CN114049002A - Wind power plant construction project construction plan and progress optimization scheduling management system - Google Patents

Wind power plant construction project construction plan and progress optimization scheduling management system Download PDF

Info

Publication number
CN114049002A
CN114049002A CN202111330103.0A CN202111330103A CN114049002A CN 114049002 A CN114049002 A CN 114049002A CN 202111330103 A CN202111330103 A CN 202111330103A CN 114049002 A CN114049002 A CN 114049002A
Authority
CN
China
Prior art keywords
construction
progress
project
plan
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202111330103.0A
Other languages
Chinese (zh)
Inventor
张明杰
孟欣
王献文
王学平
邢李方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhenlai Wind Power Plant of Huaneng Jilin Power Generation Co Ltd
Original Assignee
Zhenlai Wind Power Plant of Huaneng Jilin Power Generation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhenlai Wind Power Plant of Huaneng Jilin Power Generation Co Ltd filed Critical Zhenlai Wind Power Plant of Huaneng Jilin Power Generation Co Ltd
Priority to CN202111330103.0A priority Critical patent/CN114049002A/en
Publication of CN114049002A publication Critical patent/CN114049002A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/101Collaborative creation, e.g. joint development of products or services
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • General Health & Medical Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a wind power plant construction project construction plan and progress optimizing scheduling management system, which comprises a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction plan unit and a construction progress optimizing unit; according to the wind power plant construction project construction plan and progress optimizing and scheduling management system provided by the structure, the progress of each sub project is planned and monitored through the intelligent management system, the difference between the current construction progress and the planned construction progress is calculated, the construction plan is completed with guaranteed quality and quantity, the current construction progress of the total project is visually displayed through the plan completion ratio of the sub projects which are constructed and are not constructed in each part of project, and the personnel and material resources in the construction task are conveniently adjusted through the data by engineering management personnel, so that the current construction progress is effectively adjusted in real time.

Description

Wind power plant construction project construction plan and progress optimization scheduling management system
Technical Field
The invention relates to the technical field of construction project schedule, in particular to a wind power plant construction project construction plan and schedule optimization scheduling management system.
Background
At present, in the construction project implementation process of the building engineering, project progress data information is usually recorded in a form that engineering technicians manually record or input carriers such as computers, and due to the fact that work technicians have a plurality of problems of lagging and being prone to making mistakes when recording data, progress management of the construction project cannot be timely mastered, the construction progress is prone to being slow in progress and difficult to guarantee quality and guarantee quantity to complete the construction plan.
Disclosure of Invention
Based on the technical problems in the prior art, the invention provides a wind power plant construction project construction plan and progress optimization scheduling management system, and solves the problems that the progress of each part in construction of a construction project is different, and the construction progress cannot be accurately mastered.
The invention provides a wind power plant construction project construction plan and progress optimizing and scheduling management system, which comprises a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction plan unit and a construction progress optimizing unit;
the construction management system is a system for realizing efficient construction by performing collection management on all production data of the construction of the whole project according to the construction requirements of a project contracting party;
the construction scheduling system schedules factors influencing construction progress in the construction process according to the instruction requirements of the construction management system so as to realize that the overall construction progress is promoted according to a plan;
the construction monitoring system realizes the planned construction progress by monitoring the actual construction progress and acquiring factors influencing the construction progress;
and the construction early warning system compares the plan of the construction management system with the actual construction progress to realize the early warning function of the construction progress.
Further, the construction management system comprises a total package project management subsystem, a sub-package project management subsystem and an engineering management center, wherein the total package project management subsystem manages the construction of a total package project, and the sub-package project management subsystem manages the construction of a sub-package project.
Further, the total package project management subsystem comprises a total package construction planning unit and a total package progress optimization unit, wherein the total package construction planning unit comprises a capital construction planning module, a main body installation planning module, a supporting facility installation planning module and an operation debugging planning module.
Further, the sub-package project management subsystem comprises a sub-package construction planning unit and a sub-package progress optimization unit, wherein the sub-package construction planning unit comprises a supporting facility installation planning module and an auxiliary facility construction planning module.
Further, the total package construction planning unit and the sub-package construction planning unit carry out BIM model based on construction drawings, and the BIM model is led into a construction management system; the construction management system distributes project classification to a total package project management subsystem, a sub-package project management subsystem and an engineering management center, and associates the BIM with a construction progress plan; and the construction management is carried out by the three-dimensional visual BIM model.
Furthermore, the construction scheduling system receives the real-time construction progress of the construction monitoring system, compares the real-time construction progress with the planned construction progress, analyzes and obtains an over-progress construction sub-project, a synchronous progress sub-project and a backward progress sub-project, converts the analysis data into a visual chart and sends the visual chart to a total package progress optimizing unit, a sub-package progress optimizing unit and a construction early warning system, the total package progress optimizing unit and the sub-package progress optimizing unit optimize and analyze specific factors and send the factors to a construction field team, and problem reasons are obtained through feedback of the construction field team.
Further, the construction monitoring system comprises a material management unit, a team work log unit and a field imaging unit, wherein the material management unit adopts label access management, all materials in a project field are input into a label system, a label is used for scanning codes to access, the team work log unit collects the day work records of workers, the field imaging unit utilizes a camera device and computer analysis software to estimate the construction progress in proportion, the real-time actual construction progress is comprehensively calculated through the data of the material management unit, the team work log unit and the field imaging unit, and the actual construction progress is sent to the construction scheduling system.
And further, the construction early warning system receives data of the construction monitoring system and the construction scheduling system, and collects and classifies factors influencing construction progress and sends the factors to an engineering command center.
Furthermore, the construction management system also comprises an epidemic situation management unit and an emergency management unit, wherein the epidemic situation management unit is in real-time communication with a national health department data center and regulates and controls project construction progress in real time according to epidemic situation; and the emergency management unit is in real-time communication with a national emergency department data center and regulates and controls project construction progress in real time according to emergency conditions.
And further setting the planned schedule time to be consistent with the actual schedule time, comparing whether the real-time space position lags behind the planned space position, and comparing the real-time construction schedule with the planned construction schedule according to the corresponding relation between the space position and the construction schedule.
The wind power plant construction project construction plan and progress optimizing scheduling management system provided by the invention has the advantages that: according to the wind power plant construction project construction plan and progress optimizing and scheduling management system provided by the structure, the progress of each sub project is planned and monitored through the intelligent management system, the difference between the current construction progress and the planned construction progress is calculated, the construction plan is completed with guaranteed quality and quantity, the current construction progress of the total project is visually displayed through the plan completion ratio of the sub projects which are constructed and are not constructed in each part of project, and the personnel and material resources in the construction task are conveniently adjusted through the data by engineering management personnel, so that the current construction progress is effectively adjusted in real time.
Drawings
Fig. 1 is a schematic structural diagram of a wind power plant construction project construction plan and progress optimization scheduling management system provided by the invention.
Detailed Description
As shown in fig. 1, fig. 1 is a wind farm construction project construction plan and progress optimization scheduling management system disclosed by the invention, and solves the problems that the progress of each part in construction of a construction project is different and the construction progress cannot be accurately mastered.
Referring to fig. 1, the construction planning and progress optimizing and scheduling management system for the wind power plant construction project, provided by the invention, comprises a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction planning unit and a construction progress optimizing unit;
the construction management system is a system for realizing efficient construction by performing collection management on all production data of the construction of the whole project according to the construction requirements of a project contracting party; the construction management system comprises a main package project management subsystem, a sub-package project management subsystem and an engineering management center, wherein the main package project management subsystem manages the construction of a main package project, and the sub-package project management subsystem manages the construction of sub-package projects. The total package project management subsystem comprises a total package construction planning unit and a total package progress optimization unit, wherein the total package construction planning unit comprises a capital construction planning module, a main body installation planning module, a supporting facility installation planning module and an operation debugging planning module. The sub-package project management subsystem comprises a sub-package construction planning unit and a sub-package progress optimization unit, wherein the sub-package construction planning unit comprises a supporting facility installation planning module and an auxiliary facility construction planning module. The total package construction planning unit and the sub-package construction planning unit carry out BIM model based on construction drawings, and the BIM model is led into a construction management system; the construction management system distributes project classification to a total package project management subsystem, a sub-package project management subsystem and an engineering management center, and associates the BIM with a construction progress plan; and the construction management is carried out by the three-dimensional visual BIM model. Setting the planned progress time to be consistent with the actual progress time, comparing whether the real-time space position lags behind the planned space position, and comparing the real-time construction progress with the planned construction progress according to the corresponding relation between the space position and the construction progress.
The construction scheduling system schedules factors influencing construction progress in the construction process according to the instruction requirements of the construction management system so as to realize that the overall construction progress is promoted according to a plan; the construction scheduling system receives the real-time construction progress of the construction monitoring system, compares the real-time construction progress with the planned construction progress, analyzes and obtains an over-progress construction sub-project, a synchronous progress sub-project and a behind-progress sub-project, converts analysis data into a visual chart and sends the visual chart to a total package progress optimizing unit, a sub-package progress optimizing unit and a construction early warning system, the total package progress optimizing unit and the sub-package progress optimizing unit optimize and analyze specific factors and send the factors to a construction field team, and problem reasons are obtained through feedback of the construction field team.
The construction monitoring system realizes the planned construction progress by monitoring the actual construction progress and acquiring factors influencing the construction progress; the construction monitoring system comprises a material management unit, a team work log unit and a field imaging unit, wherein the material management unit adopts label access management, all materials in a project field are input into a label system, a label is used for scanning a code to access, the team work log unit collects the day work record of workers, the field imaging unit utilizes a camera device and computer analysis software to estimate the construction progress in proportion, the real-time actual construction progress is comprehensively calculated through the data of the material management unit, the team work log unit and the field imaging unit, and the actual construction progress is sent to the construction scheduling system.
And the construction early warning system compares the plan of the construction management system with the actual construction progress to realize the early warning function of the construction progress. And the construction early warning system receives data of the construction monitoring system and the construction scheduling system, summarizes and classifies factors influencing construction progress and sends the factors to the engineering command center. The construction management system also comprises an epidemic situation management unit and an emergency management unit, wherein the epidemic situation management unit is in real-time communication with a national health department data center and regulates and controls project construction progress in real time according to epidemic situation; and the emergency management unit is in real-time communication with a national emergency department data center and regulates and controls project construction progress in real time according to emergency conditions.
In summary, the wind farm construction project construction plan and progress optimization scheduling management system provided in the structure of the present invention plans and monitors the progress of each sub-project through the intelligent management system, further calculates the difference between the current construction progress and the planned construction progress, ensures the quality and quantity to complete the construction plan, and visually displays the current construction progress of the total project through the plan completion ratio of the sub-projects of each part of the project which are constructed and not constructed, so that the project managers can conveniently adjust the personnel and material resources in the construction task through the data, and further effectively adjust the current construction progress in real time.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (10)

1. A wind power plant construction project construction plan and progress optimizing scheduling management system is characterized by comprising a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction plan unit and a construction progress optimizing unit;
the construction management system is a system for realizing efficient construction by performing collection management on all production data of the construction of the whole project according to the construction requirements of a project contracting party;
the construction scheduling system schedules factors influencing construction progress in the construction process according to the instruction requirements of the construction management system so as to realize that the overall construction progress is promoted according to a plan;
the construction monitoring system realizes the planned construction progress by monitoring the actual construction progress and acquiring factors influencing the construction progress;
and the construction early warning system compares the plan of the construction management system with the actual construction progress to realize the early warning function of the construction progress.
2. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the construction management system comprises a total package project management subsystem, a sub-package project management subsystem and a project management center, the total package project management subsystem manages construction of a total package project, and the sub-package project management subsystem manages construction of a sub-package project.
3. The wind farm construction project construction plan and progress optimizing and scheduling management system according to claim 2, wherein the total package project management subsystem comprises a total package construction plan unit and a total package progress optimizing unit, and the total package construction plan unit comprises a capital construction plan module, a main body installation plan module, a supporting facility installation plan module and an operation debugging plan module.
4. The wind farm construction project construction plan and progress optimizing and scheduling management system according to claim 1, wherein the sub-package project management subsystem comprises a sub-package construction plan unit and a sub-package progress optimizing unit, and the sub-package construction plan unit comprises a supporting facility installation plan module and an auxiliary facility construction plan module.
5. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the total package construction plan unit and the sub-package construction plan unit perform a BIM model based on a construction drawing, and the BIM model is led into the construction management system; the construction management system distributes project classification to a total package project management subsystem, a sub-package project management subsystem and an engineering management center, and associates the BIM with a construction progress plan; and the construction management is carried out by the three-dimensional visual BIM model.
6. The wind farm construction project construction plan and progress optimizing, scheduling and managing system according to claim 1, wherein the construction scheduling system receives a real-time construction progress of the construction monitoring system, compares the real-time construction progress with a planned construction progress, analyzes to obtain an over-progress construction sub-project, a synchronous progress sub-project and an behind-progress sub-project, converts analysis data into a visual chart and sends the visual chart to a total package progress optimizing unit, a sub-package progress optimizing unit and a construction early warning system, the total package progress optimizing unit and the sub-package progress optimizing unit optimize and analyze specific factors and send the optimized and analyzed specific factors to a construction field team, and obtains a problem cause through feedback of the construction field team.
7. The wind farm construction project construction plan and progress optimizing, scheduling and managing system according to claim 1, wherein the construction monitoring system comprises a material management unit, a team work log unit and a field imaging unit, the material management unit adopts label access management, all materials in a project field are recorded into a label system, label code scanning access is used, the team work log unit collects the day work records of workers, the field imaging unit utilizes a camera device and computer analysis software to estimate the construction progress in proportion, real-time actual construction progress is comprehensively calculated through data of the material management unit, the team work log unit and the field imaging unit, and the actual construction progress is sent to the construction scheduling system.
8. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the construction early warning system receives data of a construction monitoring system and a construction scheduling system, collects and classifies factors influencing construction progress, and sends the factors to an engineering command center.
9. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the construction management system further comprises an epidemic situation management unit and an emergency management unit, the epidemic situation management unit is in real-time communication with a national health department data center, and project construction progress is regulated and controlled in real time according to epidemic situation; and the emergency management unit is in real-time communication with a national emergency department data center and regulates and controls project construction progress in real time according to emergency conditions.
10. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 5, wherein the planned progress time is set to be consistent with the actual progress time, whether the real-time spatial position lags behind the planned spatial position is compared, and the real-time construction progress and the planned construction progress are compared according to the corresponding relationship between the spatial position and the construction progress.
CN202111330103.0A 2021-11-11 2021-11-11 Wind power plant construction project construction plan and progress optimization scheduling management system Withdrawn CN114049002A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111330103.0A CN114049002A (en) 2021-11-11 2021-11-11 Wind power plant construction project construction plan and progress optimization scheduling management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111330103.0A CN114049002A (en) 2021-11-11 2021-11-11 Wind power plant construction project construction plan and progress optimization scheduling management system

Publications (1)

Publication Number Publication Date
CN114049002A true CN114049002A (en) 2022-02-15

Family

ID=80208241

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111330103.0A Withdrawn CN114049002A (en) 2021-11-11 2021-11-11 Wind power plant construction project construction plan and progress optimization scheduling management system

Country Status (1)

Country Link
CN (1) CN114049002A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114580752A (en) * 2022-03-08 2022-06-03 武汉大博智能科技有限公司 Intelligent engineering construction progress management system based on BIM technology

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114580752A (en) * 2022-03-08 2022-06-03 武汉大博智能科技有限公司 Intelligent engineering construction progress management system based on BIM technology
CN114580752B (en) * 2022-03-08 2023-04-25 广东鼎耀工程技术有限公司 Engineering construction progress intelligent management system based on BIM technology

Similar Documents

Publication Publication Date Title
CN110378606B (en) Mobile visual safety management and control system
CN108320069B (en) Production and manufacturing execution system
CN113534760A (en) Manufacturing industry factory management system based on digital twin platform
CN110568829A (en) Mine full production chain intelligence management and control system
CN111930088A (en) Edge management system
CN105824300A (en) Heavy type intelligent factory system based on IoT (Internet of Things) technology and digital management technology
CN109754227A (en) Intelligent precise forging operation management system
CN111047257A (en) Production order management system based on 5G network
CN112462702A (en) Intelligent monitoring and intelligent scheduling system based on industrial internet
CN115330955A (en) Product visualization management and control method based on digital twinning technology
CN110232504A (en) A kind of quality manufacturing execution system platform and terminal
CN115879728A (en) Based on capital construction overall process platform system
CN111240296A (en) Industrial and mining equipment remote power-on and power-off system and use method thereof
CN114049002A (en) Wind power plant construction project construction plan and progress optimization scheduling management system
CN107545519B (en) Power grid enterprise operation and inspection management and control method
CN117455462A (en) Repair project informatization management system based on repair process structured data
CN211906071U (en) Long-range power transmission system that stops of industrial and mining equipment
CN117217675A (en) Digitalized system and method based on substation equipment delivery and operation and maintenance process
CN114581032A (en) Design plan tracking and visualization system based on cloud platform
CN106502230A (en) A kind of intelligence pushes away the method that case equipment carries out information gathering
CN113589770A (en) Production system based on MES
CN112801809A (en) Salt and salt chemical industry intelligent manufacturing integrated management system
Liu et al. Initial logistics management system of prefabricated component based on BIM and RFID technology
CN114066113A (en) Production and manufacturing execution system for environment-friendly paper tableware industry
Fuqiang et al. Research on MES system based on production management of railway vehicle reducer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20220215