CN114737618A - Water-stopping construction method for front-support grouting steel pipe - Google Patents

Water-stopping construction method for front-support grouting steel pipe Download PDF

Info

Publication number
CN114737618A
CN114737618A CN202210270103.4A CN202210270103A CN114737618A CN 114737618 A CN114737618 A CN 114737618A CN 202210270103 A CN202210270103 A CN 202210270103A CN 114737618 A CN114737618 A CN 114737618A
Authority
CN
China
Prior art keywords
water stop
steel pipe
steel plate
front support
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210270103.4A
Other languages
Chinese (zh)
Inventor
钟满群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN202210270103.4A priority Critical patent/CN114737618A/en
Publication of CN114737618A publication Critical patent/CN114737618A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A front support grouting steel pipe water stop construction method is characterized by comprising the following steps: a. and c, processing a water stop steel plate, b, welding the water stop steel plate, and c, installing the water stop steel plate, wherein when the grouting steel pipe penetrates through the outer wall and the bottom plate of the basement, the grouting steel pipe and the welded water stop steel plate are installed in a water facing area of the outer wall and the bottom plate of the basement in the middle of the concrete structure during concrete pouring, so that the water stop steel plate forms a complete waterproof system. The front support grouting steel pipe water stop construction method has the advantages that the water stop steel plate is simple in structure and convenient to manufacture, the front support grouting steel pipe water stop device is convenient to assemble and good in waterproof effect, and can be flexibly installed in a water facing area of a concrete structure and prevent the structure from leaking.

Description

Water-stopping construction method for front-support grouting steel pipe
Technical Field
The invention relates to a water stop steel plate, in particular to a front support grouting steel pipe water stop construction method.
Background
In the foundation pit enclosure, the traditional front support grouting steel pipe passes through the outer wall of the basement, the bottom plate of the basement and the like and is directly wrapped by concrete, so that the structure has the defects of leakage and poor water stop effect, the service life of the building is shortened, and the construction and maintenance cost is increased.
Therefore, in the prior art, how to complete the water stopping problem of the front-support grouting steel pipe is a technical problem to be solved urgently in the field.
Disclosure of Invention
The invention aims to provide a safe and reliable water stopping construction method for a front support grouting steel pipe.
In order to achieve the purpose, the technical solution of the invention is as follows:
a front support grouting steel pipe water stop construction method is characterized by comprising the following steps:
a. processing water stop steel plate
Processing a water stop steel plate according to the size of the front support grouting steel pipe according to the design, wherein the water stop steel plate is square, and the square water stop steel plate is divided into two symmetrical half plates;
b. welding water stop steel plate
The water-stopping steel plate is obliquely welded with the front support grouting steel pipe by adopting a common method of the water-stopping steel plate, so that the two symmetrical half plates are matched and welded on the outer side of the front support grouting steel pipe at a certain angle to form the water-stopping steel plate;
c. installation stagnant water steel sheet
When the grouting steel pipe penetrates through the outer wall and the bottom plate of the basement, the grouting steel pipe and the welded water stop steel plate are arranged in the water facing area of the outer wall and the bottom plate of the basement in the middle of the concrete structure when concrete is poured, so that the water stop steel plate forms a complete waterproof system.
The front support grouting steel pipe water stop construction method can be further realized by adopting the following technical measures.
In the method, the side length of the square water stop steel plate is more than or equal to 600 mm.
In the method, the thickness of the square water stop steel plate is more than or equal to 6 mm.
The method, wherein the specification of the front-support grouting steel pipe is phi Q325 × 8.
The method wherein said welding is with an electrode of type E43.
In the method, the height of the welding seam between the two symmetrical half plates is more than or equal to 6 mm.
In the method, the height of the welded joint between the water stop steel plate and the front support grouting steel pipe is more than or equal to 6 mm.
After the technical scheme is adopted, the front support grouting steel pipe water stop construction method has the following advantages:
1. the water stop steel plate has simple structure and convenient manufacture;
2. the front support grouting steel pipe water stop device is convenient to assemble and good in waterproof effect;
3. can be flexibly installed in the water-facing area of the concrete structure to prevent the structure from leaking.
Drawings
FIG. 1 is a schematic layout view of a front stay grouting steel pipe and a water stop steel plate according to an embodiment of the invention;
fig. 2 is a schematic structural diagram of a welding structure of a front support grouting steel pipe and a water stop steel plate according to an embodiment of the invention.
In the figure: 1 stagnant water steel sheet, 2 preceding brace slip casting steel pipes, 3 welded joint between the stagnant water steel sheet half slab, 4 welded joint between stagnant water steel sheet and the preceding brace slip casting steel pipe.
Detailed Description
The present invention will be further described with reference to the following examples and the accompanying drawings.
Example 1
The invention discloses a water stop construction method for a front support grouting steel pipe, which comprises the following steps of:
referring to fig. 1, fig. 1 is a schematic view illustrating an arrangement of a front-support grouting steel pipe and a water stop steel plate according to an embodiment of the present invention. The material is divided into two half boards by blanking the 600mm water stop steel plate 1 in advance, the two half boards are used for enabling the grouting steel pipe to penetrate through the basement outer wall, the basement bottom plate and the like, and the front support grouting steel pipe 2 is connected through the water stop steel plate, so that welding and installation are facilitated. According to the water stopping method of the front support grouting steel pipe, the water stopping method of the front support grouting steel pipe adopts a Q235B water stopping steel plate, the thickness is 6mm, and the welding rod adopts an E43 type, so that the height of a welding seam 3 between half plates of the water stopping steel plate and the height of a welding seam 4 between the water stopping steel plate and the front support grouting steel pipe are not less than 6mm, and the anti-seepage effect of the basement is remarkable. When concrete is poured, the water-stopping steel plate is installed in place and positioned in the middle of the concrete structure, and a complete waterproof system is formed after the water-stopping steel plate is welded. Fig. 2 is a structural schematic diagram of a welding structure of a front support grouting steel pipe and a water stop steel plate according to an embodiment of the invention. The water stopping method of the front support grouting steel pipe is convenient to assemble and good in waterproof effect, and has the greatest advantage.
The construction method for stopping water of the front support grouting steel pipe has the advantages of substantial characteristics and obvious technical progress, and is a construction method with simple structure, convenient operation and good water stopping effect. As long as the water stop steel plate is fed in advance, the grouting steel pipe can penetrate through the basement outer wall, the basement bottom plate and the like, and the grouting steel pipe is connected with the water stop steel plate, so that welding installation is facilitated. The structure is very simple, the water stopping effect is good, the water stopping device can be flexibly installed in the water-facing area of the basement, the structure is prevented from leaking, the service life of the building is prolonged, and the construction and maintenance cost is reduced.
The above embodiments are provided only for illustrating the present invention and not for limiting the present invention, and those skilled in the art can make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalent technical solutions should also fall within the scope of the present invention, and should be defined by the claims.

Claims (7)

1. A front support grouting steel pipe water stop construction method is characterized by comprising the following steps:
a. processing water stop steel plate
Processing a water stop steel plate according to the size of the front support grouting steel pipe according to the design, wherein the water stop steel plate is square, and the square water stop steel plate is divided into two symmetrical half plates;
b. welding water stop steel plate
The water-stopping steel plate is obliquely welded with the front support grouting steel pipe by adopting a common method of the water-stopping steel plate, so that the two symmetrical half plates are matched and welded on the outer side of the front support grouting steel pipe at a certain angle to form the water-stopping steel plate;
c. installation water stop steel plate
When the grouting steel pipe penetrates through the outer wall and the bottom plate of the basement, the grouting steel pipe and the welded water stop steel plate are arranged in the water facing area of the outer wall and the bottom plate of the basement in the middle of the concrete structure when concrete is poured, so that the water stop steel plate forms a complete waterproof system.
2. The front support grouting steel pipe water stop construction method according to claim 1, wherein the side length of the square water stop steel plate is more than or equal to 600 mm.
3. The front support grouting steel pipe water stop construction method according to claim 1, wherein the thickness of the square water stop steel plate is more than or equal to 6 mm.
4. The water stop construction method for the front support grouting steel pipe as claimed in claim 1, wherein the specification of the front support grouting steel pipe is phi Q325B x 8.
5. The water stop construction method for the front-support grouting steel pipe as claimed in claim 1, wherein the welding is an E43 type welding rod.
6. The water stop construction method for the front support grouting steel pipe as claimed in claim 1, wherein the height of the welding seam between the two symmetrical half plates is more than or equal to 6 mm.
7. The front support grouting steel pipe water stop construction method according to claim 1, wherein the height of a welded joint between the water stop steel plate and the front support grouting steel pipe is more than or equal to 6 mm.
CN202210270103.4A 2022-03-18 2022-03-18 Water-stopping construction method for front-support grouting steel pipe Pending CN114737618A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210270103.4A CN114737618A (en) 2022-03-18 2022-03-18 Water-stopping construction method for front-support grouting steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210270103.4A CN114737618A (en) 2022-03-18 2022-03-18 Water-stopping construction method for front-support grouting steel pipe

Publications (1)

Publication Number Publication Date
CN114737618A true CN114737618A (en) 2022-07-12

Family

ID=82276693

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210270103.4A Pending CN114737618A (en) 2022-03-18 2022-03-18 Water-stopping construction method for front-support grouting steel pipe

Country Status (1)

Country Link
CN (1) CN114737618A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04339919A (en) * 1991-05-15 1992-11-26 Hakko Co Ltd Water-proof device for pipe inserting section for pit
CN208748662U (en) * 2018-08-06 2019-04-16 浙江国泰建设集团有限公司 Foundation pit front-supporting type slip casting steel pipe support structure
CN210368980U (en) * 2019-06-10 2020-04-21 江苏省岩土工程公司 Earlier prop formula bracing strut supporting construction system
CN111364481A (en) * 2020-04-24 2020-07-03 上海勘察设计研究院(集团)有限公司 End embedded type prestressed inclined pile and construction method thereof
CN213538991U (en) * 2020-09-29 2021-06-25 上海勘察设计研究院(集团)有限公司 Wall-penetrating connecting structure for front-supporting type grouting steel pipe
CN113550323A (en) * 2021-07-16 2021-10-26 五冶集团上海有限公司 Fixing sleeve capable of recycling front support grouting steel pipe

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04339919A (en) * 1991-05-15 1992-11-26 Hakko Co Ltd Water-proof device for pipe inserting section for pit
CN208748662U (en) * 2018-08-06 2019-04-16 浙江国泰建设集团有限公司 Foundation pit front-supporting type slip casting steel pipe support structure
CN210368980U (en) * 2019-06-10 2020-04-21 江苏省岩土工程公司 Earlier prop formula bracing strut supporting construction system
CN111364481A (en) * 2020-04-24 2020-07-03 上海勘察设计研究院(集团)有限公司 End embedded type prestressed inclined pile and construction method thereof
CN213538991U (en) * 2020-09-29 2021-06-25 上海勘察设计研究院(集团)有限公司 Wall-penetrating connecting structure for front-supporting type grouting steel pipe
CN113550323A (en) * 2021-07-16 2021-10-26 五冶集团上海有限公司 Fixing sleeve capable of recycling front support grouting steel pipe

Similar Documents

Publication Publication Date Title
CN209811582U (en) Large diameter pipeline aligning deviation processing positioning device
CN113700046A (en) Basement structure antiseep bushing apparatus
CN213682129U (en) Deep foundation pit unilateral die carrier
CN114737618A (en) Water-stopping construction method for front-support grouting steel pipe
CN207177286U (en) Add region mould after fabricated shear wall is reserved
CN211171973U (en) Positioning protection device for assisting in lowering of pile foundation reinforcement cage
CN209760872U (en) Diagonal draw bar for supporting-free formwork
CN215717264U (en) Novel adjustable aluminium template leak protection thick liquid device
CN211898553U (en) Fixing template of underground pipe gallery band steel edge rubber waterstop
CN210858015U (en) Supporting device for adjusting verticality of single-sided template
CN108396961A (en) Construction joint formwork erection method between a kind of dual wall
CN211396589U (en) Concrete shear wall construction control node
CN217974502U (en) Basement post-cast strip retaining wall structure
CN220704798U (en) Vertical post-cast strip shutoff frock in advance
CN207526109U (en) Hole device is blocked up around through the erect riser of floor
CN207392530U (en) A kind of avoid-dismantle outer wall of basement flange single side formwork device
CN215669716U (en) Basement structure antiseep bushing apparatus
CN216238605U (en) Well plugging device for dewatering well
CN215669465U (en) Novel rolling combined mechanism for piling
CN217398304U (en) Overhanging type tower crane supporting mechanism
CN214832409U (en) High-pressure water retaining reinforced concrete wall seepage-proofing structure
CN212616797U (en) Wall-penetrating pipeline with water seepage prevention function
CN220927931U (en) Tubular prefabricated bolt hole die
CN220888721U (en) Tool for quickly constructing cable trench and bracket
CN217500582U (en) Novel be applied to slip form silo tower crane and attach wall built-in fitting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220712

RJ01 Rejection of invention patent application after publication