KR100935304B1 - Project progress management system and the method - Google Patents

Project progress management system and the method Download PDF

Info

Publication number
KR100935304B1
KR100935304B1 KR1020090088551A KR20090088551A KR100935304B1 KR 100935304 B1 KR100935304 B1 KR 100935304B1 KR 1020090088551 A KR1020090088551 A KR 1020090088551A KR 20090088551 A KR20090088551 A KR 20090088551A KR 100935304 B1 KR100935304 B1 KR 100935304B1
Authority
KR
South Korea
Prior art keywords
project
progress
progress rate
management
calculating
Prior art date
Application number
KR1020090088551A
Other languages
Korean (ko)
Inventor
이종석
전형권
곽송해
김상원
박진철
Original Assignee
에스케이씨앤씨 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 에스케이씨앤씨 주식회사 filed Critical 에스케이씨앤씨 주식회사
Priority to KR1020090088551A priority Critical patent/KR100935304B1/en
Application granted granted Critical
Publication of KR100935304B1 publication Critical patent/KR100935304B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Stored Programmes (AREA)

Abstract

PURPOSE: A project progress management system and a method thereof are provided to grasp the exact progress of a project by visualizing the progress on a real time basis. CONSTITUTION: A progress rate management unit(110) of a project server(100) manages the progress rates calculated for each project step. A cost calculating unit(120) produces the planned budget/final budget. A progress rate adding unit(130) adds up the above progress rates. A test management server(200) is connected to the project server. The test management server supports overall activities of the test project including a project plan, a project design and a project case management, etc. A defect management server(300) is connected to the project server. The defect management server supports the management of defects and tracing of a project.

Description

프로젝트 진척관리 시스템 및 그 방법{Project progress management system and the method}Project progress management system and the method

본 발명은 프로젝트 진척관리 시스템 및 그 방법에 관한 것으로, 보다 자세하게는 프로젝트 단계별 산출되는 진척율을 관리하는 진척율 관리부를 포함하는 프로젝트 서버를 구비한 프로젝트 진척관리 시스템 및 그 방법에 관한 것이다.The present invention relates to a project progress management system and a method thereof, and more particularly, to a project progress management system and a method including a project server including a progress rate management unit for managing the progress rate calculated for each project.

일반적인 프로젝트 관리 시스템은 산업계에서 대규모 프로젝트를 관리하기 위한 프로젝트으로 최적의 프로젝트 계획과 통제를 위해 일정/비용 요소를 이용하는 프로젝트 작업을 정의한다. 그리고 프로젝트 관리 시스템은 팀원, 프로젝트 리더(PL:Part Leader), 프로젝트 관리자(PM:Project Manager)로 이루어지는 구성원으로 구성될수 있다. 이때, 각 구성원은 주어진 역할에 따라 권한 및 책임을 가지고 프로젝트를 수행하게 된다. 각 구성원의 역할에 대해 보다 자세하게 설명하면 먼저 팀원은 프로젝트를 수행하는 주체로, 프로젝트의 가장 중요한 자원이다. 프로젝트 리더는 프로젝트 매니저를 도와 개발에 직접 참여하여 일을 분담하고 관리하는 역 할을 하며, 프로젝트 관리자는 프로젝트가 올바른 방향으로 진행되어 제대로 된 결과가 만들어질 수 있도록 하기 위한 모든 것들을 관리하는 역할을 한다.A typical project management system is a project for managing large projects in the industry, which defines project tasks that use schedule / cost elements for optimal project planning and control. In addition, the project management system may be composed of members consisting of team members, part leaders (PLs), and project managers (PM). At this time, each member carries out the project with authority and responsibility according to the given role. The role of each member is explained in more detail. First, the team member is the person who carries out the project and is the most important resource of the project. Project leaders assist project managers in directing the development, sharing and managing work, and project managers managing everything to ensure the project goes the right way and produces the right results. .

도 1은 프로젝트 관리 시스템의 프로젝트 진척관리방법과 그에 따른 각 구성원의 역할을 나타낸 도면이고, 도 2는 프로젝트 단계를 나타낸 도면이다.1 is a view showing a project progress management method and a role of each member according to the project management system, Figure 2 is a view showing a project step.

도 1을 참조하여 설명하면, 프로젝트 관리 시스템의 프로젝트 진척관리방법은 크게 프로젝트 준비단계, 초기 데이터 로드단계, 실적 관리단계, 생산성 관리단계로 이루어진다. Referring to Figure 1, the project progress management method of the project management system is largely composed of a project preparation phase, initial data load phase, performance management phase, productivity management phase.

먼저, 프로젝트 준비단계에서 프로젝트 관리자는 프로젝트 및 프로젝트 리더를 등록한다. 그 다음 프로젝트 관리자는 등록한 프로젝트 리더와 서브시스템을 등록한다. First, in the project preparation phase, the project manager registers the project and the project leader. The project manager then registers the registered project leader and subsystem.

다음 초기 데이터 로드단계에서 프로젝트 관리자와 프로젝트 리더는 팀원을 등록하고, F&E 등록한다. 그리고 프로젝트 리더는 업무분류체계(WBS)를 등록한다. 그 다음 프로젝트 관리자는 업무분류체계를 통합한다. In the next initial data load phase, project managers and project leaders register team members and register for F & E. The project leader then registers a WBS. The project manager then integrates the WBS.

다음으로 실적관리 단계에서, 팀원은 전체 실적 및 일일 실적을 등록하고 프로젝트 리더는 팀원이 등록한 전체 실적 및 일일 실적을 승인하고 확인한다. 그 다음 프로젝트 리더와 프로젝트 관리자는 프로젝트 단계별로 팀원이 등록한 전체 실적 및 일일 실적을 토대로 획득가치(EV:Earned Value) 및 진척율 현황을 확인한다. 이때, 프로젝트 단계는 도 2에 도시된 바와 같이 분석 및 설계 단계, 개발 단계, 테스트 단계로 이루어질 있다. 먼저 획득가치는 계획공수, 완료된 계획공수, 실제투입공수로 관리될 수 있다. 그리고 진척율은 실적 진척율, 계획 진척율, 가중치 측정으로 관리될 수 있다. 이때, 실적 진척율은 완료예정 계획 작업/전체작업으로 측정되고, 계획 진척율은 완료된 실제 작업/전체작업으로 측정된다. 그리고 가중치는 투입입력×기간을 기준으로 작업의 비중을 결정하는 것으로, 작업항목의 가중치 합을 100으로 세분화되어 측정된다.Next, in the performance management phase, the team member registers the overall performance and the daily performance, and the project leader approves and confirms the overall performance and the daily performance registered by the team members. Project leaders and project managers then check the earned value (EV) status and progress rate based on the overall and daily performance registered by team members at the project level. At this time, the project phase is composed of an analysis and design stage, a development stage, a test stage as shown in FIG. Firstly, the earned value can be managed as plan maneuver, completed plan maneuver, and actual input maneuver. Progress rates can be managed by measuring performance progress, planning progress, and weighting. At this time, the performance progress rate is measured as planned work / total work completed, and the plan progress rate is measured as actual work / total work completed. The weight is used to determine the specific gravity of the work based on the input input × duration, and the weighted sum of the work items is divided into 100 and measured.

그러나 이와 같이 작업별 항목의 가중치 합을 100으로 세분화시켜 측정할 경우, 일정 항목에 속한 내부작업의 가중치가 하나라도 변경되면 전체작업의 가중치를 수정해야만 하는 단점이 있었다. 따라서, 작업 시간이 증가하여 작업성 및 효율성이 떨어지는 문제점이 있었다. 그리고 개발단계에서 상기와 같은 방법으로 진척율을 산출하면 가시성을 평가하기 어려워지는 단점이 있었다. 따라서, 개발단계에서는 아무 문제없이 일정대로 진행되는 듯해도 테스트단계에 오면 문제가 불거지는 등 프로젝트 지연 등에 대한 위험 요소를 미리 예측하고 사전에 대비하는데 어려움이 커 정확한 프로젝트 진척관리가 이루어지지 않는 문제점이 있었다.However, in the case of measuring by dividing the sum of the weight of each task by 100 as described above, there is a disadvantage that the weight of the whole task must be corrected if any weight of the internal task belonging to a certain item is changed. Therefore, there is a problem in that work time is increased and workability and efficiency are lowered. In addition, when the progress rate is calculated in the above-described manner, it is difficult to evaluate the visibility. Therefore, even though the development stage seems to proceed without any problems, it is difficult to accurately predict and prepare for risk factors for project delays, such as problems when the test stages come to the test stage. there was.

본 발명은, 종래 기술에 제기된 프로젝트 개발단계에서 가중치를 이용하여 진척율을 산출할 경우 가시성을 평가하기 어려워지는 문제점을 해결하기 위한 것으로, 프로젝트 단계별 산출되는 진척율을 관리하는 진척율 관리부를 포함하는 프로젝트 서버를 구비하여 개발 단계에서 프로그램 단위를 이용하여 진척율을 개별적으로 산출한 다음 가중치를 이용하여 산출되는 분석 및 설계 단계와 테스트 단계의 진척율에 합산하여 전체 진척율을 산출함으로써, 실시간으로 정확한 프로젝트 진척사항을 파악할 수 있는 프로젝트 진척관리 시스템 및 그 방법을 제공하는데 그 목적이 있다.The present invention is to solve the problem that it is difficult to evaluate the visibility when calculating the progress rate by using the weight in the project development stage proposed in the prior art, and includes a progress rate management unit for managing the progress rate calculated for each project In the development stage, the progress rate is individually calculated by using the program unit, and then the total progress rate is calculated by adding the progress rate of the analysis and design stages and the test stages which are calculated using the weights. The purpose is to provide a project progress management system and method for identifying accurate project progress.

삭제delete

상기의 목적을 달성하기 위한 본 발명은 업무분류체계의 프로젝트 진척관리 시스템에 있어서, 프로젝트 분석 및 설계 단계에서 가중치를 이용하여 산출되는 진척율을 관리하는 분석 및 설계 진척율 관리부, 프로젝트 개발단계에서 프로그램 단위를 이용하여 산출되는 진척율을 관리하는 개발 진척율 관리부, 및 프로젝트 테스트단계에서 가중치를 이용하여 산출되는 진척율을 관리하는 테스트 진척율 관리부를 포함하는 프로젝트 단계별 산출되는 진척율을 관리하는 진척율 관리부와 프로젝트 단계별 공수를 통한 계획예산 및 종료예산을 산출하는 비용 산출부를 포함하는 프로젝트 서버; 프로젝트 서버와 연동되고, 프로젝트 계획, 프로젝트 설계 및 프로젝트 케이스 관리 등의 테스트 프로젝트 전반의 활동을 지원하는 테스트 관리서버; 및 프로젝트 서버와 연동되고, 프로젝트의 결함관리, 결함에 대한 추적관리의 활동을 지원하는 결함 관리서버;를 포함하는 것을 특징으로 하는 프로젝트 진척관리 시스템을 제공하는데 그 복적이 있다.The present invention for achieving the above object in the project progress management system of the business classification system, the analysis and design progress rate management unit for managing the progress rate calculated by using the weight in the project analysis and design stage, the program in the project development stage Progress rate managing projected progress rate, comprising a development progress rate management unit that manages the progress rate calculated using units, and a test progress rate management unit that manages the progress rate calculated using weights in the project testing phase. A project server including a management unit and a cost calculator configured to calculate a plan budget and a final budget through the airborne for each project step; A test management server interworking with the project server and supporting activities of a test project, such as project planning, project design, and project case management; And a defect management server interworking with the project server and supporting the project's defect management and tracking of defect management activities. The project progress management system includes a project management system.

삭제delete

그리고 프로젝트 서버는 프로젝트 전 단계의 진척율을 합산하는 진척율 합산부를 더 포함할 수 있다.The project server may further include a progress rate adder that adds the progress rate of the pre-project stage.

또한, 분석 및 설계 진척율 관리부와 테스트 진척율 관리부는 프로젝트에서 수행되는 작업항목을 상,하위로 분류하여 등록하는 등록부; 상,하위 작업항목에 대한 투입인력 및 기간정보를 입력하는 입력부; 동일한 레벨에 있는 상,하위 작업항목에 동일한 가중치의 합을 부여하여 각각의 작업항목에 대한 가중치를 산출하는 가중치 산출부; 및 상,하위 작업항목의 가중치를 이용하여 진척율을 산출하는 제 1 진척율 산출부;를 포함할 수 있다.In addition, the analysis and design progress rate management unit and the test progress rate management unit registers the classification of the work items to be performed in the project, the lower and lower; An input unit for inputting input manpower and period information for upper and lower work items; A weight calculator configured to calculate a weight for each work item by applying a sum of the same weights to upper and lower work items at the same level; And a first progress rate calculator configured to calculate a progress rate using weights of the upper and lower work items.

그리고 개발 진척율 관리부는 프로그램 단위를 입력하는 프로그램 입력부; 및 프로그램 단위를 이용하여 진척율을 산출하는 제 2 진척율 산출부;를 포함할 수 있다.The development progress rate manager may include a program input unit configured to input a program unit; And a second progress rate calculator configured to calculate a progress rate using the program unit.

이때, 프로그램 단위는 프로그램 본수 또는 규모측정자료(FP)로 이루질 수 있다.In this case, the program unit may be composed of the number of programs or scale data (FP).

상기의 목적을 달성하기 위한 본 말명은 업무분류체계의 프로 진척관리방법에 있어서, 프로젝트 서버는 프로젝트에서 수행되는 작업항목을 상,하위로 분류하여 등록하는 단계; 프로젝트 서버는 분석 및 설계 단계에서 가중치를 이용하여 진척율을 산출하는 단계; 프로젝트 서버는 개발 단계에서 프로그램 단위를 이용하여 진척율을 산출하는 단계; 및 프로젝트 서버는 테스트 단계에서 가중치를 이용하여 진척율을 산출하는 단계;를 포함하는 것을 특징으로 하는 프로젝트 진척관리 방법을 제공하는데 그 목적이 있다.The present invention for achieving the above object is a professional progress management method of the business classification system, the project server is a step of registering the work items performed in the project classified into upper and lower; The project server calculating a progress rate using the weights in the analysis and design phases; The project server calculating a progress rate using a program unit in a development stage; And a project server calculating a progress rate using weights in a test step.

또한, 작업항목을 상,하위로 분류하여 등록하는 단계 이후에, 상,하위 작업 항목에 대한 투입인력 및 기간 정보를 입력하는 단계가 포함될 수 있다.In addition, after classifying and registering the work items into upper and lower parts, inputting personnel and period information on the upper and lower work items may be included.

그리고 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계에서, 가중치는 투입인력×기간으로 산출되는 작업항목의 비중을 나타내는 지표일 수 있다.In the calculating of the progress rate of the analysis and design stages and the progress rate of the test stages, the weight may be an index indicating the weight of the work item calculated as the input labor x time period.

또한, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계에서, 가중치는 백분율로 표현되며 상,하위 작업항목의 가중치 합은 각각 100%일 수 있다.In addition, in calculating the progress rate of the analysis and design stage and the progress rate of the test stage, the weight is expressed as a percentage and the sum of the weights of the upper and lower work items may be 100%, respectively.

또한, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계에서, 작업항목에 대한 실적 진척율 및 계획 진척율을 산출될 수 있다.In addition, in the step of calculating the progress rate in the analysis and design phase and the progress rate in the test phase, the performance progress rate and the plan progress rate for the work item may be calculated.

이때, 작업항목에 대한 실적 진척율을 산출하는 단계에서, 상위 작업항목의 가중치×(하위 작업항목의 가중치×진척율)/100으로 산출될 수 있다.At this time, in the step of calculating the performance progress rate for the work item, the weight of the higher work item x (weight of the lower work item x progress rate) / 100 may be calculated.

이때, 작업항목에 대한 실적 진척율을 산출하는 단계에서, 하위 작업항목이 다수개일 경우, 상위 작업항목의 가중치×((제 1하위 작업항목의 가중치×진척율)+(제 2하위 작업항목의 가중치×진척율))/100으로 산출될 수 있다.At this time, in the step of calculating the performance progress rate for the work item, when there are a plurality of lower work items, the weight of the parent work item × ((weight of the first child work item × progress rate) + (the second child work item) Weight x progress rate)) / 100.

이때, 작업항목에 대한 계획 진척율을 산출하는 단계에서, 계획 진척율은 예상 소요기간을 기준으로 경과한 기간을 백분율로 표현되어 산출될 수 있다.At this time, in the step of calculating the planned progress rate for the work item, the planned progress rate may be calculated by expressing the elapsed time period as a percentage.

또한, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계 이후에, 공수를 통한 계획 예산 및 종료 예산을 산출하는 단계가 더 포함될 수 있다.In addition, after calculating the progress rate of the analysis and design stage and the progress rate of the test stage, the step of calculating the planned budget and finish budget through airlift may be further included.

이때, 계획예산은 지난월까지의 계획누적공수+(당월 계획공수×기간 진행율)로 산출되며, 종료예산은 전체 계획 공수×기준일 현재의 실적 진척율로 산출될 수 있다.In this case, the planned budget may be calculated as the cumulative cumulative number of flights up to the last month + (planned number of months x progress rate of the current month), and the final budget may be calculated as the performance progress rate as of the total plan number of times x base date.

또한, 프로그램 단위를 이용하여 개발 단계의 진척율을 산출하는 단계에서,프로그램 단위로 프로그램 본수가 이용되거나, 규모측정자료(FP)가 이용될 수 있다. In addition, in the step of calculating the progress rate of the development stage by using the program unit, the program head or the scale data FP may be used as the program unit.

또한, 프로그램 단위를 이용하여 개발 단계의 진척율을 산출하는 단계 이후에, 공수를 통한 계획 예산 및 종료 예산을 산출하는 단계가 더 포함될 수 있다.In addition, after calculating the progress rate of the development stage by using the program unit, the step of calculating the planned budget and the end budget through the airborne may be further included.

그리고 테스트 단계의 진척율을 산출하는 단계 이후에, 프로젝트 전 단계의 진척율을 합산하는 단계가 포함될 수 있다.And after calculating the progress rate of the test phase, the process may include adding up the progress rate of the pre-project phase.

이상에서 설명한 바와 같이, 본 발명에 따른 프로젝트 진척관리 시스템 및 그 방법은 프로젝트 단계별 산출되는 진척율을 관리하는 진척율 관리부를 포함하는 프로젝트 서버를 구비하여 개발 단계에서 프로그램 단위를 이용하여 진척율을 개별적으로 산출한 다음 가중치를 이용하여 산출되는 분석 및 설계 단계와 테스트 단계의 진척율에 합산하여 전체 진척율을 산출함으로써, 가시성을 확보하여 실시간으로 정확한 프로젝트 진척사항을 파악할 수 있는 효과가 있다. As described above, the project progress management system and method according to the present invention includes a project server including a progress rate management unit that manages the progress rate calculated for each project, and uses the program unit in the development stage to individually measure the progress rate. The total progress rate is calculated by adding the progress rate of the analysis and design stages and the test stages, which are calculated using weights, to obtain visibility and identify accurate project progress in real time.

또한, 분석 및 설계 단계와 테스트 단계에서 동일한 레벨에 있는 상,하위 작업항목에 동일한 가중치 합을 부여하여 각각의 작업항목에 대한 가중치를 산출함으로써, 하위 작업항목의 가중치가 변경되는 경우 동일한 레벨에 있는 작업항목들의 가중치의 합만 변경시키고 전체 작업항목의 가중치 변경을 하지 않아도 되는 효과가 있다. 따라서, 작업 시간이 단축되고 가중치 변경 및 수정이 용이하게 이루어져 작업의 효율성이 향상되는 효과가 있다.In addition, by assigning the same weighted sum to the upper and lower work items at the same level in the analysis and design stage and the test stage to calculate the weight for each work item, if the weight of the lower work item is changed, There is an effect that it is not necessary to change only the sum of the weights of the work items and not change the weight of the whole work items. Therefore, the working time is shortened and weight change and modification are easily performed, thereby improving the efficiency of the work.

또한, 프로젝트 서버는 테스트 관리 서버 및 결함 관리 서버와 연동되어 통합 관리됨으로써, 보다 효율적이고 신속한 프로젝트 진척관리가 수행될 수 있는 효과가 있다.In addition, the project server is integrated with the test management server and defect management server to be integrated management, there is an effect that can be carried out more efficient and rapid project progress management.

본 발명에 따른 프로젝트 진척관리 시스템 및 그 방법에 대한 기술적 구성을 비롯한 작용효과에 관한 사항은 본 발명의 바람직한 실시예가 도시된 도면을 참조하여 아래의 상세한 설명에 의해서 명확하게 이해될 것이다.Matters concerning the operational effects, including the technical configuration of the project progress management system and method according to the present invention will be clearly understood by the following detailed description with reference to the drawings in which preferred embodiments of the present invention are shown.

도 3 내지 도 7을 참조하여 본 발명의 실시예에 따른 프로젝트 진척관리 시스템 및 그 방법에 대하여 상세히 설명한다.3 to 7 will be described in detail with respect to the project progress management system and method according to an embodiment of the present invention.

프로젝트 진척관리 시스템Project Progress Management System

도 3 및 도 4는 본 발명의 실시예에 따른 업무분류체계의 프로젝트 진척관리 시스템을 나타낸 도면이다.3 and 4 are diagrams showing a project progress management system of a business classification system according to an embodiment of the present invention.

도 3 및 4를 참조하여 설명하면, 본 발명의 실시예에 따른 프로젝트 진척관리 시스템은 프로젝트 서버(100), 프로젝트 서버(100)와 연동되어 통합 관리되는 테스트 관리서버(200) 및 결함 관리서버(300)를 포함할 수 있다.Referring to Figures 3 and 4, the project progress management system according to an embodiment of the present invention is integrated with the project server 100, the project server 100, the test management server 200 and defect management server ( 300).

여기서, 프로젝트 진척관리 시스템는 획득가치가 원가를 관리하지 않기 때문에 투입공수(계획 및 실적)을 기준으로 산출하여 기산일 기준으로 프로젝트 종료시점의 실적 투입공수 예측 정보를 제공하는 시스템이다.Here, the project progress management system is a system that calculates the input labor cost (plan and performance) based on the acquisition cost because the acquired value does not manage the cost, and provides information on the projected input labor performance at the end of the project on the basis of the start date.

우선, 프로젝트 서버(100)는 프로젝트 단계별 산출되는 진척율을 관리하는 진척율 관리부(110)를 포함할 수 있다. 이때, 진척율 관리부(110)는 분석 및 설계단계에서의 진척율을 관리하는 분석 및 설계 진척율 관리부(111), 개발단계에서의 진척율을 관리하는 개발 진척율 관리부(112), 테스트단계에서의 진척율을 관리하는 테스트 진척율 관리부(113)를 포함할 수 있다. First, the project server 100 may include a progress rate management unit 110 for managing a progress rate calculated for each project. At this time, the progress rate management unit 110 in the analysis and design progress rate management unit 111 for managing the progress rate in the analysis and design stage, the development progress rate management unit 112 for managing the progress rate in the development stage, the test stage It may include a test progress rate management unit 113 to manage the progress rate of.

분석 및 설계 진척율 관리부(111)와 테스트 진척율 관리부(113)는 등록부(114), 입력부(115), 가중치 산출부(116), 제 1 진척율 산출부(117)를 포함할 수 있다. 이때, 등록부(114), 입력부(115), 가중치 산출부(116), 제 1 진척율 산출부(117)는 분석 및 설계 진척율 관리부(111)와 테스트 진척율 관리부(113)에 각각 별도로 구비될 수 있는 것이나, 본 발명에서는 구성 및 역할이 동일하여 동시에 설명한다.The analysis and design progress rate managing unit 111 and the test progress rate managing unit 113 may include a register 114, an input unit 115, a weight calculator 116, and a first progress rate calculator 117. In this case, the register 114, the input 115, the weight calculator 116, and the first progress rate calculator 117 are separately provided in the analysis and design progress rate manager 111 and the test progress rate manager 113, respectively. However, in the present invention, the configuration and the role are the same and will be described at the same time.

등록부(114)는 프로젝트에서 수행되는 작업항목을 상, 하위로 분류하여 등록 하며, 입력부(115)는 상,하위 작업항목에 대한 투입인력 및 기간정보를 입력한다. The registration unit 114 classifies and registers work items performed in the project into upper and lower positions, and the input unit 115 inputs input manpower and period information for upper and lower work items.

그리고 가중치 산출부(116)는 동일한 레벨에 있는 상,하위 작업항목에 동일한 가중치의 합을 부여하여 각각의 작업항목에 대한 가중치를 산출한다. 이때, 가중치는 투입인력×기간으로 산출되는 작업항목의 비중을 나타내는 지표를 말한다. 그리고 본 발명에서의 가중치는 상,하위 작업항목의 상대적인 가중치는 백분율로 표현되고 상,하위 작업항목의 가중치 합이 각각 100%로 이루어질 수 있다. 가중치 산출 방법에 대해서는 이후 자세하게 후술하기로 한다. 제 1 진척율 산출부(117)는 가중치 산출부에서 산출된 가중치를 이용하여 실적 및 계획 진척율이 산출할 수 있다. 이때, 실적 진척율은 전체작업에서 완료된 실제 작업에 대한 진척율이며, 계획 진척율은 전체작업에서 완료 예정 계획인 작업에 대한 진척율을 말한다. 실적 진척율 및 계획 진척율 산출 방법에 대해서는 이후 자세하게 후술하기로 한다.The weight calculator 116 calculates the weight for each work item by assigning the same weighted sum to the upper and lower work items at the same level. In this case, the weight refers to an index indicating the specific gravity of the work item calculated as the input manpower x period. In the present invention, the weight may be expressed as a percentage and the sum of the weights of the upper and lower work items may be 100%, respectively. The weight calculation method will be described later in detail. The first progress rate calculator 117 may calculate the performance and the plan progress rate using the weights calculated by the weight calculator. At this time, the performance progress rate is the progress rate for the actual work completed in the whole work, and the planning progress rate is the progress rate for the work that is planned to be completed in the whole work. The method of calculating the performance progress rate and the plan progress rate will be described later in detail.

개발 진척율 관리부(112)는 프로그램 입력부(118), 제 2 진척율 산출부(119)를 포함할 수 있다. The development progress rate managing unit 112 may include a program input unit 118 and a second progress rate calculating unit 119.

프로그램 입력부(118)는 프로그램 단위를 입력하며, 이때 프로그램 단위는 프로그램 본수 또는 규모측정자료(FP)로 이루어질 수 있다. 제 2 진척율 산출부(119)는 프로그램 단위를 이용하여 개별적으로 진척율을 산출한다. The program input unit 118 inputs a program unit, where the program unit may be the number of programs or scale data FP. The second progress rate calculator 119 separately calculates the progress rate using the program unit.

이와 같이, 개발 단계에서 프로그램 단위를 이용하여 진척율을 개별적으로 산출하여 전체 진척율을 산출함으로써, 가시성을 확보하여 실시간으로 정확한 프로젝트 진척사항을 파악할 수 있게 된다.In this way, by using the program unit in the development stage to calculate the progress rate individually to calculate the overall progress rate, it is possible to obtain accurate project progress in real time by securing visibility.

또한, 프로젝트 서버(100)는 프로젝트 단계별 공수를 통한 계획예산 및 종료 예산을 산출하는 비용 산출부(120)를 더 포함할 수 있다. 계획예산 및 종료예산 산출 방법에 대해서는 이후 자세하게 후술하기로 한다. 그리고 프로젝트 서버(100)는 각 단게별 진척율을 합산하는 진척율 합산부(130)를 더 포함할 수 있다.In addition, the project server 100 may further include a cost calculation unit 120 for calculating a plan budget and a final budget through the airborne project step by step. The planned budget and the final budget calculation method will be described later in detail. And the project server 100 may further include a progress rate adding unit 130 for summing the progress rate for each step.

테스트 관리서버(200)는 프로젝트 서버(100)와 연동되어 통합 관리되는 서버로, 프로젝트 계획 및 리스크 기반 테스트 전략 수립부터 프로젝트 설계, 프로젝트 케이스 관리 등의 테스트 프로젝트 전반의 활동을 지원하는 역할을 한다.The test management server 200 is a server that is integrated and managed in conjunction with the project server 100, and serves to support the overall activities of the test project, such as project planning and risk-based test strategy establishment, project design, project case management.

결함 관리서버(300)는 프로젝트 서버(100)와 연동되어 통합 관리되는 서버로, 프로젝트의 결함관리, 결함에 대한 추적관리의 활동을 지원하는 역할을 한다.The defect management server 300 is a server that is integrated and managed in conjunction with the project server 100, and serves to support the activities of project defect management and tracking of defects.

이와 같이, 본 발명에 따른 프로젝트 진척관리 시스템은 프로젝트 관리 서버(100), 테스트 관리서버(200) 및 결함 관리서버(300)가 상호 연동되어 통합 관리됨으로써, 보다 효율적이고 신속한 프로젝트 진척관리가 수행될 수 있게 된다.As described above, the project progress management system according to the present invention is integrated with the project management server 100, the test management server 200, and the defect management server 300 to be integrated and managed so that more efficient and rapid project progress management can be performed. It becomes possible.

프로젝트 진척관리 방법Project progress management method

도 5는 본 발명의 실시예에 따른 업무분류체계의 프로젝트 진척관리 방법을 순차적으로 나타낸 도면이다. 5 is a view sequentially showing a project progress management method of a business classification system according to an embodiment of the present invention.

도 5를 참조하여 설명하면, 본 발명의 실시예에 따른 프로젝트 진척관리 방법은 앞서 설명한 도 3 및 도 4와 같은 구성으로 이루어진 프로젝트 진척관리 시스템을 이용하여 프로젝트 진척관리를 수행하는 방법으로 이하 중복되는 설명은 생략한다. Referring to FIG. 5, the project progress management method according to the embodiment of the present invention is duplicated as a method of performing project progress management using the project progress management system having the configuration as described above with reference to FIGS. 3 and 4. Description is omitted.

먼저, 프로젝트 진척관리 방법은 프로젝트에서 수행되는 작업항목을 상,하위 로 분류하여 등록한다.(S100) 이는 등록부(114)에 의해 수행될 수 있다.First, the project progress management method registers the work items performed in the project classified into upper and lower (S100). This may be performed by the registration unit 114.

보다 자세하게 설명하면 개발 방법론에 따른 프로젝트 중 적용해야 할 작업항목을 상,하위로 분류하여 등록하고, 방법론에 따른 프로젝트 단계를 설정한다. 이때, 프로젝트 단계는 분석 및 설계, 개발, 테스트 단계 중 하나로 설정될 수 있다.In more detail, the work items to be applied among the projects according to the development methodology are classified into upper and lower levels, and the project stages are set according to the methodology. In this case, the project phase may be set as one of analysis and design, development, and test stages.

그 다음, 각각의 작업항목을 수행하기 위해 필요한 계획공수를 주 단위로 입력한다. 이때, 공수란 일정한 작업에 요하는 인원수를 노동시간 또는 노동일로 나타내는 개념이다. Next, enter the number of weeks required to perform each work item. At this time, airborne is a concept that represents the number of people required for a certain work in working hours or working days.

다음으로 상,하위 작업항목에 대한 투입인력 및 기간 정보를 입력한다.(S110) 이는 입력부(115)에 의해 수행될 수 있다.Next, input manpower and period information for the upper and lower work items (S110). This may be performed by the input unit 115.

다음으로 분석 및 설계단계에서 가중치를 이용하여 진척율을 산정한다.(S120) 이는 분석 및 설계 진척율 관리부(111)의 가중치 산출부(116)에 의해 수행될 수 있다. 도 6은 가중치를 산출하는 방법을 자세하게 설명하기 위한 도면이다. 도 6을 참조하여 설명하면, 도면의 도시된 개요번호는 각각의 작업항목에 지정된 고유의 번호이며, 작업이름은 작업항목에서 수행되는 작업내용이며, 가중치는 투입인력×기간으로 산출되는 작업항목의 비중을 나타내는 지표이다. 이때, 가중치는 사용자가 임의로 정의할 수도 있다. 만약 사용자가 정의하지 않았을 경우에는 별도의 시스템에서 투입인력×기간을 기준으로 자동으로 산출하여 제공할 수도 있다. Next, the progress rate is calculated using the weights in the analysis and design stage (S120). This may be performed by the weight calculator 116 of the analysis and design progress rate manager 111. 6 is a diagram for describing in detail a method for calculating a weight. Referring to FIG. 6, the outline number shown in the drawing is a unique number assigned to each work item, the work name is the work content to be performed in the work item, and the weight is the work item calculated by the input labor x time period. It is an indicator of specific gravity. In this case, the weight may be arbitrarily defined by the user. If it is not defined by the user, it can be automatically calculated and provided based on input manpower × period in a separate system.

그리고 본 발명에서 상,하위 작업항목의 상대적인 가중치는 백분율로 표현되며 상,하위 작업항목의 가중치 합은 각각 100%으로 이루어질 수 있다. In the present invention, the relative weights of the upper and lower work items are expressed as percentages, and the sum of the weights of the upper and lower work items may be 100%.

예를 들어 설명하면, 개요번호 [1.1.1.1]과 [1.1.1.2]는 상위 작업항목 [1.1.1]에 속한 동일한 레벨을 가진 하위 작업항목으로 가중치가 각각 40%와 60%로 이루어져 가중치 합이 100%로 이루어진다. 또한, 개요번호 [1.1.1],[1.1.2],[1.1.3]도 상위 작업항목[1.1]에 속한 동일한 레벨을 가진 하위 작업항목으로 가중치가 각각 20%,40%,40%로 이루어져 가중치의 합이 100%로 이루어진다. For example, outline numbers [1.1.1.1] and [1.1.1.2] are child work items with the same level belonging to the parent work item [1.1.1], with weights of 40% and 60%, respectively. This is done 100%. In addition, outline numbers [1.1.1], [1.1.2], and [1.1.3] are also child work items with the same level belonging to the higher work item [1.1], with weights of 20%, 40%, and 40%, respectively. The sum of the weights is 100%.

이와 같이, 작업항목에 동일하게 가중치 합을 각각 100%로 산출될 경우, 하위 작업항목의 가중치가 변경될 때 동일한 레벨에 있는 작업항목들의 가중치의 합만 변경시켜주면 됨으로써, 전체 작업항목의 가중치 변경을 하지 않아도 된다. 즉, 동일한 레벨에 있지않은 작업항목의 가중치는 변경할 필요가 없어 작업 시간이 단축됨으로써, 가중치 변경 및 수정이 용이하게 이루어져 작업의 효율성이 향상될 수 있다.As such, when the weighted sum is equal to 100% for each work item, only the weighted sum of the work items at the same level is changed when the weight of the lower work item is changed, thereby changing the weight of the entire work item. You do not have to do. That is, the weight of work items that are not at the same level do not need to be changed, and thus the work time is shortened, so that the weight can be easily changed and modified, thereby improving work efficiency.

다음으로, 작업항목에 대한 실적 진척율 및 계획 진척율을 산출한다.(S130) 이는 분석 및 설계 진척율 관리부(111)의 제 1 진척율 산출부(117)에 의해 수행될 수 있다. 먼저, 실적 신척율은 앞서 설명한 가중치 산출 방법에 의해 산출된 가중치를 토대로 산출된다. 도 7은 실적 진척율를 산출하는 방법을 자세하게 설명하기 위한 도면이다. 도 7을 참조하여 설명하면, 실적 진척율은 상위 작업항목의 가중치×(하위 작업항목의 가중치×진척율)/100으로 산출될 수 있다. 또한, 하위 작업항목이 다수개일 경우, 상위 작업항목의 가중치×((제 1하위 작업항목의 가중치×진척율)+(제 2하위 작업항목의 가중치×진척율))/100으로 산출될 수 있다. 이때, 진 척율은 상단의 진척율(후)를 기준으로 한다. Next, the performance progress rate and the planning progress rate for the work item are calculated (S130). This may be performed by the first progress rate calculation unit 117 of the analysis and design progress rate management unit 111. First, the performance freshness rate is calculated based on the weight calculated by the weight calculation method described above. 7 is a diagram for explaining in detail the method of calculating the performance progress rate. Referring to FIG. 7, the performance progress rate may be calculated as a weight x of a higher work item x (weight x progress rate of a lower work item) / 100. In addition, when there are a plurality of lower work items, it may be calculated as the weight of the upper work item x ((weight of the first lower work item x progress rate) + (weight of the second lower work item x progress rate)) / 100. . At this time, the progress rate is based on the progress rate (after) of the upper end.

예를 들어 설명하면 개요번호 [1.1.1]의 진척율은 개요번호 [1.1.1]의 가중치×((개요번호 [1.1.1.1]의 가중치×진척율)+(개요번호 [1.1.1.2]의 가중치×진척율)+(개요번호 [1.1.1.3]의 가중치×진척율))을 100으로 나눈 값이다. 즉, 개요번호 [1.1.1]의 진척율은 50×((50×100%)+(20×100%)+(30×90%))/100=48.5로 산출될 수 있다. 또한, 개요번호 [1.1.2]의 진척율은 개요번호 [1.1.2]의 가중치×((개요번호 [1.1.2.1]의 가중치×진척율)+(개요번호 [1.1.2.2]의 가중치×진척율))을 100으로 나눈 값이다. 즉, 개용번호 [1.1.2]의 진척율은 50×((60×70%)+(40×20%))/100= 25로 산출될 수 있다. For example, the progress rate of the outline number [1.1.1] is the weight of the outline number [1.1.1] × ((weight of the outline number [1.1.1.1] × progress rate) + (summary number [1.1.1.2]) Is a value obtained by dividing the weight × progress rate) + (the weight × progress rate of the outline number [1.1.1.3]) by 100. That is, the progress rate of the outline number [1.1.1] may be calculated as 50 × ((50 × 100%) + (20 × 100%) + (30 × 90%)) / 100 = 48.5. Further, the progress rate of the outline number [1.1.2] is the weight × of the outline number [1.1.2] × ((weight of the outline number [1.1.2.1] × progress rate)) + (weight × of the outline number [1.1.2.2] Progress rate)) divided by 100. That is, the progress rate of the general reference [1.1.2] can be calculated as 50 × ((60 × 70%) + (40 × 20%)) / 100 = 25.

그리고 계획 진척율은 기간 경과율을 기준으로 경과한 기간만큼 완료된 것으로 판단하여 산출된다. 예를 들어 설명하면, 10일이 소요되는 작업항목이 현재 5일째 진행중이면 해당 작업항목의 계획 진척율은 50% 완료된 것으로 산출할 수 있다.The plan progress rate is calculated based on the elapsed time period and is determined to have been completed. For example, if a work item that takes 10 days is currently in progress on the fifth day, the planning progress rate of the work item may be calculated as 50% completed.

다음으로, 분석 및 설계단계에서 공수를 통한 계획예산 및 종료예산을 산출한다.(S140) 이는 비용 산출부(120)에 의해 이루어질 수 있다. 계획 예산은 기준일까지 계획된 누적 계획공수를 말하며, 산출방법은 지난월까지의 계획누적공수+(당월 계획공수×기간 진행율)으로 이루어질 수 있다. 그리고 종료예산은 종료예정일까지의 총 계획공수를 말하며, 산출방법은 전체계획공수×기준일 현재의 실적 진척율(실질적인 획득가치)로 이루어질 수 있다.Next, at the analysis and design stage, the plan budget and the end budget are calculated through the airlift (S140). This may be made by the cost calculator 120. The planned budget refers to the cumulative planned work scheduled up to the base date, and the method of calculation may consist of planned cumulative work up to last month + (current plan work time × period progress rate). The final budget refers to the total planned delivery up to the scheduled end date, and the calculation method may be the total planned delivery time x the actual progress rate (actual acquisition value) as of the reference date.

다음으로, 개발단계에서 프로그램 단위를 이용하여 개별적으로 진척율을 산출한다.(S150) 이때, 프로그램 단위는 프로그램 본수 또는 규모측정자료(FP)로 이 루어질 수 있다. 이는 개발 진척율 관리부(112)의 프로그램 입력부(118) 및 제 2 진척율 산출부(119)에 의해 수행될 수 있다.Next, the progress rate is calculated individually using the program unit in the development stage. (S150) In this case, the program unit may be the number of programs or scale data (FP). This may be performed by the program input unit 118 and the second progress rate calculator 119 of the development progress rate manager 112.

다음으로, 개발단계에서 공수를 통한 계획예산 및 종료예산을 산출한다.(S160) 이는 분석 및 설계단계에서 설명한 산출방법과 동일하게 이루어진다. Next, at the development stage, the planned budget and the final budget are calculated through airlift (S160). This is performed in the same manner as the calculation method described in the analysis and design stage.

다음으로, 테스트단계에서 가중치를 이용하여 진척율을 산출한다.(S170) 이때, 테스트단계는 앞서 설명한 분석 및 설계단계와 동일한 방식으로 진척율, 실적 진척율, 계획 진척율 그리고 계획예산 및 종료예산이 산출된다.(S180,S190) 이는 테스트 진척율 관리부(113)에 의해 수행될 수 있다.Next, the progress rate is calculated using the weight in the test step (S170). In this case, the test step includes the progress rate, the performance progress rate, the planning progress rate, and the planned budget and the final budget in the same manner as the above-described analysis and design steps. This is calculated. (S180, S190) This may be performed by the test progress rate management unit 113.

다음으로, 프로젝트 전 단계의 진척율을 합산한다.(S200) 이는 진척율 합산부(130)에 의해 수행될 수 있다.Next, the progress rate of the pre-project stage is added up (S200). This may be performed by the progress rate adding unit 130.

이와 같이, 개발 단계에서 프로그램 단위를 이용하여 진척율을 개별적으로 산출한 다음 가중치를 이용하여 산출되는 분석 및 설계 단계와 테스트 단계의 진척율에 합산하여 전체 진척율을 산출함으로써, 가시성을 확보하여 실시간으로 정확한 프로젝트 진척사항을 파악할 수 있는 효과가 있다.As such, the progress rate is individually calculated using the program unit in the development stage, and then the overall progress rate is calculated by adding the progress rates of the analysis and design stages and the test stage calculated using the weights to obtain visibility and real time. This can be effective in identifying the exact project progress.

이상에서 설명한 본 발명의 바람직한 실시예에 대하여 상세하게 설명하였지만 당해 기술분야에서 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 수 있을 것이다.Although the preferred embodiments of the present invention described above have been described in detail, those skilled in the art will understand that various modifications and equivalent other embodiments are possible therefrom.

따라서, 본 발명의 권리 범위는 개시된 실시예에 한정되는 것은 아니고 다음의 청구범위에서 정의하고 있는 본 발명의 기본 개념을 이용한 당업자의 여러 변경 및 개량 형태 또는 본 발명의 권리 범위에 속하는 것으로 보아야 할 것이다Accordingly, the scope of the present invention should not be limited to the disclosed embodiments but should be regarded as belonging to various modifications and improvements of those skilled in the art using the basic concept of the present invention as defined in the following claims, or the scope of the present invention.

도 1은 프로젝트 관리 시스템의 프로젝트 진척관리방법과 그에 따른 각 구성원의 역할을 나타낸 도면.1 is a view showing a project progress management method and a role of each member according to the project management system.

도 2는 프로젝트 단계를 나타낸 도면.2 shows a project phase.

도 3 및 도 4는 본 발명의 실시예에 따른 업무분류체계의 프로젝트 진척관리 시스템을 나타낸 도면.3 and 4 is a view showing a project progress management system of a business classification system according to an embodiment of the present invention.

도 5는 본 발명의 실시예에 따른 업무분류체계의 프로젝트 진척관리 방법을 순차적으로 나타낸 도면.5 is a view sequentially showing a project progress management method of a business classification system according to an embodiment of the present invention.

도 6은 가중치를 산출하는 방법을 자세하게 설명하기 위한 도면.6 is a diagram for explaining in detail a method for calculating a weight.

도 7은 실적 진척율를 산출하는 방법을 자세하게 설명하기 위한 도면.7 is a diagram for explaining in detail a method of calculating the performance progress rate.

Claims (22)

삭제delete 업무분류체계의 프로젝트 진척관리 시스템에 있어서, In the project progress management system of the work classification system, 프로젝트 분석 및 설계 단계에서 가중치를 이용하여 산출되는 진척율을 관리하는 분석 및 설계 진척율 관리부, 프로젝트 개발단계에서 프로그램 단위를 이용하여 산출되는 진척율을 관리하는 개발 진척율 관리부, 및 프로젝트 테스트단계에서 가중치를 이용하여 산출되는 진척율을 관리하는 테스트 진척율 관리부를 포함하는 프로젝트 단계별 산출되는 진척율을 관리하는 진척율 관리부와 프로젝트 단계별 공수를 통한 계획예산 및 종료예산을 산출하는 비용 산출부를 포함하는 프로젝트 서버; In the analysis and design progress rate management unit, which manages the progress rate calculated using weights in the project analysis and design stage, the development progress rate management unit, which manages the progress rate calculated using program units in the project development stage, and the project test stage. A project including a progress rate management unit for managing a progress rate calculated for each stage and a cost calculation unit for calculating a planned budget and an end budget through airborne project stages. server; 프로젝트 서버와 연동되고, 프로젝트 계획, 프로젝트 설계 및 프로젝트 케이스 관리 등의 테스트 프로젝트 전반의 활동을 지원하는 테스트 관리서버; 및 A test management server interworking with the project server and supporting activities of a test project, such as project planning, project design, and project case management; And 프로젝트 서버와 연동되고, 프로젝트의 결함관리, 결함에 대한 추적관리의 활동을 지원하는 결함 관리서버;A defect management server interworking with the project server and supporting the project's defect management and tracking of defects; 를 포함하는 것을 특징으로 하는 프로젝트 진척관리 시스템.Project progress management system comprising a. 삭제delete 제 2항에 있어서,The method of claim 2, 프로젝트 서버는Project server 프로젝트 전 단계의 진척율을 합산하는 진척율 합산부를 더 포함하는 것을 특징으로 하는 프로젝트 진척관리 시스템.Project progress management system, characterized in that it further comprises a progress rate adding unit for summing the progress rate of the pre-project stage. 제 2항에 있어서, The method of claim 2, 분석 및 설계 진척율 관리부와 테스트 진척율 관리부는 Analysis and design progress rate management department and test progress rate management department 프로젝트에서 수행되는 작업항목을 상,하위로 분류하여 등록하는 등록부; A register that classifies and registers the work items performed in the project into upper and lower parts; 상,하위 작업항목에 대한 투입인력 및 기간정보를 입력하는 입력부;An input unit for inputting input manpower and period information for upper and lower work items; 동일한 레벨에 있는 상,하위 작업항목에 동일한 가중치의 합을 부여하여 각각의 작업항목에 대한 가중치를 산출하는 가중치 산출부; 및A weight calculator configured to calculate a weight for each work item by applying a sum of the same weights to upper and lower work items at the same level; And 상,하위 작업항목의 가중치를 이용하여 진척율을 산출하는 제 1 진척율 산출 부;A first progress rate calculation unit configured to calculate a progress rate using weights of upper and lower work items; 를 포함하는 것을 특징으로 하는 프로젝트 진척관리 시스템.Project progress management system comprising a. 제 2항에 있어서,The method of claim 2, 개발 진척율 관리부는Development progress management department 프로그램 단위를 입력하는 프로그램 입력부; 및A program input unit for inputting a program unit; And 프로그램 단위를 이용하여 진척율을 산출하는 제 2 진척율 산출부;A second progress rate calculator configured to calculate a progress rate using a program unit; 를 포함하는 것을 특징으로 하는 프로젝트 진척관리 시스템.Project progress management system comprising a. 제 2항에 있어서,The method of claim 2, 프로그램 단위는 프로그램 본수 또는 규모측정자료(FP)로 이루어지는 것을 특징으로 하는 프로젝트 진척관리 시스템.Project progress management system, characterized in that the program unit consists of the number of programs or scale data (FP). 업무분류체계의 프로젝트 진척관리방법에 있어서,In project progress management method of work classification system, 프로젝트 서버는 프로젝트에서 수행되는 작업항목을 상,하위로 분류하여 등록하는 단계;The project server registers the work items performed in the project classified into upper and lower parts; 프로젝트 서버는 분석 및 설계 단계에서 가중치를 이용하여 진척율을 산출하는 단계;The project server calculating a progress rate using the weights in the analysis and design phases; 프로젝트 서버는 개발 단계에서 프로그램 단위를 이용하여 진척율을 산출하는 단계; 및The project server calculating a progress rate using a program unit in a development stage; And 프로젝트 서버는 테스트 단계에서 가중치를 이용하여 진척율을 산출하는 단계;The project server calculating a progress rate using the weights in the testing step; 를 포함하는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method comprising a. 제 8항에 있어서,The method of claim 8, 작업항목을 상,하위로 분류하여 등록하는 단계 이후에,After the step of registering work items into upper and lower levels, 상,하위 작업 항목에 대한 투입인력 및 기간 정보를 입력하는 단계가 포함되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method comprising the step of inputting input personnel and period information for the upper and lower work items. 제 8항에 있어서,The method of claim 8, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계에서,In calculating the progress rate in the analysis and design phase and the progress rate in the test phase, 가중치는 투입인력×기간으로 산출되는 작업항목의 비중을 나타내는 지표인 것을 특징으로 하는 프로젝트 진척관리 방법.The weighting method is a project progress management method, characterized in that it is an index indicating the weight of the work item calculated by the input labor x time period. 제 8항에 있어서,The method of claim 8, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계에서,In calculating the progress rate in the analysis and design phase and the progress rate in the test phase, 가중치는 백분율로 표현되며 상,하위 작업항목의 가중치 합은 각각 100%인 것을 특징으로 하는 프로젝트 진척관리 방법.The weight is expressed as a percentage, and the sum of the weights of the upper and lower work items is 100%, respectively. 제 8항에 있어서,The method of claim 8, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계에서,In calculating the progress rate in the analysis and design phase and the progress rate in the test phase, 작업항목에 대한 실적 진척율 및 계획 진척율을 산출하는 단계가 더 포함되는 것을 특징으로 하는 프로젝트 진척관리 방법.The project progress management method, characterized in that it further comprises the step of calculating the performance progress rate and planning progress rate for the work item. 제 12항에 있어서,The method of claim 12, 작업항목에 대한 실적 진척율을 산출하는 단계에서,In calculating the performance progress rate for a work item, 상위 작업항목의 가중치×(하위 작업항목의 가중치×진척율)/100으로 산출되는 것을 특징으로 하는 프로젝트 진척관리 방법.A project progress management method, characterized in that it is calculated by the weight x of the higher work item x (weight x progress rate of the lower work item) / 100. 제 13항에 있어서,The method of claim 13, 작업항목에 대한 실적 진척율을 산출하는 단계에서,In calculating the performance progress rate for a work item, 하위 작업항목이 다수개일 경우, 상위 작업항목의 가중치×((제 1하위 작업항목의 가중치×진척율)+(제 2하위 작업항목의 가중치×진척율))/100으로 산출되는 것을 특징으로 하는 프로젝트 진척관리 방법.When there are a plurality of lower work items, the weight of the upper work item x ((weight of the first lower work item x progress rate) + (weight of the second lower work item x progress rate)) / 100 is calculated. How to manage project progress. 제 12항에 있어서,The method of claim 12, 작업항목에 대한 계획 진척율을 산출하는 단계에서,In calculating the planned progress rate for the work item, 계획 진척율은 예상 소요기간을 기준으로 경과한 기간을 백분율로 표현하여 산출되는 것을 특징으로 하는 프로젝트 진척관리 방법. The project progress management method is a project progress management method characterized in that it is calculated by expressing the elapsed time period as a percentage based on the expected lead time. 제 8항에 있어서,The method of claim 8, 분석 및 설계 단계의 진척율 및 테스트 단계의 진척율을 산출하는 단계 이후에, After calculating the progress rate in the analysis and design phase and the progress rate in the test phase, 공수를 통한 계획 예산 및 종료 예산을 산출하는 단계가 더 포함되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method further comprises the step of calculating the planned budget and the end budget through the airlift. 제 16항에 있어서,The method of claim 16, 계획예산은 지난월까지의 계획누적공수+(당월 계획공수×기간 진행율)로 산출되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project budget management method characterized in that the project budget calculated by the cumulative cumulative number + (current month plan number x period progress rate) until last month. 제 16항에 있어서,The method of claim 16, 종료예산은 전체 계획 공수×기준일 현재의 실적 진척율로 산출되는 것을 특징으로 하는 프로젝트 진척관리 방법.The final budget is a project progress management method, characterized in that it is calculated by the performance progress rate as of the total plan number x base date. 제 8항에 있어서, The method of claim 8, 프로그램 단위를 이용하여 개발 단계의 진척율을 산출하는 단계에서,In calculating the progress rate of the development stage using the program unit, 프로그램 단위로 프로그램 본수가 이용되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method characterized in that the program head is used in the program unit. 제 8항에 있어서,The method of claim 8, 프로그램 단위를 이용하여 개발 단계의 진척율을 산출하는 단계에서,In calculating the progress rate of the development stage using the program unit, 프로그램 단위로 규모측정자료(FP)가 이용되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method characterized in that the FP is used as a program unit. 제 8항에 있어서,The method of claim 8, 프로그램 단위를 이용하여 개발 단계의 진척율을 산출하는 단계 이후에, After calculating the progress rate of the development stage using the program unit, 공수를 통한 계획 예산 및 종료 예산을 산출하는 단계가 더 포함되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method further comprises the step of calculating the planned budget and the end budget through the airlift. 제 8항에 있어서,The method of claim 8, 테스트 단계의 진척율을 산출하는 단계 이후에.After the step of calculating the progress rate of the test step. 프로젝트 전 단계의 진척율을 합산하는 단계가 포함되는 것을 특징으로 하는 프로젝트 진척관리 방법.Project progress management method comprising the step of adding up the progress rate of the pre-project phase.
KR1020090088551A 2009-09-18 2009-09-18 Project progress management system and the method KR100935304B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090088551A KR100935304B1 (en) 2009-09-18 2009-09-18 Project progress management system and the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090088551A KR100935304B1 (en) 2009-09-18 2009-09-18 Project progress management system and the method

Publications (1)

Publication Number Publication Date
KR100935304B1 true KR100935304B1 (en) 2010-01-06

Family

ID=41809426

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090088551A KR100935304B1 (en) 2009-09-18 2009-09-18 Project progress management system and the method

Country Status (1)

Country Link
KR (1) KR100935304B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100968709B1 (en) 2010-04-14 2010-07-06 지에스건설 주식회사 Method to obtain the required completion percentage of milestone in construction project, method to establish the milestone schedule and evaluation method for established milestone schedule
CN102999817A (en) * 2012-12-06 2013-03-27 苏州工业园区职业技术学院 Term project management system
CN103778506A (en) * 2014-01-10 2014-05-07 国网冀北电力有限公司 Power grid technology innovation project standard cost management system
KR101841161B1 (en) * 2015-09-22 2018-05-04 주식회사 프리모아 System for managing project and method for managing project
KR20200106856A (en) 2019-03-05 2020-09-15 디지테크정보 주식회사 Project management system and method using template
KR20200106817A (en) 2020-01-02 2020-09-15 디지테크정보 주식회사 Project management system and method using template
CN113298437A (en) * 2021-06-22 2021-08-24 北京华档致远科技有限公司 Data productivity management system
KR102529138B1 (en) 2022-12-21 2023-05-08 주식회사 큐브인터랙티브 Library-based project management method, device and system by process
KR102532750B1 (en) 2023-02-24 2023-05-16 주식회사 슈퍼스타트 Software development project management system and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10269076A (en) * 1997-03-24 1998-10-09 Nec Corp Progress management system and record medium
JP2007334568A (en) * 2006-06-14 2007-12-27 Hitachi Ltd System for creating test plan for business process control
KR20090062417A (en) * 2007-12-13 2009-06-17 대림산업 주식회사 All working process management system of all working process using e.v.m.s progrem

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10269076A (en) * 1997-03-24 1998-10-09 Nec Corp Progress management system and record medium
JP2007334568A (en) * 2006-06-14 2007-12-27 Hitachi Ltd System for creating test plan for business process control
KR20090062417A (en) * 2007-12-13 2009-06-17 대림산업 주식회사 All working process management system of all working process using e.v.m.s progrem

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100968709B1 (en) 2010-04-14 2010-07-06 지에스건설 주식회사 Method to obtain the required completion percentage of milestone in construction project, method to establish the milestone schedule and evaluation method for established milestone schedule
CN102999817A (en) * 2012-12-06 2013-03-27 苏州工业园区职业技术学院 Term project management system
CN103778506A (en) * 2014-01-10 2014-05-07 国网冀北电力有限公司 Power grid technology innovation project standard cost management system
KR101841161B1 (en) * 2015-09-22 2018-05-04 주식회사 프리모아 System for managing project and method for managing project
KR20200106856A (en) 2019-03-05 2020-09-15 디지테크정보 주식회사 Project management system and method using template
KR20200106817A (en) 2020-01-02 2020-09-15 디지테크정보 주식회사 Project management system and method using template
CN113298437A (en) * 2021-06-22 2021-08-24 北京华档致远科技有限公司 Data productivity management system
CN113298437B (en) * 2021-06-22 2023-09-05 北京华档致远科技有限公司 Data productivity management system
KR102529138B1 (en) 2022-12-21 2023-05-08 주식회사 큐브인터랙티브 Library-based project management method, device and system by process
KR102532750B1 (en) 2023-02-24 2023-05-16 주식회사 슈퍼스타트 Software development project management system and method

Similar Documents

Publication Publication Date Title
KR100935304B1 (en) Project progress management system and the method
Tribelsky et al. Measuring information flow in the detailed design of construction projects
Poghosyan et al. A web-based design for occupational safety and health capability maturity indicator
US20070016432A1 (en) Performance and cost analysis system and method
CN103714411B (en) Project management system
Wesz et al. Planning and controlling design in engineered-to-order prefabricated building systems
Hernández-López et al. Software engineering job productivity—a systematic review
US20160048785A1 (en) A computer implemented system and method for project controls
Yilmaz et al. BIM-CAREM: Assessing the BIM capabilities of design, construction and facilities management processes in the construction industry
US20120179512A1 (en) Change management system
Calvetti et al. Sensing technologies embedding construction workers outcomes/key performance indicators
Lee et al. Key performance indicator (KPI) of contractor on project performance for housing construction in Malaysia
KR100930208B1 (en) Project productivity management system and the method
Heires What I did last summer: A software development benchmarking case study
Arenhart et al. Estimating the cost of calibration services using the TDABC costing method
Choudhury Project management information systems for construction of thermal power plant: A case study with special reference to National Thermal Power Corporation Ltd., India
Mei et al. Application of DMAIC approach to improve the centralized procurement process in construction logistics enterprises
Sinenko Analyzing the functional capabilities of modern systems, methods and means for scheduling
Abdel-Raheem et al. A framework for developing a new tool for contract time determination system
ERDÕS Different Techniques to Quantify the Yield of IT Projects.
Mehta et al. An Approach to Reduce Non-Value Added Time and Improve Process Cycle Efficiency by Implementing Project Information System
Raja et al. Elemental Approach to Design a Worker Profile as a Selection Tool in Last Planner System©
Fukuyama et al. A software process improvement support system: SPIS
Nam Construction scheduling with primavera P6
Shin et al. Development of Business and Performance Record Standard Template for Rail Infrastructure BIM Performance Management

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121210

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20131210

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20161123

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20190926

Year of fee payment: 13