CN114233352A - Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure - Google Patents

Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure Download PDF

Info

Publication number
CN114233352A
CN114233352A CN202111459793.XA CN202111459793A CN114233352A CN 114233352 A CN114233352 A CN 114233352A CN 202111459793 A CN202111459793 A CN 202111459793A CN 114233352 A CN114233352 A CN 114233352A
Authority
CN
China
Prior art keywords
section
grouting
anchoring
surrounding rock
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111459793.XA
Other languages
Chinese (zh)
Inventor
李文洲
张镇
武龙云
孟宪志
吴志刚
王志超
郝登云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tiandi Science and Technology Co Ltd
CCTEG Coal Mining Research Institute
Original Assignee
Tiandi Science and Technology Co Ltd
CCTEG Coal Mining Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tiandi Science and Technology Co Ltd, CCTEG Coal Mining Research Institute filed Critical Tiandi Science and Technology Co Ltd
Priority to CN202111459793.XA priority Critical patent/CN114233352A/en
Publication of CN114233352A publication Critical patent/CN114233352A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/025Grouting with organic components, e.g. resin
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Road Signs Or Road Markings (AREA)

Abstract

The invention relates to the technical field of roadway support, and provides a multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure. The multi-section grooving and splitting grouting modified surrounding rock cooperative control method comprises the following steps: drilling a hole in surrounding rock of a roadway to form an anchor hole, and performing multi-section grooving on the hole wall of the anchor hole to form a grooving section; placing an anchoring piece into the anchor hole, and placing a hole sealing device at the tail part of the anchoring piece close to the side wall of the roadway, wherein the hole sealing device is used for sealing the anchor hole; and forming a grouting section in the anchor hole through high-pressure splitting grouting so as to form a high-pressure splitting grouting reinforced area on the surrounding rock around the grouting section. According to the multi-section grooving and splitting grouting modified surrounding rock cooperative control method, the anchoring part is stably anchored, and the safety degree and effect of surrounding rock control are improved.

Description

Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure
Technical Field
The invention relates to the technical field of roadway support, in particular to a multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure.
Background
The roadway surrounding rock control technology is a key technology in coal mining, and the safe, reasonable and effective roadway support technology is a necessary condition for ensuring high yield and high efficiency of mines.
Aiming at the problem of surrounding rock control in the roadway excavation process, the conventional anchor net cable support is popularized and applied in a large scale due to safety and convenience. The stable reinforcing zone is formed in the surrounding rock through anchor rod and anchor cable support, the bearing effect of the surrounding rock is fully exerted, and the stability of the surrounding rock is ensured.
However, in the excavation process of a coal mine tunnel, the geological conditions of surrounding rocks are complex, cracks develop, the content of soft rock components such as kaolin, chlorite and the like in different rock strata is high, and the soft rock components are influenced by water drenching, temperature and geological structure in the excavation process, so that the anchoring force of an anchor rod and an anchor cable is insufficient in the control process of the tunnel surrounding rocks, the deformation of the surrounding rocks is large, the fracture surface is seriously shrunk, the coal mine tunnel is repaired for many times, even a disaster roof accident can be caused, and the safety production of a coal mine is seriously influenced.
Disclosure of Invention
The invention provides a multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure, which are used for overcoming the defects of insufficient anchoring force and serious later attenuation in the anchoring process of an anchor rod and an anchor cable caused by large deformation of surrounding rock in the prior art and realizing the improvement of the safety degree and effect of surrounding rock control.
The invention provides a multi-section grooving and splitting grouting modified surrounding rock cooperative control method, which comprises the following steps:
drilling a hole in surrounding rock of a roadway to form an anchor hole, and performing multi-section grooving on the hole wall of the anchor hole to form a grooving section;
placing an anchoring piece into the anchor hole, and placing a hole sealing device at the tail part of the anchoring piece close to the side wall of the roadway, wherein the hole sealing device is used for sealing the anchor hole;
and forming a grouting section in the anchor hole through high-pressure splitting grouting so as to form a high-pressure splitting grouting reinforced area on the surrounding rock around the grouting section.
According to the cooperative control method for the multi-section cutting groove and splitting grouting modified surrounding rock, provided by the invention, the step of forming the grouting section in the anchor hole through high-pressure splitting grouting comprises the following steps:
firstly, injecting a resin anchoring agent into the bottom of the anchor hole to form an anchoring agent anchoring section, wherein the anchoring agent anchoring section wraps the anchoring end of the anchoring element;
and forming the grouting section on the rest part of the anchor hole by high-pressure splitting grouting.
According to the cooperative control method for the multi-section cutting groove and splitting grouting modified surrounding rock, provided by the invention, the step of forming the grouting section in the anchor hole through high-pressure splitting grouting comprises the following steps:
and forming the grouting section on the full-length section of the anchor hole by high-pressure splitting grouting.
According to the cooperative control method for the multi-section grooving and splitting grouting modified surrounding rock, provided by the invention, the steps of drilling holes in the surrounding rock of the roadway to form anchor holes and performing multi-section grooving on the hole walls of the anchor holes comprise:
determining the intervals of the multiple sections of the grooving sections according to the drilling depth and the surrounding rock property;
and utilizing a drilling grooving tool to perform multi-section grooving, and forming the anchor hole and the grooving section through one-time hole forming.
According to the cooperative control method for the multi-section grooving and splitting grouting modified surrounding rock, provided by the invention, the step of placing the anchoring piece into the anchor hole comprises the following steps:
the rod body of the anchoring piece is provided with a plurality of friction structures, and the distance between the friction structures is determined according to the drilling depth.
The invention also provides a multi-section grooving and splitting grouting modified surrounding rock cooperative control structure, which comprises:
the anchoring part is arranged on the side wall of the roadway, and a hole sealing device is arranged at the tail part of the anchoring part close to the side wall of the roadway;
the grouting section is positioned in surrounding rocks of the roadway and provided with a plurality of grouting groove cutting sections which are arranged at intervals along the length direction of the anchoring piece, and the grouting section wraps the anchoring piece and abuts against the hole sealing device;
and the high-pressure splitting grouting strengthening area is positioned at the periphery of the grouting section.
According to the multi-section cutting groove and splitting grouting modified surrounding rock cooperative control structure provided by the invention, the multi-section cutting groove and splitting grouting modified surrounding rock cooperative control structure further comprises an anchoring agent anchoring section, the anchoring agent anchoring section is provided with a plurality of sections of anchoring agent cutting groove sections which are arranged at intervals along the length direction of an anchoring piece, the anchoring agent anchoring section and the grouting section are arranged in parallel along the length direction of the anchoring piece, and the anchoring agent anchoring section is positioned on one side of the anchoring end of the anchoring piece.
According to the multi-section grooving and splitting grouting modified surrounding rock cooperative control structure provided by the invention, the grouting section extends to the hole sealing device from the anchoring end of the anchoring part.
According to the multi-section grooving and splitting grouting modified surrounding rock cooperative control structure provided by the invention, the rod body of the anchoring part is also provided with a plurality of friction structures arranged at intervals, and the grouting section is wrapped on the friction structures.
The invention also provides a roadway surrounding rock modified structure, which comprises a plurality of multi-section cutting grooves and split grouting modified surrounding rock cooperative control structures;
and the high-pressure splitting grouting reinforcement areas of the adjacent multi-section cutting groove and splitting grouting modified surrounding rock cooperative control structure are arranged in a crossing manner.
According to the multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure, the anchoring strength of the anchoring section is improved through the grooving section formed by the multi-section grooving, in addition, the surrounding rock is modified through the high-pressure splitting grouting strengthening area formed by splitting grouting during grouting, the strength of the surrounding rock around the anchor hole is improved, the compactness of the anchoring section and the surrounding rock is improved, the control effects of fast tunneling of a large-deformation soft rock roadway and the surrounding rock are obviously improved through anchor supporting, and the management level of the top plate of the large-deformation soft rock roadway is improved. Compared with the anchor bolt supporting method in the prior art, the multi-section cutting groove and splitting grouting modified surrounding rock cooperative control method provided by the invention has the advantages that the anchoring of the anchor is stable, and the safety degree and effect of surrounding rock control are improved.
Drawings
In order to more clearly illustrate the technical solutions of the present invention or the prior art, the drawings needed for the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and those skilled in the art can also obtain other drawings according to the drawings without creative efforts.
FIG. 1 is a schematic flow chart of a cooperative control method for multi-section grooving and splitting grouting modified surrounding rock provided by the invention;
FIG. 2 is one of the schematic diagrams of the cooperative control structure of the multi-section grooving and splitting grouting modified surrounding rock provided by the invention;
FIG. 3 is a second schematic diagram of a cooperative control structure of multi-stage grooving and splitting grouting modified surrounding rock provided by the present invention;
FIG. 4 is a schematic diagram of a modified structure of roadway surrounding rock provided by the invention;
reference numerals:
10: an anchoring member; 11: a hole sealing device; 12: grouting a tray;
13: a friction structure; 20: a grouting section; 21: grouting a slot cutting section;
22: high-pressure splitting grouting strength of 30: an anchoring agent anchoring section; 31: and the anchoring agent is cut into groove sections. A chemical region;
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
When the roadway is supported, the anchoring piece is used for forming a reinforcing zone in the roadway surrounding rock, the bearing effect of the surrounding rock is exerted, and the stability of the surrounding rock is ensured, so that the anchoring stability of the anchoring piece needs to be ensured, and the problems of insufficient anchoring force and support failure cannot occur. The method and the structure of the invention are not only used in the laneway, but also can be used in other places needing to improve the supporting effect according to the needs. The method and the structure can be a preset supporting method before the roadway is excavated or a repairing supporting method during later roadway repairing, wherein the roadway needs to be repaired to the initial design shape of the roadway first during the roadway repairing, and then the method is adopted. The shape of the tunnel is not limited to the arch shape provided in the embodiment of the present invention, and may also be a square shape or other shapes according to the use requirement, which is not described in detail.
The anchoring member may be an anchoring structure such as a bolt or an anchor cable.
The cooperative control method and structure of the multi-section grooving and splitting grouting modified surrounding rock of the invention are described below with reference to fig. 1 to 4.
Referring to fig. 1, in an embodiment of the present invention, a method for cooperatively controlling a multi-section grooving and splitting grouting modified surrounding rock includes:
drilling a hole in surrounding rock of a roadway to form an anchor hole, and performing multi-section grooving on the hole wall of the anchor hole to form a grooving section; the drilling is perpendicular to the side wall of the roadway, the grooving sections are formed on the hole wall of the anchor hole, the positions and the intervals of the grooving sections are not limited, in the embodiment, the grooving sections are of annular ring-shaped hole structures, the grooving sections of the structure can improve the structural strength of the anchoring section placed on the surrounding rock, the anchoring section is prevented from being separated from the surrounding rock, and the supporting effect of the anchoring piece 10 is improved.
Placing an anchoring part 10 into the anchor hole, and placing a hole sealing device 11 at the tail part of the anchoring part 10 close to the side wall of the roadway, wherein the hole sealing device 11 is used for sealing the anchor hole; the afterbody of anchor assembly 10 is equipped with sealing device 11, and in this embodiment, this sealing device 11 is body of rod gripping formula side direction sealing device, and the sealer interface of sealing device 11 can link to each other with the grouting pump to grout into the anchor eye, and avoid mud to spill, in addition, still is equipped with slip casting tray 12 at the afterbody of anchor assembly 10, and slip casting tray 12 supports the lateral wall in tunnel, can be used for fixed anchor net isotructure.
Forming a grouting section 20 in the anchor hole through high-pressure splitting grouting so as to form a high-pressure splitting grouting reinforced area 22 in the surrounding rock around the grouting section 20; adopt high-pressure splitting slip casting in the anchor hole, can will fill in the crack around to realize modifying to crack around, form high-pressure splitting slip casting and reinforce district 22, reach the effect of miniature bored pile, improve the closely knit nature of country rock, guarantee the anchor effect, in this embodiment, high-pressure splitting slip casting is low pressure and fills high-pressure splitting chronogenesis slip casting.
In addition, before drilling, firstly, investigation is carried out on the stress, the structure (such as surrounding rock cracks), the soft rock components (such as kaolin, chlorite and the like), the influence range and the like of the surrounding rock of the roadway, the investigation result is evaluated, the characteristics of the weakly cemented soft rock and the high-stress soft rock are determined, and on the basis of the former investigation, the control width of the surrounding rock of the single anchoring piece 10 and the depth of the anchoring piece 10 needing drilling are determined, so that subsequent construction is facilitated.
In the embodiment, the grooving sections formed by the multiple grooving sections improve the anchoring strength of the anchoring section, and during grouting, the high-pressure splitting grouting strengthening area 22 formed by splitting grouting modifies surrounding rocks, improves the strength of the surrounding rocks around the anchor hole, improves the compactness of the anchoring section and the surrounding rocks, supports by the anchoring part 10, obviously improves the control effect of fast tunneling and surrounding rocks of the large-deformation soft rock roadway, and improves the management level of the top plate of the large-deformation soft rock roadway. Compared with the anchor bolt supporting method of the anchoring part 10 provided by the prior art, the multi-section cutting groove and split grouting modified surrounding rock cooperative control method provided by the invention has the advantages that the anchoring part 10 is stably anchored, and the safety degree and effect of surrounding rock control are improved.
Referring to fig. 1, in one embodiment of the present invention, there are at least two methods for anchoring the anchoring element 10, and in one embodiment, the step of forming the grouting section 20 in the anchor hole by high-pressure split grouting includes:
firstly, injecting resin anchoring agent into the bottom of the anchor hole to form an anchoring agent anchoring section 30, wherein the anchoring agent anchoring section 30 wraps the anchoring end of the anchoring element 10;
and forming the grouting section 20 in the rest part of the anchor hole by high-pressure split grouting.
The bottom of the anchor hole is anchored by resin to form an anchoring agent anchoring section 30 with a certain length, the rest of the anchoring agent anchoring section is anchored by grouting, and the anchoring agent anchoring section 30 is also filled in the given slot section, so that the anchoring effect of the end part of the anchoring element 10 can be ensured.
Referring to fig. 1, in another embodiment, the step of forming a grouting section 20 in the anchor hole by high-pressure split grouting includes:
the grouted section 20 is formed by high pressure cleavage grouting over the full length of the anchor eye.
That is, the grouting is performed in all areas of the anchor hole, so that the strength of the whole anchoring section can be improved, and the high-pressure split grouting reinforcement area 22 is larger than that of the embodiment, so that the structural strength of surrounding rocks is higher, and the method is suitable for the roadway with loose supporting time.
Referring to fig. 1, in an embodiment of the present invention, the step of drilling a hole in a surrounding rock of a roadway to form an anchor hole and performing a multi-stage grooving on a hole wall of the anchor hole includes:
determining the intervals of the multiple sections of the grooving sections according to the drilling depth and the surrounding rock property;
and utilizing a drilling grooving tool to perform multi-section grooving, and forming the anchor hole and the grooving section through one-time hole forming.
In the process of tunneling and drilling, a mechanical or hydraulic grooving mode is adopted, self-grooving is formed at the hole wall at a certain interval, secondary construction of common hole expansion is avoided, and drilling efficiency is improved.
Of course, in other embodiments, the hole may be drilled first, and then the slot may be cut into the anchor hole for multiple times to obtain the slot segment, which will not be described in detail.
Referring to fig. 1, in addition, in an embodiment of the present invention, the step of placing the anchor member 10 into the anchor hole is preceded by:
a plurality of friction structures 13 are arranged on a rod body of the anchoring piece 10, and the distance between the friction structures 13 is determined according to the drilling depth.
Through setting up friction structure 13, can make the joint strength between anchor assembly 10 and the anchor section further improve to improve and strut the effect, in this embodiment, the interval between a plurality of friction structure 13 equals, in order to improve the holistic anchor effect of anchor assembly 10. Optionally, the distance of the friction structure 13 is 30-50cm, and the distance can be specifically adjusted according to the surrounding rock conditions.
In one embodiment, the friction structure 13 may be a plurality of screws welded to the outer periphery of the anchor 10, and after the grout is injected, the screws and grout may form a reinforced concrete structure, further increasing the overall structural strength. Of course, in other embodiments, the friction structure 13 may be a steel wire or other structure surrounding the periphery of the anchor 10, which is not described in detail.
In one embodiment of the invention, when high-pressure splitting grouting is used, the grouting pressure for a coal roadway is not more than 10Mpa, and the grouting pressure for a rock roadway is not more than 30Mpa, so that the grouting effect is ensured, and the filling of high-pressure splitting grouting on the cracks of the drilled surrounding rock is met, so that the surrounding rock is reinforced.
Referring to fig. 2 and fig. 3 in combination, based on the above method, the present invention obtains a multi-section grooving and splitting grouting modified surrounding rock cooperative control structure, including:
the anchoring part 10 is arranged on the side wall of the roadway, and a hole sealing device 11 is arranged at the tail part, close to the side wall of the roadway, of the anchoring part 10;
the grouting section 20 is positioned in surrounding rocks of the roadway, the grouting section 20 is provided with a plurality of grouting groove cutting sections 21 which are arranged at intervals along the length direction of the anchoring piece 10, and the grouting section 20 wraps the anchoring piece 10 and abuts against the hole sealing device 11;
and the high-pressure splitting grouting strengthening area 22 is positioned at the periphery of the grouting section 20, and the high-pressure splitting grouting strengthening area 22 is positioned at the periphery of the grouting section 20.
The structure improves the structural strength of the anchoring section and surrounding rocks, so that the anchoring part 10 is stably anchored, and the safety degree and effect of surrounding rock control are improved.
Corresponding to the method, when the resin anchoring agent and grouting are adopted to fill the anchor hole simultaneously, the multi-section grooving and splitting grouting modified surrounding rock cooperative control structure further comprises an anchoring agent anchoring section 30, the anchoring agent anchoring section 30 is provided with a plurality of sections of anchoring agent grooving sections 31 arranged at intervals along the length direction of the anchoring element 10, the anchoring agent anchoring section 30 and the grouting section 20 are arranged in parallel along the length direction of the anchoring element 10, and the anchoring agent anchoring section 30 is positioned on one side of the anchoring end of the anchoring element 10.
When full-length grouting is adopted, the grouting section 20 extends from the anchoring end of the anchoring part 10 to the hole sealing device 11.
In addition, still be provided with a plurality of interval arrangement friction structure 13 on the body of rod of anchor member 10, slip casting section 20 parcel in friction structure 13. Based on the two anchoring methods of the anchoring part 10, when the resin anchoring agent and the grouting are adopted to fill the anchoring hole at the same time, the anchoring part 30 and the grouting part 20 both wrap the friction structure 13 and are fully contacted with the friction structure 13, so that the anchoring strength of the anchoring part 10 is improved, and when the full-length grouting is adopted, the whole anchoring part can form a structure similar to reinforced concrete, so that the integral strength is further improved.
Referring to fig. 4, in addition, the present invention further provides a roadway surrounding rock modified structure, which includes a plurality of multi-section cutting grooves and split grouting modified surrounding rock cooperative control structures as described above;
and the high-pressure splitting grouting strengthening areas 22 of the adjacent multi-section cutting groove and splitting grouting modified surrounding rock cooperative control structure are arranged in a crossed manner.
Namely, in order to improve the holistic control effect in tunnel, set up a plurality of cooperative control structures, and high pressure splitting slip casting intensification district 22 cross arrangement to make the country rock structure in tunnel modified, the very big improvement of intensity forms the whole anchor structure of tunnel country rock, guarantees that tunnel country rock is stable, has improved the control effect of tunnel country rock greatly.
Specifically, on the basis of the prior investigation, the control width of the surrounding rock of the single anchoring piece 10 is determined, so as to determine the distance between the adjacent anchoring pieces 10, in this embodiment, the anchoring pieces 10 are uniformly arranged at intervals along the width direction of the surrounding rock of the roadway. Further, along the length direction of tunnel country rock, the even interval of a plurality of anchor assembly 10 sets up, and a plurality of anchor assembly 10 are whole to be plum blossom form and arrange, like this, compare with other modes, can guarantee that the country rock is whole to be modified, and the effect is better, and then improves the structural strength of tunnel country rock to improve and strut the effect.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (10)

1. A multi-section grooving and splitting grouting modified surrounding rock cooperative control method is characterized by comprising the following steps:
drilling a hole in surrounding rock of a roadway to form an anchor hole, and performing multi-section grooving on the hole wall of the anchor hole to form a grooving section;
placing an anchoring piece into the anchor hole, and placing a hole sealing device at the tail part of the anchoring piece close to the side wall of the roadway, wherein the hole sealing device is used for sealing the anchor hole;
and forming a grouting section in the anchor hole through high-pressure splitting grouting so as to form a high-pressure splitting grouting reinforced area on the surrounding rock around the grouting section.
2. The cooperative control method for the multi-section cutting groove and splitting grouting modified surrounding rock according to claim 1, wherein the step of forming a grouting section in the anchor hole through high-pressure splitting grouting comprises the following steps:
firstly, injecting a resin anchoring agent into the bottom of the anchor hole to form an anchoring agent anchoring section, wherein the anchoring agent anchoring section wraps the anchoring end of the anchoring element;
and forming the grouting section on the rest part of the anchor hole by high-pressure splitting grouting.
3. The cooperative control method for the multi-section cutting groove and splitting grouting modified surrounding rock according to claim 1, wherein the step of forming a grouting section in the anchor hole through high-pressure splitting grouting comprises the following steps:
and forming the grouting section on the full-length section of the anchor hole by high-pressure splitting grouting.
4. The cooperative control method for the multi-segment grooving and splitting grouting modified surrounding rock according to any one of claims 1 to 3, wherein the step of drilling a hole in the surrounding rock of a roadway to form an anchor hole and performing multi-segment grooving on the hole wall of the anchor hole comprises the following steps:
determining the intervals of the multiple sections of the grooving sections according to the drilling depth and the surrounding rock property;
and utilizing a drilling grooving tool to perform multi-section grooving, and forming the anchor hole and the grooving section through one-time hole forming.
5. The cooperative control method for the multi-section grooving and splitting grouting modified surrounding rock according to any one of claims 1 to 3, wherein the step of placing the anchoring element into the anchoring hole is preceded by:
the rod body of the anchoring piece is provided with a plurality of friction structures, and the distance between the friction structures is determined according to the drilling depth.
6. The utility model provides a modified country rock cooperative control structure of multistage grooving and splitting slip casting which characterized in that includes:
the anchoring part is arranged on the side wall of the roadway, and a hole sealing device is arranged at the tail part of the anchoring part close to the side wall of the roadway;
the grouting section is positioned in surrounding rocks of the roadway and provided with a plurality of grouting groove cutting sections which are arranged at intervals along the length direction of the anchoring piece, and the grouting section wraps the anchoring piece and abuts against the hole sealing device;
and the high-pressure splitting grouting strengthening area is positioned at the periphery of the grouting section.
7. The multi-segment cutting groove and splitting grouting modified surrounding rock cooperative control structure as claimed in claim 6, wherein the multi-segment cutting groove and splitting grouting modified surrounding rock cooperative control structure further comprises an anchoring agent anchoring section, the anchoring agent anchoring section is provided with a plurality of segments of anchoring agent cutting groove sections which are arranged at intervals along the length direction of an anchoring element, the anchoring agent anchoring section and the grouting section are arranged side by side along the length direction of the anchoring element, and the anchoring agent anchoring section is positioned on one side of the anchoring end of the anchoring element.
8. The cooperative control structure of the multi-segment cutting groove and splitting grouting modified surrounding rock of claim 6, wherein the grouting segment extends from the anchoring end of the anchoring part to the hole sealing device.
9. The cooperative control structure of the multi-section cutting groove and the split grouting modified surrounding rock according to any one of claims 6 to 8, wherein a plurality of friction structures are arranged at intervals on a rod body of the anchoring piece, and the grouting section is wrapped on the friction structures.
10. A roadway surrounding rock modified structure, which is characterized by comprising a plurality of multi-section cutting and splitting grouting modified surrounding rock cooperative control structures according to any one of claims 6 to 9;
and the high-pressure splitting grouting reinforcement areas of the adjacent multi-section cutting groove and splitting grouting modified surrounding rock cooperative control structure are arranged in a crossing manner.
CN202111459793.XA 2021-12-02 2021-12-02 Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure Pending CN114233352A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111459793.XA CN114233352A (en) 2021-12-02 2021-12-02 Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111459793.XA CN114233352A (en) 2021-12-02 2021-12-02 Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure

Publications (1)

Publication Number Publication Date
CN114233352A true CN114233352A (en) 2022-03-25

Family

ID=80752973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111459793.XA Pending CN114233352A (en) 2021-12-02 2021-12-02 Multi-section grooving and splitting grouting modified surrounding rock cooperative control method and structure

Country Status (1)

Country Link
CN (1) CN114233352A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793157A (en) * 2010-03-23 2010-08-04 北京科技大学 Method for supporting filling body
CN103758450A (en) * 2014-01-17 2014-04-30 北京市市政工程研究院 Self-drilling anchor rod boring device capable of reaming at the same time
CN205477690U (en) * 2016-03-23 2016-08-17 山东科技大学 Antiskid slip casting stock
CN109798140A (en) * 2019-02-21 2019-05-24 平顶山天安煤业股份有限公司六矿 Km Deep Soft Rock fracture grouting support reinforcement method
WO2020007055A1 (en) * 2018-12-27 2020-01-09 山东科技大学 Combined tension and compression yielding and energy-absorbing grouting anchor bolt for large deformation in surrounding rock, and working method
CN110761819A (en) * 2019-10-31 2020-02-07 天地科技股份有限公司 Prestressed grouting anchor rod
CN111764864A (en) * 2020-07-10 2020-10-13 中国矿业大学 Drilling and guniting reinforcement method for loose and broken coal and rock area

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793157A (en) * 2010-03-23 2010-08-04 北京科技大学 Method for supporting filling body
CN103758450A (en) * 2014-01-17 2014-04-30 北京市市政工程研究院 Self-drilling anchor rod boring device capable of reaming at the same time
CN205477690U (en) * 2016-03-23 2016-08-17 山东科技大学 Antiskid slip casting stock
WO2020007055A1 (en) * 2018-12-27 2020-01-09 山东科技大学 Combined tension and compression yielding and energy-absorbing grouting anchor bolt for large deformation in surrounding rock, and working method
CN109798140A (en) * 2019-02-21 2019-05-24 平顶山天安煤业股份有限公司六矿 Km Deep Soft Rock fracture grouting support reinforcement method
CN110761819A (en) * 2019-10-31 2020-02-07 天地科技股份有限公司 Prestressed grouting anchor rod
CN111764864A (en) * 2020-07-10 2020-10-13 中国矿业大学 Drilling and guniting reinforcement method for loose and broken coal and rock area

Similar Documents

Publication Publication Date Title
CN111305876A (en) Deep roadway anchoring-splitting grouting-hydraulic fracturing pressure relief cooperative control method
CN102937030B (en) Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN108678769A (en) Deep Gateway anchor note cuts top master control and stays lane method
CN102996149B (en) Support method for bolt-grouting composite crushing dynamic-pressure roadway soft rock roof by high-pre-stressed anchor cable
CN104389628B (en) Landslide location tunnel reinforcement device and reinforced construction method
CN105804767B (en) A kind of the surrounding rock supporting construction method and surrounding rock supporting structure in the aqueous tunnel of coal mine
CN110374600B (en) Non-offset arrangement method for mining roadway of extremely-close coal seam group
CN110344831B (en) Roof-cutting pressure-relief non-coal-pillar gob-side entry-forming entry retaining method
AU2015387618B2 (en) Method for fracturing filler wall left behind in adjacent coal-mining face
CN108035742B (en) Active and passive harmonious support method for extremely soft coal seam roadway
CN107143338B (en) A kind of coal mine roadway driving and method for protecting support
CN105351001B (en) A kind of method based on gob side entry retaining region reinforcement gas pumping
CN111535817A (en) Working face double-lane tunneling small coal pillar reinforcement construction method
CN103216244B (en) Roadway soft roof anchoring beam-arch combined structure supporting system and supporting method
CN112610251B (en) Control method of coal mining roadway top plate
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN109236297A (en) Split the coal-mining method filled and leave coal seam in conjunction with the residual exploiting field of uplink second mining tool post
CN102900446A (en) Step-by-step strengthening method by anchoring and forming hole in downward sleeve of cracking medium
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN113833467A (en) Method for solving rock burst of coal field mining area through grouting filling
CN109707422A (en) A kind of goaf roadway fender grouting method for protecting support
CN109057820A (en) A kind of rich water weak broken formation tunnel method for protecting support
CN111075479B (en) Stability control method for surrounding rock of roadway
CN209818093U (en) Be used for soft rock tunnel face reinforcing apparatus
CN207554077U (en) The passive harmonious supporting construction of extreme rockburst tunnel master

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination