CN113743782A - Elevator inspection process optimization method and optimization system based on overall planning method - Google Patents

Elevator inspection process optimization method and optimization system based on overall planning method Download PDF

Info

Publication number
CN113743782A
CN113743782A CN202111033636.2A CN202111033636A CN113743782A CN 113743782 A CN113743782 A CN 113743782A CN 202111033636 A CN202111033636 A CN 202111033636A CN 113743782 A CN113743782 A CN 113743782A
Authority
CN
China
Prior art keywords
inspection
elevator
elevator inspection
procedure
route
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111033636.2A
Other languages
Chinese (zh)
Inventor
罗恒
张东平
程航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING SPECIAL EQUIPMENT INSPECTION AND RESEARCH INSTITUTE
Original Assignee
CHONGQING SPECIAL EQUIPMENT INSPECTION AND RESEARCH INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING SPECIAL EQUIPMENT INSPECTION AND RESEARCH INSTITUTE filed Critical CHONGQING SPECIAL EQUIPMENT INSPECTION AND RESEARCH INSTITUTE
Priority to CN202111033636.2A priority Critical patent/CN113743782A/en
Publication of CN113743782A publication Critical patent/CN113743782A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K19/00Record carriers for use with machines and with at least a part designed to carry digital markings
    • G06K19/06Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code
    • G06K19/06009Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code with optically detectable marking
    • G06K19/06037Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code with optically detectable marking multi-dimensional coding
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Indicating And Signalling Devices For Elevators (AREA)
  • Maintenance And Inspection Apparatuses For Elevators (AREA)

Abstract

The invention discloses an elevator inspection process optimization method and an elevator inspection process optimization system based on an overall planning method. Belong to elevator inspection technical field, include: making an elevator inspection process route; drawing an overall plan; optimizing the elevator inspection procedure route to obtain an elevator inspection procedure optimization scheme; generating an inspection work order according to the elevator inspection procedure optimization scheme, and attaching a corresponding work order two-dimensional code to the inspection work order; and finishing elevator inspection work according to the work order two-dimensional code. Through carrying out meticulous division to each process in the inspection, drawing inspection flow overall plan, utilize time parameter to calculate, form the best optimization scheme of elevator inspection process flow and form the inspection worksheet that has the two-dimensional code, carry out inspection work through the inspection worksheet that has the two-dimensional code, shorten check-out time, can show improvement inspection efficiency and quality to very strong maneuverability has.

Description

Elevator inspection process optimization method and optimization system based on overall planning method
Technical Field
The invention relates to the technical field of elevator inspection, in particular to an elevator inspection procedure optimization method and an elevator inspection procedure optimization system based on an overall planning method.
Background
At present, with the increasing of urban high-rise buildings, elevators are widely applied to daily trips of people, and inspection of the elevators is carried out by inspection institutions with inspection qualification to execute standard regulation and implement safety responsibility to elevator production and use units according to inspection regulations, so as to carry out verification inspection for ensuring and autonomously confirming relevant working quality conditions of elevator safety. The traditional elevator inspection process is that an inspector carries out inspection items one by one according to the sequence of each inspection item in an elevator inspection gauge, and the inspection cannot omit any inspection item in the manner, so that the integrity of inspection contents is ensured.
However, in the face of the rapid increase of the current elevator inspection task and the requirements on elevator inspection timeliness and quality, the traditional inspection process flow obviously cannot meet the current inspection work gradually.
The overall planning method is a scientific method which is reasonably arranged by applying the basic idea of overall planning and consideration and performing unified planning on complex and various works and is a branch of operational planning. However, although the overall scheme is applied to many applications, there is a gap in the technical field of elevator detection.
Therefore, how to provide an elevator inspection process optimization method and an elevator inspection process optimization system based on an overall planning method is a problem that needs to be solved urgently by those skilled in the art.
Disclosure of Invention
In view of the above, the invention provides an elevator inspection process optimization method and an elevator inspection process optimization system based on an overall planning method, which are characterized in that each process in the inspection is finely divided, an inspection process overall planning chart is drawn, a time parameter calculation is utilized to form an optimal elevator inspection process flow optimization scheme and an inspection work order with two-dimensional codes, the inspection work is performed through the inspection work order with the two-dimensional codes, the inspection time is shortened, the inspection efficiency and quality can be remarkably improved, and the elevator inspection process optimization method and the elevator inspection process optimization system have strong operability.
In order to achieve the above purpose, the invention provides the following technical scheme:
on one hand, the invention provides an elevator inspection process optimization method based on an overall planning method, which comprises the following steps:
s100: acquiring elevator inspection project data, calculating the correlation degree between elevator inspection projects, and formulating an elevator inspection process route according to the correlation degree;
s200: drawing a planning chart according to the elevator inspection process route;
s300: optimizing the elevator inspection procedure route according to the overall plan to obtain an elevator inspection procedure optimization scheme;
s400: generating a checking work order according to the elevator checking procedure optimization scheme, and generating a corresponding work order two-dimensional code;
s500: and finishing elevator inspection work according to the work order two-dimensional code.
Preferably, the S300 includes the steps of:
s310: calculating the time required by each section of procedure route according to the overall planning map;
s320: determining a key process route and a non-key process route according to the time required by each section of process route;
s330: and optimizing the elevator inspection procedure route according to the key procedure route and the non-key procedure route to obtain an elevator inspection procedure optimization scheme.
Preferably, the work order two-dimensional code includes: process type ID, type of work used, inspection instrument used, inspection threshold, and inspection data entry box.
Preferably, the S500 includes:
s510: identifying the work order two-dimensional code, and displaying the current process type ID, the current work type, the current inspection instrument, the current inspection threshold and an inspection data entry frame;
s520: inputting a detection result into the detection data input frame to confirm that the detection procedure is completed;
s530: and distributing the work order two-dimensional codes filled with the inspection results to the next inspection process, scanning the codes by staff of the next inspection process to pick up the task of the inspection process, returning to S510 to carry out the next inspection process until all the inspection processes are completed, and obtaining an elevator inspection report.
Preferably, the S500 further includes: and performing over-range alarm analysis and predictive maintenance analysis on the elevator inspection report to obtain an inspection analysis result, and optimizing an elevator inspection process route according to a key process route, a non-key process route and the inspection analysis result to obtain an elevator inspection process optimization scheme.
In another aspect, the present invention provides an elevator inspection process optimization system based on a coordination method, including:
the acquisition module is used for acquiring elevator inspection project data, calculating the correlation degree between elevator inspection projects and formulating an elevator inspection process route according to the correlation degree;
the drawing module is connected with the acquisition module and draws a planning chart according to the elevator inspection procedure route;
the optimization module is connected with the drawing module and used for optimizing the elevator inspection procedure route according to the overall plan to obtain an elevator inspection procedure optimization scheme;
the generating module is connected with the optimizing module, generates an inspection work order according to the elevator inspection procedure optimizing scheme, and attaches a corresponding work order two-dimensional code to the inspection work order;
a checking module: and the elevator inspection module is connected with the generation module and finishes elevator inspection work according to the work order two-dimensional code.
Preferably, the optimization module includes:
the first calculation unit is connected with the drawing module and calculates the time required by each section of process route according to the overall planning map;
the second calculation unit is connected with the first calculation unit and determines a key process route and a non-key process route according to the time required by each section of process route;
and the output unit is connected with the second calculation unit and is used for optimizing the elevator inspection procedure route according to the key procedure route and the non-key procedure route to obtain an elevator inspection procedure optimization scheme.
Preferably, the generation module includes a generation inspection work order unit and a generation work order two-dimensional code unit which are connected in sequence, and the generated work order two-dimensional code information includes: process type ID, type of work used, inspection instrument used, inspection threshold, and inspection data entry box.
Preferably, the inspection module comprises:
the identification unit is used for identifying the work order two-dimensional code and displaying the current process type ID, the current work type, the current inspection instrument, the current inspection threshold and the inspection data entry frame;
the entry unit is used for entering the overhaul start time, the number of the overhaul personnel and the inspection result in the inspection data entry frame and confirming that the inspection process is finished;
and the report generating unit is used for distributing the work order two-dimensional codes filled with the inspection results to the next inspection process, scanning the codes by staff of the next inspection process to pick up the inspection process tasks, returning to S510 to carry out the next inspection process, integrating the results of all the inspection process tasks and generating an elevator inspection report.
Preferably, the inspection module further comprises: and the analysis unit is used for performing out-of-range alarm analysis and predictive maintenance analysis on the elevator inspection report to obtain an inspection analysis result, sending the inspection analysis result to the second calculation unit, and optimizing the elevator inspection process route according to the key process route, the non-key process route and the inspection analysis result to obtain an elevator inspection process optimization scheme.
According to the technical scheme, compared with the prior art, the elevator inspection process optimization method and the elevator inspection process optimization system based on the overall method are provided, each process in inspection is finely divided, an inspection process overall diagram is drawn, a time parameter calculation is utilized, an optimal elevator inspection process flow optimization scheme is formed, inspection time is shortened, fine management is carried out on other elevator inspection projects and inspection processes for the later stage through the generated work order two-dimensional code, the elevator inspection process is more reasonable and ordered, the automation level is improved, visual inspection information and execution information of each inspection process are provided, query is convenient and fast, the requirements of equipment management of a production enterprise can be well met, inspection efficiency and quality can be remarkably improved, and strong operability is achieved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
Fig. 1 is a schematic flow chart of an elevator inspection process optimization method provided in this embodiment;
fig. 2 is an overall plan of an elevator inspection process provided in this embodiment;
fig. 3 is a schematic structural diagram of an elevator inspection process optimization system provided in this embodiment.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to the attached drawing 1, the embodiment of the invention provides an elevator inspection process optimization method based on an overall planning method, which comprises the following steps:
s100: acquiring elevator inspection project data, calculating the correlation degree between elevator inspection projects, and making an elevator inspection process route according to the correlation degree;
s200: drawing a planning chart according to the elevator inspection process route;
s300: optimizing the elevator inspection procedure route according to the overall plan to obtain an elevator inspection procedure optimization scheme;
s400: generating a checking work order according to the elevator checking procedure optimization scheme, and generating a corresponding work order two-dimensional code;
s500: and finishing elevator inspection work according to the work order two-dimensional code.
Specifically, the elevator inspection item data includes: machine room equipment, a car and counterweight, a steel wire rope and a suspension device, a landing and a door, pit equipment and the like;
specifically, the association degree matching is performed on 14 important process inspection items, and the association degree relation of the inspection items on multiple requirements in time and space is determined according to the process and organization requirements of the inspection items, for example, the precondition of 125% braking test is that the balance coefficient test is qualified. Thereby forming the following list of elevator inspection process routes:
TABLE 1 Elevator inspection Process route List
Figure BDA0003246148520000051
Figure BDA0003246148520000061
Specifically, the elevator inspection process overall plan is drawn according to an elevator inspection process route detail table obtained through analysis, the sequence and the interrelation of each process of elevator inspection are reflected in a network diagram mode, and the whole inspection process can be clearly calculated and analyzed through the overall plan.
More specifically, the drawing principle for drawing the overall plan is as follows:
(1) each process is connected by an arrow line and a front node and a rear node, the nodes are represented by circles, numbers are arranged in the circles, process codes are marked on the arrow line, and the duration of the process is written under the arrow line;
(2) only one arrow line is arranged between a pair of nodes, and a loop is not allowed to appear; if the parallel operation occurs, a virtual process can be introduced or the process can be artificially divided into two;
(3) the cross operation is not allowed to occur, and if the cross operation occurs, a virtual process is introduced;
(4) the node numbers increase from left to right, and the end node number of the process is greater than the start node number.
(5) The overall plot only has a starting point and an end point;
more specifically, referring to fig. 2, an elevator inspection process overall plan is drawn by using an elevator inspection process route list obtained by analysis, taking elevator periodic inspection as an example.
In particular, the circuit
Figure BDA0003246148520000062
T in (1)L(i)/TE(i)The relationship is as follows: 0/0 → 8/8 → 10/10 → 13/13 → 25/25 → 35/35 → 55/55 → 57/57 → 62/62, TL(i)=TE(i)Time difference of nodes R(i)All are 0, which indicates that the line is a key line, the used inspection time is longest, the total inspection time is 62 minutes, and 90 minutes is needed according to the traditional inspection process flow, so that the inspection time can be shortened by 30 percent by using a planning method, and the inspection efficiency can be obviously improved. In addition, after the key route is found out by a planning method, in the inspection process, if redundant manpower, material resources, resources and the like are inclined to the key route, the effect of further shortening the inspection time can be achieved by reducing the time of the key route.
In one embodiment, S300 includes the steps of:
s310: calculating the time required by each section of process route according to the overall plan;
s320: determining a key process route and a non-key process route according to the time required by each section of process route;
s330: and optimizing the elevator inspection procedure route according to the key procedure route and the non-key procedure route to obtain an elevator inspection procedure optimization scheme.
Specifically, the time required for each process route is calculated as follows:
the required time parameters are important indexes reflecting time progress of each process and the whole project, key processes and key routes in the overall scheme can be found out through calculation of the required time parameters, and rationality, efficiency and scientificity of the overall scheme can be guaranteed only by combining the overall scheme with the time parameters. The time parameters are not simply superposed on the duration time of the working procedures, but are comprehensively calculated by integrating parallel working procedures, cross working procedures, adjacent working procedures and the like, and mainly comprise parameters such as single working duration (D value), the earliest node realization time (TE (j)), the latest node realization time (TL (i)), the node time difference R (i) and the like
More specifically, the single process duration (D value) is calculated by the following method:
the duration (D value) of a single process is generally calculated in two ways: empirical and expert methods (mean) and three-point estimation (also known as sextant).
(1) Empirical and expert methods (mean): the method is suitable for repeated work and has few uncertain factors. The main parameter dj is the estimate (or trial value) of the duration of the procedure by expert j (or the j-th trial repeated).
Figure BDA0003246148520000071
(2) Three-point estimation (also called sextant): and obtaining an empirical formula according to the probability distribution. The main parameters are a (the most optimistic time for the process duration), b (the most pessimistic time for the process duration), and M (the most probable time for the process duration).
Figure BDA0003246148520000072
The procedures in the elevator inspection are various and complex, wherein some procedures are not changed greatly and have strong repeatability, and some procedures are influenced by factors such as site environment, resource allocation and the like, so that when the duration of a single procedure is calculated, a proper calculation method is selected according to the content and the characteristics of the procedure, and the calculation error can be reduced to the minimum. For example: the data examination is generally in a fixed mode, the duration time is not very different, and the method is suitable for an empirical method and a professional method; the 125% braking test is greatly influenced by factors such as the technical level of field coordinators, and a three-point estimation method is suitable for the 125% braking test.
More specifically, the method for calculating the earliest implementation time (te (j)) of the node is as follows:
the earliest realization time of the node refers to the earliest realized time limit of the node on the premise of ensuring that all the immediately previous processes can be completed, which is called as early knot for short, and the specific calculation formula is as follows:
Figure BDA0003246148520000081
more specifically, the method for calculating the latest realization time (tl (i)) of the node is as follows:
the latest realization time (tl (i)) of a node is a time limit for the latest realization of the node under the premise of ensuring that all the operations immediately after the node are not delayed, which is also called as delay, and a specific calculation formula is as follows:
Figure BDA0003246148520000082
more specifically, the method for calculating the node time difference r (i) comprises the following steps:
the node time difference r (i) is the latest realization time of the node minus the earliest realization time of the node, i.e. the maneuvering time of the node. In the overall graph line, when the node time difference r (i) is 0, it represents the time of the node without movement, the procedure in which the two adjacent nodes r (i) are both 0 is called a key procedure, and the lines in which all the nodes r (i) are 0 in the whole line are called key lines, and the specific calculation formula is as follows:
R(i)=TL(i)-TE(i)
optimizing the elevator inspection process route according to the obtained key process route and non-key process route to obtain an elevator inspection process optimization scheme
In one embodiment, the work order two-dimensional code information includes: process type ID, type of work used, inspection instrument used, inspection threshold, and inspection data entry box.
In a specific embodiment, S500 includes:
s510: identifying the work order two-dimensional code, and displaying the current process type ID, the current work type, the current inspection instrument, the current inspection threshold and an inspection data entry frame;
s520: inputting a detection result into the detection data input frame to confirm that the detection procedure is completed;
s530: and distributing the work order two-dimensional codes filled with the inspection results to the next inspection process, scanning the codes by staff of the next inspection process to pick up the task of the inspection process, returning to S510 to carry out the next inspection process until all the inspection processes are completed, and obtaining an elevator inspection report.
In a specific embodiment, S500 further includes: and performing over-range alarm analysis and predictive maintenance analysis on the elevator inspection report to obtain an inspection analysis result, and optimizing the elevator inspection process route according to the key process route, the non-key process route and the inspection analysis result to obtain an elevator inspection process optimization scheme.
Specifically, other inspection projects and inspection processes of the elevator are subjected to fine management in the later period through the generated work order two-dimensional code, the automation level is improved, inspection information and execution information of all sections of inspection processes can be visual, the query is convenient and quick, and the requirement of equipment management of a production enterprise can be well met.
Referring to fig. 3, the present embodiment provides an elevator inspection process optimization system based on an orchestration method, including:
the acquisition module is used for acquiring elevator inspection project data, calculating the correlation degree between elevator inspection projects and formulating an elevator inspection process route according to the correlation degree;
the drawing module is connected with the acquisition module and is used for drawing a planning chart according to the elevator inspection procedure route;
the optimization module is connected with the drawing module and used for optimizing the elevator inspection procedure route according to the overall plan to obtain an elevator inspection procedure optimization scheme;
the generating module is connected with the optimizing module, generates an inspection work order according to the elevator inspection procedure optimizing scheme, and attaches the corresponding work order two-dimensional code to the inspection work order;
a checking module: and the elevator inspection module is connected with the generation module and finishes elevator inspection work according to the work order two-dimensional code.
In one particular embodiment, the optimization module includes:
the first calculation unit is connected with the drawing module and used for calculating the time required by each section of process route according to the overall plan;
the second calculation unit is connected with the first calculation unit and determines a key process route and a non-key process route according to the time required by each section of process route;
and the output unit is connected with the second calculation unit and is used for optimizing the elevator inspection procedure route according to the key procedure route and the non-key procedure route to obtain an elevator inspection procedure optimization scheme.
In a specific embodiment, the generation module includes a generation inspection work order unit and a generation work order two-dimensional code unit which are connected in sequence, and the generated work order two-dimensional code includes: process type ID, type of work used, inspection instrument used, inspection threshold, and inspection data entry box.
In one particular embodiment, the verification module includes:
the identification unit is used for identifying the work order two-dimensional code and displaying the current process type ID, the current work type, the current inspection instrument, the current inspection threshold and the inspection data entry frame;
the entry unit is used for entering the overhaul start time, the number of the overhaul personnel and the inspection result in the inspection data entry frame and confirming that the inspection process of the section is finished;
and the report generating unit is used for distributing the work order two-dimensional codes filled with the inspection results to the next inspection process, scanning the codes by staff of the next inspection process to pick up the inspection process tasks, returning to S510 to carry out the next inspection process, integrating the results of all the inspection process tasks and generating an elevator inspection report.
In one embodiment, the verification module further comprises: and the analysis unit is used for performing out-of-range alarm analysis and predictive maintenance analysis on the elevator inspection report to obtain an inspection analysis result, sending the inspection analysis result to the second calculation unit, and optimizing the elevator inspection process route according to the key process route, the non-key process route and the inspection analysis result to obtain an elevator inspection process optimization scheme.
According to the technical scheme, compared with the prior art, the elevator inspection process optimization method and the elevator inspection process optimization system based on the overall method are provided, each process in inspection is finely divided, an inspection process overall diagram is drawn, a time parameter calculation is utilized, an optimal elevator inspection process flow optimization scheme is formed, inspection time is shortened, fine management is carried out on other elevator inspection projects and inspection processes for the later stage through the generated work order two-dimensional code, the elevator inspection process is more reasonable and ordered, the automation level is improved, visual inspection information and execution information of each inspection process are provided, query is convenient and fast, the requirements of equipment management of a production enterprise can be well met, inspection efficiency and quality can be remarkably improved, and strong operability is achieved.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. The device disclosed by the embodiment corresponds to the method disclosed by the embodiment, so that the description is simple, and the relevant points can be referred to the method part for description.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1. An elevator inspection process optimization method based on an overall planning method is characterized by comprising the following steps:
s100: acquiring elevator inspection project data, calculating the correlation degree between elevator inspection projects, and formulating an elevator inspection process route according to the correlation degree;
s200: drawing a planning chart according to the elevator inspection process route;
s300: optimizing the elevator inspection procedure route according to the overall plan to obtain an elevator inspection procedure optimization scheme;
s400: generating a checking work order according to the elevator checking procedure optimization scheme, and generating a corresponding work order two-dimensional code;
s500: and finishing elevator inspection work according to the work order two-dimensional code.
2. The orchestration-based elevator inspection process optimization method according to claim 1, wherein the S300 comprises the steps of:
s310: calculating the time required by each section of procedure route according to the overall planning map;
s320: determining a key process route and a non-key process route according to the time required by each section of process route;
s330: and optimizing the elevator inspection procedure route according to the key procedure route and the non-key procedure route to obtain an elevator inspection procedure optimization scheme.
3. The elevator inspection process optimization method based on the orchestration method according to claim 1, wherein the work order two-dimensional code information comprises: process type ID, type of work used, inspection instrument used, inspection threshold, and inspection data entry box.
4. The orchestration-based elevator inspection procedure optimization method according to claim 3, wherein the S500 comprises:
s510: identifying the work order two-dimensional code, and displaying the current process type ID, the current work type, the current inspection instrument, the current inspection threshold and an inspection data entry frame;
s520: inputting a detection result into the detection data input frame to confirm that the detection procedure is completed;
s530: and distributing the work order two-dimensional codes filled with the inspection results to the next inspection process, scanning the codes by staff of the next inspection process to pick up the task of the inspection process, returning to S510 to carry out the next inspection process until all the inspection processes are completed, and obtaining an elevator inspection report.
5. The orchestration-based elevator inspection procedure optimization method according to claim 4, wherein S500 further comprises: and performing over-range alarm analysis and predictive maintenance analysis on the elevator inspection report to obtain an inspection analysis result, and optimizing an elevator inspection process route according to a key process route, a non-key process route and the inspection analysis result to obtain an elevator inspection process optimization scheme.
6. An elevator inspection process optimization system based on an orchestration method, comprising:
the acquisition module is used for acquiring elevator inspection project data, calculating the correlation degree between elevator inspection projects and formulating an elevator inspection process route according to the correlation degree;
the drawing module is connected with the acquisition module and draws a planning chart according to the elevator inspection procedure route;
the optimization module is connected with the drawing module and used for optimizing the elevator inspection procedure route according to the overall plan to obtain an elevator inspection procedure optimization scheme;
the generating module is connected with the optimizing module, generates an inspection work order according to the elevator inspection procedure optimizing scheme, and attaches a corresponding work order two-dimensional code to the inspection work order;
a checking module: and the elevator inspection module is connected with the generation module and finishes elevator inspection work according to the work order two-dimensional code.
7. The orchestration-based elevator inspection procedure optimization system of claim 6, wherein the optimization module comprises:
the first calculation unit is connected with the drawing module and calculates the time required by each section of process route according to the overall planning map;
the second calculation unit is connected with the first calculation unit and determines a key process route and a non-key process route according to the time required by each section of process route;
and the output unit is connected with the second calculation unit and is used for optimizing the elevator inspection procedure route according to the key procedure route and the non-key procedure route to obtain an elevator inspection procedure optimization scheme.
8. The elevator inspection process optimization system based on the orchestration method according to claim 6, wherein the generation module comprises a generation inspection work order unit and a generation work order two-dimensional code unit which are connected in sequence, and the generated work order two-dimensional code comprises: process type ID, type of work used, inspection instrument used, inspection threshold, and inspection data entry box.
9. The orchestration-based elevator inspection process optimization system of claim 8, wherein the inspection module comprises:
the identification unit is used for identifying the work order two-dimensional code and displaying the current process type ID, the current work type, the current inspection instrument, the current inspection threshold and the inspection data entry frame;
the entry unit is used for entering the overhaul start time, the number of the overhaul personnel and the inspection result in the inspection data entry frame and confirming that the inspection process is finished;
and the report generating unit is used for distributing the work order two-dimensional codes filled with the inspection results to the next inspection process, scanning the codes by staff of the next inspection process to pick up the inspection process tasks, returning to S510 to carry out the next inspection process, integrating the results of all the inspection process tasks and generating an elevator inspection report.
10. The orchestration-based elevator inspection process optimization system of claim 9, wherein the inspection module further comprises: and the analysis unit is used for performing out-of-range alarm analysis and predictive maintenance analysis on the elevator inspection report to obtain an inspection analysis result, sending the inspection analysis result to the second calculation unit, and optimizing the elevator inspection process route according to the key process route, the non-key process route and the inspection analysis result to obtain an elevator inspection process optimization scheme.
CN202111033636.2A 2021-09-03 2021-09-03 Elevator inspection process optimization method and optimization system based on overall planning method Pending CN113743782A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111033636.2A CN113743782A (en) 2021-09-03 2021-09-03 Elevator inspection process optimization method and optimization system based on overall planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111033636.2A CN113743782A (en) 2021-09-03 2021-09-03 Elevator inspection process optimization method and optimization system based on overall planning method

Publications (1)

Publication Number Publication Date
CN113743782A true CN113743782A (en) 2021-12-03

Family

ID=78735551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111033636.2A Pending CN113743782A (en) 2021-09-03 2021-09-03 Elevator inspection process optimization method and optimization system based on overall planning method

Country Status (1)

Country Link
CN (1) CN113743782A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101108121B1 (en) * 2011-07-25 2012-01-31 (주)필컴정보시스템 Management method for manufacturing process of the component
CN103399994A (en) * 2013-07-23 2013-11-20 中国人民解放军海军航空工程学院 Optimization method of periodic inspection process and maintenance of airplanes based on uncertain network planning techniques
CN107862472A (en) * 2017-12-01 2018-03-30 中国兵器装备集团自动化研究所 Quality data collection system and its collecting method based on terminal profile
CN109426867A (en) * 2017-09-05 2019-03-05 国核华清(北京)核电技术研发中心有限公司 Device maintenance method based on two dimensional code and database
CN109697530A (en) * 2018-12-22 2019-04-30 中铁十八局集团有限公司 Rail yard construction period optimization method based on network technology
CN110232466A (en) * 2019-03-28 2019-09-13 济南森坤企业管理咨询有限公司 A kind of all kinds of project organization plan resources balance optimization methods of critical path method
CN110232469A (en) * 2019-03-28 2019-09-13 济南森坤企业管理咨询有限公司 A kind of all kinds of minimum optimization methods of project organization plan resource of critical path method
CN110472905A (en) * 2019-07-02 2019-11-19 湖北北辰时代信息技术有限公司 It is a kind of based on the material quality detecting method for automatically generating two dimensional code intelligent terminal barcode scanning
WO2021077983A1 (en) * 2019-10-23 2021-04-29 日立楼宇技术(广州)有限公司 Elevator fault determination logic verification method and system and storage medium

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101108121B1 (en) * 2011-07-25 2012-01-31 (주)필컴정보시스템 Management method for manufacturing process of the component
CN103399994A (en) * 2013-07-23 2013-11-20 中国人民解放军海军航空工程学院 Optimization method of periodic inspection process and maintenance of airplanes based on uncertain network planning techniques
CN109426867A (en) * 2017-09-05 2019-03-05 国核华清(北京)核电技术研发中心有限公司 Device maintenance method based on two dimensional code and database
CN107862472A (en) * 2017-12-01 2018-03-30 中国兵器装备集团自动化研究所 Quality data collection system and its collecting method based on terminal profile
CN109697530A (en) * 2018-12-22 2019-04-30 中铁十八局集团有限公司 Rail yard construction period optimization method based on network technology
CN110232466A (en) * 2019-03-28 2019-09-13 济南森坤企业管理咨询有限公司 A kind of all kinds of project organization plan resources balance optimization methods of critical path method
CN110232469A (en) * 2019-03-28 2019-09-13 济南森坤企业管理咨询有限公司 A kind of all kinds of minimum optimization methods of project organization plan resource of critical path method
CN110472905A (en) * 2019-07-02 2019-11-19 湖北北辰时代信息技术有限公司 It is a kind of based on the material quality detecting method for automatically generating two dimensional code intelligent terminal barcode scanning
WO2021077983A1 (en) * 2019-10-23 2021-04-29 日立楼宇技术(广州)有限公司 Elevator fault determination logic verification method and system and storage medium

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
周华编著: "《军工智能工厂建设的理论与实践》", 30 April 2020, 北京理工大学出版社, pages: 106 *
彭扬,蒋长兵编著: "《物联网技术与应用基础》", 31 January 2011, 中国物资出版社, pages: 104 *
罗恒;张东平;: "统筹法在电梯检验工艺流程优化中的应用", 中国电梯, vol. 31, no. 20, 13 October 2020 (2020-10-13), pages 32 - 34 *

Similar Documents

Publication Publication Date Title
Alizadehsalehi et al. A concept for automated construction progress monitoring: Technologies adoption for benchmarking project performance control
CN114037311B (en) Information system engineering supervision project risk assessment method
JP4380596B2 (en) Structure estimation method and apparatus for business process model
Adrian et al. Modeling method-productivity
KR100935304B1 (en) Project progress management system and the method
CN109490072A (en) A kind of civil engineering work detection system and its detection method
US20220137609A1 (en) Production information management system and production information management method
CN116596483A (en) Bridge construction organization method based on three-dimensional digital technology
Yang et al. Assessment of automation and integration technology's impacts on project stakeholder success
CN111144677B (en) Efficiency evaluation method and efficiency evaluation system
CN115330180A (en) Engineering management and control method and device based on BIM (building information modeling)
CN111105204A (en) Construction project progress reporting and managing method and information processing device
CN111260327A (en) Project construction cooperation management and control platform based on cloud service
CN113743782A (en) Elevator inspection process optimization method and optimization system based on overall planning method
Ezzeddine et al. Singularity functions to enhance monitoring in the last planner system
Khalili et al. Performance evaluation in aggregate production planning using integrated RED-SWARA method under uncertain condition
CN116051055A (en) Digital project management system
Lahiani et al. A novel improving method of industrial performance based on human resources management
CN115330216A (en) Supervision data management system, method, equipment and medium
CN101110034A (en) Method for automatically digging high-performance task in software course task warehouse and system thereof
Saini et al. Development of a machine learning based-labour productivity prediction tool to practice lean construction
CN113052557A (en) Three-dimensional model generation and analysis system and method for approval
An et al. A model-based productivity improvement of reinforced concrete work in a multi-housing project
CN113052556A (en) Three-dimensional-based auxiliary approval process management system and method
Shehab et al. Singularity functions for early warning guidance in the last planner system®

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination