CN114508244A - Reconstruction method of rail transit ground station - Google Patents

Reconstruction method of rail transit ground station Download PDF

Info

Publication number
CN114508244A
CN114508244A CN202110774828.2A CN202110774828A CN114508244A CN 114508244 A CN114508244 A CN 114508244A CN 202110774828 A CN202110774828 A CN 202110774828A CN 114508244 A CN114508244 A CN 114508244A
Authority
CN
China
Prior art keywords
canopy
station
shed
movable
installing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110774828.2A
Other languages
Chinese (zh)
Inventor
张良
汪全信
丁习斌
刘洋
敖凌宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN202110774828.2A priority Critical patent/CN114508244A/en
Publication of CN114508244A publication Critical patent/CN114508244A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/166Landings, receiving platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H3/00Buildings or groups of buildings for public or similar purposes; Institutions, e.g. infirmaries or prisons

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a reconstruction method of a rail transit ground station, which comprises the following steps: installing side type platforms on two sides of a station, installing shed protecting tracks on the side type platforms, and building extension platforms at two ends of the side type platforms at two ends; installing shed ground rails, assembling movable shed units, hoisting the movable shed units to shed rails on two sides of a station and sliding the movable shed units to the upper side of an existing station canopy, and splicing a plurality of movable shed units into a tunnel type protective shed; installing a newly-built canopy supporting upright post and a temporary supporting structure, and installing an upper steel structure of the newly-built canopy; and (4) dismantling the existing canopy, the movable protection canopy and the extension platform. The construction method of the invention concentrates continuous operation of dominant resources, fully compresses duration of key lines, fully utilizes the hoisting radius of the truck crane and the crawler crane, and builds extension platforms at two ends of the old canopy as transfer platforms of various machines and materials, thereby saving intermediate transfer flow to the maximum extent.

Description

Reconstruction method of rail transit ground station
Technical Field
The invention relates to a method for reconstructing an existing station.
Background
With the expansion and development of cities, some originally built rail platforms cannot meet the requirements of passenger flow or modernization, and original stations need to be reconstructed. The existing platform canopy structure is generally arranged along a tunnel type track, the tracks on two sides of the platform and the platform are arranged below the canopy, along with reconstruction of the station, the canopy needs to be reconstructed into a larger and more attractive structure, and the existing canopy needs to be dismantled.
The reconstruction construction needs to ensure the normal operation of the existing subway line and the normal operation of ground traffic at the same time. The general stations needing to be modified are located in busy sections of cities, the original stations cannot be stopped, the problem that the available construction site is small in order to meet traffic smoothness as far as possible exists, the site operation area and the material yard are compact, and the situation of multiple material transfer is formed. The high-altitude operations such as engineering hoisting, welding and the like are more, and a large amount of operations close to and cross an operation line exist. The key line works in the skylight, so that the effective operation time is short, the safety risk is high, and the social influence is large.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the problems of narrow construction time window, narrow site and high safety risk existing in the reconstruction of the existing station are solved.
The technical scheme of the invention is as follows:
a reconstruction method of a rail transit station on the ground comprises the following steps:
(1) reconstructing a station entrance, installing a protective shed of a motorway, and back-supporting an underground structure;
(2) installing side type platforms on two sides of a station, installing shed protecting tracks on the side type platforms, and building extension platforms at two ends of the side type platforms at two ends;
(3) installing shed ground rails, assembling movable shed units, hoisting the movable shed units to shed rails on two sides of a station and sliding the movable shed units to the upper side of an existing station canopy, and splicing a plurality of movable shed units into a tunnel type protective shed;
(4) installing a newly-built canopy supporting upright post and a temporary supporting structure, and installing an upper steel structure of the newly-built canopy;
(5) landscape platforms are arranged on two sides of the station;
(6) dismantling the temporary support of the newly-built canopy, and installing and decorating the roof panel of the newly-built canopy;
(7) and (4) dismantling the existing canopy, the movable protection canopy and the extension platform.
Each movable shed protecting unit consists of a front portal structure and a rear portal structure through a connection rod piece, each portal structure consists of a left upright post, a right upright post, a left cross beam and a right cross beam, the two cross beams are inclined upwards by a certain angle, and a longitudinal hanging rail is arranged below the front cross beam and the rear cross beam in a top structure which is connected at the end to form a slope top shape.
In the step (4), the newly-built canopy is in a cross-star shape and is divided into five parts, namely a left part, a middle part, a right part, an upper part and a lower part, firstly the canopy frameworks at the two ends of the track are installed, then the canopy frameworks at the two ends are connected by the main truss, then the canopy framework at the middle part is installed, and finally the canopy frameworks at the two sides of the track are installed.
In the step (2), a movable protective shed reverse support, a station pillar and a station reverse support are arranged below the side type station platform, and the movable protective shed reverse support and the station reverse support are detached after the step (7) is completed.
In step (3), after the movable shed protecting unit slides to a preset position above the existing station canopy, the roller supports of the movable shed protecting unit are converted into fixed supports, isolation structures on two sides of the movable shed protecting unit are installed, and meanwhile, the outer side of the platform is protected by facing edges.
The installation and decoration of the rainshed roof panel in the step (6) comprises the following steps: the rain shed main body steel structure and the steel base recheck and correct, the positioning of the adapter piece, the round pipe main keel and the secondary keel is realized, the installation of the ribbon and the water channel keel is realized, the processing of the special-shaped aluminum plate is realized, the installation of the bottom plate, the special-shaped aluminum plate and the glass rock wool is realized, the installation of the waterproof aluminum plate and the panel is realized, the installation of the ribbon and the float grass aluminum plate is realized, the installation of the transparent daylighting plate is realized, and the thin part is collected and glued and bottomed.
The step of dismantling the existing canopy and the movable protection canopy in the step (7) is as follows: install the lighting fixture and pass through to the lighting fixture with the equipment on the existing canopy in existing canopy below, remove the fixed stay who protects the canopy and convert the gyro wheel into and support, divide the segmentation to existing canopy, carry out structural connection with existing canopy and removal canopy unit, demolish the tie rod between existing canopy segmentation, the connection structure between disconnection existing canopy and the platform, will remove canopy unit and existing canopy segmentation slip to extend the platform and hang from.
And (4) performing patching construction on the landscape platform after the movable protection shed reverse support and the platform reverse support are removed.
And (7) after the step (7) is finished, installing the side type platform and decorating.
And after the installation of the side type platform and decoration and renovation are finished, equipment and decoration and renovation are carried out on the original platform.
The invention has the beneficial effects that:
the construction method of the invention concentrates continuous operation of dominant resources, fully compresses duration of key lines, carries out professional and partition organization according to the principle of first structure, later electromechanical, decoration, multiple parallels, multiple interpenetration and less running water, synchronously carries out construction of the canopy structure from the station house size mileage two ends to the center in parallel after the construction of the side type station structure is completed, simultaneously carries out interpenetration construction of landscape platform layers of the east-west side station house, fully utilizes the radius of an automobile crane and a crawler crane, and saves the middle transfer flow to the maximum extent.
The movable protection shed is used for supporting the newly-built canopy unit blocks in the rail-mounted area, the newly-built canopy unit blocks can be directly transported to the required design positions through the longitudinal movement of the movable protection shed units, the necessary support of the rail-mounted area canopy units and the top of the movable protection shed units of the transportation channel are fully closed, and necessary protection measures of an existing platform and a rail area are formed during the construction of the newly-built canopy unit blocks. After a plurality of movable shed protecting units are connected into a whole, necessary means and passages for hoisting and transporting the existing canopy in blocks can be formed by the aid of the lower hanging type rails attached to the movable shed protecting units. The movable protection shed integrates the functions of new and old canopy unit blocks stressed and supported, a transportation channel and a protection shed, avoids the repeated investment and the installation and dismantling workload of the supporting structure, saves the material and labor cost, and effectively saves the construction time.
Set up the transfer platform of extension platform as various machinery and material at old canopy both ends to the solution is smooth and easy and the narrow and small problem of construction space that leads to for satisfying the traffic, removes canopy unit and new, old canopy and all transports the hoist and mount on extending the platform, has reduced the material and has stacked the place.
Old canopy is not demolishd when newly-built canopy, does not influence the normal use originally at station, protects the protective structure of canopy unit concatenation for old canopy through a plurality of removals, guarantees construction safety. And after the new canopy is installed, the old canopy is dismantled, so that seamless connection of the new canopy and the old canopy is realized. The construction can be synchronously carried out at the two ends of the track, and the construction period is saved.
Drawings
Fig. 1 is a schematic diagram of the installation of the west station in step two.
Fig. 2 is a schematic diagram of the installation of the east station in step two.
Fig. 3 is a schematic diagram of the mobile shelter unit hoisted to the rail row area in the third step.
Fig. 4 is a schematic diagram of the newly-built canopy framework in the fourth step.
And 5, constructing the landscape platform in the fifth step.
Fig. 6 is a schematic view of the sequence of installing the canopy panels in step six.
Fig. 7 is a sectional split schematic view of an old canopy.
Fig. 8 is a schematic view of an old canopy dismantling section hoisted by adopting the movable canopy protection unit, and a newly built canopy is hidden in the diagram.
Detailed Description
Example (b): the embodiment is a reconstruction construction scheme taking a certain station of Shenzhen as an example, the track is in the north-south direction, the two sides of the station are the east region and the west region respectively, the transportation core is located on the west side of the track, one motorway is arranged on the west side of the track, and two motorways are arranged on the east side of the track. The construction process comprises the following steps:
step one, traffic dismissal, access and field leveling planning.
1.1 newly building a temporary access in the western region, and dismantling the original access.
1.2 newly building two temporary entrances and exits in the east region, and dismantling the two original entrances and exits.
1.3 building a protective shed for the lanes on the east and west sides.
1.4 underground structure back-supporting is carried out on the driveway and the crane walking area.
And step two, constructing the side type platform structure and the extension platform.
2.1 the rail-mounted area is protected and isolated, and protective nets are arranged on two sides of the existing canopy, and the length of each protective net is about 240 m.
2.2, excavating a column base at the west side,
2.3 installing the protective shed reverse support, the station pillar, the station reverse support and the station beam plate.
2.4 concrete pouring of the platform column.
And 2.5 binding the platform plate steel bars.
And 2.6, concrete pouring of the platform plate.
And 2.7, constructing the track of the movable protection shed of the platform (installing the track on the platform).
2.8, constructing the extended platform at two ends.
2.9 repeating the steps 2.1-2.8 to complete the construction of the side platform structure and the extension platform in the east area.
And step three, mounting the movable protective shed. Each movable shed protecting unit consists of a front portal structure and a rear portal structure through a connection rod piece, each portal structure consists of a left upright post, a right upright post, a left cross beam and a right cross beam, the two cross beams are inclined upwards by a certain angle, and a longitudinal hanging rail is arranged below the front cross beam and the rear cross beam in a top structure which is connected at the end to form a slope top shape.
3.1 installing the ground track of the movable protective shed.
3.2 the movable shed protection units are spliced in advance. 13 pieces are processed in a factory and spliced in advance on site,
3.3 the movable shed protecting unit is hoisted and slides. And hoisting the movable shed protecting units to the extension platform in sequence, and sliding to a preset position.
3.4 the movable protective shed is fixed. Firstly, system conversion is carried out, a jack is used for supporting a column foot of the movable shed protecting unit, the roller support is converted into the jack support, and then reinforcement and lateral pulling are carried out.
3.5 moving the isolation outside the protective shed. Protective nets are arranged on two sides of the movable shed protecting unit.
3.6 the outer side of the platform is protected.
And step four, constructing a steel structure at the upper part of the newly-built canopy. The newly-built canopy is in a cross star shape and is divided into five parts, namely a left part, a middle part, a right part, an upper part and a lower part, the canopy frameworks at the two ends of the rail are firstly installed, then the canopy frameworks at the two ends are connected through the main truss, the canopy framework at the middle part is installed, and finally the canopy frameworks at the two sides of the rail are installed.
4.1 temporary supporting and hoisting of the canopy.
4.2 lifting the rain shed columns at the platform.
4.3 the installation of the main truss and the main girder of the canopy construction is divided into areas.
Step five, constructing a landscape platform,
5.1 hoisting east landscape platform beam columns, and hoisting east landscape platform beam columns after the east rain shed columns and the temporary supports are completed.
5.2 hoisting the western landscape platform beam column.
And 5.3, constructing the rest structure of the landscape platform.
And step six, installing and decorating the roof panel of the canopy. This step is started after the temporary support of the canopy is removed.
6.1 rechecking the steel structure and the steel base of the main body of the canopy and correcting BIM model data.
Firstly, a main steel structure construction unit provides a measurement coordinate value for steel structure completion acceptance, and the coordinate value and model deviation are checked;
sampling to check whether the coordinate value of the total package is matched with the site;
if the prestressed cable, the tension rod and the support structure exist on site, secondary rechecking is carried out after the prestress is removed and stabilized;
fourthly, the best complete output of one working surface is actually measured on site, and the method is not suitable for being segmented and batched too many times
The purpose is as follows: and controlling the deformation and displacement of the main structure, and determining whether the field structure is consistent with the model, thereby determining whether construction can be carried out according to the model, and if the deformation is larger, increasing the following construction process and time cost.
6.2 the adapter, the circular tube keel and the secondary keel are positioned in a paying-off mode.
Extracting coordinates of the paying-off positioning points by the model, finding positioning reference points on the main structure on site and marking the reference points (several positioning points are selected again to perform recheck verification every time the instrument is re-erected to ensure the accuracy of an instrument coordinate system), and positioning the instrument: positioning reference point of main body structure → steel frame adapter → main upright post/single truss → secondary keel/horizontal through rod → panel
6.3 installation of adaptor, circular tube keel and secondary keel, and 1:1 field installation of large sample
6.4 mounting the streamer and the water channel keel.
And 6.5 processing the special-shaped aluminum plate BIM outside the three-dimensional blanking field.
6.6 installation of bottom plate, special-shaped aluminum plate and glass rock wool
6.7 waterproof aluminum plate and panel installation.
6.8 mounting the ribbon and the water tank aluminum plate.
6.9 installing transparent daylighting panel.
6.10 gluing and closing the fine part.
And step seven, dismantling the existing canopy, the movable protective canopy and the extension platform.
7.1 transition between the original island platform lamp stand and the equipment. A lamp bracket is arranged below the original canopy, and equipment arranged on the original canopy is transited to the lamp bracket.
7.2 the jack below the upright post of the movable shed protection unit is lowered to enable the roller wheel to be in contact with the track.
7.3 existing canopy is connected with removal protection canopy and is disconnected with the platform structure. And (3) removing a panel of the existing canopy, connecting a steel frame of the existing canopy with the electric block, and installing the electric block on hanging rails at two sides of the movable canopy protection unit. And cutting off the connecting mechanism of the existing canopy and the ground. The existing canopy is divided into a plurality of segments, and the connection relation between the segments is cut off.
7.4 the movable shed protecting unit is glidingly moved to the extension platform, and the movable shed protecting unit and the rain shed subsection unit hung below the movable shed protecting unit are lifted away.
7.5 removing the movable protective shed rail and the extension platform.
And step eight, dismantling the reverse supports of the movable protection shed, dismantling the reverse supports of the platform, dismantling the underground reverse supports, and constructing the embedding sections of the landscape platform.
And step nine, widening the side type platform, and carrying out equipment installation and decoration.
Step ten, reforming the original island type platform.

Claims (10)

1. A reconstruction method of a rail transit ground station is characterized by comprising the following steps:
(1) reconstructing an entrance and an exit of a station, installing a protective shed of an automobile way, and supporting an underground structure;
(2) installing side platforms on two sides of a station, installing shed protecting tracks on the side platforms, and building extension platforms at two ends of the side platforms at two ends;
(3) installing shed ground rails, assembling movable shed units, hoisting the movable shed units to shed rails on two sides of a station and sliding the movable shed units to the upper side of an existing station canopy, and splicing a plurality of movable shed units into a tunnel type protective shed;
(4) installing a newly-built canopy supporting upright post and a temporary supporting structure, and installing an upper steel structure of the newly-built canopy;
(5) landscape platforms are arranged on two sides of the station;
(6) dismantling the temporary support of the newly-built canopy, and installing and decorating the roof panel of the newly-built canopy;
(7) and (4) dismantling the existing canopy, the movable protection canopy and the extension platform.
2. The rebuilding method of a rail transit station on the ground according to claim 1, characterized in that: each movable shed protecting unit consists of a front portal structure and a rear portal structure through a connection rod piece, each portal structure consists of a left upright post, a right upright post, a left cross beam and a right cross beam, the two cross beams are inclined upwards by a certain angle, and a longitudinal hanging rail is arranged below the front cross beam and the rear cross beam in a top structure which is connected at the end to form a slope top shape.
3. The rebuilding method of a rail transit station on the ground according to claim 2, characterized in that: in the step (4), the newly-built canopy is in a cross-star shape and is divided into five parts, namely a left part, a middle part, a right part, an upper part and a lower part, firstly the canopy frameworks at the two ends of the track are installed, then the canopy frameworks at the two ends are connected by the main truss, then the canopy framework at the middle part is installed, and finally the canopy frameworks at the two sides of the track are installed.
4. A rebuilding method of a rail transit station according to claim 3, wherein: in the step (2), a movable protective shed reverse support, a station pillar and a station reverse support are arranged below the side type station platform, and the movable protective shed reverse support and the station reverse support are detached after the step (7) is completed.
5. The rebuilding method of a rail transit station on the ground according to claim 4, characterized in that: in step (3), after the movable shed protecting unit slides to a preset position above the existing station canopy, the roller supports of the movable shed protecting unit are converted into fixed supports, isolation structures on two sides of the movable shed protecting unit are installed, and meanwhile, the outer side of the platform is protected by facing edges.
6. The rebuilding method of a station on a rail transit ground according to claim 5, wherein the installing and finishing of the rainshed roof panel in the step (6) comprises: the rain shed main body steel structure and the steel base recheck and correct, the positioning of the adapter piece, the round pipe main keel and the secondary keel is realized, the installation of the ribbon and the water channel keel is realized, the processing of the special-shaped aluminum plate is realized, the installation of the bottom plate, the special-shaped aluminum plate and the glass rock wool is realized, the installation of the waterproof aluminum plate and the panel is realized, the installation of the ribbon and the float grass aluminum plate is realized, the installation of the transparent daylighting plate is realized, and the thin part is collected and glued and bottomed.
7. A rebuilding method of a station on a rail transit ground according to claim 5, wherein the step of removing the existing canopy and the movable protection canopy in the step (7) is: install the lighting fixture and pass through to the lighting fixture with the equipment on the existing canopy in existing canopy below, remove the fixed stay who protects the canopy and convert the gyro wheel into and support, divide the segmentation to existing canopy, carry out structural connection with existing canopy and removal canopy unit, demolish the tie rod between existing canopy segmentation, the connection structure between disconnection existing canopy and the platform, will remove canopy unit and existing canopy segmentation slip to extend the platform and hang from.
8. The rebuilding method of a rail transit station on the ground according to claim 4, characterized in that: and (4) performing patching construction on the landscape platform after the movable protection shed reverse support and the platform reverse support are removed.
9. A rebuilding method of a station on a rail transit ground according to any of claims 1 to 8, characterized in that: and (7) after the step (7) is finished, installing the side type platform and decorating.
10. A rebuilding method of a station on a rail transit ground according to claim 9, characterized in that: and after the installation and decoration of the side type platform are finished, equipment and decoration transformation are carried out on the original platform.
CN202110774828.2A 2021-07-08 2021-07-08 Reconstruction method of rail transit ground station Pending CN114508244A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110774828.2A CN114508244A (en) 2021-07-08 2021-07-08 Reconstruction method of rail transit ground station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110774828.2A CN114508244A (en) 2021-07-08 2021-07-08 Reconstruction method of rail transit ground station

Publications (1)

Publication Number Publication Date
CN114508244A true CN114508244A (en) 2022-05-17

Family

ID=81548053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110774828.2A Pending CN114508244A (en) 2021-07-08 2021-07-08 Reconstruction method of rail transit ground station

Country Status (1)

Country Link
CN (1) CN114508244A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010121286A (en) * 2008-11-17 2010-06-03 Tekken Constr Co Ltd Construction method of steel structure
CN110080440A (en) * 2019-04-17 2019-08-02 深装总建设集团股份有限公司 A kind of special-shaped mixing curtain wall based on BIM technology
CN110331802A (en) * 2019-06-20 2019-10-15 成张佳宁 A kind of construction method of polymorphic structure aluminium veneer curtain wall
CN112727132A (en) * 2020-12-10 2021-04-30 中铁五局集团建筑工程有限责任公司 Method for dismantling existing canopy of overhead operation subway station
CN112727134A (en) * 2020-12-10 2021-04-30 中铁五局集团建筑工程有限责任公司 Construction method for rebuilding and expanding main structure of existing overhead operation subway station building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010121286A (en) * 2008-11-17 2010-06-03 Tekken Constr Co Ltd Construction method of steel structure
CN110080440A (en) * 2019-04-17 2019-08-02 深装总建设集团股份有限公司 A kind of special-shaped mixing curtain wall based on BIM technology
CN110331802A (en) * 2019-06-20 2019-10-15 成张佳宁 A kind of construction method of polymorphic structure aluminium veneer curtain wall
CN112727132A (en) * 2020-12-10 2021-04-30 中铁五局集团建筑工程有限责任公司 Method for dismantling existing canopy of overhead operation subway station
CN112727134A (en) * 2020-12-10 2021-04-30 中铁五局集团建筑工程有限责任公司 Construction method for rebuilding and expanding main structure of existing overhead operation subway station building

Similar Documents

Publication Publication Date Title
CN103967050B (en) Construction system of subway station
CN105370287A (en) Mechanical underground excavation construction method for large underground parking lot
CN105970836A (en) Method for erecting large-span lower chord variable truss high continuous steel trussed beam cantilever
CN106193117B (en) A kind of assembling and construction method of the prefabricated pipe gallery in underground
CN112609912B (en) Construction method for newly building canopy in overhead operation subway station
KR20210054303A (en) Concrete lining formwork for tunnels with sloped construction
CN114961334A (en) Closed protection dismantling system for high-altitude large-span cantilever structure and construction method thereof
CN113235972A (en) Trolley for dismantling existing station canopy and construction method
CN101324054B (en) Incremental launching positioning construction method of bridge subsection girder temporary pier
CN105463997A (en) Erecting method for segmental beam
KR20100138121A (en) Movable temporary structure for constructing composite covering arch structure
CN114876239A (en) Closed protection dismantling system for high-altitude cantilever structure and construction method thereof
CN114482349A (en) Construction method of straight-through double-pull-rod steel frame supported long-span glass curtain wall system
CN109537912A (en) A kind of safe and stable type Provincial Rink and its construction technology
CN106241234B (en) A kind of self-propelled transport assembly car for prefabricated pipe gallery
CN114508244A (en) Reconstruction method of rail transit ground station
CN112610023B (en) Construction method for dismantling building in existing track operation interval
CN113833292A (en) Reconstruction method of station canopy
CN112610244B (en) Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof
CN112983460B (en) Subway station and section structural layout and mechanical rapid construction method thereof
CN213952287U (en) Truss vehicle device for reconstruction and extension construction of existing overhead operation subway station
CN212388598U (en) Pipe jacking pipe piece and parking steel structure combined prefabricated underground mechanical stereo garage structure
CN210563326U (en) Overhead unit type overhead sliding splicing operation platform
CN210636293U (en) Vertical steel arch cable-stayed bridge
CN112681372B (en) Truss vehicle for reconstruction and extension construction of existing overhead operation subway station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination