CN113901382A - Method for calculating real-time waste incineration amount of three-furnace two-machine household waste incineration power generation project - Google Patents

Method for calculating real-time waste incineration amount of three-furnace two-machine household waste incineration power generation project Download PDF

Info

Publication number
CN113901382A
CN113901382A CN202111376079.4A CN202111376079A CN113901382A CN 113901382 A CN113901382 A CN 113901382A CN 202111376079 A CN202111376079 A CN 202111376079A CN 113901382 A CN113901382 A CN 113901382A
Authority
CN
China
Prior art keywords
real
time
incinerator
data
amount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111376079.4A
Other languages
Chinese (zh)
Other versions
CN113901382B (en
Inventor
王大鹏
杜保华
范奇
吴智群
褚贵宏
何新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Thermal Power Research Institute Co Ltd
Xian TPRI Power Station Information Technology Co Ltd
Original Assignee
Xian Thermal Power Research Institute Co Ltd
Xian TPRI Power Station Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Thermal Power Research Institute Co Ltd, Xian TPRI Power Station Information Technology Co Ltd filed Critical Xian Thermal Power Research Institute Co Ltd
Priority to CN202111376079.4A priority Critical patent/CN113901382B/en
Publication of CN113901382A publication Critical patent/CN113901382A/en
Application granted granted Critical
Publication of CN113901382B publication Critical patent/CN113901382B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/21Design, administration or maintenance of databases
    • G06F16/215Improving data quality; Data cleansing, e.g. de-duplication, removing invalid entries or correcting typographical errors

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Data Mining & Analysis (AREA)
  • General Physics & Mathematics (AREA)
  • Mathematical Physics (AREA)
  • General Engineering & Computer Science (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Pure & Applied Mathematics (AREA)
  • Computational Mathematics (AREA)
  • Software Systems (AREA)
  • Algebra (AREA)
  • Quality & Reliability (AREA)
  • Incineration Of Waste (AREA)

Abstract

The invention discloses a method for calculating the real-time garbage incineration amount of a three-furnace two-machine household garbage incineration power generation project based on the historical relationship between the evaporation amount of a waste heat boiler and the garbage incineration amount of an incinerator, which comprises the steps of determining three types of real-time parameters, acquiring data from a real-time database, starting the current t moment as a reference, collecting historical data of yesterday and the same year of the last year, judging whether the three-furnace two machines are in steady-state operation, cleaning the real-time data of the calculated parameters, calculating the real-time garbage incineration amount of a whole plant by using cleaned effective data, carrying out data verification on the real-time garbage incineration amount of the whole plant, calculating the real-time garbage incineration amount of each incinerator by using the real-time garbage incineration amount of the whole plant qualified through verification, writing the calculated real-time garbage incineration amount of the whole plant and the real-time garbage incineration amount of each incinerator into the real-time database, and finishing the current calculation, and entering the next round of real-time calculation.

Description

Method for calculating real-time waste incineration amount of three-furnace two-machine household waste incineration power generation project
Technical Field
The invention belongs to the technical field of the power industry, and particularly relates to a method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project.
Background
In the three-furnace two-machine household garbage incineration power generation project, the fuel entering the mechanical grate type garbage incinerator for combustion is urban household garbage subjected to solid waste treatment, and the garbage is weighed by the grab bucket weighing and metering device before entering the incinerator for combustion, so that the accumulated garbage incineration amount is given, but the real-time garbage incineration amount cannot be obtained.
At present, for the waste incineration amount, a waste incineration amount weighing system designed by converting irregular signal values such as torque, rotating speed and the like of a hoisting frequency converter into weight data through an algorithm is reported in documents, such as "waste incineration amount weighing system of a waste incineration power plant, modern industrial economy and informatization, 2019 (09)", but an online calculation method for the real-time waste incineration amount of a three-furnace two-machine domestic waste incineration power generation project is not reported.
Because the three furnaces and the two machines adopt the unique arrangement mode of three mechanical grate type garbage incinerators, three waste heat boilers and two steam turbine generator units, a real-time calculation method for researching the garbage incineration amount is necessary for the household garbage incineration power generation project of the three furnaces and the two machines; the waste is burnt in the incinerator and heat is transferred to the main steam, so that the real-time waste incineration amount is converted through the historical relationship between the evaporation amount of the waste heat boiler and the waste incineration amount of the incinerator and is relatively accurate.
Disclosure of Invention
In order to overcome the technical problems, the invention provides a method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project, which is convenient for technicians to know the real-time waste incineration treatment conditions of three incinerators in real time.
In order to achieve the purpose, the invention adopts the technical scheme that:
the method for calculating the real-time waste incineration amount of the three-furnace two-machine household waste incineration power generation project comprises the following steps;
1) determining real-time parameters
Real-time parameters are classified into three categories, the first category: steady state operating condition parameters of the incinerator, the waste heat boiler and the steam turbine generator; the second type: the incinerator accumulates the incineration amount calibration parameter; in the third category: calculating parameters of the real-time waste incineration amount; all real-time parameters acquire data from a real-time database;
2) start the current round of real-time calculation
Starting the current round of real-time calculation by taking the current time t as reference time;
3) collecting yesterday and last year contemporaneous history data
Aiming at a three-furnace two-machine household garbage incineration power generation project, collecting yesterday and last year contemporaneous history data of evaporation capacity and garbage disposal capacity;
4) judging whether the three furnaces and the two machines are in steady-state operation
Defining 3 incinerator boundary conditions and 2 turbonator boundary conditions, wherein at least one of the 3 incinerator boundary conditions and the 2 turbonator boundary conditions is satisfied, considering that the three furnaces and the two turbonators are in a steady-state operation condition, and continuing to calculate in the next step; otherwise, the three furnaces and the two machines are considered to be in an unsteady state operation condition, the calculation of the current t moment is skipped, and the calculation is carried out at the next t +1s moment (namely, the next round is carried out);
5) data cleansing
If the three furnaces and the two machines are in the steady-state operation condition according to the step 4), acquiring real-time data Y (t) of the third type real-time waste incineration amount calculation parameter in the step 1) at the current time t from a real-time database, and cleaning the data according to a method of the formula (1):
Figure BDA0003364004540000031
in the formula (1), m is the statistical quantity of data of the parameter in the delta t time period;
if the real-time data Y (t) meets the formula (1), the real-time data Y (t) is regarded as effective data, and the next calculation is continued; otherwise, the data is considered as invalid data, the data does not participate in the real-time calculation of the current round, and the next round of calculation is started;
6) calculating real-time garbage incineration amount of whole plant
If the three furnaces and the two machines are in the steady-state operation condition according to the step 4), determining the main steam flow F of the waste heat boiler No. 1 at the current t moment according to the step 5)B1No. 2 waste heat boiler main steam flow FB2And No. 3 exhaust-heat boiler main steam flow FB3When the real-time data is effective data, calculating the total plant real-time waste incineration capacity GF (t) at the current t moment according to the formula (2), and continuing the current round of real-time calculation:
Figure BDA0003364004540000032
7) checking real-time garbage incineration amount of whole plant
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and acquiring the accumulated incineration quantity Q of the No. 1 incinerator determined in the step 1) from a real-time databaseTotal-F1Verification parameter, No. 2 incinerator accumulative total incineration quantity QTotal-F1Calibration parameter, No. 3 incinerator accumulative total incineration quantity QTotal-F1Checking three historical data with non-repeated numerical values of the parameters before the current time t, and firstly carrying out data checking on the total plant real-time waste incineration amount GF (t) at the current time t calculated in the step 6) according to the step (3):
Figure BDA0003364004540000041
in the formula (3), GFCheck(t) is the basic calibration data of the real-time waste incineration amount of the whole plant, and is calculated according to the formula (4):
Figure BDA0003364004540000042
in the formula (4), t-3、t-2、t-1Respectively representing historical moments corresponding to three historical data with non-repeated numerical values before the current t moment;
if the total plant real-time waste incineration amount GF (t) at the current time t is verified to be qualified, the current round of real-time calculation is continued; if the verification is not qualified, the result is not output, the calculation of the current round is terminated, and the next round of calculation is carried out;
8) calculating the real-time garbage burning amount of each incinerator
9) Writing the data into the real-time database and finishing the real-time calculation of the current round
And finally, writing the real-time garbage incineration amount of the whole plant calculated in the step 6) and the real-time garbage incineration amount of each incinerator calculated in the step 8) into a real-time database, finishing the real-time calculation of the current round, and entering the next round of calculation (at the moment of t +1 s).
The specific calculation method in the step 8) comprises the following steps:
8-1) calculating the real-time waste incineration amount of the No. 1 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the waste heat boiler No. 1 at the current t moment according to the step 5)B1When the data is valid data, the real-time garbage incineration amount GF of the No. 1 incinerator is calculated according to the formula (5)F1(t):
Figure BDA0003364004540000051
8-2) calculating the real-time waste incineration amount of the No. 2 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the No. 2 waste heat boiler at the current t moment according to the step 5)B2When the data is valid data, the real-time garbage incineration amount GF of the No. 2 incinerator is calculated according to the formula (6)F2(t):
Figure BDA0003364004540000052
8-3) calculating the real-time waste incineration amount of the No. 3 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the No. 3 waste heat boiler at the current t moment according to the step 5)B3When the data is valid data, the real-time garbage incineration amount GF of the No. 3 incinerator is calculated according to the formula (7)F3(t):
Figure BDA0003364004540000053
In the step 1), the first type: steady state operating condition parameters of the incinerator, the waste heat boiler and the steam turbine generator;
determination of No. 1 incinerator operating State SF1No. 1 waste heat boiler drum pressure PB1(unit: MPa), temperature of No. 1 incinerator at 850 deg.C for 2 seconds
Figure BDA0003364004540000061
The unit is the stable state operation condition parameters of the No. 1 incinerator and the waste heat boiler; determination of No. 2 incinerator operating State SF2No. 2 waste heat boiler drum pressure PB2(unit: MPa), temperature of No. 2 incinerator at 850 deg.C for 2 seconds
Figure BDA0003364004540000062
The unit is the stable state operation condition parameters of the No. 2 incinerator and the waste heat boiler; determination of No. 3 incinerator operating State SF3No. 3 waste heat boiler drum pressure PB3(unit: MPa), and 850 ℃ 2 seconds temperature of No. 3 incinerator
Figure BDA0003364004540000063
The unit is the stable state operation condition parameter of the No. 3 incinerator and the waste heat boiler; determining the running state S of No. 1 turbonatorG1SPEED of No. 1 steam turbineG1The RPM is a parameter of the steady-state operation condition of the number 1 turbonator; determining running state S of No. 2 turbonatorG2SPEED of No. 2 steam turbineG2The RPM is a parameter of the steady-state operation condition of the No. 2 turbonator;
the second type: calibration parameter for accumulated burning amount of incinerator
Determining cumulative burning quantity Q of No. 1 incineratorTotal-F1(unit: ton) is No. 1 incinerator real-time garbage incineration amount calculation calibration parameter, and the accumulative incineration amount Q of No. 2 incinerator is determinedTotal-F2(unit: ton) is No. 2 incinerator real-time garbage incineration amount calculation calibration parameter, and No. 3 incinerator cumulative incineration amount Q is determinedTotal-F3The real-time garbage burning amount of a No. 3 incinerator (unit: ton) is calculated and checked;
in the third category: real-time calculation parameter of waste incineration amount
Determining main steam flow F of waste heat boiler No. 1B1(unit: ton/hour) No. 2 waste heat boiler main steam flow FB2(unit: ton/hour) No. 3 waste heat boiler main steam flow FB3(unit: ton/hour) is related parameters for real-time calculation of the waste incineration amount of three furnaces and two machines.
Yesterday and last year contemporaneous history data of the evaporation capacity and the garbage disposal capacity collected in the step 3) are as follows:
yesterday history data: yesterday accumulated evaporation capacity of No. 1 waste heat boiler
Figure BDA0003364004540000071
Yesterday cumulative evaporation capacity of No. 2 incinerator
Figure BDA0003364004540000072
Yesterday cumulative evaporation capacity of No. 3 incinerator
Figure BDA0003364004540000073
(unit: ton), yesterday accumulated garbage disposal quantity Q of whole factoryZR(unit: ton);
historical data of the same year (this year) in the past: no. 1 waste heat boiler last year synchronization accumulated evaporation capacity
Figure BDA0003364004540000074
(unit: ton) and No. 2 incinerator annual cumulative evaporation capacity
Figure BDA0003364004540000075
(unit: ton) and No. 3 incinerator annual cumulative evaporation capacity
Figure BDA0003364004540000076
(unit: ton), the same period of the last year of the whole plant and the accumulated garbage treatment amount QTQ(unit: ton).
The boundary conditions of the steady-state operation conditions in the step 4) are defined as follows:
Figure BDA0003364004540000077
Figure BDA0003364004540000081
and acquiring historical operating data of the steady-state operating condition parameters of the first-class incinerator, the waste heat boiler and the steam turbine generator in the step 2) within delta t time from a real-time database (wherein delta t is defined as a time period t-600 s-t-1 s).
The invention has the beneficial effects that:
the invention provides an online method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project, can calculate the real-time waste incineration amount more accurately, and has guiding significance for online comparison and analysis of energy consumption indexes of the waste incineration power generation project.
Drawings
FIG. 1 is a schematic diagram of the real-time computing process of the present invention.
FIG. 2 is a schematic diagram of a real-time waste incineration curve according to the present invention.
Detailed Description
The present invention will be described in further detail with reference to examples.
1) Determining real-time parameters
The real-time parameters are divided into three categories, and all the real-time parameters acquire data from a real-time database.
The first type: steady state operation condition parameters of incinerator, waste heat boiler and turbine generator
Determination of No. 1 incinerator operating State SF1No. 1 waste heat boiler drum pressure PB1(unit: MPa), temperature of No. 1 incinerator at 850 deg.C for 2 seconds
Figure BDA0003364004540000091
The unit is the steady state operation condition parameter of the No. 1 incinerator and the waste heat boiler, and the operation state S of the No. 2 incinerator is determinedF2No. 2 waste heat boiler drum pressure PB2(unit: MPa), temperature of No. 2 incinerator at 850 deg.C for 2 seconds
Figure BDA0003364004540000092
The unit is a parameter of the steady-state operation condition of the No. 2 incinerator and the waste heat boiler, and the operation state S of the No. 3 incinerator is determinedF3No. 3 waste heat boiler drum pressure PB3(unit: MPa), and 850 ℃ 2 seconds temperature of No. 3 incinerator
Figure BDA0003364004540000093
The unit is a parameter of the steady-state operation condition of the No. 3 incinerator and the waste heat boiler, and the operation state S of the No. 1 turbonator is determinedG1SPEED of No. 1 steam turbineG1(unit: RPM) is a parameter of the steady-state operation condition of the No. 1 turbonator, and the operation state S of the No. 2 turbonator is determinedG2SPEED of No. 2 steam turbineG2And the (unit: RPM) is a parameter of the steady-state operation condition of the No. 2 steam turbine generator.
The second type: calibration parameter for accumulated burning amount of incinerator
Determining cumulative burning quantity Q of No. 1 incineratorTotal-F1(unit: ton) is No. 1 incinerator real-time garbage incineration amount calculation calibration parameter, and the accumulative incineration amount Q of No. 2 incinerator is determinedTotal-F2(unit: ton) is No. 2 incinerator real-time garbage incineration amount calculation calibration parameter, and No. 3 incinerator cumulative incineration amount Q is determinedTotal-F3And (unit: ton) 3 # incinerator real-time waste incineration amount calculation calibration parameters.
In the third category: real-time calculation parameter of waste incineration amount
Determining main steam flow F of waste heat boiler No. 1B1(unit: ton/small)Hour), No. 2 exhaust-heat boiler main steam flow FB2(unit: ton/hour) No. 3 waste heat boiler main steam flow FB3(unit: ton/hour) is related parameters for real-time calculation of the waste incineration amount of three furnaces and two machines.
2) Start the current round of real-time calculation
And starting the current round of real-time calculation by taking the current time t as reference time.
3) Collecting yesterday and last year contemporaneous history data
Aiming at the three-furnace two-machine household garbage incineration power generation project, yesterday and last year synchronization historical data are collected:
yesterday history data: yesterday accumulated evaporation capacity of No. 1 waste heat boiler
Figure BDA0003364004540000101
Yesterday cumulative evaporation capacity of No. 2 incinerator
Figure BDA0003364004540000102
Yesterday cumulative evaporation capacity of No. 3 incinerator
Figure BDA0003364004540000103
(unit: ton), yesterday accumulated garbage disposal quantity Q of whole factoryZR(unit: ton).
Historical data of the same year (this year) in the past: no. 1 waste heat boiler last year synchronization accumulated evaporation capacity
Figure BDA0003364004540000104
(unit: ton) and No. 2 incinerator annual cumulative evaporation capacity
Figure BDA0003364004540000105
(unit: ton) and No. 3 incinerator annual cumulative evaporation capacity
Figure BDA0003364004540000106
(unit: ton), the same period of the last year of the whole plant and the accumulated garbage treatment amount QTQ(unit: ton).
4) Judging whether the three furnaces and the two machines are in steady-state operation
Acquiring historical operation data of steady-state operation condition parameters of the first-class incinerator, the waste heat boiler and the steam turbine generator in the step 2) in delta t time from a real-time database (wherein delta t is defined as a time period t-600 s-t-1 s), and defining boundary conditions according to the following table.
Figure BDA0003364004540000107
Figure BDA0003364004540000111
If at least one of the 3 incinerator boundary conditions and the 2 turbonators boundary conditions is met, the three furnaces and the two turbines are considered to be in a steady-state operation condition, and the calculation of the next step can be continued; otherwise, the three furnaces and the two machines are considered to be in an unsteady state operation condition, the calculation of the current t moment is skipped, and the calculation is carried out at the next t +1s moment (namely, the next round is carried out).
5) Data cleansing
If the three furnaces and the two machines are in the steady-state operation condition according to the step 4), acquiring the real-time data Y (t) of 5 third-class real-time waste incineration quantity calculation parameters in the step 2) at the current t moment from a real-time database, and cleaning the data according to the formula (1):
Figure BDA0003364004540000121
in equation (1), m is the statistical number of data in the Δ t time period of the parameter.
If the real-time data Y (t) meets the formula (1), the real-time data Y (t) is regarded as effective data, and the next calculation is continued; otherwise, the data is considered as invalid data, and the data does not participate in the real-time calculation of the current round and enters the next round of calculation.
6) Calculating real-time garbage incineration amount of whole plant
If the three furnaces and the two machines are in the steady-state operation condition according to the step 4), determining No. 1 waste heat at the current t moment according to the step 5)Main steam flow F of boilerB1No. 2 waste heat boiler main steam flow FB2And No. 3 exhaust-heat boiler main steam flow FB3When the real-time data is effective data, calculating the total plant real-time waste incineration capacity GF (t) at the current t moment according to the formula (2), and continuing the current round of real-time calculation:
Figure BDA0003364004540000122
7) checking real-time garbage incineration amount of whole plant
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and acquiring the accumulated incineration quantity Q of the No. 1 incinerator determined in the step 2) from a real-time databaseTotal-F1Verification parameter, No. 2 incinerator accumulative total incineration quantity QTotal-F1Calibration parameter, No. 3 incinerator accumulative total incineration quantity QTotal-F1Checking three historical data with non-repeated numerical values of the parameters before the current time t, and firstly carrying out data checking on the total plant real-time waste incineration amount GF (t) at the current time t calculated in the step 6) according to the step (3):
Figure BDA0003364004540000131
in the formula (3), GFCheck(t) is the basic calibration data of the real-time waste incineration amount of the whole plant, and is calculated according to the formula (4):
Figure BDA0003364004540000132
in the formula (4), t-3、t-2、t-1The history time points corresponding to three pieces of history data whose numerical values are not repeated before the current time point t are respectively shown.
If the total plant real-time waste incineration amount GF (t) at the current time t is verified to be qualified, the current round of real-time calculation is continued; and if the verification is unqualified, the result is not output, the calculation of the current round is terminated, and the next round of calculation is carried out.
8) Calculating the real-time garbage burning amount of each incinerator
8-1) calculating the real-time waste incineration amount of the No. 1 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the waste heat boiler No. 1 at the current t moment according to the step 5)B1When the data is valid data, the real-time garbage incineration amount GF of the No. 1 incinerator is calculated according to the formula (5)F1(t):
Figure BDA0003364004540000141
8-2) calculating the real-time waste incineration amount of the No. 2 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the No. 2 waste heat boiler at the current t moment according to the step 5)B2When the data is valid data, the real-time garbage incineration amount GF of the No. 2 incinerator is calculated according to the formula (6)F2(t):
Figure BDA0003364004540000142
8-3) calculating the real-time waste incineration amount of the No. 3 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the No. 3 waste heat boiler at the current t moment according to the step 5)B3When the data is valid data, the real-time garbage incineration amount GF of the No. 3 incinerator is calculated according to the formula (7)F3(t):
Figure BDA0003364004540000143
9) Writing the data into the real-time database and finishing the real-time calculation of the current round
And finally, writing the real-time garbage incineration amount of the whole plant calculated in the step 6) and the real-time garbage incineration amount of each incinerator calculated in the step 8) into a real-time database, finishing the real-time calculation of the current round, and entering the next round of calculation (at the moment of t +1 s).

Claims (5)

1. A method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project is characterized by comprising the following steps;
1) determining real-time parameters
Real-time parameters are classified into three categories, the first category: steady state operating condition parameters of the incinerator, the waste heat boiler and the steam turbine generator; the second type: the incinerator accumulates the incineration amount calibration parameter; in the third category: calculating parameters of the real-time waste incineration amount; all real-time parameters acquire data from a real-time database;
2) start the current round of real-time calculation
Starting the current round of real-time calculation by taking the current time t as reference time;
3) collecting yesterday and last year contemporaneous history data
Aiming at a three-furnace two-machine household garbage incineration power generation project, collecting yesterday and last year contemporaneous history data of evaporation capacity and garbage disposal capacity;
4) judging whether the three furnaces and the two machines are in steady-state operation
Defining 3 incinerator boundary conditions and 2 turbonator boundary conditions, wherein at least one of the 3 incinerator boundary conditions and the 2 turbonator boundary conditions is satisfied, considering that the three furnaces and the two turbonators are in a steady-state operation condition, and continuing to calculate in the next step; otherwise, the three furnaces and the two machines are considered to be in an unsteady state operation condition, the calculation of the current t moment is skipped, and the calculation is carried out at the next t +1s moment (namely, the next round is carried out);
5) data cleansing
If the three furnaces and the two machines are in the steady-state operation condition according to the step 4), acquiring real-time data Y (t) of the third type real-time waste incineration amount calculation parameter in the step 1) at the current time t from a real-time database, and cleaning the data according to a method of the formula (1):
Figure FDA0003364004530000021
in the formula (1), m is the statistical quantity of data of the parameter in the delta t time period;
if the real-time data Y (t) meets the formula (1), the real-time data Y (t) is regarded as effective data, and the next calculation is continued; otherwise, the data is considered as invalid data, the data does not participate in the real-time calculation of the current round, and the next round of calculation is started;
6) calculating real-time garbage incineration amount of whole plant
If the three furnaces and the two machines are in the steady-state operation condition according to the step 4), determining the main steam flow F of the waste heat boiler No. 1 at the current t moment according to the step 5)B1No. 2 waste heat boiler main steam flow FB2And No. 3 exhaust-heat boiler main steam flow FB3When the real-time data is effective data, calculating the total plant real-time waste incineration capacity GF (t) at the current t moment according to the formula (2), and continuing the current round of real-time calculation:
Figure FDA0003364004530000022
7) checking real-time garbage incineration amount of whole plant
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and acquiring the accumulated incineration quantity Q of the No. 1 incinerator determined in the step 2) from a real-time databaseTotal-F1Verification parameter, No. 2 incinerator accumulative total incineration quantity QTotal-F1Calibration parameter, No. 3 incinerator accumulative total incineration quantity QTotal-F1Checking three historical data with non-repeated numerical values of the parameters before the current time t, and firstly carrying out data checking on the total plant real-time waste incineration amount GF (t) at the current time t calculated in the step 6) according to the step (3):
Figure FDA0003364004530000031
in the formula (3), GFCheck(t) is the basic calibration data of the real-time waste incineration amount of the whole plant, and is calculated according to the formula (4):
Figure FDA0003364004530000032
in the formula (4), t-3、t-2、t-1Respectively representing historical moments corresponding to three historical data with non-repeated numerical values before the current t moment;
if the total plant real-time waste incineration amount GF (t) at the current time t is verified to be qualified, the current round of real-time calculation is continued; if the verification is not qualified, the result is not output, the calculation of the current round is terminated, and the next round of calculation is carried out;
8) calculating the real-time garbage burning amount of each incinerator
9) Writing the data into the real-time database and finishing the real-time calculation of the current round
And finally, writing the real-time garbage incineration amount of the whole plant calculated in the step 6) and the real-time garbage incineration amount of each incinerator calculated in the step 8) into a real-time database, finishing the real-time calculation of the current round, and entering the next round of calculation (at the moment of t +1 s).
2. The method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project according to claim 1, wherein the step 8) is specifically as follows:
8-1) calculating the real-time waste incineration amount of the No. 1 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the waste heat boiler No. 1 at the current t moment according to the step 5)B1When the data is valid data, the real-time garbage incineration amount GF of the No. 1 incinerator is calculated according to the formula (5)F1(t):
Figure FDA0003364004530000041
8-2) calculating the real-time waste incineration amount of the No. 2 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the No. 2 waste heat boiler at the current t moment according to the step 5)B2When the data is valid data, the real-time garbage incineration amount GF of the No. 2 incinerator is calculated according to the formula (6)F2(t):
Figure FDA0003364004530000042
8-3) calculating the real-time waste incineration amount of the No. 3 incinerator
According to the step 4), judging that the three furnaces and the two machines are in steady-state operation conditions, and determining the main steam flow F of the No. 3 waste heat boiler at the current t moment according to the step 5)B3When the data is valid data, the real-time garbage incineration amount GF of the No. 3 incinerator is calculated according to the formula (7)F3(t):
Figure FDA0003364004530000043
3. The method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project according to claim 1, wherein in the step 1), the first type: steady state operating condition parameters of the incinerator, the waste heat boiler and the steam turbine generator;
determination of No. 1 incinerator operating State SF1No. 1 waste heat boiler drum pressure PB1(unit: MPa), temperature of No. 1 incinerator at 850 deg.C for 2 seconds
Figure FDA0003364004530000051
The unit is the steady state operation condition parameter of the No. 1 incinerator and the waste heat boiler, and the operation state S of the No. 2 incinerator is determinedF2No. 2 waste heat boiler drum pressure PB2(unit: MPa), temperature of No. 2 incinerator at 850 deg.C for 2 seconds
Figure FDA0003364004530000052
The unit is a parameter of the steady-state operation condition of the No. 2 incinerator and the waste heat boiler, and the operation state S of the No. 3 incinerator is determinedF3No. 3 waste heat boiler drum pressure PB3(unit: MPa), and 850 ℃ 2 seconds temperature of No. 3 incinerator
Figure FDA0003364004530000053
(unit:. degree. C.) is No. 3 incinerator and exhaust-heat boiler steady state operationDetermining running condition parameters of the number 1 turbonatorG1SPEED of No. 1 steam turbineG1(unit: RPM) is a parameter of the steady-state operation condition of the No. 1 turbonator, and the operation state S of the No. 2 turbonator is determinedG2SPEED of No. 2 steam turbineG2The RPM is a parameter of the steady-state operation condition of the No. 2 turbonator;
the second type: calibration parameter for accumulated burning amount of incinerator
Determining cumulative burning quantity Q of No. 1 incineratorTotal-F1(unit: ton) is No. 1 incinerator real-time garbage incineration amount calculation calibration parameter, and the accumulative incineration amount Q of No. 2 incinerator is determinedTotal-F2(unit: ton) is No. 2 incinerator real-time garbage incineration amount calculation calibration parameter, and No. 3 incinerator cumulative incineration amount Q is determinedTotal-F3The real-time garbage burning amount of a No. 3 incinerator (unit: ton) is calculated and checked;
in the third category: real-time calculation parameter of waste incineration amount
Determining main steam flow F of waste heat boiler No. 1B1(unit: ton/hour) No. 2 waste heat boiler main steam flow FB2(unit: ton/hour) No. 3 waste heat boiler main steam flow FB3(unit: ton/hour) is related parameters for real-time calculation of the waste incineration amount of three furnaces and two machines.
4. The method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project according to claim 1, wherein yesterday and last year contemporaneous history data of the evaporation amount and the waste disposal amount collected in the step 3) are as follows:
yesterday history data: yesterday accumulated evaporation capacity of No. 1 waste heat boiler
Figure FDA0003364004530000061
Yesterday cumulative evaporation capacity of No. 2 incinerator
Figure FDA0003364004530000062
Yesterday cumulative evaporation capacity of No. 3 incinerator
Figure FDA0003364004530000063
(unit: ton), yesterday accumulated garbage disposal quantity Q of whole factoryZR(unit: ton);
historical data of the same year (this year) in the past: no. 1 waste heat boiler last year synchronization accumulated evaporation capacity
Figure FDA0003364004530000064
(unit: ton) and No. 2 incinerator annual cumulative evaporation capacity
Figure FDA0003364004530000065
(unit: ton) and No. 3 incinerator annual cumulative evaporation capacity
Figure FDA0003364004530000066
(unit: ton), the same period of the last year of the whole plant and the accumulated garbage treatment amount QTQ(unit: ton).
5. The method for calculating the real-time waste incineration amount of a three-furnace two-machine household waste incineration power generation project according to claim 1, wherein the boundary conditions of the steady-state operation conditions in the step 4) are defined as follows:
Figure FDA0003364004530000067
Figure FDA0003364004530000071
and acquiring historical operating data of the steady-state operating condition parameters of the first-class incinerator, the waste heat boiler and the steam turbine generator in the step 2) within delta t time from a real-time database (wherein delta t is defined as a time period t-600 s-t-1 s).
CN202111376079.4A 2021-11-19 2021-11-19 Method for calculating real-time garbage incineration amount of three-furnace two-machine household garbage incineration power generation project Active CN113901382B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111376079.4A CN113901382B (en) 2021-11-19 2021-11-19 Method for calculating real-time garbage incineration amount of three-furnace two-machine household garbage incineration power generation project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111376079.4A CN113901382B (en) 2021-11-19 2021-11-19 Method for calculating real-time garbage incineration amount of three-furnace two-machine household garbage incineration power generation project

Publications (2)

Publication Number Publication Date
CN113901382A true CN113901382A (en) 2022-01-07
CN113901382B CN113901382B (en) 2024-03-26

Family

ID=79194702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111376079.4A Active CN113901382B (en) 2021-11-19 2021-11-19 Method for calculating real-time garbage incineration amount of three-furnace two-machine household garbage incineration power generation project

Country Status (1)

Country Link
CN (1) CN113901382B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000017498A1 (en) * 1998-09-22 2000-03-30 Siemens Aktiengesellschaft Method and device for catalytically removing a pollutant from the exhaust gas of an internal combustion system
JP2008025965A (en) * 2006-07-25 2008-02-07 Public Works Research Institute Pressure incinerator equipment and its operation method
JP2014088812A (en) * 2012-10-30 2014-05-15 Takuma Co Ltd Operational method for urban refuse incineration plant with steam turbine power generation device and calculation controller for adjusting steam pressure of steam turbine inlet
CN110007058A (en) * 2019-02-28 2019-07-12 苏州西热节能环保技术有限公司 The method for real-time measurement of moisture content in a kind of burning power plant fuel
CN110822401A (en) * 2019-08-26 2020-02-21 国网天津市电力公司电力科学研究院 Load control method for parallel operation waste incineration treatment boiler
CN112818509A (en) * 2020-12-31 2021-05-18 深圳市深能环保东部有限公司 Method for rapidly calculating waste incineration heat value on line

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000017498A1 (en) * 1998-09-22 2000-03-30 Siemens Aktiengesellschaft Method and device for catalytically removing a pollutant from the exhaust gas of an internal combustion system
JP2008025965A (en) * 2006-07-25 2008-02-07 Public Works Research Institute Pressure incinerator equipment and its operation method
JP2014088812A (en) * 2012-10-30 2014-05-15 Takuma Co Ltd Operational method for urban refuse incineration plant with steam turbine power generation device and calculation controller for adjusting steam pressure of steam turbine inlet
CN110007058A (en) * 2019-02-28 2019-07-12 苏州西热节能环保技术有限公司 The method for real-time measurement of moisture content in a kind of burning power plant fuel
CN110822401A (en) * 2019-08-26 2020-02-21 国网天津市电力公司电力科学研究院 Load control method for parallel operation waste incineration treatment boiler
CN112818509A (en) * 2020-12-31 2021-05-18 深圳市深能环保东部有限公司 Method for rapidly calculating waste incineration heat value on line

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
湛腾西;: "垃圾焚烧过程智能集成控制", 机床与液压, no. 18, 28 September 2010 (2010-09-28) *
王智微;范奇;张浩;马朋波;徐威;赖菲;廖梅;滕勇;: "垃圾焚烧发电厂实时性能计算方法的研究与应用", 热力发电, no. 09, 25 September 2012 (2012-09-25) *
罗成俊;周旭;李军;: "生活垃圾焚烧炉推料器故障分析及改进", 中国环保产业, no. 09, 20 September 2018 (2018-09-20) *

Also Published As

Publication number Publication date
CN113901382B (en) 2024-03-26

Similar Documents

Publication Publication Date Title
Carneiro et al. Energy, exergy, environmental and economic analysis of hybrid waste-to-energy plants
EP1698956B1 (en) Method for optimizing combined cycle/combined process facilities
CN106768068A (en) Fired power generating unit fire coal calorific value and consumption of standard coal for power generation index on-line monitoring system and method
Gu¨ len et al. Real-time on-line performance diagnostics of heavy-duty industrial gas turbines
CN104090560A (en) Device monitoring power supply integrated environment evaluation indexes
CN112016781A (en) Method and system for online evaluation of small production and operation indexes of waste incineration power plant
CN111931346A (en) Real-time calculation method and application of low calorific value of coal as fired in coal-fired boiler
Behbahaninia et al. Markov and monte carlo simulation of waste-to-energy power plants considering variable fuel analysis and failure rates
CN113901382B (en) Method for calculating real-time garbage incineration amount of three-furnace two-machine household garbage incineration power generation project
CN113468732B (en) System and method for determining production cost for heat supply of steam extraction heat supply unit
CN110298534A (en) F grades of gas-steam combined circulating generation unit energy consumption index on-line monitorings and power consumption analysis method
CN113946789B (en) Method for calculating garbage incineration amount of four-furnace three-machine garbage incineration power plant in real time
CN111723331B (en) Method for calculating rights and interests distribution of load of combined cycle two-to-one unit turbine
CN106016295A (en) Automatic combustion fuzzy control method and system for incinerator
CN113901381B (en) Real-time calculation method for garbage incineration amount of two-furnace one-machine household garbage incineration power plant
CN112348696B (en) BP neural network-based heating unit peak regulation upper limit evaluation method and system
CN113962826A (en) Method for calculating real-time waste incineration amount of small household waste incineration power generation project
CN100366876C (en) Online analysis method and system for operation efficiency of combined gas-steam cycle power station
CN102661974B (en) Thermal-operating-parameters-based pulverized coal heat value on-line identification method
CN101825273A (en) Device for on-line monitoring residue calendar life of high-temperature pressure-containing member outside furnace and method thereof
CN113793073A (en) Method for calculating real-time waste incineration amount of large-scale waste incineration power plant
CN110610276B (en) Comprehensive energy system scheduling method and system containing generalized predictive control
CN204202642U (en) A kind of electric power system region environment monitoring system
CN103968879A (en) Area environmental protection monitoring method for power supply system
CN103968880A (en) Area environmental protection monitoring system for power supply system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant