CN114753315A - Construction method for replacing reinforcing steel bars with glass fiber reinforcements for dam panels - Google Patents

Construction method for replacing reinforcing steel bars with glass fiber reinforcements for dam panels Download PDF

Info

Publication number
CN114753315A
CN114753315A CN202210407590.4A CN202210407590A CN114753315A CN 114753315 A CN114753315 A CN 114753315A CN 202210407590 A CN202210407590 A CN 202210407590A CN 114753315 A CN114753315 A CN 114753315A
Authority
CN
China
Prior art keywords
glass fiber
steel bars
reinforcing steel
bound
sample frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210407590.4A
Other languages
Chinese (zh)
Other versions
CN114753315B (en
Inventor
余万龙
谢小东
代江
胡应洪
李林涛
姚江涛
鄢锐
李佐武
邓捍东
刘传军
李文超
赵四海
李秋菊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 2 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 2 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 2 Engineering Co Ltd filed Critical China Gezhouba Group No 2 Engineering Co Ltd
Priority to CN202210407590.4A priority Critical patent/CN114753315B/en
Publication of CN114753315A publication Critical patent/CN114753315A/en
Application granted granted Critical
Publication of CN114753315B publication Critical patent/CN114753315B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/07Reinforcing elements of material other than metal, e.g. of glass, of plastics, or not exclusively made of metal
    • E04C5/073Discrete reinforcing elements, e.g. fibres
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention relates to a construction method for replacing reinforcing steel bars with glass fiber bars for dam panels, which solves the problems of slow installation speed, poor crack resistance and high cost of the conventional hot-rolled ribbed reinforcing steel bars for the dam panels of a reservoir, horizontally transports the glass fiber bars to a temporary storage yard of the reinforcing steel bars at the top of a dam by using a truck crane, and transports the reinforcing steel bars to a binding part by using a 5T hoist. The steel bar inserting device is erected on a slope surface, and two layers of phi 22mm (diameter) 1 st and 2 nd horizontal sample frame steel bars are welded on the steel bar inserting device, the 1 st bottom layer glass fiber bar is connected with the 2 nd horizontal sample frame steel bar through a binding wire, the longitudinal 1 st bottom layer glass fiber bar is connected with the transverse 2 nd bottom layer glass fiber bar through a binding wire, the 1 st and 2 nd bottom layer glass fiber bar are bound and connected after being bound and finished, the 2 nd surface layer glass fiber bar is bound and connected with the upper 1 st horizontal sample frame steel bar, the upper part of the longitudinal 2 nd surface layer glass fiber bar is bound and connected with the 1 st surface layer glass fiber bar.

Description

Construction method for replacing reinforcing steel bars with glass fiber reinforcements for dam panels
Technical Field
The glass fiber reinforcement is mainly used for dam panels of hydroelectric and hydraulic engineering in place of reinforcing steel bar construction, and can be used for dam panel construction to replace reinforcing steel bar installation.
Background
The traditional reservoir dam panel adopts common hot-rolled ribbed steel bars, and the traditional steel bars have large mass, slow installation progress, more required manpower and poor panel crack resistance.
Disclosure of Invention
The invention aims to provide a dam panel construction method which is easy to install on site, improves the crack resistance of the panel, is low in cost and uses less human resources and adopts glass fiber reinforced plastics to replace steel bars.
The purpose of the invention is realized by the following steps:
the dam panel adopts a construction method of replacing reinforcing steel bars with glass fiber reinforcing bars, a truck-mounted crane is utilized to horizontally transport the glass fiber reinforcing bars to a dam crest reinforcing bar temporary storage yard for stacking, a winch is adopted to pull a reinforcing bar trolley to transport the reinforcing bar trolley to a binding position, reinforcing bars 1 vertical to the slope surface are erected on the slope surface, the reinforcing bars 1 form a network consisting of longitudinal and transverse lines with the same interval on the slope surface, the reinforcing bars 1 are positioned at four corners of a 2 x 2m grid, the reinforcing bars 1 penetrate slope-fixing mortar to enter a bedding material for 35-45cm, upper and lower layers of 1 and 2 horizontal sample frame reinforcing bars 3 and 2 are welded on the reinforcing bars 1, the 1 and 2 horizontal sample frame reinforcing bars 3 and 2 are positioned in the transverse direction of the slope surface, the outer leakage part of the reinforcing bars 1 is flush with the surface of the upper layer 1 horizontal sample frame reinforcing bar 3, the 1 and 2 glass fiber reinforcing bars 4 and 5 are bound, the 1, 2 bottom layer glass fiber reinforcing bars 4 and 5 are respectively positioned in the longitudinal direction and the transverse direction of the slope surface, firstly binding a 1 st bottom glass fiber rib 4, connecting the 1 st bottom glass fiber rib 4 with a 2 nd horizontal sample frame reinforcing steel bar 2 through a binding wire, binding the 1 st bottom glass fiber rib 4 with the 2 nd bottom glass fiber rib 5 through the binding wire after the 1 st bottom glass fiber rib 4 is bound, binding the intersecting points of the 1 st bottom glass fiber rib 4 and the 2 nd bottom glass fiber rib 5 by the binding wire, binding the intersecting points of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib close to two rows of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib close to the periphery of the network point by point, binding the intersecting points of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib at the rest parts of the network according to 50 percent of the intersecting points, binding the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib 4 and the 5, then carrying out the construction of the 1 st glass fiber rib and the 2 nd bottom glass fiber rib 6 and 7, respectively arranging the 1 st glass fiber rib and the 2 nd bottom glass fiber rib 6 and the 7 transversely and longitudinally, binding the 2 nd bottom glass fiber rib 7 with the upper layer 1 st horizontal sample frame reinforcing steel bar 3, and the 2 nd longitudinal surface layer glass fiber rib 7 is subjected to binding of the 1 st transverse surface layer glass fiber rib 6 after installation, and the 2 nd surface layer glass fiber rib 7 is bound and connected with the 1 st surface layer glass fiber rib 6.
The 1 st, 2 bottom glass fiber muscle 4, 5 and 1 st, 2 surface course glass fiber muscle 6, 7 constitute by a plurality of glass fiber overlap joints, and two adjacent glass fiber overlap joints length must not be less than 40 centimetres, ties the silk and adopts 12 # iron wires.
Slope surface inserted steel bar 1 is welded with the 1 st and 2 nd horizontal sample frame steel bars after finishing.
The glass fiber manufacturing lengths are different, and the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 and the 1 st and 2 nd surface layer glass fiber ribs 6 and 7 are ensured to be bound and connected on the same section.
The dam panel construction method adopting glass fiber reinforcement to replace steel bars comprises the following steps:
manufacturing and transporting glass fiber reinforced plastic bars
The surface of the fiber ribs should be clean, the stains on the surface should be removed before use, and if the surface of the material is polluted by some substances or reagents, the material can be wiped clean by using a solvent. The glass fiber ribs are brittle materials, and must be prevented from being thrown and collided during loading, unloading and transportation; and transverse support rods are adopted for hoisting and transportation, so that bending and breakage caused by overweight materials are avoided. All the glass fiber reinforcements are required to be numbered, 18T truck-mounted cranes are used for horizontally transporting the glass fiber reinforcements to a temporary dam top reinforcement storage yard for stacking, a 25T crane is used for placing the processed and formed fiber reinforcements on a slope reinforcement trolley according to the numbers, a 5T winch is used for pulling the reinforcement trolley, 1T of fiber reinforcements are conveyed to an installation working surface each time, the fiber reinforcements are manually installed on site,
Do a wall and lay domatic inserting reinforcing bar
The total station is adopted for measuring and lofting, the grid lines are arranged by piling, the inserted steel bars are deformed steel bars with the diameter of 25mm, the spacing is 2 multiplied by 2m, the inserted steel bars are manually driven into the bedding material by an iron hammer for 40cm, personnel use the ladder stand to go up and down and bind the safety ropes, the leaking parts of the inserted steel bars are flush with the surface of the steel bars of the upper horizontal sample frame, the design positions of the steel bars 2 and 3 of the 1 st and 2 nd sample frames are marked on the inserted steel bars by measuring,
mounting the sample frame steel bars
After the slope inserted steel bars are laid, sample frame steel bars are immediately installed, the sample frame steel bars are round steel with the diameter of 22mm, an upper layer and a lower layer are arranged, the 1 st sample frame steel bars and the 2 nd sample frame steel bars are horizontally arranged, the distance is 2.0m, the 1 st sample frame steel bars and the 2 nd sample frame steel bars are manually welded at the positions marked by the inserted steel bars 1 by using an electric welding machine, the outer leakage parts of the inserted steel bars are flush with the surfaces of the upper layer horizontal sample frame steel bars,
fourth 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 are installed
After the construction of the sample frame ribs is finished, bottom layer fiber rib installation is carried out, the binding of the 1 st bottom layer glass fiber rib 4 is firstly carried out, the 1 st bottom layer glass fiber rib 4 is bound and connected with the 2 nd horizontal sample frame reinforcing steel bar 2 by using a 12# iron wire, the connecting position meets the requirement of a design drawing, the binding of the 2 nd bottom layer glass fiber rib 5 is started after the binding of the 1 st bottom layer glass fiber rib 4 is finished, the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 are bound by using a 12# iron wire, the intersection points of two lines of the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 close to the periphery are firmly bound point by point, the intersection points of the rest 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 are bound according to 50 percent of intersection points,
Binding of face layer glass fiber ribs
1, 2 bottom glass fiber muscle 4, 5 ligatures are accomplished the back, carry out the 1 st, 2 surface course fibre muscle 6, 7 construction, vertical 2 nd surface course fibre muscle 7 carries out the ligature with upper 2 nd level appearance frame reinforcing bar 3 and is connected, the installation of 2 nd surface course fibre muscle 7 is accomplished the back and is carried out the 6 ligatures of horizontal 1 st surface course fibre muscle in upper portion again, the 1 st, 2 surface course fibre muscle adopts the ligature of pricking the silk, go up the fibre muscle and all adopt the overlap joint, overlap joint length must not be less than 40 centimetres, it adopts No. 12 iron wires to prick the silk.
The invention has the advantages that:
the construction method of the material increases the anti-cracking performance of the concrete on the premise of ensuring that the strength of the reinforcing steel bar is not changed, improves the construction timeliness compared with the traditional material, and saves the cost.
The glass fiber rib has high tensile strength, light weight, strong corrosion resistance and strong material binding force, and effectively reduces the crack generation of the panel. The glass fiber reinforcement replaces the steel bar, which is a new material technology and can be complementary with the steel bar.
The glass fiber reinforced plastic new material is adopted for construction, so that the labor can be effectively saved, and a large amount of time is saved for subsequent construction.
Drawings
FIG. 1 is a schematic view of a large panel.
Fig. 2 is a sectional view of fig. 1.
FIG. 3 is a plan view of the glass fiber ribs of the surface layer and the bottom layer.
The specific implementation mode is as follows:
wendeng pumped storage power station participated in each building party and proposed the idea of applying the glass fiber reinforced material to the field of water and electricity. Considering the performance index of the material, the self stress characteristic of the structure, the influence on later-stage maintenance and the like, and under the condition of relatively complete technical support data, the construction application of replacing the reinforcing steel bars with the glass fiber reinforced bars is developed for improving the crack resistance of the panel concrete. The glass fiber reinforcement is light in weight, convenient and efficient to construct, the input cost is lower than that of the used reinforcing steel bars, and the crack resistance of the concrete is improved.
The dam panel adopts a construction method of replacing reinforcing steel bars with glass fiber reinforcing bars, a truck-mounted crane is utilized to horizontally transport the glass fiber reinforcing bars to a dam crest reinforcing bar temporary storage yard for stacking, a winch is adopted to pull a reinforcing bar trolley to transport the reinforcing bar trolley to a binding position, reinforcing bars 1 vertical to the slope surface are erected on the slope surface, the reinforcing bars 1 form a network consisting of longitudinal and transverse lines with the same interval on the slope surface, the reinforcing bars 1 are positioned at four corners of a 2 x 2m grid, the reinforcing bars 1 penetrate slope-fixing mortar to enter a bedding material by 40cm, upper and lower two layers of phi 22mm, 1 st and 2 nd horizontal sample frame reinforcing bars 3 and 2 are welded on the reinforcing bars 1, the outer leakage parts of the reinforcing bars 1 are flush with the surface of the upper layer 1 st horizontal sample frame reinforcing bars 3, the binding of the 1 st and 2 nd glass fiber reinforcing bars 4 and 5 is started, the 1 st and 2 nd bottom layer glass fiber reinforcing bars 4 and 5 are respectively positioned in the longitudinal direction and the horizontal direction of the slope surface, firstly binding a 1 st bottom glass fiber rib 4, connecting the 1 st bottom glass fiber rib 4 with a 2 nd horizontal sample frame reinforcing steel bar 2 through a binding wire, binding the 1 st bottom glass fiber rib 4 with the 2 nd bottom glass fiber rib 5 through the binding wire after the 1 st bottom glass fiber rib 4 is bound, binding the intersecting points of the 1 st bottom glass fiber rib 4 and the 2 nd bottom glass fiber rib 5 by the binding wire, binding the intersecting points of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib close to two rows of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib close to the periphery of the network point by point, binding the intersecting points of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib at the rest parts of the network according to 50 percent of the intersecting points, binding the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib 4 and the 5, then carrying out the construction of the 1 st glass fiber rib and the 2 nd bottom glass fiber rib 6 and 7, respectively arranging the 1 st glass fiber rib and the 2 nd bottom glass fiber rib 6 and the 7 transversely and longitudinally, binding the 2 nd bottom glass fiber rib 7 with the upper layer 1 st horizontal sample frame reinforcing steel bar 3, and the 2 nd longitudinal surface layer glass fiber rib 7 is subjected to binding of the 1 st transverse surface layer glass fiber rib 6 after installation, and the 2 nd surface layer glass fiber rib 7 is bound and connected with the 1 st surface layer glass fiber rib 6.
The 1 st, 2 bottom glass fiber muscle 4, 5 and 1 st, 2 surface course glass fiber muscle 6, 7 constitute by a plurality of glass fiber overlap joints, and two adjacent glass fiber overlap joints length must not be less than 40 centimetres, ties the silk and adopts 12 # iron wires.
Slope surface insertion steel bars 1 are welded with the 1 st and 2 nd horizontal sample frame steel bars after being completed.
The glass fiber manufacturing lengths are different, and the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 and the 1 st and 2 nd surface layer glass fiber ribs 6 and 7 are ensured to be bound and connected on the same section.
The construction method for replacing reinforcing steel bars with glass fiber reinforced plastics for the dam panel comprises the following steps:
making and transporting glass fiber rib
The surface of the fiber ribs should be clean, the stains on the surface should be removed before use, and if the surface of the material is polluted by certain substances or reagents, the material can be wiped clean by using a solvent. The glass fiber rib is a brittle material, and must be prevented from throwing and colliding during loading, unloading and transportation; and the transverse support rods are adopted for hoisting and transportation, so that the material is prevented from being too heavy, bent and damaged. All the glass fiber reinforcements are required to be numbered, 18T truck-mounted cranes are used for horizontally transporting the glass fiber reinforcements to a temporary dam top reinforcement storage yard for stacking, a 25T crane is used for placing the processed and formed fiber reinforcements on a slope reinforcement trolley according to the numbers, a 5T winch is used for pulling the reinforcement trolley, 1T of fiber reinforcements are conveyed to an installation working surface each time, the fiber reinforcements are manually installed on site,
Do a wall and lay domatic inserting reinforcing bar
The total station is adopted for measuring and lofting, the grid lines are arranged by piling, the inserted steel bars are deformed steel bars with the diameter of 25mm, the spacing is 2 multiplied by 2m, the inserted steel bars are manually driven into the bedding material by an iron hammer for 40cm, personnel use the ladder stand to go up and down and bind the safety ropes, the leaking parts of the inserted steel bars are flush with the surface of the steel bars of the upper horizontal sample frame, the design positions of the steel bars 2 and 3 of the 1 st and 2 nd sample frames are marked on the inserted steel bars by measuring,
mounting the sample frame steel bars
After the slope inserted steel bars are laid, sample frame steel bars are immediately installed, the sample frame steel bars are round steel with the diameter of 22mm, an upper layer and a lower layer are arranged, the 1 st sample frame steel bars and the 2 nd sample frame steel bars are horizontally arranged, the distance is 2.0m, the 1 st sample frame steel bars and the 2 nd sample frame steel bars are manually welded at the positions marked by the inserted steel bars 1 by using an electric welding machine, the outer leakage parts of the inserted steel bars are flush with the surfaces of the upper layer horizontal sample frame steel bars,
fourth 1 st and 2 nd base layer glass fiber ribs 4 and 5 are installed
After the construction of the sample frame ribs is finished, bottom layer fiber rib installation is carried out, the binding of the 1 st bottom layer glass fiber rib 4 is firstly carried out, the 1 st bottom layer glass fiber rib 4 is bound and connected with the 2 nd horizontal sample frame reinforcing steel bar 2 by using a 12# iron wire, the connecting position meets the requirement of a design drawing, the binding of the 2 nd bottom layer glass fiber rib 5 is started after the binding of the 1 st bottom layer glass fiber rib 4 is finished, the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 are bound by using a 12# iron wire, the intersection points of two lines of the 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 close to the periphery are firmly bound point by point, the intersection points of the rest 1 st and 2 nd bottom layer glass fiber ribs 4 and 5 are bound according to 50 percent of intersection points,
Binding of face layer glass fiber ribs
1, 2 bottom glass fiber muscle 4, 5 ligatures are accomplished the back, carry out the 1 st, 2 surface course fibre muscle 6, 7 construction, vertical 2 nd surface course fibre muscle 7 carries out the ligature with upper 2 nd horizontal appearance frame reinforcing bar 3 and is connected, the installation of 2 nd surface course fibre muscle 7 is accomplished the back upper portion and is carried out the ligature of horizontal 1 st surface course fibre muscle 6 again, the 1 st, 2 surface course fibre muscle adopts the ligature of pricking the silk, it all adopts the overlap joint to go up the fibre muscle, overlap joint length must not be less than 40 centimetres, it adopts No. 12 iron wires to prick the silk.

Claims (5)

1. A construction method for replacing reinforcing steel bars with glass fiber reinforcing steel bars on a dam panel is characterized in that a truck-mounted crane is used for horizontally transporting the glass fiber reinforcing steel bars to a dam top reinforcing steel bar temporary storage yard for stacking, a winch is used for pulling reinforcing steel bar trolleys to a binding position, inserting reinforcing steel bars (1) vertical to a slope surface are erected on the slope surface, the inserting reinforcing steel bars form a network consisting of longitudinal and transverse lines with the same interval on the slope surface, the inserting reinforcing steel bars are positioned at four corners of a 2 x 2m grid, the inserting reinforcing steel bars penetrate slope-fixing mortar to enter bedding materials for 35-45cm, upper and lower layers of 1 and 2 horizontal sample frame reinforcing steel bars (3) and (2) are welded on the inserting reinforcing steel bars, the 1 and 2 horizontal sample frame reinforcing steel bars are positioned in the transverse direction of the slope surface, the outer leakage parts of the inserting reinforcing steel bars are flush with the surface of the 1 st horizontal sample frame reinforcing steel bar, the 1 nd 2 bottom layer glass fiber reinforcing steel bars (4) and (5) are respectively positioned in the longitudinal direction and the transverse direction of the slope surface, the bottom layer glass fiber reinforcing steel bars are firstly bound, the 1 st bottom glass fiber rib (4) is connected with the 2 nd horizontal sample frame reinforcing steel bar (2) through a binding wire, after the 1 st bottom glass fiber rib is bound, the longitudinal 1 st bottom glass fiber rib is connected with the transverse 2 nd bottom glass fiber rib through the binding wire, the intersecting position of the 1 st bottom glass fiber rib and the 2 nd bottom glass fiber rib is bound by the binding wire, the intersecting points of the two rows of the 1 st and 2 nd bottom glass fiber ribs near the periphery of the network are bound point by point, the intersecting points of the 1 st and 2 nd bottom glass fiber ribs at the other positions of the network are bound according to 50 percent of the intersecting points, after the 1 st and 2 nd bottom glass fiber ribs are bound, the 1 st and 2 nd surface glass fiber ribs (6) and (7) are constructed, the 1 st and 2 nd surface glass fiber ribs are respectively arranged transversely and longitudinally, the 2 nd surface glass fiber rib (7) is bound with the upper 1 st horizontal sample frame reinforcing steel bar (3), after the installation of the transverse 2-layer glass fiber ribs is finished, the upper part of the transverse 1 st-layer glass fiber rib (6) is bound, and the 2 nd-layer glass fiber rib and the 1 st-layer glass fiber rib are bound and connected.
2. The dam panel construction method of claim 1 using glass fiber reinforcement instead of steel reinforcement, wherein the first and second bottom glass fiber reinforcements and the first and second face glass fiber reinforcements are formed by overlapping a plurality of glass fibers, the overlapping length of two adjacent glass fibers is not less than 40 cm, and the binding wire is made of 12 # iron wire.
3. The dam panel construction method of claim 1 using glass fiber reinforcement instead of reinforcement, wherein the slope surface is welded to the 1 st and 2 nd horizontal sample frames after the insertion of reinforcement 1.
4. The dam panel construction method of claim 2 using glass fiber reinforcement instead of reinforcement, wherein the glass fiber is made in different lengths, ensuring that the 1 st and 2 nd bottom layer glass fiber reinforcement and the 1 st and 2 nd face layer glass fiber reinforcement binding joints are not on the same cross section.
5. The construction method for replacing reinforcing steel bars with glass fiber reinforced plastics for the dam panel comprises the following steps:
manufacturing and transporting glass fiber reinforced plastic bars
The surface of the fiber rib should be clean, surface stains should be removed before use, if the surface of the material is polluted by some substances or reagents, the material can be wiped clean by using a solvent, the glass fiber rib is a brittle material, and throwing and collision need to be avoided during loading, unloading and transportation; the transverse brace rods are adopted for hoisting and transporting, the bending and the breakage caused by overweight of materials are avoided, all the glass fiber reinforcements are required to be numbered, the vehicle-mounted crane is used for horizontally transporting the glass fiber reinforcements to a dam top reinforcement temporary storage yard for stacking, the crane is used for placing the processed and formed fiber reinforcements on a slope reinforcement trolley according to the numbers, the reinforcement trolley is pulled by a winch, the fiber reinforcements are conveyed to a mounting working face each time and are manually mounted on site,
Dome laying slope surface insertion steel bar
The total station is adopted for measuring and lofting, the grid lines are arranged by piling, the inserted steel bars are deformed steel bars with the diameter of 25mm, the spacing is 2 multiplied by 2m, the inserted steel bars are manually driven into the bedding material by an iron hammer for 40cm, personnel use the ladder stand to go up and down and bind the safety ropes, the leaking parts of the inserted steel bars are flush with the surface of the steel bars of the upper horizontal sample frame, the design positions of the steel bars of the 1 st and the 2 nd sample frames are marked on the inserted steel bars by measuring,
mounting the sample frame reinforcing steel bars
After the slope inserted steel bars are laid, sample frame steel bars are immediately installed, the sample frame steel bars are round steel with the diameter of 22mm, an upper layer and a lower layer are arranged, the 1 st sample frame steel bars and the 2 nd sample frame steel bars are horizontally arranged, the distance is 2.0m, the 1 st sample frame steel bars and the 2 nd sample frame steel bars (2) and (3) are manually welded at the positions marked by the inserted steel bars 1 by using an electric welding machine, the outer leakage parts of the inserted steel bars are flush with the surface of the upper layer horizontal sample frame steel bars,
the No. 1 and No. 2 bottom glass fiber ribs (4) and (5) are installed
After the construction of the sample frame ribs is finished, bottom layer fiber rib installation is carried out, the 1 st bottom layer glass fiber rib (4) is bound, the 1 st bottom layer glass fiber rib is bound and connected with the 2 nd horizontal sample frame reinforcing steel bar (2) by using a 12# iron wire, the connecting position meets the requirement of a design drawing, the 2 nd bottom layer glass fiber rib (5) is bound after the 1 st bottom layer glass fiber rib is bound, the 1 st and 2 nd bottom layer glass fibers are bound by using a 12# iron wire, the intersection points of two lines of the 1 st and 2 nd bottom layer glass fiber ribs close to the periphery are firmly bound point by point, the intersection points of the rest 1 st and 2 nd bottom layer glass fiber ribs are bound according to 50 percent of intersection points,
Binding of face layer glass fiber ribs
1, 2 back is accomplished in the ligature of bottom glass fiber muscle, carry out 1, 2 surface course fibre muscle (6), (7) construction, vertical 2 nd surface course fibre muscle carries out the ligature with upper 2 nd level appearance frame reinforcing bar (3) and is connected, 2 nd surface course fibre muscle installation is accomplished the back and is the upper portion again carry out horizontal 1 st surface course fibre muscle ligature, 1 st, 2 surface course fibre muscle adopts the ligature of bundling, above the fibre muscle all adopt the overlap joint, overlap joint length must not be less than 40 centimetres, bundle the silk and adopt No. 12 iron wires.
CN202210407590.4A 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels Active CN114753315B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210407590.4A CN114753315B (en) 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210407590.4A CN114753315B (en) 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels

Publications (2)

Publication Number Publication Date
CN114753315A true CN114753315A (en) 2022-07-15
CN114753315B CN114753315B (en) 2024-04-26

Family

ID=82330834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210407590.4A Active CN114753315B (en) 2022-04-19 2022-04-19 Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels

Country Status (1)

Country Link
CN (1) CN114753315B (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080279634A1 (en) * 2005-11-24 2008-11-13 James Heselden Gabions
CN201351253Y (en) * 2009-01-09 2009-11-25 长沙理工大学 Continuous reinforced concrete pavement
JP2011179310A (en) * 2010-02-03 2011-09-15 Taiyo Kogyo Corp Overtopping preventive apparatus
CN203583432U (en) * 2013-11-11 2014-05-07 中国建筑第八工程局有限公司 FRP (Fiber Reinforced Polymer) bar reinforced concrete parapet structure and formwork structure thereof
CN204373989U (en) * 2015-02-04 2015-06-03 中国葛洲坝集团第六工程有限公司 A kind of glass fiber bend bar test unit
US20160108619A1 (en) * 2014-10-16 2016-04-21 Emin Buzimkic Prefabricated modular rebar modules and methods of using the same
CN105603846A (en) * 2016-03-10 2016-05-25 长沙理工大学 Dual-layer glass fiber concrete pavement structure applicable to city roads
CN105625298A (en) * 2016-03-16 2016-06-01 中冶集团武汉勘察研究院有限公司 Underground continuous wall structure adopting glass fiber bar lapping and milling and construction method for underground continuous wall structure
CN205605222U (en) * 2015-12-17 2016-09-28 北京建筑大学 Netting structure among net shotcrete
CN107435318A (en) * 2017-09-14 2017-12-05 国家电网公司 A kind of insulation anchor structure and construction method suitable for water resources dam polyureas barrier coat
CN108221876A (en) * 2018-02-08 2018-06-29 吕桂兰 A kind of hydraulic engineering flood discharge antiseepage dam
CN109235374A (en) * 2018-12-03 2019-01-18 唐山工业职业技术学院 A kind of constructing device and construction method for assisting high steep reinforced earth dam to fill
CN111779194A (en) * 2020-07-21 2020-10-16 湖北三江航天建筑工程有限公司 Method for installing glass fiber reinforcement in constructional engineering
CN212358199U (en) * 2020-03-26 2021-01-15 广东水利水电第三工程局有限公司 Reverse filtering layer structure of dam heel at downstream of earth dam
US11053675B1 (en) * 2018-11-17 2021-07-06 Juan Jose Santandreu Construction panel and construction panel assembly with improved structural integrity

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080279634A1 (en) * 2005-11-24 2008-11-13 James Heselden Gabions
CN201351253Y (en) * 2009-01-09 2009-11-25 长沙理工大学 Continuous reinforced concrete pavement
JP2011179310A (en) * 2010-02-03 2011-09-15 Taiyo Kogyo Corp Overtopping preventive apparatus
CN203583432U (en) * 2013-11-11 2014-05-07 中国建筑第八工程局有限公司 FRP (Fiber Reinforced Polymer) bar reinforced concrete parapet structure and formwork structure thereof
US20160108619A1 (en) * 2014-10-16 2016-04-21 Emin Buzimkic Prefabricated modular rebar modules and methods of using the same
CN204373989U (en) * 2015-02-04 2015-06-03 中国葛洲坝集团第六工程有限公司 A kind of glass fiber bend bar test unit
CN205605222U (en) * 2015-12-17 2016-09-28 北京建筑大学 Netting structure among net shotcrete
CN105603846A (en) * 2016-03-10 2016-05-25 长沙理工大学 Dual-layer glass fiber concrete pavement structure applicable to city roads
CN105625298A (en) * 2016-03-16 2016-06-01 中冶集团武汉勘察研究院有限公司 Underground continuous wall structure adopting glass fiber bar lapping and milling and construction method for underground continuous wall structure
CN107435318A (en) * 2017-09-14 2017-12-05 国家电网公司 A kind of insulation anchor structure and construction method suitable for water resources dam polyureas barrier coat
CN108221876A (en) * 2018-02-08 2018-06-29 吕桂兰 A kind of hydraulic engineering flood discharge antiseepage dam
US11053675B1 (en) * 2018-11-17 2021-07-06 Juan Jose Santandreu Construction panel and construction panel assembly with improved structural integrity
CN109235374A (en) * 2018-12-03 2019-01-18 唐山工业职业技术学院 A kind of constructing device and construction method for assisting high steep reinforced earth dam to fill
CN212358199U (en) * 2020-03-26 2021-01-15 广东水利水电第三工程局有限公司 Reverse filtering layer structure of dam heel at downstream of earth dam
CN111779194A (en) * 2020-07-21 2020-10-16 湖北三江航天建筑工程有限公司 Method for installing glass fiber reinforcement in constructional engineering

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
余万龙: "玻璃纤维筋在抽水蓄能电站 大坝面板中的应用", 《电力勘测设计》, 31 March 2023 (2023-03-31), pages 88 - 92 *
周国凯: "玻璃纤维筋在即有库区取水口预留岩坎中的应用", 《中国水运》, vol. 21, no. 6, 16 June 2021 (2021-06-16), pages 120 - 121 *
李殿平: "《混凝土结构加固设计与施工》", 30 November 2012, 天津:天津大学出版社, pages: 22 *

Also Published As

Publication number Publication date
CN114753315B (en) 2024-04-26

Similar Documents

Publication Publication Date Title
CN103352429B (en) Bracket reverse drawing loads the stretch-draw preloading method of prepressing device
CN103276662B (en) Large-cantilever steel web spinal box beam segment
CN113752379B (en) Concrete T beam prefabrication construction method adopting secondary tensioning process and movable pedestal
CN208668765U (en) Precast prestressed beam and assembled composite frame structure
CN206859479U (en) A kind of steel bar girder laminated floor slab
CN212210305U (en) Transmission line strides across block structure
CN108457422A (en) Precast prestressed beam, assembled composite frame structure and its installation method
CN106567542A (en) Super high-rise double tower building steel structure corridor assembling method
CN210342375U (en) Concrete laminated slab
CN114753315A (en) Construction method for replacing reinforcing steel bars with glass fiber reinforcements for dam panels
CN107975184A (en) A kind of assembled architecture integrated wall and its construction method
CN108004932A (en) Constructed the method for steel reinforced concrete combination beam using beam mode is transported under beam
CN218521787U (en) Simple prefabricated pipe pile core filling auxiliary device
CN204311457U (en) A kind of Metro station excavation excavation construction composite retaining structure system
CN217353122U (en) Assembled exempts from to prop up mould building carrier plate
CN213062094U (en) Ground storehouse roof reservation entrance to a cave retaining wall convenient to demolish
CN211621667U (en) Tubular pile cushion cap girder steel rail mounted tower machine walking foundation structure
CN211648368U (en) Prefabricated polygonal prestressed concrete tower cylinder
CN213087172U (en) Reinforced concrete floor and connecting node thereof
CN212956548U (en) Inner support and main structure stress conversion bracket component
CN218541133U (en) Precast concrete superimposed sheet
CN110578333A (en) temporary slope supporting device for garbage pile excavation and construction method thereof
CN218758630U (en) Remove elevartor shaft operation platform
CN109989478A (en) A kind of precast prestressed concrete frame structure
CN215291319U (en) Multi-point elevator shaft construction lifting platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant