CN114049002A - Wind power plant construction project construction plan and progress optimization scheduling management system - Google Patents
Wind power plant construction project construction plan and progress optimization scheduling management system Download PDFInfo
- Publication number
- CN114049002A CN114049002A CN202111330103.0A CN202111330103A CN114049002A CN 114049002 A CN114049002 A CN 114049002A CN 202111330103 A CN202111330103 A CN 202111330103A CN 114049002 A CN114049002 A CN 114049002A
- Authority
- CN
- China
- Prior art keywords
- construction
- progress
- project
- plan
- unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000010276 construction Methods 0.000 title claims abstract description 242
- 238000005457 optimization Methods 0.000 title description 11
- 238000009430 construction management Methods 0.000 claims abstract description 32
- 238000012544 monitoring process Methods 0.000 claims abstract description 19
- 239000000463 material Substances 0.000 claims abstract description 15
- 238000007726 management method Methods 0.000 claims description 73
- 238000003384 imaging method Methods 0.000 claims description 9
- 238000009434 installation Methods 0.000 claims description 9
- 230000000007 visual effect Effects 0.000 claims description 9
- 238000004891 communication Methods 0.000 claims description 6
- 238000000034 method Methods 0.000 claims description 4
- 238000004458 analytical method Methods 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 230000001360 synchronised effect Effects 0.000 claims description 3
- 230000001105 regulatory effect Effects 0.000 claims 1
- 239000000969 carrier Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0633—Workflow analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/101—Collaborative creation, e.g. joint development of products or services
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Strategic Management (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Life Sciences & Earth Sciences (AREA)
- Biodiversity & Conservation Biology (AREA)
- General Health & Medical Sciences (AREA)
- Water Supply & Treatment (AREA)
- Public Health (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a wind power plant construction project construction plan and progress optimizing scheduling management system, which comprises a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction plan unit and a construction progress optimizing unit; according to the wind power plant construction project construction plan and progress optimizing and scheduling management system provided by the structure, the progress of each sub project is planned and monitored through the intelligent management system, the difference between the current construction progress and the planned construction progress is calculated, the construction plan is completed with guaranteed quality and quantity, the current construction progress of the total project is visually displayed through the plan completion ratio of the sub projects which are constructed and are not constructed in each part of project, and the personnel and material resources in the construction task are conveniently adjusted through the data by engineering management personnel, so that the current construction progress is effectively adjusted in real time.
Description
Technical Field
The invention relates to the technical field of construction project schedule, in particular to a wind power plant construction project construction plan and schedule optimization scheduling management system.
Background
At present, in the construction project implementation process of the building engineering, project progress data information is usually recorded in a form that engineering technicians manually record or input carriers such as computers, and due to the fact that work technicians have a plurality of problems of lagging and being prone to making mistakes when recording data, progress management of the construction project cannot be timely mastered, the construction progress is prone to being slow in progress and difficult to guarantee quality and guarantee quantity to complete the construction plan.
Disclosure of Invention
Based on the technical problems in the prior art, the invention provides a wind power plant construction project construction plan and progress optimization scheduling management system, and solves the problems that the progress of each part in construction of a construction project is different, and the construction progress cannot be accurately mastered.
The invention provides a wind power plant construction project construction plan and progress optimizing and scheduling management system, which comprises a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction plan unit and a construction progress optimizing unit;
the construction management system is a system for realizing efficient construction by performing collection management on all production data of the construction of the whole project according to the construction requirements of a project contracting party;
the construction scheduling system schedules factors influencing construction progress in the construction process according to the instruction requirements of the construction management system so as to realize that the overall construction progress is promoted according to a plan;
the construction monitoring system realizes the planned construction progress by monitoring the actual construction progress and acquiring factors influencing the construction progress;
and the construction early warning system compares the plan of the construction management system with the actual construction progress to realize the early warning function of the construction progress.
Further, the construction management system comprises a total package project management subsystem, a sub-package project management subsystem and an engineering management center, wherein the total package project management subsystem manages the construction of a total package project, and the sub-package project management subsystem manages the construction of a sub-package project.
Further, the total package project management subsystem comprises a total package construction planning unit and a total package progress optimization unit, wherein the total package construction planning unit comprises a capital construction planning module, a main body installation planning module, a supporting facility installation planning module and an operation debugging planning module.
Further, the sub-package project management subsystem comprises a sub-package construction planning unit and a sub-package progress optimization unit, wherein the sub-package construction planning unit comprises a supporting facility installation planning module and an auxiliary facility construction planning module.
Further, the total package construction planning unit and the sub-package construction planning unit carry out BIM model based on construction drawings, and the BIM model is led into a construction management system; the construction management system distributes project classification to a total package project management subsystem, a sub-package project management subsystem and an engineering management center, and associates the BIM with a construction progress plan; and the construction management is carried out by the three-dimensional visual BIM model.
Furthermore, the construction scheduling system receives the real-time construction progress of the construction monitoring system, compares the real-time construction progress with the planned construction progress, analyzes and obtains an over-progress construction sub-project, a synchronous progress sub-project and a backward progress sub-project, converts the analysis data into a visual chart and sends the visual chart to a total package progress optimizing unit, a sub-package progress optimizing unit and a construction early warning system, the total package progress optimizing unit and the sub-package progress optimizing unit optimize and analyze specific factors and send the factors to a construction field team, and problem reasons are obtained through feedback of the construction field team.
Further, the construction monitoring system comprises a material management unit, a team work log unit and a field imaging unit, wherein the material management unit adopts label access management, all materials in a project field are input into a label system, a label is used for scanning codes to access, the team work log unit collects the day work records of workers, the field imaging unit utilizes a camera device and computer analysis software to estimate the construction progress in proportion, the real-time actual construction progress is comprehensively calculated through the data of the material management unit, the team work log unit and the field imaging unit, and the actual construction progress is sent to the construction scheduling system.
And further, the construction early warning system receives data of the construction monitoring system and the construction scheduling system, and collects and classifies factors influencing construction progress and sends the factors to an engineering command center.
Furthermore, the construction management system also comprises an epidemic situation management unit and an emergency management unit, wherein the epidemic situation management unit is in real-time communication with a national health department data center and regulates and controls project construction progress in real time according to epidemic situation; and the emergency management unit is in real-time communication with a national emergency department data center and regulates and controls project construction progress in real time according to emergency conditions.
And further setting the planned schedule time to be consistent with the actual schedule time, comparing whether the real-time space position lags behind the planned space position, and comparing the real-time construction schedule with the planned construction schedule according to the corresponding relation between the space position and the construction schedule.
The wind power plant construction project construction plan and progress optimizing scheduling management system provided by the invention has the advantages that: according to the wind power plant construction project construction plan and progress optimizing and scheduling management system provided by the structure, the progress of each sub project is planned and monitored through the intelligent management system, the difference between the current construction progress and the planned construction progress is calculated, the construction plan is completed with guaranteed quality and quantity, the current construction progress of the total project is visually displayed through the plan completion ratio of the sub projects which are constructed and are not constructed in each part of project, and the personnel and material resources in the construction task are conveniently adjusted through the data by engineering management personnel, so that the current construction progress is effectively adjusted in real time.
Drawings
Fig. 1 is a schematic structural diagram of a wind power plant construction project construction plan and progress optimization scheduling management system provided by the invention.
Detailed Description
As shown in fig. 1, fig. 1 is a wind farm construction project construction plan and progress optimization scheduling management system disclosed by the invention, and solves the problems that the progress of each part in construction of a construction project is different and the construction progress cannot be accurately mastered.
Referring to fig. 1, the construction planning and progress optimizing and scheduling management system for the wind power plant construction project, provided by the invention, comprises a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction planning unit and a construction progress optimizing unit;
the construction management system is a system for realizing efficient construction by performing collection management on all production data of the construction of the whole project according to the construction requirements of a project contracting party; the construction management system comprises a main package project management subsystem, a sub-package project management subsystem and an engineering management center, wherein the main package project management subsystem manages the construction of a main package project, and the sub-package project management subsystem manages the construction of sub-package projects. The total package project management subsystem comprises a total package construction planning unit and a total package progress optimization unit, wherein the total package construction planning unit comprises a capital construction planning module, a main body installation planning module, a supporting facility installation planning module and an operation debugging planning module. The sub-package project management subsystem comprises a sub-package construction planning unit and a sub-package progress optimization unit, wherein the sub-package construction planning unit comprises a supporting facility installation planning module and an auxiliary facility construction planning module. The total package construction planning unit and the sub-package construction planning unit carry out BIM model based on construction drawings, and the BIM model is led into a construction management system; the construction management system distributes project classification to a total package project management subsystem, a sub-package project management subsystem and an engineering management center, and associates the BIM with a construction progress plan; and the construction management is carried out by the three-dimensional visual BIM model. Setting the planned progress time to be consistent with the actual progress time, comparing whether the real-time space position lags behind the planned space position, and comparing the real-time construction progress with the planned construction progress according to the corresponding relation between the space position and the construction progress.
The construction scheduling system schedules factors influencing construction progress in the construction process according to the instruction requirements of the construction management system so as to realize that the overall construction progress is promoted according to a plan; the construction scheduling system receives the real-time construction progress of the construction monitoring system, compares the real-time construction progress with the planned construction progress, analyzes and obtains an over-progress construction sub-project, a synchronous progress sub-project and a behind-progress sub-project, converts analysis data into a visual chart and sends the visual chart to a total package progress optimizing unit, a sub-package progress optimizing unit and a construction early warning system, the total package progress optimizing unit and the sub-package progress optimizing unit optimize and analyze specific factors and send the factors to a construction field team, and problem reasons are obtained through feedback of the construction field team.
The construction monitoring system realizes the planned construction progress by monitoring the actual construction progress and acquiring factors influencing the construction progress; the construction monitoring system comprises a material management unit, a team work log unit and a field imaging unit, wherein the material management unit adopts label access management, all materials in a project field are input into a label system, a label is used for scanning a code to access, the team work log unit collects the day work record of workers, the field imaging unit utilizes a camera device and computer analysis software to estimate the construction progress in proportion, the real-time actual construction progress is comprehensively calculated through the data of the material management unit, the team work log unit and the field imaging unit, and the actual construction progress is sent to the construction scheduling system.
And the construction early warning system compares the plan of the construction management system with the actual construction progress to realize the early warning function of the construction progress. And the construction early warning system receives data of the construction monitoring system and the construction scheduling system, summarizes and classifies factors influencing construction progress and sends the factors to the engineering command center. The construction management system also comprises an epidemic situation management unit and an emergency management unit, wherein the epidemic situation management unit is in real-time communication with a national health department data center and regulates and controls project construction progress in real time according to epidemic situation; and the emergency management unit is in real-time communication with a national emergency department data center and regulates and controls project construction progress in real time according to emergency conditions.
In summary, the wind farm construction project construction plan and progress optimization scheduling management system provided in the structure of the present invention plans and monitors the progress of each sub-project through the intelligent management system, further calculates the difference between the current construction progress and the planned construction progress, ensures the quality and quantity to complete the construction plan, and visually displays the current construction progress of the total project through the plan completion ratio of the sub-projects of each part of the project which are constructed and not constructed, so that the project managers can conveniently adjust the personnel and material resources in the construction task through the data, and further effectively adjust the current construction progress in real time.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.
Claims (10)
1. A wind power plant construction project construction plan and progress optimizing scheduling management system is characterized by comprising a construction management system, a construction scheduling system, a construction monitoring system and a construction early warning system, wherein the construction management system comprises a construction plan unit and a construction progress optimizing unit;
the construction management system is a system for realizing efficient construction by performing collection management on all production data of the construction of the whole project according to the construction requirements of a project contracting party;
the construction scheduling system schedules factors influencing construction progress in the construction process according to the instruction requirements of the construction management system so as to realize that the overall construction progress is promoted according to a plan;
the construction monitoring system realizes the planned construction progress by monitoring the actual construction progress and acquiring factors influencing the construction progress;
and the construction early warning system compares the plan of the construction management system with the actual construction progress to realize the early warning function of the construction progress.
2. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the construction management system comprises a total package project management subsystem, a sub-package project management subsystem and a project management center, the total package project management subsystem manages construction of a total package project, and the sub-package project management subsystem manages construction of a sub-package project.
3. The wind farm construction project construction plan and progress optimizing and scheduling management system according to claim 2, wherein the total package project management subsystem comprises a total package construction plan unit and a total package progress optimizing unit, and the total package construction plan unit comprises a capital construction plan module, a main body installation plan module, a supporting facility installation plan module and an operation debugging plan module.
4. The wind farm construction project construction plan and progress optimizing and scheduling management system according to claim 1, wherein the sub-package project management subsystem comprises a sub-package construction plan unit and a sub-package progress optimizing unit, and the sub-package construction plan unit comprises a supporting facility installation plan module and an auxiliary facility construction plan module.
5. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the total package construction plan unit and the sub-package construction plan unit perform a BIM model based on a construction drawing, and the BIM model is led into the construction management system; the construction management system distributes project classification to a total package project management subsystem, a sub-package project management subsystem and an engineering management center, and associates the BIM with a construction progress plan; and the construction management is carried out by the three-dimensional visual BIM model.
6. The wind farm construction project construction plan and progress optimizing, scheduling and managing system according to claim 1, wherein the construction scheduling system receives a real-time construction progress of the construction monitoring system, compares the real-time construction progress with a planned construction progress, analyzes to obtain an over-progress construction sub-project, a synchronous progress sub-project and an behind-progress sub-project, converts analysis data into a visual chart and sends the visual chart to a total package progress optimizing unit, a sub-package progress optimizing unit and a construction early warning system, the total package progress optimizing unit and the sub-package progress optimizing unit optimize and analyze specific factors and send the optimized and analyzed specific factors to a construction field team, and obtains a problem cause through feedback of the construction field team.
7. The wind farm construction project construction plan and progress optimizing, scheduling and managing system according to claim 1, wherein the construction monitoring system comprises a material management unit, a team work log unit and a field imaging unit, the material management unit adopts label access management, all materials in a project field are recorded into a label system, label code scanning access is used, the team work log unit collects the day work records of workers, the field imaging unit utilizes a camera device and computer analysis software to estimate the construction progress in proportion, real-time actual construction progress is comprehensively calculated through data of the material management unit, the team work log unit and the field imaging unit, and the actual construction progress is sent to the construction scheduling system.
8. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the construction early warning system receives data of a construction monitoring system and a construction scheduling system, collects and classifies factors influencing construction progress, and sends the factors to an engineering command center.
9. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 1, wherein the construction management system further comprises an epidemic situation management unit and an emergency management unit, the epidemic situation management unit is in real-time communication with a national health department data center, and project construction progress is regulated and controlled in real time according to epidemic situation; and the emergency management unit is in real-time communication with a national emergency department data center and regulates and controls project construction progress in real time according to emergency conditions.
10. The wind farm construction project construction plan and progress optimizing scheduling management system according to claim 5, wherein the planned progress time is set to be consistent with the actual progress time, whether the real-time spatial position lags behind the planned spatial position is compared, and the real-time construction progress and the planned construction progress are compared according to the corresponding relationship between the spatial position and the construction progress.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111330103.0A CN114049002A (en) | 2021-11-11 | 2021-11-11 | Wind power plant construction project construction plan and progress optimization scheduling management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111330103.0A CN114049002A (en) | 2021-11-11 | 2021-11-11 | Wind power plant construction project construction plan and progress optimization scheduling management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114049002A true CN114049002A (en) | 2022-02-15 |
Family
ID=80208241
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111330103.0A Withdrawn CN114049002A (en) | 2021-11-11 | 2021-11-11 | Wind power plant construction project construction plan and progress optimization scheduling management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114049002A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114580752A (en) * | 2022-03-08 | 2022-06-03 | 武汉大博智能科技有限公司 | Intelligent engineering construction progress management system based on BIM technology |
-
2021
- 2021-11-11 CN CN202111330103.0A patent/CN114049002A/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114580752A (en) * | 2022-03-08 | 2022-06-03 | 武汉大博智能科技有限公司 | Intelligent engineering construction progress management system based on BIM technology |
CN114580752B (en) * | 2022-03-08 | 2023-04-25 | 广东鼎耀工程技术有限公司 | Engineering construction progress intelligent management system based on BIM technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110378606B (en) | Mobile visual safety management and control system | |
CN108320069B (en) | Production and manufacturing execution system | |
CN113534760A (en) | Manufacturing industry factory management system based on digital twin platform | |
CN110568829A (en) | Mine full production chain intelligence management and control system | |
CN111930088A (en) | Edge management system | |
CN105824300A (en) | Heavy type intelligent factory system based on IoT (Internet of Things) technology and digital management technology | |
CN109754227A (en) | Intelligent precise forging operation management system | |
CN111047257A (en) | Production order management system based on 5G network | |
CN112462702A (en) | Intelligent monitoring and intelligent scheduling system based on industrial internet | |
CN115330955A (en) | Product visualization management and control method based on digital twinning technology | |
CN110232504A (en) | A kind of quality manufacturing execution system platform and terminal | |
CN115879728A (en) | Based on capital construction overall process platform system | |
CN111240296A (en) | Industrial and mining equipment remote power-on and power-off system and use method thereof | |
CN114049002A (en) | Wind power plant construction project construction plan and progress optimization scheduling management system | |
CN107545519B (en) | Power grid enterprise operation and inspection management and control method | |
CN117455462A (en) | Repair project informatization management system based on repair process structured data | |
CN211906071U (en) | Long-range power transmission system that stops of industrial and mining equipment | |
CN117217675A (en) | Digitalized system and method based on substation equipment delivery and operation and maintenance process | |
CN114581032A (en) | Design plan tracking and visualization system based on cloud platform | |
CN106502230A (en) | A kind of intelligence pushes away the method that case equipment carries out information gathering | |
CN113589770A (en) | Production system based on MES | |
CN112801809A (en) | Salt and salt chemical industry intelligent manufacturing integrated management system | |
Liu et al. | Initial logistics management system of prefabricated component based on BIM and RFID technology | |
CN114066113A (en) | Production and manufacturing execution system for environment-friendly paper tableware industry | |
Fuqiang et al. | Research on MES system based on production management of railway vehicle reducer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20220215 |