CN114294056A - Open pit treatment method combining waste rock and dry tailings - Google Patents

Open pit treatment method combining waste rock and dry tailings Download PDF

Info

Publication number
CN114294056A
CN114294056A CN202111528049.0A CN202111528049A CN114294056A CN 114294056 A CN114294056 A CN 114294056A CN 202111528049 A CN202111528049 A CN 202111528049A CN 114294056 A CN114294056 A CN 114294056A
Authority
CN
China
Prior art keywords
layer
dry
pile
waste
open pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111528049.0A
Other languages
Chinese (zh)
Other versions
CN114294056B (en
Inventor
李涛
刘敬智
沈汉
周斌
李路
梁昌鸿
宋洪勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WANBAO MINING Ltd
Original Assignee
WANBAO MINING Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WANBAO MINING Ltd filed Critical WANBAO MINING Ltd
Priority to CN202111528049.0A priority Critical patent/CN114294056B/en
Publication of CN114294056A publication Critical patent/CN114294056A/en
Priority to PCT/CN2022/130710 priority patent/WO2023109378A1/en
Application granted granted Critical
Publication of CN114294056B publication Critical patent/CN114294056B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The invention relates to a method for jointly treating an open pit by using waste rocks and dry tailings, and belongs to the field of backfill treatment of an open pit of a mine. The method comprises the following steps: backfilling a waste stone layer 2 at the bottom of the open pit, conveying the dehydrated and filter-pressed dry tailings onto the waste stone layer 2, compacting to form a dry tailings layer 3, and alternately stacking the waste stone layer 2 and the dry tailings layer 3; laying an initial dam 4 above the stacking layer of the waste stone layer 2 and the dry tailing layer 3, and stacking a dry tailing pile 3' at the upstream of the initial dam 4 in a layered manner in an inverted manner; piling the waste rock pile 10 in layers at the periphery of the dry tailing pile 3 'piled in the middle in an inverted mode until the top surface of the area of the waste rock pile 10 is bordered by the top surface of the area of the dry tailing pile 3'; paving a drainage prism body 5 at the periphery of the waste rock pile 10; an inverted filter 6 is constructed between the waste rock pile 10 and the drainage prism 5. The risk of secondary geological disasters such as landslide and debris flow caused by instability of the open side slope can be reduced, safety accidents caused by tailing leakage and dam break can be avoided, and safe stockpiling of waste rocks and tailings is realized.

Description

Open pit treatment method combining waste rock and dry tailings
Technical Field
The invention belongs to the field of backfill treatment of an open pit of a mine, and particularly relates to a method for jointly treating the open pit by using waste rocks and dry tailings.
Background
The open pit formed by the open-pit mining of the mine has great influence on the surrounding environment: on one hand, the open-air side slope is easy to induce local side slope instability under the action of external force, so that secondary geological disasters such as landslide and debris flow are further caused, and the method is a great potential safety hazard for safe production of mines; on the other hand, in rainy season, catchment in open-sky pits is easy to cause groundwater environmental pollution through fracture seepage, and the problems of surface cracks, collapse and the like can be caused if the water is not treated for a long time. In recent years, there have been increasing mines that face pit closure or open pit to underground, and attention has been paid to a method for disposing open pits. In conclusion, reasonable backfill treatment of open pits, shortage of mine dump area, insufficient tailing pond capacity and the like become main problems restricting the development of open mines.
The existing open pit backfill disposal methods mainly comprise low-concentration tailing backfill, paste backfill, dry tailing backfill and waste stone backfill, wherein: (1) the low-concentration tailing backfilling means that tailing slurry discharged from a concentrating mill is directly conveyed to an open pit through a pipeline for backfilling. The method has higher requirements on the geological stability of the open pit and the permeability of the pit, and anti-seepage treatment must be carried out before backfilling, otherwise, moisture in tailing slurry seeps to the four sides of the pit; and because the low-concentration tail mortar has high water content, safety accidents are easy to happen when the low-concentration tail mortar meets unfavorable geological action; (2) the paste backfill is to add cementing materials such as cement and the like into the thickened tail mortar, stir the tail mortar to prepare a paste material with the content of-20 um fine particles not less than 15 percent and the mass concentration between 75 and 80 percent, and convey the paste material to an open pit for backfill through a pipeline. The method needs to be provided with equipment such as a deep cone thickener, a stirring tank, a plunger pump and the like, the investment in the capital construction period is relatively high, in addition, a flocculating agent and a cementing material need to be added for preparing the paste, and the operation cost is relatively high; (3) and the dry tailing backfilling refers to pressing and filtering the tailing slurry to prepare a filter cake, and conveying the filter cake to a pit for backfilling through an automobile or a belt. The dry tailings and the waste rocks are independently backfilled, the requirement on the permeability of the open pit is low, but in a multi-open pit mining mine or a mine with short land area, the waste rocks and the dry tailings are jointly discharged, so that the occupied area can be greatly saved, and the investment of environmental management funds is reduced.
Disclosure of Invention
Technical problem to be solved
The technical problem to be solved by the invention is as follows: how to provide a method for jointly treating an open pit by waste rocks and dry tailings, which is used for solving the problem of secondary disasters induced by an open slope.
(II) technical scheme
In order to solve the technical problem, the invention provides a method for jointly treating an open pit by using waste rocks and dry tailings, which comprises the following steps:
step 1: backfilling a waste stone layer 2 at the bottom of the open pit, conveying the dehydrated and filter-pressed dry tailings onto the waste stone layer 2, compacting to form a dry tailings layer 3, and alternately stacking the waste stone layer 2 and the dry tailings layer 3 until the open pit is completely backfilled;
step 2: laying an initial dam 4 above a stacking layer of the waste rock layer 2 and the dry tailing layer 3, stacking dry tailing piles 3' on the upstream of the initial dam 4 in a layered mode in an inverted mode, and gradually pushing the dry tailing piles to the initial dam 4 until the design elevation is reached;
and step 3: piling the waste rock pile 10 in a layered manner at the periphery of the dry tailing pile 3 'piled in the step 2 in an inverted manner until the top surface of the region of the waste rock pile 10 is bordered by the top surface of the region of the dry tailing pile 3';
and 4, step 4: paving a drainage prism body 5 at the periphery of the waste rock pile 10 in the step 3;
and 5: in step 4, an inverted filter layer 6 is formed between the waste rock pile 10 and the drainage arris 5.
Wherein, useless stone layer 2 piles up with low moisture content dry tailings layer 3 in turn in step 1, includes:
step 11: calculating the thickness of each waste stone layer 2 and the dry tailing layer 3 according to the backfilling depth of the open pit, wherein the thickness of each waste stone layer 3 is controlled to be 5-8m, and the thickness of the dry tailing layer 3 is controlled to be below 5 m;
step 12: and (4) backfilling the open pit according to the thickness of each waste stone layer 2 and the dry tailing layer 3 in the step (11), wherein the highest backfilling body at the end of backfilling is the waste stone layer 2.
Wherein, the water content of the dry tailings layer 3 in the step 12 is controlled within the range of 5-10%;
and in the step 2, the water content of the dry tailing pile 3' is controlled within a range of 10-20%.
Wherein, the slope of the top surface of the dry tailings pile 3' in the step 2 relative to the ground surface is between 0.5 percent and 1 percent;
in the step 3, the slope of the top surface of the waste rock pile 10 relative to the ground surface is between 1 and 2 percent.
Wherein, the inverted filter layer 6 in the step 5 comprises 3 crushed stone layers with different particle sizes;
the grain composition of the 3 layers of the crushed stone layers along the direction from the waste stone pile 10 to the drainage prism body 5 is from small to large.
Wherein a horizontal drain pipe 7 is arranged below the dry tailings pile 3' and the waste rock pile 10;
one end of the drain pipe 7 extends outwards and is connected with a water collecting tank 8;
the surface precipitation on the pile surface and the water in the pile are discharged into a water collecting tank 8 through the drainage arris body 5, the inverted filter layer 6 and the drain pipe 7, so that the infiltration line in the dry tailing pile 3' is reduced, the fine-particle tailing is prevented from losing, and the stability of the pile is enhanced.
And in the step 1, the bottom and the side slope of the open pit are cleaned before the waste stone layer 2 is backfilled at the bottom of the open pit, and a hydraulic channel communicated with the open pit and the underground water is plugged.
And after the slope surface and the top of the waste stone pile 10 are leveled, a surface soil layer 9 is laid, and the thickness of the soil layer is not less than 0.5 m.
(III) advantageous effects
Compared with the prior art, the invention has the following beneficial effects:
(1) the open pit treatment is effectively combined with the construction of a waste dump and a tailing pond, so that the risk of secondary geological disasters such as landslide and debris flow caused by instability of an open side slope can be reduced, safety accidents caused by tailing leakage and dam break can be avoided, and the safe stockpiling of waste rocks and tailings is realized.
(2) The method reduces the environmental damage, realizes the optimal allocation of resources and waste replacement, and creates conditions for mine reclamation and green mine construction.
Drawings
FIG. 1 is a sectional view of the waste rock-dry tailings backfill in layers according to the present invention;
FIG. 2 is a cross-sectional view of the waste rock-dry tailings surface stockpiling of the present invention;
fig. 3 is a plan view of the waste rock-dry tailings surface stockpiling of the present invention.
Detailed Description
In order to make the objects, contents, and advantages of the present invention clearer, the following detailed description of the embodiments of the present invention will be made in conjunction with the accompanying drawings and examples.
In order to solve the technical problem, the method for jointly disposing the open pit by the waste rocks and the dry tailings, as shown in fig. 1-3, comprises the following steps:
step 1: backfilling a waste stone layer 2 at the bottom of the open pit, conveying the dehydrated and filter-pressed dry tailings onto the waste stone layer 2, compacting to form a dry tailings layer 3, and alternately stacking the waste stone layer 2 and the dry tailings layer 3 until the open pit is completely backfilled;
step 2: laying an initial dam 4 above a stacking layer of the waste rock layer 2 and the dry tailing layer 3, stacking dry tailing piles 3' on the upstream of the initial dam 4 in a layered mode in an inverted mode, and gradually pushing the dry tailing piles to the initial dam 4 until the design elevation is reached;
and step 3: piling the waste rock pile 10 in a layered manner at the periphery of the dry tailing pile 3 'piled in the step 2 in an inverted manner until the top surface of the region of the waste rock pile 10 is bordered by the top surface of the region of the dry tailing pile 3';
and 4, step 4: paving a drainage prism body 5 at the periphery of the waste rock pile 10 in the step 3;
and 5: in step 4, an inverted filter layer 6 is formed between the waste rock pile 10 and the drainage arris 5.
Wherein, useless stone layer 2 piles up with low moisture content dry tailings layer 3 in turn in step 1, includes:
step 11: calculating the thickness of each waste stone layer 2 and the dry tailing layer 3 according to the backfilling depth of the open pit, wherein the thickness of each waste stone layer 3 is controlled to be 5-8m, and the thickness of the dry tailing layer 3 is controlled to be below 5 m;
step 12: and (4) backfilling the open pit according to the thickness of each waste stone layer 2 and the dry tailing layer 3 in the step (11), wherein the highest backfilling body at the end of backfilling is the waste stone layer 2.
Wherein, the water content of the dry tailings layer 3 in the step 12 is controlled within the range of 5-10%;
and in the step 2, the water content of the dry tailing pile 3' is controlled within a range of 10-20%.
Wherein, the slope of the top surface of the dry tailings pile 3' in the step 2 relative to the ground surface is between 0.5 percent and 1 percent;
in the step 3, the slope of the top surface of the waste rock pile 10 relative to the ground surface is between 1 and 2 percent.
Wherein, the inverted filter layer 6 in the step 5 comprises 3 crushed stone layers with different particle sizes;
the grain composition of the 3 layers of the crushed stone layers along the direction from the waste stone pile 10 to the drainage prism body 5 is from small to large.
Wherein a horizontal drain pipe 7 is arranged below the dry tailings pile 3' and the waste rock pile 10;
one end of the drain pipe 7 extends outwards and is connected with a water collecting tank 8;
the surface precipitation on the pile surface and the water in the pile are discharged into a water collecting tank 8 through the drainage arris body 5, the inverted filter layer 6 and the drain pipe 7, so that the infiltration line in the dry tailing pile 3' is reduced, the fine-particle tailing is prevented from losing, and the stability of the pile is enhanced.
And in the step 1, the bottom and the side slope of the open pit are cleaned before the waste stone layer 2 is backfilled at the bottom of the open pit, and a hydraulic channel communicated with the open pit and the underground water is plugged.
And after the slope surface and the top of the waste stone pile 10 are leveled, a surface soil layer 9 is laid, and the thickness of the soil layer is not less than 0.5 m.
Example 1
Taking the deep concave open sky pit as an example, the elevation of the surface closed circle is set to be 0 m. In the first treatment engineering stage, firstly, the bottom and the side slope of the open pit are cleaned, and the hydraulic channel communicated with the open pit and the underground water is plugged, so that the backfill body is prevented from polluting the underground water and the water in the surrounding rock 1.
As shown in figure 1, the waste stone 2 is discharged to the bottom of an open pit through an automobile or a belt conveyor, and is rolled by a road roller to form a waste stone layer with the thickness of 5-8 m. And then conveying the filter-pressed and dehydrated dry tailings 3 to a bottom waste stone layer through a belt conveyor and compacting to form a dry tailings layer, wherein the thickness of the dry tailings layer is controlled to be below 5 m. Wherein, the dry tailings 3 used for open pit backfill in the first-stage disposal engineering stage are formed by thickening and press-filtering low-concentration full-tailing mortar (the mass concentration is between 15 and 25 percent), and the water content of the dry tailings is required to meet the requirements of rolling compaction and filling and is generally between 5 and 10 percent. And performing alternate operation until the open pit is completely backfilled. The thickness of each layer of waste rock and dry tailings is designed according to the backfill depth of the open pit, so that the highest backfill body at the end of backfill is ensured to be the waste rock.
Fig. 2 and 3 show a sectional view and a plan view of the second stage treatment process. And constructing the dry tailing pile initial dam 4 according to the design site, wherein the dry tailing pile initial dam is used as a regional boundary between the dry tailing pile and the waste rock pile, and the dry tailing pile initial dam plays a supporting role. Wherein the initial dam 4 is constructed of waste rocks and tamped. In order to reduce the filter pressing cost, the water content of the dry tailings 3' in the second stage treatment engineering stage can be controlled between 10% and 20%. And (3) piling dry tailings in a reverse-discharging manner from the upstream of the initial dam in a layered manner, controlling the layer height within 5m, gradually advancing towards the initial dam until the designed elevation is reached, and finally enabling the top surface gradient of the dry tailings pile to be 0.5-1%. The drainage arris body 5 is constructed in the dry tail sand piling process, the waste rock pile 2 is also piled in an inverted-discharging type layering mode, the layer height is controlled to be 5-8m, and each layer needs to be rolled to meet the design requirement of compactness. The slope of the outer slope of the waste rock pile is determined by the specific physical and mechanical properties of the waste rock, and the slope of the top surface of the waste rock pile is 1-2%. An inverted filter 6 is constructed between the drainage arris body 5 and the waste rock pile, the inverted filter 6 is composed of 3 layers of gravels with different particle sizes, and the particle grading is from small to large along the direction from the waste rock pile to the drainage arris body 5. When the inverted filter layer is paved and buried, a flat plate vibrator is adopted for tamping, and the clear level is ensured. Through drainage arris body 5, inverted filter 6 and lay horizontal drain pipe 7 under dry tail sand heap and the barren rock heap with the earth's surface precipitation on the heap face and the moisture of doing the heap in the drainage catch basin 8, can effectively reduce the infiltration line in the dry tail sand heap and guarantee that the fine grain tailings does not run off, and then the stability of reinforcing heap body. And the sewage collected in the water collecting tank 8 is discharged after reaching the standard through precipitation treatment. And finally, leveling the waste stone heap slope surface and the slope top and paving a surface soil layer with the layer thickness not less than 0.5m so as to carry out reclamation work at the later stage.
The concentration of tail mortar discharged from concentrating mill is generally between 15% -25%, after the low-concentration full-tail mortar is dewatered and concentrated by thickener, the underflow concentration can be up to 50% -65%, and the high-concentration underflow slurry is dewatered by filter press to obtain filter cake (i.e. dry tail sand). Wherein, the water content of the dry tailings for backfilling the open pit needs to meet the rolling and filling requirements, and is generally between 5 and 10 percent; the water content of the dry tailings for surface stockpiling can be between 10 and 20 percent.
The above description is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, several modifications and variations can be made without departing from the technical principle of the present invention, and these modifications and variations should also be regarded as the protection scope of the present invention.

Claims (8)

1. A method for jointly treating open pit by waste rocks and dry tailings is characterized by comprising the following steps:
step 1: backfilling a waste stone layer (2) at the bottom of the open pit, conveying the dehydrated and filter-pressed dry tailings onto the waste stone layer (2), compacting to form a dry tailings layer (3), and alternately stacking the waste stone layer (2) and the dry tailings layer (3) until the open pit is completely backfilled;
step 2: laying an initial dam (4) above a stacking layer of the waste stone layer (2) and the dry tailing layer (3), stacking dry tailing piles (3') in layers at the upstream of the initial dam (4) in an inverted mode, and gradually advancing to the initial dam (4) until a design elevation is reached;
and step 3: piling the waste rock pile (10) in a layered manner at the periphery of the dry tailings pile (3 ') piled in the step 2 in an inverted manner until the top surface of the region of the waste rock pile (10) is bordered by the top surface of the region of the dry tailings pile (3');
and 4, step 4: paving a drainage prism (5) at the periphery of the waste stone pile (10) in the step 3;
and 5: in step 4, an inverted filter layer (6) is constructed between the waste rock pile (10) and the drainage prism body (5).
2. The method for jointly disposing the waste rock and the dry tailings in the open pit according to the claim 1, wherein the step 1, in which the waste rock layers (2) and the dry tailings layers (3) with low water content are alternately stacked, comprises:
step 11: calculating the thickness of each waste stone layer (2) and the dry tailing layer (3) according to the backfilling depth of the open pit, controlling the thickness of each waste stone layer (3) to be 5-8m, and controlling the thickness of the dry tailing layer (3) to be below 5 m;
step 12: and (4) backfilling the open pit according to the thickness of each waste stone layer (2) and the dry tail sand layer (3) in the step (11), wherein the top backfilling body at the end of backfilling is the waste stone layer (2).
3. The method for jointly disposing the waste rocks and the dry tailings in the open pit according to claim 2, wherein the water content of the dry tailings layer (3) in the step 12 is controlled to be in a range of 5-10%;
and in the step 2, the water content of the dry tailings pile (3') is controlled within a range of 10-20%.
4. A method for disposing an open pit by combining waste rock and dry tailings as claimed in claim 3, wherein the top surface of the dry tailings pile (3') in step 2 has a slope of between 0.5% and 1% with respect to the ground surface;
in the step 3, the slope of the top surface of the waste rock pile (10) relative to the ground surface is between 1% and 2%.
5. A method for disposing an open pit by combining waste rock and dry tailings as claimed in claim 4, wherein the inverted filter layer (6) in the step 5 comprises 3 crushed rock layers with different particle sizes;
the grain composition of the 3 layers of the crushed stone layers along the direction from the waste stone pile (10) to the drainage prism body (5) is from small to large.
6. A pit method for the joint disposal of waste rock and dry tailings as defined in claim 5, characterized in that a horizontal drain (7) is provided below the dry tailings pile (3') and the waste rock pile (10);
one end of the drain pipe (7) extends outwards and is connected with a water collecting tank (8);
the surface precipitation on the pile surface and the water in the pile are discharged into a water collecting tank (8) through the drainage arris body (5), the inverted filter layer (6) and the drain pipe (7), so that the infiltration line in the dry tailing pile (3') is reduced, the fine-particle tailing is prevented from losing, and the stability of the pile body is enhanced.
7. The method for jointly disposing the waste rock and the dry tailings in the open pit according to the claim 1, wherein the bottom and the side slope of the open pit are cleaned before a layer of waste rock layer (2) is backfilled at the bottom of the open pit in the step 1, and a hydraulic channel through which the open pit is communicated with underground water is plugged.
8. The method for jointly disposing the waste rock and the dry tailings in the open pit according to claim 1, wherein a topsoil layer (9) is laid after the slope surface and the top of the waste rock pile (10) are leveled, and the thickness of the soil layer is not less than 0.5 m.
CN202111528049.0A 2021-12-14 2021-12-14 Method for combined disposal of waste stone and dry tailings in open pit Active CN114294056B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202111528049.0A CN114294056B (en) 2021-12-14 2021-12-14 Method for combined disposal of waste stone and dry tailings in open pit
PCT/CN2022/130710 WO2023109378A1 (en) 2021-12-14 2022-11-08 Waste rock and dry tailings combined treatment method for open pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111528049.0A CN114294056B (en) 2021-12-14 2021-12-14 Method for combined disposal of waste stone and dry tailings in open pit

Publications (2)

Publication Number Publication Date
CN114294056A true CN114294056A (en) 2022-04-08
CN114294056B CN114294056B (en) 2024-07-30

Family

ID=80967833

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111528049.0A Active CN114294056B (en) 2021-12-14 2021-12-14 Method for combined disposal of waste stone and dry tailings in open pit

Country Status (2)

Country Link
CN (1) CN114294056B (en)
WO (1) WO2023109378A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115144567A (en) * 2022-09-01 2022-10-04 中国有色金属工业昆明勘察设计研究院有限公司 Upstream type tailing dam accumulation surveying and stability evaluation method and system
WO2023109378A1 (en) * 2021-12-14 2023-06-22 万宝矿产有限公司 Waste rock and dry tailings combined treatment method for open pit

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2061141C1 (en) * 1993-08-02 1996-05-27 Всероссийский научно-исследовательский институт Научно-производственного объединения "Виогем" Method for stacking tailings
KR100879917B1 (en) * 2008-06-04 2009-02-26 (주)시엠씨 Tailing stability method of river at mine district
RU2392377C1 (en) * 2009-04-29 2010-06-20 Василий Петрович Ягин Method for erection of sludge pond tier build-up dam
CN103953008A (en) * 2014-04-25 2014-07-30 化工部长沙设计研究院 Modified mixed dam applicable to tailings ponds
CN104846779A (en) * 2015-05-22 2015-08-19 辽宁工程技术大学 Method for heaping up waterproof tailings pond dam
CN105040711A (en) * 2015-06-25 2015-11-11 中钢集团马鞍山矿山研究院有限公司 Method for strengthening dry tailing storage yard by utilizing barren rocks
CN106168133A (en) * 2016-08-25 2016-11-30 中国恩菲工程技术有限公司 Open-air pit fill method
WO2018192066A1 (en) * 2017-04-19 2018-10-25 中国矿业大学 Method for controlling subsidence area caused by underground mining in adjoining open-pit mine
CN110566207A (en) * 2019-09-10 2019-12-13 东北大学 covering layer full-tailings piling method for open-air to underground non-bottom-pillar sublevel caving method
CN110735639A (en) * 2019-11-12 2020-01-31 中冶沈勘秦皇岛工程设计研究总院有限公司 Open pit backfilling method after mining by open pit to underground caving method
CN111322109A (en) * 2020-04-26 2020-06-23 锡林郭勒盟山金阿尔哈达矿业有限公司 Waste stone and tailing synergistic cemented filling method
WO2020253264A1 (en) * 2019-06-20 2020-12-24 中国矿业大学 Method for constructing reservoir, segment by segment, at bottom of inner-dumping open-pit mine
CN112709233A (en) * 2020-12-24 2021-04-27 矿冶科技集团有限公司 Mine waste rock and concentrated tailing cooperative disposal system and construction method
CN112814732A (en) * 2021-02-20 2021-05-18 中南大学 Preparation of mixed ground paste of barren rock and tailings and pump sending filling device

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216239B (en) * 2013-04-27 2015-06-17 北京科技大学 Backfill handling method for activity subsidence area of mine
CN104653224B (en) * 2014-12-12 2016-08-03 河北联合大学 The method that open-air pit tailing cemented filling is administered
CN106894817B (en) * 2017-03-03 2018-11-23 中南大学 A kind of mechanization Upward slicing wedging mixed filling mining codes
CN108941146B (en) * 2018-07-02 2021-05-04 北京科技大学 Waste rock and full tailings mixing and stacking method
CN110106838B (en) * 2019-05-29 2020-05-19 中国水利水电科学研究院 Cemented dam construction method based on whole-process quality control
CN114294056B (en) * 2021-12-14 2024-07-30 万宝矿产有限公司 Method for combined disposal of waste stone and dry tailings in open pit

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2061141C1 (en) * 1993-08-02 1996-05-27 Всероссийский научно-исследовательский институт Научно-производственного объединения "Виогем" Method for stacking tailings
KR100879917B1 (en) * 2008-06-04 2009-02-26 (주)시엠씨 Tailing stability method of river at mine district
RU2392377C1 (en) * 2009-04-29 2010-06-20 Василий Петрович Ягин Method for erection of sludge pond tier build-up dam
CN103953008A (en) * 2014-04-25 2014-07-30 化工部长沙设计研究院 Modified mixed dam applicable to tailings ponds
CN104846779A (en) * 2015-05-22 2015-08-19 辽宁工程技术大学 Method for heaping up waterproof tailings pond dam
CN105040711A (en) * 2015-06-25 2015-11-11 中钢集团马鞍山矿山研究院有限公司 Method for strengthening dry tailing storage yard by utilizing barren rocks
CN106168133A (en) * 2016-08-25 2016-11-30 中国恩菲工程技术有限公司 Open-air pit fill method
WO2018192066A1 (en) * 2017-04-19 2018-10-25 中国矿业大学 Method for controlling subsidence area caused by underground mining in adjoining open-pit mine
WO2020253264A1 (en) * 2019-06-20 2020-12-24 中国矿业大学 Method for constructing reservoir, segment by segment, at bottom of inner-dumping open-pit mine
CN110566207A (en) * 2019-09-10 2019-12-13 东北大学 covering layer full-tailings piling method for open-air to underground non-bottom-pillar sublevel caving method
CN110735639A (en) * 2019-11-12 2020-01-31 中冶沈勘秦皇岛工程设计研究总院有限公司 Open pit backfilling method after mining by open pit to underground caving method
CN111322109A (en) * 2020-04-26 2020-06-23 锡林郭勒盟山金阿尔哈达矿业有限公司 Waste stone and tailing synergistic cemented filling method
CN112709233A (en) * 2020-12-24 2021-04-27 矿冶科技集团有限公司 Mine waste rock and concentrated tailing cooperative disposal system and construction method
CN112814732A (en) * 2021-02-20 2021-05-18 中南大学 Preparation of mixed ground paste of barren rock and tailings and pump sending filling device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
鲁明星;张博文;丁爱华;: "露天坑废石尾砂混排边坡稳定性研究", 金属矿山, no. 05 *
鲁明星;张博文;丁爱华;: "露天坑废石尾砂混排边坡稳定性研究", 金属矿山, no. 05, 15 May 2017 (2017-05-15) *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023109378A1 (en) * 2021-12-14 2023-06-22 万宝矿产有限公司 Waste rock and dry tailings combined treatment method for open pit
CN115144567A (en) * 2022-09-01 2022-10-04 中国有色金属工业昆明勘察设计研究院有限公司 Upstream type tailing dam accumulation surveying and stability evaluation method and system
CN115144567B (en) * 2022-09-01 2022-11-11 中国有色金属工业昆明勘察设计研究院有限公司 Upstream type tailing dam accumulation surveying and stability evaluation method and system

Also Published As

Publication number Publication date
WO2023109378A1 (en) 2023-06-22
CN114294056B (en) 2024-07-30

Similar Documents

Publication Publication Date Title
Yilmaz Advances in reducing large volumes of environmentally harmful mine waste rocks and tailings
WO2023109378A1 (en) Waste rock and dry tailings combined treatment method for open pit
CN101713291A (en) Filling-reclaiming method for building land in coal mining subsidence areas
CN112709233A (en) Mine waste rock and concentrated tailing cooperative disposal system and construction method
CN103953008A (en) Modified mixed dam applicable to tailings ponds
CN102704364A (en) Clay serging tailings subgrade structure and construction method thereof
CN113605492A (en) Three-dimensional protection and utilization method for strip mine water resources
Gowan et al. Co-disposal techniques that may mitigate risks associated with storage and management of potentially acid generating wastes
CN111593742A (en) Construction method for rectifying and improving tailing pond based on rubble silt squeezing method
CN209338948U (en) A kind of water-permeable pavement structure
CN114293990A (en) Method for filling open pit
CN113265924B (en) Construction method for using red bed mudstone blocks as high-fill dynamic compaction roadbed filling
CN111350520B (en) Underground water drainage system and construction method for underground excavation tunnel of water-rich sandy pebble stratum
CN114855762B (en) Device and method for closing and sealing tailings pond
CN217399609U (en) Device for closing and sealing tailing pond
CN216477459U (en) Open pit filling structure
CN217419178U (en) Adopt half high fill structure of parcel inflation soil of lime soil
CN110566207A (en) covering layer full-tailings piling method for open-air to underground non-bottom-pillar sublevel caving method
Breitenbach Overview: Tailings disposal and dam construction practices in the 21st century
CN103806434A (en) Method for processing saturated overwet soil foundation for prespud operation by using graded construction slag soilbag
CN108442356A (en) The construction technology of blowing filling soft soil foundation vacuum dynamic compaction method composite drainage system
CN210031758U (en) A surcharge and carry pre-compaction structure for soft soil highway section construction
CN211142675U (en) Roadbed structure of expressway filled with muck type construction waste
CN114182748A (en) Jointless continuous in-situ impervious wall construction device and curtain construction method
CN114263460B (en) Stoping method for mountain-side tailing pond

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant