CN114059705A - Novel construction method for sponge type large-area planting laminated plate roof - Google Patents

Novel construction method for sponge type large-area planting laminated plate roof Download PDF

Info

Publication number
CN114059705A
CN114059705A CN202010772448.0A CN202010772448A CN114059705A CN 114059705 A CN114059705 A CN 114059705A CN 202010772448 A CN202010772448 A CN 202010772448A CN 114059705 A CN114059705 A CN 114059705A
Authority
CN
China
Prior art keywords
layer
roofing
planting
roof
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010772448.0A
Other languages
Chinese (zh)
Inventor
徐宜军
丁华
王强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010772448.0A priority Critical patent/CN114059705A/en
Publication of CN114059705A publication Critical patent/CN114059705A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/20Roofs consisting of self-supporting slabs, e.g. able to be loaded
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/48Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/20Roofs consisting of self-supporting slabs, e.g. able to be loaded
    • E04B7/22Roofs consisting of self-supporting slabs, e.g. able to be loaded the slabs having insulating properties, e.g. laminated with layers of insulating material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/02Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/254Roof garden systems; Roof coverings with high solar reflectance
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B80/00Architectural or constructional elements improving the thermal performance of buildings
    • Y02B80/32Roof garden systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Cultivation Of Plants (AREA)

Abstract

A novel construction method for a sponge type large-area planting laminated plate roof belongs to the technical field of building construction. It comprises the following steps: prepare before the construction, inspection before the superimposed sheet installation sets up the superimposed sheet support, and the superimposed sheet hoist and mount, pipeline laying, installation superimposed sheet upper reinforcing bar pour the concrete screed-coat, set up the vapour barrier, set up the waterproof layer, roofing basic unit is handled, and the roofing module is planted to the sponge type is laid, maintains and maintains. The problem of the quality of superimposed sheet roofing retaining antiseep is solved to realize the roofing and plant the flower bed under the prerequisite that satisfies the load requirement.

Description

Novel construction method for sponge type large-area planting laminated plate roof
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a novel construction method for a sponge type large-area planting laminated plate roof.
Background
At present, the development of green building accords with the requirement of trend of times, and roofing afforestation is the important aspect that influences building quality and building quality, and roof or roofing that adopt traditional design method to construct have the bearing, roofing drainage difficulty, the durability is poor easily the seepage, energy-conserving effect quality problems such as not good, these become the bottleneck problem and the restriction factor in roofing structure and the work progress, for this reason, the adoption of the novel roofing that adapts to green building and assembly type building construction is urgent.
Disclosure of Invention
Aiming at the problems in the prior art, the invention aims to provide a novel construction method for a sponge type large-area planting laminated slab roof.
A novel construction method for a sponge type large-area planting laminated slab roof is characterized in that preparation is carried out before construction, the laminated slab is checked before installation, a laminated slab support is arranged, the laminated slab is hoisted, a pipeline is laid, upper-layer steel bars of the laminated slab are installed, a concrete leveling layer is poured, a steam barrier layer is arranged, a waterproof layer is arranged, a roof base layer is treated, and a sponge type planting roof module is laid, maintained and maintained.
The novel construction method of the sponge large-area planting laminated slab roof is characterized in that a horizontal component of the laminated slab is used as a structural functional layer, and a sponge large-area planting laminated slab roof structure with heat preservation, heat insulation, seepage resistance, energy conservation and environmental protection effects is formed by constructing a steam-proof layer, a heat preservation and insulation layer and a protective layer thereof, a waterproof layer, an ecological planting box, a planting soil layer, a vegetation layer and the like.
The novel construction method for the sponge large-area planting laminated plate roof is characterized in that the sponge large-area planting laminated plate roof can synchronously construct a water storage and drainage layer, a filter layer and a planting soil layer, a root penetration resistant waterproof layer and a protection layer used in the traditional method can be omitted, and the construction progress is remarkably accelerated.
The novel construction method for the sponge large-area planting laminated plate roof is characterized in that a water storage tank at the bottom of a planting soil layer of the sponge large-area planting laminated plate planting roof can freely discharge rainwater, debugging water and other external water during construction and operation, so that the heat preservation and heat insulation functions of the roof are not influenced by stagnant water, and damage caused by frost heaving of water in a roof structure layer is avoided.
The novel construction method for the sponge type large-area planting laminated plate roof is characterized in that the laminated plate roof is constructed by subsection synchronous hoisting, the anti-leakage effect of the water storage roof is outstanding, the maintenance is convenient, self ecological restoration can be formed, and stable operation and long-acting preservation are further ensured.
Detailed Description
The invention is further described below, but the scope of protection of the invention is not limited thereto:
the invention relates to a novel construction method for a sponge type large-area planting laminated plate roof, which comprises the following steps:
1) preparation before construction: preparing materials, instruments and the like for standby;
2) inspecting the laminated slab before installation: checking the horizontal elevation of the support: and measuring the top surface elevations of the horizontal ridges of the wall, the beam and the frame body from two different observation points by using a measuring instrument, wherein when the laminated slab is installed, the maximum allowable value of the height of the supporting top is L/700 and is less than or equal to 5mm, 5mm is on the horizontal line, and 5mm is below the horizontal line.
3) Setting a laminated slab support: the phi 48 multiplied by 2.75mm full steel pipe fastener type scaffold has the vertical and horizontal distances of the upright posts of 1000mm, the step distance of the scaffold of 1.8m, and the supports are erected in a mode of sharing the beam plate and the upright posts. 38 multiplied by 88 battens are fully paved on the horizontal steel pipe at the top of the laminated slab support, the distance is 250mm, 915 multiplied by 1830 plywood templates with the thickness of 13mm are fully paved on the laminated slab support, the laminated slab support in the middle skip layer area of 23-24/C-F shafts of 1# main building, 18-19/L-N shafts of 1# skirt house and 11-12/C-F shafts of 2# skirt house is in a high formwork supporting range, the full steel pipe fastener type scaffold with the vertical and transverse distances of 900mm is supported, and the step distance of the scaffold is 1.5 m. The support is built in a mode of sharing beam plates and upright columns.
4) Hoisting the laminated slab: the laminated slab is hoisted by a tower crane, 4 hoisting points are used for hoisting each floor slab, and lifting hooks are embedded at the positions of the hoisting points. The hoisting cable chain adopts a special cable chain and 4 closed lifting hooks, the stress is averagely shared, the multipoint balanced hoisting is carried out, the length of a single cable chain is not less than 4m, the gravity centers of a main lifting hook, a hoisting tool and a component of the hoisting equipment are ensured to be superposed in the vertical direction in the hoisting process, the horizontal included angle between the hoisting cable and the component is not less than 60 degrees, the stability is ensured as much as possible in the hoisting process, the inclination and the large-amplitude swing are avoided, the horizontal component is hoisted to about 200mm away from the ground in the hoisting process, whether the hoisting cable has a skew twist or a clamping phenomenon or not and the stress of each hoisting point is uniform in hovering inspection, when the installation position of the composite slab component is close to 600mm, the component is supported by hand and then slowly descends to be in place, the component is hoisted to the same direction in sequence, and the prefabricated composite slab is hoisted slowly to avoid impact; the method comprises the steps of entering a seat according to a design drawing or a mounting layout of the laminated slab, slightly adjusting alignment according to the laying length of a support required by the drawing by using a crowbar, tightening a lifting rope by using a tower crane if necessary, arranging anchoring steel bars thrown out from two ends of the prefabricated laminated slab in time after the prefabricated laminated slab is mounted in place, connecting the anchoring steel bars of the laminated floor slab with opposite plate steel bars, and preventing the floor slab from being bent upwards or downwards to be vertical to the surface of the plate and pressing the floor slab below the plate. And the length of the anchoring reinforcing steel bar extending over the center line of the beam is ensured to be not less than 5d, after the floor slab is laid, the lower edge of the slab should not be uneven, gaps should not appear, gaps at the positions of the supports which cannot be locally adjusted and avoided should be plugged, and the supporting upright rods can be properly adjusted, so that the bottom surface of the slab is kept flat and seamless.
5) Installing upper-layer steel bars of the floor slab: 1/water and electricity pipeline lays and inspects qualified back installation floor upper reinforcing bar, roof reinforcing bar lays the direction and lays according to the construction scheme, because of the truss direction is different, require lower floor's reinforcing bar to lay under the truss, it is inseparable to combine with prefabricated floor to water the layer after guaranteeing, for reinforcing bar and the template that the protection has been laid, lay the wooden springboard when inspection is accepted and concreting is gone up in order to avoid the reinforcing bar to receive to trample and cause the reinforcing bar protective layer to be too thick, the reinforcing bar must not cut off at will, need to break the reinforcing bar with the fingers and thumb in order to guarantee that the reinforcing bar is complete if the entrance to a cave.
6) Pouring a concrete leveling layer: before concrete pouring, sundries on the laminated floor slab should be cleaned and sprinkled with water for moistening, but no open water should be used. The concrete of the superposed layer is compactly vibrated to ensure that the superposed layer and the prefabricated layer are combined into a whole, after the post-cast layer is poured, the plastic film is adopted for covering and curing for 8-12 h, the curing time is at least 7d, the curing time can be prolonged when the temperature is the highest in summer, the concrete pouring mix proportion and the heat preservation measure are paid attention to during the construction in winter, and the construction in winter is avoided as far as possible because the post-cast layer is thinner.
7) Setting a steam-isolating layer: the PE film is selected as the steam-proof layer in the steel structure roof system, the proper thickness of the PE film is 0.3 mm, the rubber adhesive tape is adopted to process the seam of the PE film in the construction process, the steam-proof layer is guaranteed to be airtight, and meanwhile the PE film on the peripheral equal details and the whole roof are guaranteed to form an airtight whole.
8) Laying a sponge type planting layer module: the material for laying the filter layer is preferably 150g of non-woven fabric and ceramsite, so that the water permeability and air permeability of the movable greening module are ensured, and the non-woven geotextile roll is prevented from being damaged before being installed and unfolded. The geotextile rolls are piled in flat places without water accumulation, the pile height is not more than four rolls, and the geotextile rolls are required to be covered by opaque materials to prevent ultraviolet aging. The integrity of the label is kept during the carrying and storing processes of the geotextile, the handwriting is clear and recognizable, a worker can cut the geotextile after straightening two sides when cutting the non-woven fabric, a layer of ceramsite is paved at the bottom of the container, 150g of non-woven fabric is paved, the total thickness is 10 mm-20 mm, a matrix is paved, the matrix is uniformly paved in a movable greening module in advance before planting, the thickness is generally 80-100 mm, the greening module adopts a special roof greening planting matrix, a keel is paved, and angle steel is used as a supporting clamping groove at the back on the roof anti-skid shelter to serve as a welding foundation. The length of the foundation angle steel is 10 mm-20 mm longer than the width of the angle steel, one edge of the foundation angle steel is aligned with the anti-skidding shielding during welding, the foundation angle steel is welded in a lap-joint welding mode, 1-3 layers of side welding seams are welded between the steel bar and an angle steel base plate, the welding seams are full, the surfaces of the welding seams do not have defects or weakening phenomena, the supporting angle steel and the foundation angle steel can be welded after the foundation angle steel is welded and checked to be correct, and the lap-joint welding mode is mainly used in the same way.

Claims (5)

1. The utility model provides a novel construction method of plywood roofing is planted to sponge type large tracts of land, prepares before its characterized in that construction, and the inspection is set up the plywood and is supported before the plywood installation, and the plywood hoist and mount, pipeline laying, installation superimposed sheet upper reinforcing bar, concreting screed-coat sets up the vapour barrier, sets up the waterproof layer, and roofing basic unit handles, and the roofing module is planted to the sponge type, maintains and maintains.
2. The method as claimed in claim 1, wherein the horizontal component of the laminated slab is used as a structural function layer, and the construction of the steam-proof layer, the thermal insulation layer and its protective layer, the waterproof layer, the ecological planting box, the planting soil layer, the vegetation layer, etc. is performed to form the sponge-type large-area planting laminated slab roof structure with thermal insulation, anti-seepage, energy saving and environmental protection effects.
3. The novel construction method for the sponge type large-area planting laminated slab roof as claimed in claim 2, wherein the construction of the sponge type laminated slab planting roof can be synchronously performed by three processes of water storage and drainage layer, filtering layer and planting soil layer, so that a root penetration resistant waterproof layer and a protective layer used in the traditional method can be omitted, and the construction progress is remarkably accelerated.
4. The method as claimed in claim 3, wherein the bottom reservoir of the planting soil layer of the sponge-type large-area planting laminated slab roofing can freely drain rainwater, test water and other external water during construction and operation, thereby ensuring that the thermal insulation function of the roofing is not affected by stagnant water and avoiding damage caused by frost heaving of water in the structural layer of the roofing.
5. The method for constructing a novel sponge type large-area planting laminated slab roof as claimed in claim 4, wherein the laminated slab roof is constructed by subsection synchronous hoisting, the leakage-proof effect of the water storage roof is outstanding, the maintenance is convenient, self-ecological restoration can be formed, and stable operation and long-term preservation are ensured.
CN202010772448.0A 2020-08-04 2020-08-04 Novel construction method for sponge type large-area planting laminated plate roof Withdrawn CN114059705A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010772448.0A CN114059705A (en) 2020-08-04 2020-08-04 Novel construction method for sponge type large-area planting laminated plate roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010772448.0A CN114059705A (en) 2020-08-04 2020-08-04 Novel construction method for sponge type large-area planting laminated plate roof

Publications (1)

Publication Number Publication Date
CN114059705A true CN114059705A (en) 2022-02-18

Family

ID=80231865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010772448.0A Withdrawn CN114059705A (en) 2020-08-04 2020-08-04 Novel construction method for sponge type large-area planting laminated plate roof

Country Status (1)

Country Link
CN (1) CN114059705A (en)

Similar Documents

Publication Publication Date Title
CN102392549B (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN107882321A (en) Diameter Silo slding form operation engineering method
CN108677962B (en) Subway entrance and exit segment foundation pit formwork installing and dismantling method
CN104234012A (en) Ultralong concrete slip form body of concrete rockfill dam and construction method of slip form body
CN104894954B (en) Urban Bridge pier stud reinforcing bar integral installation construction method
CN110984210A (en) Iron frame foundation of power transmission line and construction method
CN108342993B (en) Underwater bearing platform suspension supporting platform and construction method thereof
CN108457243A (en) A kind of construction method of assembly concrete wave wall
CN110939051A (en) Subway hidden cover beam construction method
CN111809951A (en) Prefabricated assembled water pool and assembling method
CN113202222A (en) Construction method for assembled type superposed beam slab
CN110593477B (en) Construction method of cast-in-situ reinforced concrete special-shaped inclined plate
CN103615076A (en) Concrete construction method for big-gradient sloping roof
CN113653272B (en) Archaized eave of steel structure of high-rise building and construction method thereof
CN108756039A (en) floor construction method
CN114059705A (en) Novel construction method for sponge type large-area planting laminated plate roof
CN209293068U (en) A kind of open trench tunnel falsework system
CN111364622A (en) Construction method of long-span arched net rack strip-shaped building
CN116145675A (en) Construction method of large-volume concrete based on roof foundation bearing platform
CN211775864U (en) Double-deck chute concrete placement system
KR102291683B1 (en) Construction method of flowerbed boundary using boundary plate
CN108442598A (en) Rack and steel truss light composite board Combined roof construction
CN110258890B (en) Construction method of concrete structure with connected broken line type outer wall and roof
CN113266035A (en) Construction method for upper structure of steam turbine base
CN211736089U (en) Tower crane penetrating structure waterproof device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20220218