CN1146546A - External decomposition technology for waste heat generating technology of cement kiln - Google Patents

External decomposition technology for waste heat generating technology of cement kiln Download PDF

Info

Publication number
CN1146546A
CN1146546A CN 96107067 CN96107067A CN1146546A CN 1146546 A CN1146546 A CN 1146546A CN 96107067 CN96107067 CN 96107067 CN 96107067 A CN96107067 A CN 96107067A CN 1146546 A CN1146546 A CN 1146546A
Authority
CN
China
Prior art keywords
kiln
fluidized bed
bed calciner
waste heat
level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 96107067
Other languages
Chinese (zh)
Other versions
CN1113212C (en
Inventor
孔健民
付子诚
潘华
高原
苏姣华
孙铁军
李凤林
李峻峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Building Materials Academy CBMA
Original Assignee
China Building Materials Academy CBMA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Building Materials Academy CBMA filed Critical China Building Materials Academy CBMA
Priority to CN 96107067 priority Critical patent/CN1113212C/en
Publication of CN1146546A publication Critical patent/CN1146546A/en
Application granted granted Critical
Publication of CN1113212C publication Critical patent/CN1113212C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Curing Cements, Concrete, And Artificial Stone (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The rotary kiln with a precalcinator for power generation process by using waste heat of cement kiln is characterized by that all the kiln smoke and raw material are passed through said process system and a suction operation process is used so as to implement external circulating process of partial material. Said invention can raise kiln yield by above 80%, and the generated output is raised by 30-40%, and can implement large-scale production.

Description

The precal cination technique that is used for cement kiln residual heat generating technology
The present invention belongs to pre-burning manufacturing cement in fluid bed, utilizes a kind of improvement of kiln fume afterheat electricity-generating method simultaneously.
Precal cination technique is a kind of burning clinker of cement new technology that grows up the seventies, this method is to have set up a dore furnace between suspended preheater and rotary kiln, the fuel of adding about 60% in stove, make the exothermic process of fuel combustion and the endothermic process of raw material carbonate decomposition, make it promptly carry out heat exchange with suspended state or fluidisation attitude form, thereby the resolution ratio that makes the kiln raw material is brought up to more than 75%, has reduced the thermic load of rotary kiln thus, has improved the productivity ratio of kiln again.
Utilize the cement kiln residual heat generating technology, prior art all adopts the technology pattern of traditional hollow kiln band waste heat boiler, and this technological process kiln output is little, efficient is low, hear rate is high, generating production line small scale.Though the patent 85100898 of my institute's earlier application adopts the fluidization principle that cold wind, cold burden are directly sent into dore furnace, save 4 to 5 grades of preheaters, but its technological process is not perfect, the kiln flue gas of this patent is not by decomposition furnace system, and raw material are gone into kiln after partly decomposing through dore furnace, and the remainder raw material are directly into kiln, this patent adopts positive pressure operation, the used combustion air of dore furnace is the normal temperature air that blower fan blasts, and hear rate is still high, and system scale is again little.
The objective of the invention is: improve technological process, make full use of the kiln fume afterheat, improve raw material resolution ratio and kiln output, cut down the consumption of energy simultaneously, increase economic efficiency.
Feature of the present invention is:
(1) the kiln flue gas is all by this process system, and its flow process is that the kiln discharge flue gas is gone into fluidized bed calciner earlier, through 1-3 level rotoclone collector, goes into waste heat boiler and cottrell then;
Raw material can all feed fluidized bed calciner, also can partly feed dore furnace, and preheating, decomposition are after go into kiln behind the 1-3 level rotoclone collector;
(2) fluidized bed calciner and supporting 1-3 level rotoclone collector;
(3) under the one-level dust-precipitator, be provided with high temperature ratio tripper, make part or all of material go into fluidized bed calciner again according to running situation, realize part decomposition material stove external circulation process;
(4) total system moves under negative-pressure operation, and raw material, coal dust directly enter fluidized bed calciner, goes into fluidized bed calciner from the hot blast that kiln hood extracts through tertiary-air pipe.
Technological process of the present invention is expressed in accompanying drawing 1.
Among the figure: 1. rotary kiln 2. roots blowers 3. fluidized bed calciners 4. one-level rotoclone collectors 5. secondary rotoclone collectors 6. waste heat boilers 7. Turbo-generator Set 8. air-introduced machines 9. cottrells 10. high temperature ratio trippers
Fig. 2 is the dore furnace schematic diagram.
Advantage of the present invention:
1. fluidized bed calciner moves under negative-pressure operation, and raw material preheating and decomposition under 850 ℃ of-900 ℃ of temperature reaches more than 75% calcium carbonate decomposition rate, and kiln output improves 80%.
2. existing hollow kiln dust contained flue gas is big, and system leaks out greatly, and dust stratification is many, influence waste heat boiler efficient and scale, efficient cyclone dust-precipitator gross efficiency reaches about 95% in the system of the present invention, so Gas Parameters is stable, flow height, EGT can improve generated energy 30-40% up to 850 ℃.The present invention can be supporting with horizontal or vertical waste heat boiler, and scale and benefit are arranged, and improved the cogeneration integral level.
3. save 4-5 level pre-heating device, saved equipment investment.
The embodiment of the invention:
Technological process shown in the accompanying drawing 1 is promptly implemented at cement plant, Huhehaote City 2# kiln at present.Raw material directly feed fluidized bed calciner without preheater, the coal dust of burning usefulness directly feeds the dore furnace bottom by delivery pump from kiln hood, required combustion air major part extracts hot blast by tertiary-air pipe from kiln hood and provides, the fluidized wind of dore furnace is blasted from the bottom by roots blower, go out kiln exit gas and enter the dore furnace middle part, raw material preheating in dore furnace is also decomposed the back and is accepted into kiln by the secondary rotoclone collector, this system can make the raw material resolution ratio reach more than 75%, for the thermal efficiency and the operational stability that improves dore furnace, again return dore furnace by the partial material that the one-level rotoclone collector is accepted by the control of high temperature ratio tripper, form the stove outer circulation with this, go into the usefulness of waste heat boiler for generating by the high-temperature flue gas (about about 850 ℃) of secondary rotoclone collector.

Claims (1)

1. precal cination technique that is used for cement kiln residual heat generating technology is characterized in that:
(1) the kiln flue gas is all by this process system, and its flow process is that the kiln discharge flue gas is gone into fluidized bed calciner earlier, through 1-3 level rotoclone collector, goes into waste heat boiler and cottrell then;
Raw material can all feed fluidized bed calciner, also can partly feed dore furnace, and preheating, decomposition are after go into kiln behind the 1-3 level rotoclone collector;
(2) fluidized bed calciner and supporting 1-3 level rotoclone collector thereof;
(3) under the one-level dust-precipitator, be provided with high temperature ratio tripper, make part or all of material go into fluidized bed calciner again according to running situation, realize part decomposition material stove external circulation process;
(4) total system moves under negative-pressure operation, and raw material, coal dust directly enter fluidized bed calciner, goes into fluidized bed calciner from the hot blast that kiln hood extracts through tertiary-air pipe.
CN 96107067 1996-07-15 1996-07-15 External decomposition technology for waste heat generating technology of cement kiln Expired - Fee Related CN1113212C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 96107067 CN1113212C (en) 1996-07-15 1996-07-15 External decomposition technology for waste heat generating technology of cement kiln

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 96107067 CN1113212C (en) 1996-07-15 1996-07-15 External decomposition technology for waste heat generating technology of cement kiln

Publications (2)

Publication Number Publication Date
CN1146546A true CN1146546A (en) 1997-04-02
CN1113212C CN1113212C (en) 2003-07-02

Family

ID=5119506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 96107067 Expired - Fee Related CN1113212C (en) 1996-07-15 1996-07-15 External decomposition technology for waste heat generating technology of cement kiln

Country Status (1)

Country Link
CN (1) CN1113212C (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011009321A1 (en) * 2009-07-24 2011-01-27 天津水泥工业设计研究院有限公司 Predecomposition kiln tail system used outside of cement kiln for processing raw materials with combustible substances
CN101571573B (en) * 2008-09-10 2012-10-24 安徽海螺川崎工程有限公司 Method for testing power generating performance of waste heat of cement kiln
CN105276573A (en) * 2015-12-01 2016-01-27 天津德诚志成水泥建材技术咨询服务有限公司 Air, coal and material graded low-nitrogen combustion equipment and process as well as cement clinker sintering system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101571573B (en) * 2008-09-10 2012-10-24 安徽海螺川崎工程有限公司 Method for testing power generating performance of waste heat of cement kiln
WO2011009321A1 (en) * 2009-07-24 2011-01-27 天津水泥工业设计研究院有限公司 Predecomposition kiln tail system used outside of cement kiln for processing raw materials with combustible substances
CN105276573A (en) * 2015-12-01 2016-01-27 天津德诚志成水泥建材技术咨询服务有限公司 Air, coal and material graded low-nitrogen combustion equipment and process as well as cement clinker sintering system

Also Published As

Publication number Publication date
CN1113212C (en) 2003-07-02

Similar Documents

Publication Publication Date Title
CN201254529Y (en) Cement clinker calcination system
CN104075332A (en) System and method for increasing comprehensive utilization rate of yellow phosphorus tail gas
CN216049201U (en) Device for improving waste heat utilization of grate cooler of cement clinker production line
CN206496338U (en) A kind of co-generation unit under superhigh temperature super-pressure parameter
CN104101225A (en) System and method for increasing comprehensive utilization ratio of tail gas of calcium carbide furnace
CN212610308U (en) Cement clinker firing production line capable of improving waste gas waste heat utilization rate
CN105402737A (en) Mechanical grate-type garbage single-furnace gasifying incineration and boiler system
CN106610016A (en) Combined heat and power generation system under super-high temperature and super-high pressure parameters and method thereof
CN210400021U (en) Complete equipment for treating dust-containing tail gas of calcining furnace
CN1113212C (en) External decomposition technology for waste heat generating technology of cement kiln
CN2517518Y (en) Ecological integrated utilizing prodn. appts. for gangue
CN110118492B (en) Waste heat utilization production system based on super internal combustion baked brick tunnel kiln
CN205560763U (en) Mechanical stoker formula rubbish list stove gasification incineration boiler system
CN213363368U (en) High-efficiency low-resistance energy-saving decomposing furnace
CN109058983A (en) Recirculating fluidized bed combustion with meagre oxygen catalysis oxidation fractional combustion boiler system and method
CN108680040A (en) The efficient Distribution utilization system of sintering mine sensible heat and distribution method
CN2319767Y (en) High temp. waste heat generating kiln with preheater
CN211921416U (en) System for preparing active coke powder in thermal power plant
CN204063993U (en) The bypass device of cement kiln associated treatment rubbish
CN207990606U (en) A kind of boiler is for exhaust system
CN210050992U (en) Coal-fired boiler type hot-blast stove
CN208688277U (en) The efficient Distribution utilization system of sintering mine sensible heat
CN2262697Y (en) Intensified decomposing furnace for concrete waste heat electric generating kiln
CN212108336U (en) High-efficient clean steam island
CN218723206U (en) Industrial silicon smelting and granular silicon production heat energy coupling system

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee