bars 2 and the 2 nd sample frame steel bars 3 are marked on the inserted steel bars through measurement,
⑶ Sample rack steel bar installation
Immediately installing sample frame steel bars after finishing the slope steel bar inserting layout, wherein the sample frame steel bars are phi 22mm round steel, an upper layer and a lower layer are arranged together, the 1 st sample frame steel bar and the 2 nd sample frame steel bar are horizontally arranged, the distance is 2.0m, the 1 st sample frame steel bar and the 2 nd sample frame steel bar are 2, 3 rd sample frame steel bars are manually welded at the marked positions of the inserted steel bars 1 by using electric welding machines, the external leakage parts of the inserted steel bars are flush with the surface of the steel bar of the upper layer horizontal sample frame,
⑷ The 1 st and 2nd bottom fiberglass tendons 4 and 5 are installed
After the construction of the sample frame rib is finished, the bottom fiber rib is installed, the 1 st bottom layer glass fiber rib 4 is firstly bound, the 1 st bottom layer glass fiber rib 4 is bound and connected with the 2 nd horizontal sample frame rib 2 by using a 12# iron wire, the connection position meets the requirement of a design drawing, the 2 nd bottom layer glass fiber rib 5 is bound after the 1 st bottom layer glass fiber rib 4 is bound, the 1 st bottom layer glass fiber rib 4 and the 2 nd bottom layer glass fiber rib 5 are bound by using a 12# iron wire, the intersection points close to the peripheral two rows of the 1 st bottom layer glass fiber rib 4 and the 2 nd bottom layer glass fiber rib 5 are bound by points, the intersection points of the rest 1 st bottom layer glass fiber rib 4 and the 2 nd bottom layer glass fiber rib 5 are bound according to 50 percent of intersection points,
⑸ Binding surface layer glass fiber ribs
After the 1 st and 2 nd bottom glass fiber ribs 4 and 5 are bound, the 1 st and 2 nd surface layer fiber ribs 6 and 7 are constructed, the longitudinal 2 nd surface layer fiber rib 7 is bound and connected with the upper layer 2 nd horizontal sample frame steel bar 3, the upper part of the 2 nd surface layer fiber rib 7 is bound by the transverse 1 st surface layer fiber rib 6 after being installed, the 1 st and 2 nd surface layer fiber ribs are bound by binding wires, the above fiber ribs are all in lap joint, the lap joint length is not less than 40 cm, and the binding wires are made of No. 12 iron wires.
The invention has the following advantages:
the construction method of the material increases the cracking resistance of the concrete on the premise of ensuring the strength of the steel bar to be unchanged, improves the construction time efficiency compared with the traditional material, and saves the cost.
The glass fiber reinforced plastic has high tensile strength, light weight, strong corrosion resistance and strong material binding force, and effectively reduces crack generation of the panel. The glass fiber reinforced plastic bar is a new material technology instead of the steel bar, and can be complementary with the steel bar.
The new material of the glass fiber reinforced plastic is adopted for construction, so that labor can be effectively saved, and a large amount of time is saved for subsequent construction.
Drawings
FIG. 1 is a schematic view of a large panel.
Fig. 2 is a cross-sectional view of fig. 1.
FIG. 3 is a plan view of the fiberglass tendon of the face and bottom layers.
The specific embodiment is as follows:
the ideas of applying the glass fiber reinforced plastic materials to the hydropower field are put forward by various parties involved in the construction of the Wenden pumped storage power station. In consideration of the performance index of the material, the stress characteristics of the structure, the influence on the later maintenance and the like, under the condition that the technical support data is relatively complete, the construction application of replacing the reinforcing steel bars with the glass fiber reinforced plastic bars is developed for improving the cracking resistance of the panel concrete. The glass fiber reinforced plastic has lighter weight, convenient and efficient construction, lower investment cost than the steel bars, and increases the cracking resistance of the concrete.
The dam panel adopts glass fiber reinforcement to replace the construction method of reinforcing steel bars, the glass fiber reinforcement is horizontally transported by a truck crane to a temporary storage yard of dam roof reinforcement for stacking, a winch is used for traction of a reinforcing steel bar trolley to a binding position, a reinforcing steel bar 1 is erected on the slope and is perpendicular to the slope, the reinforcing steel bar 1 forms a network consisting of longitudinal and transverse lines with the same spacing on the slope, the reinforcing steel bar 1 is positioned at four corners of a grid of 2 x 2m, the reinforcing steel bar 1 penetrates through solid slope mortar to enter cushion materials for 40cm, an upper layer phi 22mm reinforcing steel bar 3 and a lower layer phi 22mm reinforcing steel bar 2 are welded on the reinforcing steel bar 1, the reinforcing steel bar 2 are positioned in the transverse direction of the slope, the outer leakage part of the reinforcing steel bar 1 is flush with the surface of the reinforcing steel bar 3 of the upper layer 1 st horizontal sample frame, the 1 st and the reinforcing steel bar 2 glass fiber reinforcements 4 and 5 are bound, the 1 st and 2 bottom layer glass fiber reinforcements 4 and 5 are respectively positioned in the longitudinal direction and the transverse direction of the slope, firstly binding a1 st bottom layer glass fiber reinforced bar 4, connecting the 1 st bottom layer glass fiber reinforced bar 4 with a2 nd horizontal sample frame reinforced bar 2 through binding wires, after the 1 st bottom layer glass fiber reinforced bar 4 is bound, connecting a longitudinal 1 st bottom layer glass fiber reinforced bar 4 with a transverse 2 nd bottom layer glass fiber reinforced bar 5 through binding wires, binding the intersection position of the 1 st bottom layer glass fiber reinforced bar 4 and the 2 nd bottom layer glass fiber reinforced bar 5 by binding wires, binding intersection points of two rows of 1 st bottom layer glass fiber reinforced bars and 2 nd bottom layer glass fiber reinforced bars close to the periphery of a network, binding intersection points of the 1 st bottom layer glass fiber reinforced bars and 2 nd bottom layer glass fiber reinforced bars at the rest of the network according to 50 percent of intersection points, after the 1 st bottom layer glass fiber reinforced bar 4 and 2 nd bottom layer glass fiber reinforced bar 5 are bound, constructing 1 st surface layer glass fiber reinforced bars 6 and 7, arranging the 1 st surface layer glass fiber reinforced bars 6 and 2 surface layer 7 transversely and longitudinally respectively, the 2 nd surface layer glass fiber reinforced bar 7 is bound and connected with the upper layer 1 st horizontal sample frame reinforced bar 3, the longitudinal 2 nd surface layer glass fiber reinforced bar 7 is bound and connected with the 1 st surface layer glass fiber reinforced bar 6 by the transverse 1 st surface layer glass fiber reinforced bar 6 after being installed.
The 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 and the 1 st and 2 nd surface layer glass fiber ribs 6 and 7 are formed by overlapping a plurality of glass fibers, the overlapping length of two adjacent glass fibers is not less than 40 cm, and the binding wire adopts No. 12 iron wires.
And the slope surface inserted steel bar 1 is welded and connected with the steel bars of the 1 st horizontal sample frame and the 2 nd horizontal sample frame after finishing.
The glass fiber manufacturing lengths are different, so that the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 and the 1 st and 2 nd surface layer glass fiber ribs 6 and 7 are not bound and connected on the same section.
The construction method for the dam panel by adopting glass fiber reinforced plastic to replace steel bars comprises the following steps:
⑴ Glass fiber reinforcement manufacturing and transporting
The surface of the fiber rib should be clean, the surface stain should be cleaned before use, and if the surface of the material is polluted by certain substances or reagents, the fiber rib can be wiped by a solvent. The glass fiber ribs are made of brittle materials, and throwing and collision are avoided during loading, unloading and transportation; and the transverse stay bars are adopted for loading, hanging and transporting, so that the material is prevented from being bent and broken due to overweight. All the glass fiber reinforcements need to be numbered, 18T crane is used for transporting the glass fiber reinforcements to a temporary storage yard of dam crest reinforcements horizontally for stacking, 25T crane is used for placing the processed and formed fiber reinforcements on a slope reinforcement trolley according to the number, 5T winch is used for towing the reinforcement trolley, 1T fiber reinforcements are transported to a mounting working surface each time, and the fiber reinforcements are manually mounted on site,
⑵ Laying slope surface inserted steel bar
The total station is adopted for measuring and lofting, grid lines are piled and arranged, phi 25mm screw steel is adopted for inserting steel bars, the interval distance is 2 multiplied by 2m, the steel bars are manually driven into cushion materials by using hammers for 40cm, personnel use a crawling ladder to go up and down, and binding safety ropes are adopted, the outer leakage part of the inserted steel bars is flush with the surface of the steel bars of the upper horizontal sample frame, the design positions of the 1 st sample frame steel bars 2 and the 2 nd sample frame steel bars 3 are marked on the inserted steel bars through measurement,
⑶ Sample rack steel bar installation
Immediately installing sample frame steel bars after finishing the slope steel bar inserting layout, wherein the sample frame steel bars are phi 22mm round steel, an upper layer and a lower layer are arranged together, the 1 st sample frame steel bar and the 2 nd sample frame steel bar are horizontally arranged, the distance is 2.0m, the 1 st sample frame steel bar and the 2 nd sample frame steel bar are 2, 3 rd sample frame steel bars are manually welded at the marked positions of the inserted steel bars 1 by using electric welding machines, the external leakage parts of the inserted steel bars are flush with the surface of the steel bar of the upper layer horizontal sample frame,
⑷ The 1 st and 2nd bottom fiberglass tendons 4 and 5 are installed
After the construction of the sample frame rib is finished, the bottom fiber rib is installed, the 1 st bottom layer glass fiber rib 4 is firstly bound, the 1 st bottom layer glass fiber rib 4 is bound and connected with the 2 nd horizontal sample frame rib 2 by using a 12# iron wire, the connection position meets the requirement of a design drawing, the 2 nd bottom layer glass fiber rib 5 is bound after the 1 st bottom layer glass fiber rib 4 is bound, the 1 st bottom layer glass fiber rib 4 and the 2 nd bottom layer glass fiber rib 5 are bound by using a 12# iron wire, the intersection points close to the peripheral two rows of the 1 st bottom layer glass fiber rib 4 and the 2 nd bottom layer glass fiber rib 5 are bound by points, the intersection points of the rest 1 st bottom layer glass fiber rib 4 and the 2 nd bottom layer glass fiber rib 5 are bound according to 50 percent of intersection points,
⑸ Binding surface layer glass fiber ribs
After the 1 st and 2 nd bottom glass fiber ribs 4 and 5 are bound, the 1 st and 2 nd surface layer fiber ribs 6 and 7 are constructed, the longitudinal 2 nd surface layer fiber rib 7 is bound and connected with the upper layer 2 nd horizontal sample frame steel bar 3, the upper part of the 2 nd surface layer fiber rib 7 is bound by the transverse 1 st surface layer fiber rib 6 after being installed, the 1 st and 2 nd surface layer fiber ribs are bound by binding wires, the above fiber ribs are all in lap joint, the lap joint length is not less than 40 cm, and the binding wires are made of No. 12 iron wires.

Claims (5)

1. The construction method of the dam panel by adopting glass fiber reinforcement to replace the reinforcement is characterized in that the glass fiber reinforcement is horizontally transported to a temporary storage yard of the dam roof by using a truck crane to stack, a reinforcement trolley is pulled by a winch to transport to a binding position, a reinforcement inserting (1) vertical to the slope is erected on the slope, the reinforcement inserting forms a network with the same pitch of longitudinal and transverse lines on the slope, the reinforcement inserting is positioned at four corners of a grid of 2 x 2m, the reinforcement inserting penetrates through solid slope mortar to enter cushion materials by 35 cm to 45cm, an upper layer of 1 st horizontal sample frame reinforcement (3) and a lower layer of 2 nd horizontal sample frame reinforcement (2) are welded on the reinforcement inserting, the 1 st horizontal sample frame reinforcement and the 2 nd horizontal sample frame reinforcement are positioned in the transverse direction of the slope, the outer leakage part of the reinforcement inserting is flush with the surface of the reinforcement of the upper layer of the 1 st horizontal sample frame reinforcement, the 1 st bottom glass fiber reinforcement (4) is positioned in the longitudinal direction of the slope, the 2 nd bottom layer glass fiber rib (5) is positioned on the slope surface transversely, the 2 nd bottom layer glass fiber rib (5) is firstly bound, the 1 st bottom layer glass fiber rib (4) is connected with the 2 nd horizontal sample frame steel bar (2) through binding wires, after the 1 st bottom layer glass fiber rib (4) is bound, the longitudinal 1 st bottom layer glass fiber rib (4) is connected with the transverse 2 nd bottom layer glass fiber rib (5) through binding wires, the crossing position of the 1 st bottom layer glass fiber rib and the 2 nd bottom layer glass fiber rib adopts binding wires to bind, the crossing points of the 1 st bottom layer glass fiber rib and the 2 nd bottom layer glass fiber rib close to the periphery of the network are bound one by one, the crossing points of the 1 st bottom layer glass fiber rib and the 2 nd bottom layer glass fiber rib at the rest of the network are bound according to 50 percent of crossing points, after the 1 st bottom layer glass fiber rib binding is completed, construction of a1 st surface layer glass fiber reinforcement (6) and a2 nd surface layer glass fiber reinforcement (7) is carried out, the 1 st surface layer glass fiber reinforcement and the 2 nd surface layer glass fiber reinforcement are respectively transversely and longitudinally arranged, the 2 nd surface layer glass fiber reinforcement (7) is bound and connected with an upper layer 1 st horizontal sample frame reinforcing steel bar (3), the upper portion of the longitudinal 2 nd surface layer glass fiber reinforcement (7) is bound and connected with the 1 st surface layer glass fiber reinforcement through a transverse 1 st surface layer glass fiber reinforcement (6) after installation is completed, and the 2 nd surface layer glass fiber reinforcement is bound and connected with the 1 st surface layer glass fiber reinforcement.
2. The dam panel according to claim 1, wherein the construction method adopts glass fiber ribs to replace reinforcing steel bars, the 1 st and 2 nd bottom glass fiber ribs and the 1 st and 2 nd surface glass fiber ribs are formed by overlapping a plurality of glass fibers, the overlapping length of two adjacent glass fibers is not less than 40 cm, and the binding wire is a No. 12 iron wire.
3. The dam panel according to claim 1, wherein the glass fiber reinforcement is used for replacing the reinforcement bar, and the slope surface is welded with the 1 st and 2 nd horizontal sample frames after the reinforcement bar 1 is inserted.
4. The dam panel according to claim 2, wherein the construction method of replacing reinforcing steel bars with glass fiber ribs is characterized in that glass fibers are made in different lengths, so that the 1 st and 2 nd bottom glass fiber ribs and the 1 st and 2 nd surface glass fiber rib binding joints are not on the same section.
5. The construction method for the dam panel by adopting glass fiber reinforced plastic to replace steel bars comprises the following steps:
⑴ Glass fiber reinforcement manufacturing and transporting
The surface of the fiber rib is clean, surface stains are cleaned before use, if the surface of the material is polluted by certain substances or reagents, the fiber rib can be wiped off by a solvent, and the glass fiber rib is a brittle material and needs to be prevented from being thrown and collided during loading, unloading and transportation; the transverse brace rod is adopted for loading, hanging and transporting, so that the bending and breakage caused by overweight materials are avoided, all glass fiber reinforcements are required to be numbered, the glass fiber reinforcements are transported horizontally to a temporary storage yard of the dam crest steel reinforcements by a truck crane for stacking, the processed and molded fiber reinforcements are placed on a slope steel reinforcement trolley according to the number by a crane, the steel reinforcement trolley is pulled by a winch, the fiber reinforcements are transported to a mounting working surface each time, and the fiber reinforcements are manually mounted on site,
⑵ Laying slope surface inserted steel bar
The total station is adopted for measuring and lofting, grid lines are piled and arranged, phi 25mm screw steel is adopted for inserting the steel bars, the interval distance is 2 multiplied by 2m, the steel bars are manually driven into cushion materials by using hammers, personnel use a ladder to climb and descend, and tie safety ropes are bound, the outer leakage part of the inserted steel bars is flush with the surface of the steel bars of the upper horizontal sample frame, the design positions of the 1 st sample frame and the 2 nd sample frame steel bars are marked on the inserted steel bars through measurement,
⑶ Sample rack steel bar installation
Immediately installing sample frame steel bars after finishing the slope steel bar inserting layout, wherein the sample frame steel bars are phi 22mm round steel, an upper layer and a lower layer are arranged together, the 1 st sample frame steel bar and the 2 nd sample frame steel bar are horizontally arranged, the distance is 2.0m, the 1 st sample frame steel bar (2) and the 2 nd sample frame steel bar (3) are manually welded at the marked positions of the inserted steel bars 1 by using an electric welding machine, the outer leakage parts of the inserted steel bars are flush with the surfaces of the steel bars of the upper layer horizontal sample frame,
⑷ The 1 st bottom layer glass fiber reinforced bar (4) and the 2 nd bottom layer glass fiber reinforced bar (5) are arranged
After the construction of the sample frame rib is finished, the bottom fiber rib is installed, the 1 st bottom layer glass fiber rib (4) is firstly bound, the 1 st bottom layer glass fiber rib is bound and connected with the 2 nd horizontal sample frame rib (2) by using a 12# iron wire, the connection position meets the requirement of a design drawing, the 2 nd bottom layer glass fiber rib (5) is bound after the 1 st bottom layer glass fiber rib is bound, the 1 st bottom layer glass fiber is bound by using a 12# iron wire, the intersection points of the 1 st bottom layer glass fiber rib and the 2 nd bottom layer glass fiber rib close to the periphery are bound point by point, the intersection points of the other 1 st bottom layer glass fiber rib and the other 2 nd bottom layer glass fiber rib are bound according to 50 percent of intersection points,
⑸ Binding surface layer glass fiber ribs
After the 1 st, 2 bottom glass fiber rib ligature is accomplished, carry out 1 st surface course fiber rib (6), construction of 2 nd surface course fiber rib (7), vertical 2 nd surface course fiber rib (7) carries out the ligature with upper strata 1 st horizontal appearance frame reinforcing bar (3) and is connected, carry out horizontal 1 st surface course fiber rib (6) ligature again after 2 nd surface course fiber rib (7) are installed and accomplish, 1 st, 2 surface course fiber rib adopts the ligature, above fiber rib all adopts the overlap joint, overlap joint length is no less than 40 centimetres, the ligature adopts No. 12 iron wires.
CN202210407590.4A 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels Active CN114753315B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210407590.4A CN114753315B (en) 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210407590.4A CN114753315B (en) 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels

Publications (2)

Publication Number Publication Date
CN114753315A CN114753315A (en) 2022-07-15
CN114753315B true CN114753315B (en) 2024-04-26

Family

ID=82330834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210407590.4A Active CN114753315B (en) 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels

Country Status (1)

Country Link
CN (1) CN114753315B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201351253Y (en) * 2009-01-09 2009-11-25 长沙理工大学 Continuous reinforced concrete pavement
JP2011179310A (en) * 2010-02-03 2011-09-15 Taiyo Kogyo Corp Overtopping preventive apparatus
CN203583432U (en) * 2013-11-11 2014-05-07 中国建筑第八工程局有限公司 FRP (Fiber Reinforced Polymer) bar reinforced concrete parapet structure and formwork structure thereof
CN204373989U (en) * 2015-02-04 2015-06-03 中国葛洲坝集团第六工程有限公司 A kind of glass fiber bend bar test unit
CN105603846A (en) * 2016-03-10 2016-05-25 长沙理工大学 Dual-layer glass fiber concrete pavement structure applicable to city roads
CN105625298A (en) * 2016-03-16 2016-06-01 中冶集团武汉勘察研究院有限公司 Underground continuous wall structure adopting glass fiber bar lapping and milling and construction method for underground continuous wall structure
CN205605222U (en) * 2015-12-17 2016-09-28 北京建筑大学 Netting structure among net shotcrete
CN107435318A (en) * 2017-09-14 2017-12-05 国家电网公司 A kind of insulation anchor structure and construction method suitable for water resources dam polyureas barrier coat
CN108221876A (en) * 2018-02-08 2018-06-29 吕桂兰 A kind of hydraulic engineering flood discharge antiseepage dam
CN109235374A (en) * 2018-12-03 2019-01-18 唐山工业职业技术学院 A kind of constructing device and construction method for assisting high steep reinforced earth dam to fill
CN111779194A (en) * 2020-07-21 2020-10-16 湖北三江航天建筑工程有限公司 Method for installing glass fiber reinforcement in constructional engineering
CN212358199U (en) * 2020-03-26 2021-01-15 广东水利水电第三工程局有限公司 Reverse filtering layer structure of dam heel at downstream of earth dam
US11053675B1 (en) * 2018-11-17 2021-07-06 Juan Jose Santandreu Construction panel and construction panel assembly with improved structural integrity

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2006318823B2 (en) * 2005-11-24 2011-11-17 Hesco Bastion Limited Gabions
CA2867964C (en) * 2014-10-16 2016-04-12 Emin Buzimkic Prefabricated modular rebar modules and methods of using the same

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201351253Y (en) * 2009-01-09 2009-11-25 长沙理工大学 Continuous reinforced concrete pavement
JP2011179310A (en) * 2010-02-03 2011-09-15 Taiyo Kogyo Corp Overtopping preventive apparatus
CN203583432U (en) * 2013-11-11 2014-05-07 中国建筑第八工程局有限公司 FRP (Fiber Reinforced Polymer) bar reinforced concrete parapet structure and formwork structure thereof
CN204373989U (en) * 2015-02-04 2015-06-03 中国葛洲坝集团第六工程有限公司 A kind of glass fiber bend bar test unit
CN205605222U (en) * 2015-12-17 2016-09-28 北京建筑大学 Netting structure among net shotcrete
CN105603846A (en) * 2016-03-10 2016-05-25 长沙理工大学 Dual-layer glass fiber concrete pavement structure applicable to city roads
CN105625298A (en) * 2016-03-16 2016-06-01 中冶集团武汉勘察研究院有限公司 Underground continuous wall structure adopting glass fiber bar lapping and milling and construction method for underground continuous wall structure
CN107435318A (en) * 2017-09-14 2017-12-05 国家电网公司 A kind of insulation anchor structure and construction method suitable for water resources dam polyureas barrier coat
CN108221876A (en) * 2018-02-08 2018-06-29 吕桂兰 A kind of hydraulic engineering flood discharge antiseepage dam
US11053675B1 (en) * 2018-11-17 2021-07-06 Juan Jose Santandreu Construction panel and construction panel assembly with improved structural integrity
CN109235374A (en) * 2018-12-03 2019-01-18 唐山工业职业技术学院 A kind of constructing device and construction method for assisting high steep reinforced earth dam to fill
CN212358199U (en) * 2020-03-26 2021-01-15 广东水利水电第三工程局有限公司 Reverse filtering layer structure of dam heel at downstream of earth dam
CN111779194A (en) * 2020-07-21 2020-10-16 湖北三江航天建筑工程有限公司 Method for installing glass fiber reinforcement in constructional engineering

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李殿平.《混凝土结构加固设计与施工》.天津:天津大学出版社,2012,22. *
玻璃纤维筋在即有库区取水口预留岩坎中的应用;周国凯;《中国水运》;20210616;第21卷(第6期);120-121 *
玻璃纤维筋在抽水蓄能电站 大坝面板中的应用;余万龙;《电力勘测设计》;20230331;88-92 *

Also Published As

Publication number Publication date
CN114753315A (en) 2022-07-15

Similar Documents

Publication Publication Date Title
CN103276662B (en) Large-cantilever steel web spinal box beam segment
CN113752379B (en) Concrete T beam prefabrication construction method adopting secondary tensioning process and movable pedestal
CN103935911B (en) Tower crane attached wall supporting construction and construction method thereof
CN103669900B (en) Integral reinforcement construction method for outer barrel wall of chimney
CN104790681B (en) A kind of prevent unstability outside body of wall face from causing the device that masonry structure building earthquake is collapsed
CN104060547B (en) A kind of temporary steel trestle construction method
CN204019724U (en) Make the mold of prefabricated case beam framework of steel reinforcement
CN206859479U (en) A kind of steel bar girder laminated floor slab
CN105887704B (en) A kind of prestress rope Shear Strengthening concrete box girder and its reinforcement means
CN110983968A (en) Prefabricated assembled FRP (fiber reinforced plastic) -section steel-concrete combined bridge deck and construction method thereof
CN113585075A (en) Cast-in-place bridge deck formwork for steel-concrete composite beam
CN103216030A (en) Method for splicing and connecting precast reinforced concrete floor slabs within span
CN201202181Y (en) Connection structure for precast concrete board and beam and construction including the same
CN103696582A (en) Method and structure for improving rigidity of reinforced concrete beam
CN114753315B (en) Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels
CN203307719U (en) Large-cantilever steel web carinal box girder section
CN110106772B (en) Road cold-bending U-shaped combined beam bridge and construction method thereof
CN108004932A (en) Constructed the method for steel reinforced concrete combination beam using beam mode is transported under beam
CN202067799U (en) Non-roof bearing structure for supporting photovoltaic panel
CN111535483A (en) Concrete anti-cracking wall and construction method thereof
CN211472128U (en) Continuity combination beam
CN211648368U (en) Prefabricated polygonal prestressed concrete tower cylinder
CN210288869U (en) Precast concrete board subassembly
KR20100022703A (en) Composite slab using deck plate made by glass fiber reinforced polymer
CN207160359U (en) Prestressed concrete bidirectional laminated slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant