CN114108916B CN202111394162.4A CN202111394162A CN114108916B CN 114108916 B CN114108916 B CN 114108916B CN 202111394162 A CN202111394162 A CN 202111394162A CN 114108916 B CN114108916 B CN 114108916B
Authority
CN
China
Prior art keywords
plate
steel bar
bar truss
bottom plate
truss floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111394162.4A
Other languages
Chinese (zh)
Other versions
CN114108916A (en
Inventor
李明
黄亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jianbang Technology Group Co ltd
Original Assignee
Jiangxi Jianbang Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Jianbang Construction Group Co ltd filed Critical Jiangxi Jianbang Construction Group Co ltd
Priority to CN202111394162.4A priority Critical patent/CN114108916B/en
Publication of CN114108916A publication Critical patent/CN114108916A/en
Application granted granted Critical
Publication of CN114108916B publication Critical patent/CN114108916B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/61Connections for building structures in general of slab-shaped building elements with each other
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6801Fillings therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to a floor bearing plate, in particular to a steel bar truss floor bearing plate. The invention aims to provide a steel bar truss floor bearing plate which is convenient to assemble and can prevent concrete from leaking. The invention provides a steel bar truss floor bearing plate which comprises a bottom plate, a supporting mechanism, a connecting mechanism and the like, wherein the front side and the rear side of the left part and the rear side of the right part of the bottom plate are respectively provided with a positioning hole for mounting the steel bar truss floor bearing plate, the top of the bottom plate is provided with the supporting mechanism for improving the bearing capacity of the steel bar truss floor bearing plate, and the supporting mechanism is provided with the connecting mechanism for facilitating splicing of the steel bar truss floor bearing plates. The second hook can hook the connecting rod, and then the first cutter and the first cutter can cut the rubber bag, so that the glue in the rubber bag leaks out, and the fixing plate and the pressing plate can be stuck, thereby fixing the positions of the left and right side floor bearing plates and facilitating the assembly work of people.

Description

Steel bar truss floor support plate
Technical Field
The invention relates to a floor bearing plate, in particular to a steel bar truss floor bearing plate.
Background
The steel bar truss floor support plate is manufactured by welding upper and lower layers of longitudinal steel bars with bent small-diameter steel bars to form a small truss with certain rigidity and capable of bearing load, welding the small truss with a profiled steel sheet, and casting concrete in situ.
The application number is CN200520031277.7, the publication number is 20060809, and a steel bar combined floor bearing plate is disclosed, wherein longitudinal grooves and longitudinal convex grooves which are mutually staggered are arranged on a profiled steel plate, two side edges of the profiled steel plate are provided with lap joint structures, an approximately isosceles triangle steel bar rack is fixed in each longitudinal groove at a certain distance from front to back, an upper main steel bar is fixed at the top end of the steel bar rack, lower main steel bars are respectively fixed on two isosceles edges of the triangle steel bar rack, end transverse steel bars are respectively fixed at two end parts of the two lower main steel bars, an approximately L-shaped end vertical steel bar is respectively fixed on the upper main steel bar and the end transverse steel bar at two ends, and the lower end of the end vertical steel bar extends out of the profiled steel plate. The invention integrates the positive bending moment reinforcing steel bar and the concrete template, has reasonable design, high bearing capacity, strong fire resistance and sound insulation performance, can shorten the construction period, has wide application range and lower cost, reduces construction waste and has better social and economic benefits. Although above-mentioned patent bears the dynamic height, but inconvenient manual work is assembled, needs the manual work to alternate between the building carrier plate with the reinforcing bar, and the reuse wire is tied up the reinforcing bar, does not have stock stop moreover, and the concrete leaks out very easily, design that can not be fine.
Therefore, the steel bar truss floor support plate which is convenient to assemble and can prevent concrete from leaking is designed.
Disclosure of Invention
In order to overcome the defects that the existing steel bar truss floor support plate is simple in functional structure, inconvenient to assemble manually and free of a stop mechanism, the invention aims to provide the steel bar truss floor support plate which is convenient to assemble and can prevent concrete from leaking.
The invention is realized by the following technical approaches: a steel bar truss floor support plate comprises:
the front side and the rear side of the left part and the right part of the bottom plate are both provided with positioning holes for mounting the steel bar truss floor bearing plates, and the top of the bottom plate is provided with a supporting mechanism for improving the bearing capacity of the steel bar truss floor bearing plates;
the support mechanism is provided with a connecting mechanism which is convenient for splicing the steel bar truss floor bearing plates;
the bottom plate of the gap filling mechanism is provided with a gap filling mechanism used for fixing two adjacent steel bar truss floor bearing plates;
the right side of the bottom plate is provided with a stop mechanism for preventing concrete from leaking;
the rear side of the bottom plate is provided with a leakage-proof mechanism for preventing concrete from leaking; the supporting mechanism comprises:
three groups of side supporting rib nets are arranged at the top of the bottom plate at intervals;
the lower part of the right side of each group of the side bracing rib nets on the right side is provided with a first side lever;
the connecting rods are arranged between the upper parts of the inner sides of each group of side supporting rib nets;
the lower part of the left side of each group of the side bracing rib nets on the left side is provided with a second side lever;
excessive muscle net all is equipped with excessive muscle net on the second side lever.
Further, the connecting mechanism comprises:
the first hooks are uniformly arranged on the right connecting rod and the middle connecting rod at intervals, the middle connecting rod is hooked by the first hooks on the right side, and the left connecting rod is hooked by the first hooks on the left side;
the connecting rods on the left side of the second hook are uniformly provided with the second hook at intervals;
the left parts of the elastic pieces and the second hooks are both provided with elastic pieces in an up-and-down symmetrical mode.
Further, the caulking mechanism comprises:
the rear side and the right side of the top of the bottom plate are respectively provided with a fixed plate, and the fixed plates are uniformly provided with three grooves at intervals;
two first cutters are arranged in each groove;
the top of each fixing plate is provided with a rubber bag;
the pressing plates are arranged on the front side and the left side of the bottom plate;
the bottom of the pressing plate is uniformly provided with three filling blocks at intervals;
and the bottom of the filling block of the second cutter is provided with the second cutter.
Further, stock stop including:
the sealing plate is arranged on the right side of the top of the bottom plate;
the top of the sealing plate is provided with a supporting plate;
the vertical plate is arranged on the right side of the supporting plate;
the bottom of the vertical plate is provided with a hook plate;
the anti-tilt hook is rotationally arranged on the upper part of the left side of the vertical plate at even intervals, and hooks the first side rod on the right side;
three springs are uniformly arranged on the lower part of the left side of the vertical plate at intervals;
the laminating couple, the left side of spring all is equipped with the laminating couple, and the first side lever on right side is all hooked to the laminating couple.
Further, the leak protection mechanism includes:
the N-shaped clamping plate is arranged on the fixing plate at the rear side and is contacted with the rear side of the bottom plate;
the baffle is arranged on the rear side of the N-shaped clamping plate;
the rear side of the baffle is provided with a sealing gasket;
the front side of the baffle is provided with an inclined stay bar which is contacted with the rear side of the top of the bottom plate.
Further, still including being used for preventing that the plastic bag is punctured protection machanism, protection machanism is including:
the protective paste is arranged at the top of the right side of the plastic bag;
the pull ring is arranged at the front part of the left side of the protection sticker.
Further, still including being used for the drainage mechanism of drainage, drainage mechanism includes:
the top of the bottom plate is uniformly provided with three drain pipes at intervals;
the filter mantle, the drain pipe outside all is equipped with the filter mantle that is used for filtering the concrete.
Furthermore, the top of the drain pipe is provided with drain holes for draining water at intervals.
Compared with the prior art, the invention has the remarkable improvements that:
1. the second hook can hook the connecting rod, and then the first cutter and the first cutter can cut the rubber bag, so that the glue in the rubber bag leaks out, and the fixing plate and the pressing plate can be stuck, thereby fixing the positions of the left and right side floor bearing plates and facilitating the assembly work of people.
2. The hook plate and the anti-tilting hook can hook the adjacent first side rods, then the vertical plate can be fixed through the hook plate, so that the left side and the right side of the floor support plate are blocked, then the baffle plates are respectively arranged on the front side and the rear side of the floor support plate, so that the front side and the rear side of the floor support plate are blocked, and concrete is prevented from leaking.
3. The protective paste can be pasted above the rubber bag, so that the rubber bag is protected, and people are prevented from pricking the rubber bag carelessly.
Drawings
Fig. 1 is a schematic perspective view of the present invention.
Fig. 2 is a schematic perspective view of a first supporting mechanism according to the present invention.
Fig. 3 is a schematic perspective view of a second supporting mechanism according to the present invention.
Fig. 4 is a schematic perspective view of a third supporting mechanism according to the present invention.
Fig. 5 is a partial perspective view of the present invention.
Fig. 6 is a schematic perspective view of the connection mechanism of the present invention.
Fig. 7 is a partial perspective view of the connection mechanism of the present invention.
Fig. 8 is a perspective view of the protection mechanism and caulking mechanism of the present invention.
Fig. 9 is a schematic perspective view of the protection mechanism of the present invention.
Fig. 10 is a perspective view of the caulking mechanism of the present invention.
Fig. 11 is a schematic perspective view of a first stopping mechanism of the present invention.
Fig. 12 is a schematic perspective view of a second striker mechanism of the present invention.
FIG. 13 is a perspective view of the leakage preventing mechanism of the present invention.
FIG. 14 is a perspective view of a leakage preventing mechanism of the present invention.
Fig. 15 is a schematic perspective view of a first drainage mechanism of the present invention.
Fig. 16 is a schematic perspective view of a second drainage mechanism of the present invention.
In the reference symbols: 1_ bottom plate, 2_ positioning hole, 3_ supporting mechanism, 31_ side supporting rib net, 32_ first side bar, 33_ connecting bar, 34_ second side bar, 35_ transition rib net, 4_ connecting mechanism, 41_ first hook, 42_ second hook, 43_ elastic sheet, 5_ caulking mechanism, 51_ fixing plate, 52_ groove, 53_ first cutter, 54_ rubber bag, 55_ pressing plate, 56_ filling block, 57_ second cutter, 6_ baffle mechanism, 61_ riser, 62_ supporting plate, 63_ sealing plate, 64_ hook plate, 65_ anti-tilting hook, 66_ spring, 67_ fitting hook, 7_ leak-proof mechanism, 71_ mechanical-type clamping plate, 72_ baffle, 73_ sealing pad, 74_ diagonal supporting bar, 8_ protective mechanism, 81_ protective pad, 82_ pull ring, 9_ drainage mechanism, 91_ drainage pipe, 92_ drainage pipe, 93_ filter housing.
Detailed Description
The invention is further explained by combining the drawings in the specification and the embodiments of the invention are given by combining the drawings in the specification.
Example 1
The utility model provides a steel bar truss building carrier plate, refer to fig. 1-14, including bottom plate 1, supporting mechanism 3, coupling mechanism 4, mechanism 5 of caulking, stock stop 6 and leak protection mechanism 7, both sides all opened locating hole 2 around the bottom plate 1 left and right sides, people can fix this steel bar truss building carrier plate through locating hole 2, the top of bottom plate 1 is equipped with supporting mechanism 3, be equipped with coupling mechanism 4 on the supporting mechanism 3, be equipped with mechanism 5 of caulking on the bottom plate 1, 1 right sides of bottom plate are equipped with stock stop 6, 1 rear side of bottom plate is equipped with leak protection mechanism 7.
Referring to fig. 1-4, the supporting mechanism 3 includes side bracing wire netting 31, first side bar 32, connecting rod 33, second side bar 34 and excessive wire netting 35, the top interval welding of bottom plate 1 has three groups of side bracing wire netting 31, the quantity of every group is two, every group is located the side bracing wire netting 31 right side lower part on right side and all is equipped with first side bar 32, all be equipped with connecting rod 33 between the inboard upper portion of every group side bracing wire netting 31, the quantity of connecting rod 33 is three, every group is located left side bracing wire netting 31 left side lower part and all is equipped with second side bar 34, all weld excessive wire netting 35 on the second side bar 34, when people pour concrete on this steel bar truss building carrier plate, side bracing wire netting 31 and excessive wire netting 35 all are located inside the concrete, can improve the bearing capacity of concrete.
Referring to fig. 1, fig. 5, fig. 6 and fig. 7, coupling mechanism 4 is including first crotch 41, second crotch 42 and shell fragment 43, equal interval uniform welding has first crotch 41 on connecting rod 33 on right side and the connecting rod 33 in the middle, first crotch 41 that is located the right side all hooks middle connecting rod 33, be located left first crotch 41 and all hook left connecting rod 33, even interval welding has second crotch 42 on the left connecting rod 33, connecting rod 33 of next building carrier plate can be hooked to second crotch 42, thereby make things convenient for people's equipment work, the equal longitudinal symmetry in left part of second crotch 42 is equipped with shell fragment 43.
Referring to fig. 1, 8, 9 and 10, the caulking mechanism 5 includes a fixing plate 51, first cutters 53, rubber bags 54, a pressing plate 55, filling blocks 56 and second cutters 57, the fixing plate 51 is welded on the rear side and the right side of the top of the bottom plate 1, three grooves 52 are uniformly spaced on the fixing plate 51, two first cutters 53 are disposed in the grooves 52, the first cutters 53 are blades with sharp end faces, the rubber bags 54 are disposed on the top of the fixing plate 51, the pressing plate 55 is welded on the front side and the left side of the bottom plate 1, three filling blocks 56 are uniformly spaced at the bottom of the pressing plate 55, the second cutters 57 are disposed at the bottoms of the filling blocks 56, the second cutters 57 are blades with sharp end faces, and when the rubber bags 54 are cut by the second cutters 57 and the first cutters 53, the glue in the rubber bags 54 leaks out, so as to connect the adjacent floor decks.
Referring to fig. 1, fig. 11 and fig. 12, stock stop 6 is including riser 61, backup pad 62, the closing plate 63, hook plate 64, anti-tilt hook 65, spring 66 and laminating couple 67, closing plate 63 has been placed on bottom plate 1's top right side, closing plate 63 top is equipped with backup pad 62, backup pad 62 right side welding has riser 61, the left and right sides at this floor support board can be installed to riser 61, thereby avoid the concrete to spill, riser 61 bottom is equipped with hook plate 64, the even interval rotary type in left side upper portion of riser 61 is equipped with three anti-tilt hook 65, anti-tilt hook 65 all hooks the first side pole 32 on right side, the even interval in left side lower part of riser 61 is equipped with three springs 66, the left side of spring 66 all is equipped with laminating couple 67, laminating couple 67 all hooks the first side pole 32 on right side.
Referring to fig. 1, 13 and 14, the leakage preventing mechanism 7 includes an N-shaped card plate 71, a baffle plate 72, a sealing pad 73 and an inclined strut 74, the N-shaped card plate 71 is placed on the fixing plate 51 at the rear side, the N-shaped card plate 71 contacts with the rear side of the bottom plate 1, the baffle plate 72 is welded to the rear side of the N-shaped card plate 71, the sealing pad 73 is arranged at the rear side of the baffle plate 72, the inclined strut 74 is arranged at the front side of the baffle plate 72, and the inclined strut 74 contacts with the rear side of the top of the bottom plate 1.
When people need to use the floor support plate, one floor support plate can be placed at a designated position, then the next floor support plate is placed on the right side of the previous floor support plate, the second cutter 57 of the next floor support plate can extrude the rubber bag 54 on the right side of the top of the previous floor support plate, the rubber bag 54 can extend downwards into the groove 52, the second hook 42 of the next floor support plate can hook the connecting rod 33 on the right side of the previous floor support plate, the elastic sheet 43 has a fixing function, when the rubber bag 54 is cut by the first cutter 53 and the second cutter 57, the glue in the rubber bag 54 can leak out, the filling block 56 can extend into the corresponding groove 52 at the moment, the effect of filling and sealing is achieved, the fixing plate 51 and the pressing plate 55 can be adhered under the action of the glue, so that the floor support plates on the left side and the right side can be fixed, the splicing and assembling of a plurality of floor support plates can be realized repeatedly, then, people can put the next floor bearing plate to the rear side of the previous floor bearing plate according to the needs, the same can be obtained, under the effect of glue, the fixing plate 51 and the pressing plate 55 can be stuck, thereby the floor bearing plates on the front side and the rear side can be fixed, after all the floor bearing plates are completely spliced and assembled, the floor bearing plates are fixed through the positioning holes 2, then the second hook 42 on the leftmost floor bearing plate is sawn off according to the needs, then the sealing plates 63 are respectively arranged on the left side of the top of the leftmost floor bearing plate and the right side of the top of the rightmost floor bearing plate, so that the vertical plates 61 respectively block the left side and the right side of the floor bearing plate, the hook plates 64 can hook the adjacent bottom plate 1, then the anti-inclination hook 65 and the laminating hook 67 are respectively hooked on the adjacent first side rod 32, the spring 66 is stretched, thereby the vertical plates 61 are fixed, and the sealing plates 63 play a sealing role, then all place N shape cardboard 71 at the building carrier plate top front side of foremost and the building carrier plate top rear side of rearmost, make baffle 72 block the front and back both sides of building carrier plate respectively, diagonal brace 74 plays supporting role, sealed pad 73 can laminate the wall, then pour the concrete into on the building carrier plate that the equipment is good, baffle 72 and riser 61 homoenergetic block the concrete, thereby it is spacing to carry out the concrete, make the height of concrete can be higher than first crotch 41 and second crotch 42, then wait for the concrete to solidify can, side brace muscle net 31 and excessive muscle net 35 are all inside the concrete, and interval arrangement, thereby can improve the bearing capacity of concrete.
Example 2
On the basis of embodiment 1, referring to fig. 1, 8 and 9, the protective device further comprises a protective mechanism 8, wherein the protective mechanism 8 comprises a protective sticker 81 and a pull ring 82, the protective sticker 81 is arranged on the top of the right side of the plastic bag 54, the protective sticker 81 can protect the plastic bag 54, and the pull ring 82 is arranged on the front portion of the left side of the protective sticker 81.
Protection paste 81 can protect the plastic bag 54 on right side, avoid people to prick the plastic bag 54 carelessly, when people need use this building carrier plate, can be with the pull ring 82 of every building carrier plate up the pulling, thereby drive protection paste 81 up the motion, make protection paste 81 and plastic bag 54 separation, then can splice the equipment to every building carrier plate, also can paste protection paste 81 on the plastic bag 54 that does not need to use, thereby protect.
Referring to fig. 5, 15 and 16, the water discharging device 9 is further included, the water discharging device 9 includes a water discharging pipe 91 and a filter cover 93, three water discharging pipes 91 are uniformly arranged on the top of the bottom plate 1 at intervals, the water discharging holes 92 are uniformly arranged on the top of the water discharging pipe 91 at intervals, the filter cover 93 is arranged on the outer side of the water discharging pipe 91, and after people pour concrete on the floor support plate, the filter cover 93 can filter the concrete, so that water is discharged through the water discharging pipe 91.
The in-process that the concrete solidifies, have during moisture passes through filter mantle 93 and wash port 92 gets into drain pipe 91 to discharge outward through drain pipe 91, filter mantle 93 can filter the concrete, avoids the concrete to get into in the drain pipe 91.
Finally, it is necessary to mention that: the above-mentioned contents are only used to help understanding the technical solution of the present invention, and should not be interpreted as limiting the scope of the present invention; insubstantial modifications and adaptations of the invention as described above will occur to those skilled in the art and are intended to be within the scope of the invention as claimed.

Claims (5)

1. The utility model provides a steel bar truss building carrier plate which characterized in that, including:
the steel bar truss floor support plate comprises a bottom plate (1) and support mechanisms (3), wherein positioning holes (2) for mounting steel bar truss floor support plates are formed in the front side and the rear side of the left part and the right part of the bottom plate (1), and the support mechanisms (3) for improving the bearing capacity of the steel bar truss floor support plates are arranged at the top of the bottom plate (1);
the connecting mechanism (4) is arranged on the supporting mechanism (3), and the connecting mechanism (4) is convenient for splicing steel bar truss floor bearing plates;
the bottom plate (1) is provided with a caulking mechanism (5) for fixing two adjacent steel bar truss floor bearing plates;
the right side of the bottom plate (1) is provided with the stock stop (6) for preventing concrete from leaking;
the rear side of the bottom plate (1) is provided with a leakage-proof mechanism (7) for preventing concrete from leaking; the support mechanism (3) comprises:
the top of the bottom plate (1) is provided with three groups of side supporting rib nets (31) at intervals;
the lower part of the right side of each group of the side supporting rib nets (31) positioned on the right side is provided with a first side rod (32);
the connecting rods (33) are arranged between the upper parts of the inner sides of each group of side supporting rib nets (31);
the lower part of the left side of each group of the side supporting rib nets (31) positioned on the left side is provided with a second side lever (34);
the second side rods (34) are provided with transition rib nets (35); the connecting mechanism (4) comprises:
the first hooks (41) are uniformly arranged on the right connecting rod (33) and the middle connecting rod (33) at intervals, the middle connecting rod (33) is hooked by the first hooks (41) on the right side, and the left connecting rod (33) is hooked by the first hooks (41) on the left side;
the connecting rod (33) on the left side of the second hook (42) is provided with the second hook (42) at uniform intervals;
the elastic sheets (43) are symmetrically arranged at the upper and lower parts of the left part of the second hook (42); the caulking mechanism (5) comprises:
the rear side and the top right side of the bottom plate (1) are respectively provided with a fixed plate (51), and the fixed plates (51) are uniformly provided with three grooves (52) at intervals;
the first cutters (53), two first cutters (53) are arranged in the grooves (52);
the top of the fixing plate (51) is provided with a rubber bag (54);
the pressing plates (55) are arranged on the front side and the left side of the bottom plate (1);
the bottom of the pressing plate (55) is uniformly provided with three filling blocks (56) at intervals;
the bottom of each filling block (56) is provided with a second cutter (57); stock stop (6) including:
the sealing plate (63) is arranged on the right side of the top of the bottom plate (1);
the top of the sealing plate (63) is provided with the supporting plate (62);
the vertical plate (61) is arranged on the right side of the supporting plate (62);
the bottom of the vertical plate (61) is provided with a hook plate (64);
the anti-tilt hook comprises anti-tilt hooks (65), wherein three anti-tilt hooks (65) are uniformly and rotatably arranged on the upper part of the left side of a vertical plate (61) at intervals, and the anti-tilt hooks (65) hook a first side rod (32) on the right side;
three springs (66) are uniformly arranged at intervals on the lower part of the left side of the vertical plate (61);
laminating couple (67), the left side of spring (66) all is equipped with laminating couple (67), and laminating couple (67) all hooks first side pole (32) on right side.
2. A steel bar truss floor deck as claimed in claim 1 wherein the leakage preventing means (7) comprises:
the N-shaped clamping plate (71) is placed on the fixing plate (51) on the rear side, and the N-shaped clamping plate (71) is in contact with the rear side of the bottom plate (1);
the baffle (72) is arranged on the rear side of the N-shaped clamping plate (71);
a sealing gasket (73), wherein the sealing gasket (73) is arranged on the rear side of the baffle plate (72);
the front side of the baffle plate (72) is provided with the inclined supporting rod (74), and the inclined supporting rod (74) is in contact with the rear side of the top of the bottom plate (1).
3. The steel bar truss floor deck according to claim 2, further comprising a protection mechanism (8) for preventing the rubber bag (54) from being punctured, wherein the protection mechanism (8) comprises:
the protective paste (81) is arranged at the top of the right side rubber bag (54);
the pull ring (82) is arranged at the front part of the left side of the protective sticker (81).
4. A steel bar truss floor deck according to claim 3, further comprising a drainage mechanism (9) for draining water, wherein the drainage mechanism (9) comprises:
the top of the bottom plate (1) is uniformly provided with three drain pipes (91) at intervals;
the outer sides of the filter cover (93) and the drain pipe (91) are provided with the filter cover (93) for filtering concrete.
5. The steel bar truss floor deck as claimed in claim 4, wherein drain holes (92) for draining water are spaced at the top of the drain pipes (91).
CN202111394162.4A 2021-11-23 2021-11-23 Steel bar truss floor support plate Active CN114108916B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111394162.4A CN114108916B (en) 2021-11-23 2021-11-23 Steel bar truss floor support plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111394162.4A CN114108916B (en) 2021-11-23 2021-11-23 Steel bar truss floor support plate

Publications (2)

Publication Number Publication Date
CN114108916A CN114108916A (en) 2022-03-01
CN114108916B true CN114108916B (en) 2023-01-17

Family

ID=80440219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111394162.4A Active CN114108916B (en) 2021-11-23 2021-11-23 Steel bar truss floor support plate

Country Status (1)

Country Link
CN (1) CN114108916B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118087770A (en) * 2024-04-26 2024-05-28 淄博儒创建材科技有限公司 Steel bar truss floor support plate and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20007312U1 (en) * 2000-04-20 2000-07-27 Filigran Traegersysteme Component and lattice girder
CN107882244A (en) * 2017-11-07 2018-04-06 天津亿迅源金属制品有限公司 A kind of construction method of steel bar truss floor support plate
CN109025018A (en) * 2018-08-20 2018-12-18 四川新恒钢建材有限公司 A kind of the steel bar truss floor support plate structure and its construction method of removable bed die
CN110424619A (en) * 2019-07-22 2019-11-08 东莞市建工集团有限公司 A kind of building block and the crack resistence technique using the building block
CN111502091A (en) * 2020-05-28 2020-08-07 佛山市高明长峰建设工程有限公司 Building floor with long service life and preparation method thereof
CN112095877A (en) * 2020-08-28 2020-12-18 中冶(上海)钢结构科技有限公司 Steel bar net type floor support plate and mounting method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20007312U1 (en) * 2000-04-20 2000-07-27 Filigran Traegersysteme Component and lattice girder
CN107882244A (en) * 2017-11-07 2018-04-06 天津亿迅源金属制品有限公司 A kind of construction method of steel bar truss floor support plate
CN109025018A (en) * 2018-08-20 2018-12-18 四川新恒钢建材有限公司 A kind of the steel bar truss floor support plate structure and its construction method of removable bed die
CN110424619A (en) * 2019-07-22 2019-11-08 东莞市建工集团有限公司 A kind of building block and the crack resistence technique using the building block
CN111502091A (en) * 2020-05-28 2020-08-07 佛山市高明长峰建设工程有限公司 Building floor with long service life and preparation method thereof
CN112095877A (en) * 2020-08-28 2020-12-18 中冶(上海)钢结构科技有限公司 Steel bar net type floor support plate and mounting method thereof

Also Published As

Publication number Publication date
CN114108916A (en) 2022-03-01

Similar Documents

Publication Publication Date Title
CN114108916B (en) Steel bar truss floor support plate
CN112081068A (en) Combined box type flood control sub-dike and emergency rescue method thereof
WO2003016178A1 (en) Oil storage tank equipped with a floating roof means of floating bed type
CN108660934B (en) Joint grout stopping device for steel-concrete combined section and construction method thereof
CN220167197U (en) Basement bottom plate post-pouring belt structure
CN213014510U (en) Combined surface energy waterproof system
CN210508500U (en) Container formula fire station with function gives sound insulation
CN214941148U (en) Assembled combined surface energy waterproof system
CN210454501U (en) Outdoor electric pile base that fills of water permeability
CN208718191U (en) Pin-connected panel precast floor slab
CN112196193A (en) Combined surface energy waterproof system
CN216379132U (en) Energy-saving bridge expansion joint structure
CN207794005U (en) A kind of indentation project under construction flood water-bound
CN212335693U (en) Highway prevents stifled drainage system
CN212533926U (en) Combined box type flood control sub-dike
CN111089214A (en) PVC sheet drain pipe with base lining
CN218090710U (en) Assembled flood-fighting wall
CN214005395U (en) Bridge diversion area
CN211113436U (en) Firm and reliable wharf structure
CN219710608U (en) Waterproof construction of construction joint
CN211200647U (en) Town road drainage device
CN219118245U (en) Advanced water-stop plugging structure for post-pouring belt
CN213476521U (en) Sponge city ecological road roadbed structure
CN215758598U (en) Rainwater box culvert structure
CN212358539U (en) Novel drainage equipment of integrative structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 336000 No. 77, Yanjiang South Road, Zhangshu City, Yichun City, Jiangxi Province

Patentee after: Jianbang Technology Group Co.,Ltd.

Address before: 331200 No. 77, Yanjiang South Road, Zhangshu City, Yichun City, Jiangxi Province

Patentee before: Jiangxi Jianbang Construction Group Co.,Ltd.