CN113869874A - Project information collaborative management system based on big data - Google Patents

Project information collaborative management system based on big data Download PDF

Info

Publication number
CN113869874A
CN113869874A CN202111187365.6A CN202111187365A CN113869874A CN 113869874 A CN113869874 A CN 113869874A CN 202111187365 A CN202111187365 A CN 202111187365A CN 113869874 A CN113869874 A CN 113869874A
Authority
CN
China
Prior art keywords
auxiliary
project
materials
auditing
audit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202111187365.6A
Other languages
Chinese (zh)
Inventor
刘璐
凌汉
章政
李儒�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Mingjiang Technology Service Co ltd
Original Assignee
Hefei Mingjiang Technology Service Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Mingjiang Technology Service Co ltd filed Critical Hefei Mingjiang Technology Service Co ltd
Priority to CN202111187365.6A priority Critical patent/CN113869874A/en
Publication of CN113869874A publication Critical patent/CN113869874A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/95Retrieval from the web
    • G06F16/953Querying, e.g. by the use of web search engines

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Databases & Information Systems (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Quality & Reliability (AREA)
  • Marketing (AREA)
  • Economics (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project information collaborative management system based on big data, which is used for solving the problem that the efficiency of a project declaration process is low because an existing project information management platform cannot analyze according to auxiliary parameters to obtain a material collaborative value of an auxiliary auditing end, so that the auxiliary auditing end is reasonably selected to carry out auxiliary auditing on project declaration materials submitted by enterprises through the material collaborative value; the system comprises a data acquisition module, a collaborative management platform, a project declaration module and a request processing module; according to the project declaration processing method, the project declaration request signaling is processed through the request processing module, the auxiliary parameters are analyzed and processed to obtain the material cooperation value of the auxiliary auditing end, and therefore the auxiliary auditing end is reasonably selected to carry out auxiliary auditing on project declaration materials submitted by enterprises through the material cooperation value, so that the problems of submitted materials are reduced, the workload of a project approval mechanism is reduced, and the project declaration efficiency is improved.

Description

Project information collaborative management system based on big data
Technical Field
The invention relates to the technical field of project collaborative management, in particular to a project information collaborative management system based on big data.
Background
The project declaration refers to a series of preferential policies made by an organization for an enterprise or other research units, and the enterprise or related research units write declaration files according to government policies and then declare according to related declaration requirements and processes. The applicable projects comprise projects of different levels such as scientific and technological small and medium-sized enterprise innovation funds, small and medium-sized enterprise development special funds, enterprise scientific and technological new technologies and the like, and the qualification and conditions of the application enterprises are different. The existing enterprise applies for the first time again, because of insufficient experience, a plurality of problems can occur, and therefore a project auxiliary mechanism is required to perform cooperative processing so as to reduce the problems and improve the project declaration efficiency; the conventional project information management platform cannot analyze according to auxiliary parameters to obtain a material cooperation value of an auxiliary auditing end, so that project declaration materials submitted by enterprises are subjected to auxiliary auditing by reasonably selecting the auxiliary auditing end according to the material cooperation value, and the efficiency of a project declaration process is low.
Disclosure of Invention
The invention aims to provide a project information collaborative management system based on big data, aiming at solving the problem that the project declaration process efficiency is low because the conventional project information management platform can not analyze according to auxiliary parameters to obtain the material collaborative value of an auxiliary auditing end, so that the auxiliary auditing end is reasonably selected to carry out auxiliary auditing on project declaration materials submitted by enterprises through the material collaborative value.
The purpose of the invention can be realized by the following technical scheme: the project information collaborative management system based on big data comprises a data acquisition module, a collaborative management platform, a project declaration module and a request processing module; the data acquisition module is used for acquiring project information of the enterprise declaration project and sending the project information to the collaborative management platform for storage; the project declaration module is used for displaying project information, checking the project information, declaring the project and submitting project declaration request signaling by the enterprise main body, and sending the project declaration request signaling to the request processing module; the project declaration request signaling comprises a declared project name, an enterprise subject name and a project declaration confirmation instruction;
the request processing module is used for processing the project declaration request signaling, and the specific processing process is as follows:
analyzing the project declaration request signaling to obtain an enterprise main body name corresponding to the project declaration request, acquiring enterprise data corresponding to the enterprise main body name through the Internet and sending the enterprise data to a primary examination end; the initial auditing end audits the request processing module, and a passing instruction is fed back to the request processing module when the audit is passed; when a passing instruction is received, acquiring a bill of materials name corresponding to the project name and feeding back the bill of materials name to the enterprise main body; after receiving the name of the bill of materials, the enterprise main body submits the materials corresponding to the name of the bill of materials within a preset time range; dividing the received materials into a plurality of parts of materials according to the names of the bill of materials, and respectively marking each part of materials as the materials to be distributed; acquiring all auxiliary auditing terminals corresponding to the materials to be distributed and auxiliary parameters of the auxiliary auditing terminals; analyzing the auxiliary parameters, and obtaining a material coordination value CX of an auxiliary auditing end by using a formula CX (FG × HD1+ FS × HD 2); HD1 and HD2 are preset ratios, and take values of 0.7 and 0.3; sending a material cooperation signaling to an auxiliary auditing end with the maximum material cooperation value to obtain a result fed back by the auxiliary auditing end; when the result is a confirmation instruction, marking the auxiliary auditing end as a collaborative auditing end; when the result is a negative instruction, sending a material cooperation signaling to an auxiliary auditing end with the next material cooperation value to obtain a feedback result, when the result is a confirmation instruction, marking the auxiliary auditing end as a cooperation auditing end, when the result is a negative instruction, sending the material cooperation signaling to an auxiliary auditing end with the next material cooperation value, and so on;
sending the material to be distributed to the collaborative audit end and receiving a collaborative processing result fed back by the collaborative audit end, and marking the material to be distributed as a qualified material when the collaborative processing result is a problem-free instruction; when the cooperative processing result is a problem instruction and a correction prompt, the problem instruction and the correction prompt are sent to the corresponding enterprise end; the enterprise terminal corrects the material to be distributed according to the correction prompt and feeds the material to be distributed back to the request processing module; the request processing module sends the corrected material to be distributed to a collaborative auditing end; when the received cooperative processing result fed back by the cooperative audit end is a no-problem instruction, marking the material to be distributed as a qualified material;
when all the materials to be distributed are qualified materials, marking all the qualified materials as project declaration materials of an enterprise end and sending the project declaration materials to a project declaration auditing mechanism;
as a preferred embodiment of the present invention, the present invention further includes:
the registration login module is used for the project auxiliary company to submit company registration information for registration and send the company registration information which is successfully registered to the collaborative management platform; the company registration information comprises the name and registration data of a company, the personnel data of the company, auxiliary project data categories and the like; the collaborative management platform marks the successfully registered auxiliary companies as auxiliary auditing terminals;
and the auxiliary acquisition module is used for acquiring audit data of the auxiliary audit end and sending the audit data to the cooperative management platform, wherein the audit data comprises the time of receiving the material to be distributed, the time of feeding back the result, the total times of receiving the distributed material by the auxiliary audit end, the number of the problem modification positions corresponding to the qualified material fed back by the project application audit mechanism and the times of feeding back the qualified material by the project application audit mechanism without problems.
As a preferred embodiment of the present invention, the present invention further includes:
the parameter analysis module is used for acquiring the company registration information and the audit data of the auxiliary audit terminal and performing analysis processing to obtain the auxiliary parameters of the auxiliary audit terminal, and the specific analysis processing process comprises the following steps:
processing the company registration information, and calculating the time difference between the registration time of the auxiliary auditing end and the current time to obtain the establishment duration of the auxiliary auditing end; processing company personnel data, summing working durations of all company personnel at the auxiliary auditing end and taking an average value to obtain a working average value; normalizing the establishment duration, the working average and the number of the companies of the auxiliary auditing end, and taking the normalized values of the three, and respectively marking the normalized values as ST1, ST2 and ST 3; substitution formula
Figure BDA0003299812770000031
Obtaining an auxiliary value FS of an auxiliary auditing end; wherein bs1, bs2 and bs3 are all preset weighting factors;
processing the audit data, and calculating the time difference between the time of the material to be distributed and the time of the feedback result to obtain the single audit duration; summing all the single auditing durations and averaging to obtain an auditing average duration; summing the number of the modification treatment of the problems corresponding to all the feedback qualified materials, and dividing the sum by the total number of times of distributing the materials to obtain a modification number ratio; normalizing the mean value auditing time, the number of times that the qualified material has no problem and the modification quantity ratio, taking the values of the normalized mean value auditing time, the normalized qualified material verifying time and the normalized quantity ratio, and respectively marking the three normalized values as SD1, SD2 and SD 3; substitution formula
Figure BDA0003299812770000041
Obtaining an auxiliary audit value FG of an auxiliary audit terminal; wherein g1, g2 and g3 are preset weight factors;
and marking the auxiliary value and the auxiliary audit value as auxiliary parameters of an auxiliary audit end and sending the auxiliary parameters to the collaborative management platform for storage.
As a preferred embodiment of the present invention, the present invention further includes:
the progress acquisition module is used for acquiring progress data of materials corresponding to the material list names submitted by the enterprise terminal at the initial review terminal, the collaborative review terminal and the project declaration review mechanism and sending the progress data to the collaborative management platform;
and the query access module is used for querying the progress data of the materials corresponding to the submitted material list name by the enterprise terminal.
Compared with the prior art, the invention has the beneficial effects that: the project declaration request signaling is processed through the request processing module, and after the enterprise main body receives the material list name, the enterprise main body submits the material corresponding to the material list name within a preset time range; dividing the received materials into a plurality of parts of materials according to the names of the bill of materials, and marking each part of materials as the materials to be distributed; acquiring all auxiliary auditing terminals corresponding to the materials to be distributed and auxiliary parameters of the auxiliary auditing terminals; the auxiliary parameters are analyzed to obtain the material cooperation value of the auxiliary auditing end, so that the auxiliary auditing end is reasonably selected to perform auxiliary auditing on the project declaration materials submitted by enterprises, the problems of submitted materials are reduced, the workload of a project approval mechanism is reduced, and the project declaration efficiency is improved.
Drawings
In order to facilitate understanding for those skilled in the art, the present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a schematic block diagram of the system of the present invention.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the following embodiments, and it should be understood that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1, the project information collaborative management system based on big data includes a data acquisition module, a collaborative management platform, a project declaration module, a request processing module, a registration login module, an auxiliary acquisition module, a parameter analysis module, a progress acquisition module, and an update reminding module;
the data acquisition module acquires project information of an enterprise declaration project and sends the project information to the collaborative management platform for storage;
the project declaration module is used for displaying project information, checking the project information and project declaration by the enterprise main body, submitting project declaration request signaling and sending the project declaration request signaling to the request processing module; the project declaration request signaling comprises a declared project name, an enterprise subject name and a project declaration confirmation instruction;
the request processing module is used for processing the project declaration request signaling, and the specific processing process is as follows:
analyzing the project declaration request signaling to obtain an enterprise main body name corresponding to the project declaration request, acquiring enterprise data corresponding to the enterprise main body name through the Internet and sending the enterprise data to a primary examination end; the initial auditing end is an initial auditing organization of the government and is used for evaluating whether the enterprise main body meets the declaration conditions corresponding to the project declaration types;
the initial auditing end audits the request processing module, and a passing instruction is fed back to the request processing module when the audit is passed; when a passing instruction is received, acquiring a bill of materials name corresponding to the project name and feeding back the bill of materials name to the enterprise main body; after receiving the name of the bill of materials, the enterprise main body submits the materials corresponding to the name of the bill of materials within a preset time range;
dividing the received materials into a plurality of parts of materials according to the names of the bill of materials, and respectively marking each part of materials as the materials to be distributed; acquiring all auxiliary auditing terminals corresponding to the materials to be distributed and auxiliary parameters of the auxiliary auditing terminals; the auxiliary parameters comprise an auxiliary value and an auxiliary review value; the auxiliary value and the auxiliary review value are obtained by analyzing through a parameter analysis module, and the specific analysis process is as follows: processing the company registration information, and calculating the time difference between the registration time of the auxiliary auditing end and the current time to obtain the establishment duration of the auxiliary auditing end; processing company personnel data, summing working durations of all company personnel at the auxiliary auditing end and taking an average value to obtain a working average value; normalizing the establishment duration, the working average and the number of the companies of the auxiliary auditing end, and taking the normalized values of the three, and respectively marking the normalized values as ST1, ST2 and ST 3;
substitution formula
Figure BDA0003299812770000061
Obtaining an auxiliary value FS of an auxiliary auditing end; wherein bs1, bs2 and bs3 are all preset weighting factors; the values are 1.7, 2.3 and 4.7;
processing the audit data, and calculating the time difference between the time of the material to be distributed and the time of the feedback result to obtain the single audit duration; summing all the single auditing durations and averaging to obtain an auditing average duration; summing the number of the modification treatment of the problems corresponding to all the feedback qualified materials, and dividing the sum by the total number of times of distributing the materials to obtain a modification number ratio; then the length of the audit mean value,Normalizing the times and the modification quantity ratio of the qualified materials without problems, taking the normalized values of the three, and respectively marking the normalized values as SD1, SD2 and SD 3; substitution formula
Figure BDA0003299812770000062
Obtaining an auxiliary audit value FG of an auxiliary audit terminal; wherein g1, g2 and g3 are preset weight factors; the values are 0.4, 0.3 and 0.7;
analyzing the auxiliary parameters, and obtaining a material coordination value CX of an auxiliary auditing end by using a formula CX (FG × HD1+ FS × HD 2); HD1 and HD2 are preset ratios, and take values of 0.7 and 0.3;
sending a material cooperation signaling to an auxiliary auditing end with the maximum material cooperation value to obtain a result fed back by the auxiliary auditing end; when the result is a confirmation instruction, marking the auxiliary auditing end as a collaborative auditing end; when the result is a negative instruction, sending a material cooperation signaling to an auxiliary auditing end with the next material cooperation value to obtain a feedback result, when the result is a confirmation instruction, marking the auxiliary auditing end as a cooperation auditing end, when the result is a negative instruction, sending the material cooperation signaling to an auxiliary auditing end with the next material cooperation value, and so on;
sending the material to be distributed to the collaborative audit end and receiving a collaborative processing result fed back by the collaborative audit end, and marking the material to be distributed as a qualified material when the collaborative processing result is a problem-free instruction; when the cooperative processing result is a problem instruction and a correction prompt, the problem instruction and the correction prompt are sent to the corresponding enterprise end; the enterprise terminal corrects the material to be distributed according to the correction prompt and feeds the material to be distributed back to the request processing module; the request processing module sends the corrected material to be distributed to a collaborative auditing end; when the received cooperative processing result fed back by the cooperative audit end is a no-problem instruction, marking the material to be distributed as a qualified material;
when all the materials to be distributed are qualified materials, marking all the qualified materials as project declaration materials of an enterprise end and sending the project declaration materials to a project declaration auditing mechanism; the project declaration auditing mechanism is a project approval mechanism corresponding to the government and is used for auditing and identifying project declaration materials at an enterprise end and feeding back correction places, quantities and the like corresponding to the project declaration materials;
the registration login module is used for the project auxiliary company to submit company registration information for registration and send the company registration information which is successfully registered to the collaborative management platform; the company registration information comprises the name and registration data of a company, the personnel data of the company, auxiliary project data categories and the like; the collaborative management platform marks the successfully registered auxiliary companies as auxiliary auditing terminals; the project auxiliary company is a third-party company and is used for carrying out auxiliary auditing on materials required by the project submitted by the enterprise, so that the problem of submitting the materials is reduced, the workload of a project approval mechanism is reduced, and the project declaration efficiency is improved;
the auxiliary acquisition module is used for acquiring audit data of the auxiliary audit end and sending the audit data to the collaborative management platform, wherein the audit data comprises the time of receiving the material to be distributed, the time of feeding back the result, the total times of receiving the distributed material by the auxiliary audit end, the number of the problem modification positions corresponding to the problem feedback qualified material of the project declaration audit organization and the times of feeding back the qualified material by the project declaration audit organization without problems;
the formulas are obtained by acquiring a large amount of data and performing software simulation, and the coefficients in the formulas are set by the technicians in the field according to actual conditions;
the progress acquisition module is used for acquiring progress data of materials corresponding to the material list names submitted by the enterprise terminal at the initial auditing terminal, the collaborative auditing terminal and the project declaration auditing mechanism and sending the progress data to the collaborative management platform;
the query access module is used for querying progress data of materials corresponding to the submitted bill of materials names by the enterprise terminal;
the update reminding module is used for acquiring the initial time and the end time of the enterprise terminal by logging in the cooperative management platform and checking progress data, and carrying out update reminding processing, and the specific process is as follows: marking the initial time and the end time of the viewing progress data as Ai and Bi; i represents the number corresponding to the initial time and the end time; 1,2, … …, n; n is a positive integer; sequencing all initial moments and finishing moments according to a time sequence, wherein the time sequence is A1, B1, A2, B2, … …, Ai, Bi, … …, An and Bn; calculating the time difference between the initial time and the ending time to obtain an access duration, namely A1-B1; calculating the time difference between the adjacent end time and the initial time to obtain the interval duration, namely B1-A2; summing all the access time lengths to obtain the total access time length and marking the total access time length as FT 1; summing all the interval durations and averaging to obtain an access interval mean duration and marking as FT 2; extracting values of total access time length and average access interval time length;
the more wake value FZ is obtained by using the formula FZ ═ (FT1 × 2.7+1)/(FT2+ 1); when the awakening value is larger than the set threshold value; the enterprise end mark is marked as an update reminding enterprise by the update reminding module and is sent to the progress acquisition module;
and after receiving the update reminding enterprise, the progress acquisition module sends the new progress data to the collaborative management platform and the update reminding enterprise when acquiring the new progress data of the update reminding enterprise.
When the system is used, a project declaration request signaling is processed through the request processing module, and after the enterprise main body receives the bill of materials name, materials corresponding to the bill of materials name are submitted within a preset time range; dividing the received materials into a plurality of parts of materials according to the names of the bill of materials, and marking each part of materials as the materials to be distributed; acquiring all auxiliary auditing terminals corresponding to the materials to be distributed and auxiliary parameters of the auxiliary auditing terminals; analyzing and processing the auxiliary parameters to obtain a material cooperation value of an auxiliary auditing end; sending a material cooperation signaling to an auxiliary auditing end with the maximum material cooperation value to obtain a result fed back by the auxiliary auditing end; when the result is a confirmation instruction, marking the auxiliary auditing end as a collaborative auditing end; sending the material to be distributed to the collaborative audit end and receiving a collaborative processing result fed back by the collaborative audit end, and marking the material to be distributed as a qualified material when the collaborative processing result is a problem-free instruction; when all the materials to be distributed are qualified materials, all the qualified materials are marked as project declaration materials of an enterprise end and are sent to a project declaration auditing mechanism, the project declaration auditing mechanism is used for auditing the project declaration materials submitted by the enterprise end, and the auxiliary value of the auxiliary auditing end are processed to obtain the material cooperation value of the auxiliary auditing end, so that the project declaration materials submitted by the enterprise are subjected to auxiliary auditing by reasonably selecting the auxiliary auditing end through the material cooperation value, the problems of submitted materials are reduced, the workload of the project auditing mechanism is reduced, and the project declaration efficiency is improved.
The preferred embodiments of the invention disclosed above are intended to be illustrative only. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise forms disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and the practical application, to thereby enable others skilled in the art to best utilize the invention. The invention is limited only by the claims and their full scope and equivalents.

Claims (5)

1. The project information collaborative management system based on big data comprises a data acquisition module, a collaborative management platform, a project declaration module and a request processing module; the data acquisition module is used for acquiring project information of the enterprise declaration project and sending the project information to the collaborative management platform for storage; the system is characterized in that the project declaration module is used for displaying project information, checking the project information, declaring the project and submitting project declaration request signaling by the enterprise main body, and sending the project declaration request signaling to the request processing module;
the request processing module is used for processing the project declaration request signaling, and the specific processing process is as follows:
analyzing the project declaration request signaling to obtain an enterprise main body name corresponding to the project declaration request, acquiring enterprise data corresponding to the enterprise main body name through the Internet and sending the enterprise data to a primary examination end; the initial auditing end audits the request processing module, and a passing instruction is fed back to the request processing module when the audit is passed; when a passing instruction is received, acquiring a bill of materials name corresponding to the project name and feeding back the bill of materials name to the enterprise main body; after receiving the name of the bill of materials, the enterprise main body submits the materials corresponding to the name of the bill of materials within a preset time range; dividing the received materials into a plurality of parts of materials according to the names of the bill of materials, and respectively marking each part of materials as the materials to be distributed; acquiring all auxiliary auditing terminals corresponding to the materials to be distributed and auxiliary parameters of the auxiliary auditing terminals; analyzing and processing the auxiliary parameters to obtain a material cooperation value of an auxiliary auditing end; sending a material cooperation signaling to an auxiliary auditing end with the maximum material cooperation value to obtain a result fed back by the auxiliary auditing end; when the result is a confirmation instruction, marking the auxiliary auditing end as a collaborative auditing end;
sending the material to be distributed to the collaborative audit end and receiving a collaborative processing result fed back by the collaborative audit end, and marking the material to be distributed as a qualified material when the collaborative processing result is a problem-free instruction; when the cooperative processing result is a problem instruction and a correction prompt, the problem instruction and the correction prompt are sent to the corresponding enterprise end; the enterprise terminal corrects the material to be distributed according to the correction prompt and feeds the material to be distributed back to the request processing module; the request processing module sends the corrected material to be distributed to a collaborative auditing end; when the received cooperative processing result fed back by the cooperative audit end is a no-problem instruction, marking the material to be distributed as a qualified material;
and when all the materials to be distributed are qualified materials, marking all the qualified materials as project declaration materials of the enterprise end and sending the project declaration materials to a project declaration auditing mechanism.
2. The collaborative management system for project information based on big data according to claim 1, further comprising:
the registration login module is used for the project auxiliary company to submit company registration information for registration and send the company registration information which is successfully registered to the collaborative management platform; the collaborative management platform marks the successfully registered auxiliary companies as auxiliary auditing terminals;
and the auxiliary acquisition module is used for acquiring the audit data of the auxiliary audit end and sending the audit data to the cooperative management platform.
3. The collaborative management system for project information based on big data according to claim 2, further comprising:
the parameter analysis module is used for acquiring the company registration information and the audit data of the auxiliary audit terminal and performing analysis processing to obtain the auxiliary parameters of the auxiliary audit terminal, and the specific analysis processing process comprises the following steps:
processing the company registration information, and calculating the time difference between the registration time of the auxiliary auditing end and the current time to obtain the establishment duration of the auxiliary auditing end; processing company personnel data, summing working durations of all company personnel at the auxiliary auditing end and taking an average value to obtain a working average value; then, normalization processing is carried out on the establishment duration, the working average and the number of the company people of the auxiliary auditing end to obtain an auxiliary value of the auxiliary auditing end;
processing the audit data, and calculating the time difference between the time of the material to be distributed and the time of the feedback result to obtain the single audit duration; summing all the single auditing durations and averaging to obtain an auditing average duration; summing the number of the modification treatment of the problems corresponding to all the feedback qualified materials, and dividing the sum by the total number of times of distributing the materials to obtain a modification number ratio; then, normalizing the mean audit duration, the number of times that the qualified materials have no problem and the modification quantity ratio to obtain an auxiliary audit value of an auxiliary audit end;
and marking the auxiliary value and the auxiliary audit value as auxiliary parameters of an auxiliary audit end and sending the auxiliary parameters to the collaborative management platform for storage.
4. The collaborative management system for project information based on big data according to claim 3, further comprising:
the progress acquisition module is used for acquiring progress data of materials corresponding to the material list names submitted by the enterprise terminal at the initial review terminal, the collaborative review terminal and the project declaration review mechanism and sending the progress data to the collaborative management platform;
and the query access module is used for querying the progress data of the materials corresponding to the submitted material list name by the enterprise terminal.
5. The collaborative management system for project information based on big data according to claim 4, wherein the project declaration request signaling includes a declared project name and an enterprise subject name and a project declaration confirmation instruction; the auditing data comprise the time of receiving the material to be distributed, the time of feeding back the result, the total times of receiving the distributed material by the auxiliary auditing end, the number of the problem modification positions corresponding to the qualified material fed back by the project application auditing mechanism and the times of feeding back the qualified material by the project application auditing mechanism without problems.
CN202111187365.6A 2021-10-12 2021-10-12 Project information collaborative management system based on big data Withdrawn CN113869874A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111187365.6A CN113869874A (en) 2021-10-12 2021-10-12 Project information collaborative management system based on big data

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111187365.6A CN113869874A (en) 2021-10-12 2021-10-12 Project information collaborative management system based on big data

Publications (1)

Publication Number Publication Date
CN113869874A true CN113869874A (en) 2021-12-31

Family

ID=78999082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111187365.6A Withdrawn CN113869874A (en) 2021-10-12 2021-10-12 Project information collaborative management system based on big data

Country Status (1)

Country Link
CN (1) CN113869874A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115907277A (en) * 2023-01-09 2023-04-04 深圳市全息医疗科技有限公司 Hospital performance intelligent review system and implementation method
CN116934246A (en) * 2023-06-20 2023-10-24 联城科技(河北)股份有限公司 Method, device, equipment and readable storage medium for auditing declaration project data

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115907277A (en) * 2023-01-09 2023-04-04 深圳市全息医疗科技有限公司 Hospital performance intelligent review system and implementation method
CN116934246A (en) * 2023-06-20 2023-10-24 联城科技(河北)股份有限公司 Method, device, equipment and readable storage medium for auditing declaration project data

Similar Documents

Publication Publication Date Title
CN113869874A (en) Project information collaborative management system based on big data
CN107862450A (en) Performance appraisal system and method
CN115619134B (en) Engineering service-based mechanic platform construction method and system
CN110689325A (en) Information processing method, device and computer readable storage medium
CN111898971A (en) Wisdom building site peasant salary guarantee management platform
CN107025601A (en) Verification of data method, device and equipment
CN115577969A (en) Efficient multidimensional management method for enterprises
CN111353713A (en) Product quality certification management system for factory production
CN112801802A (en) Method, system and equipment for supervising financial special funds based on block chain
CN108681811B (en) Decentralized data ecosystem
CN117094689A (en) Novel human resource management system
CN113420987A (en) Demand scheduling method, device, server and computer readable storage medium
CN112288386A (en) Information management system for enterprise staff
CN116308225B (en) Human resource management system and method with intelligent accounting salary
CN111222965A (en) Client financial reimbursement management method
CN108960775A (en) A kind of enterprises registration electronic service method based on mobile terminal
CN115471099A (en) Scientific and technological achievement transformation service platform based on Internet
CN113537916B (en) Intelligent scientific research project management method based on scientific research data analysis
CN114066413A (en) Digitalized talent recruitment interview method and system
CN113592353A (en) Communication supervision project quality detection method
CN111709703A (en) Project review management system capable of accurately guiding project design
CN111754058A (en) Project management system based on project audit
Tikhonova Modeling the Social Consequences of Industrial Robotization
Zhang et al. Carbon market evaluation based on random walk hypothesis in China
CN113256249B (en) Special labor protection article informatization monitoring system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20211231