CN113738381B - Construction method for pile body at joint of underground excavation station and shield zone - Google Patents

Construction method for pile body at joint of underground excavation station and shield zone Download PDF

Info

Publication number
CN113738381B
CN113738381B CN202111116977.6A CN202111116977A CN113738381B CN 113738381 B CN113738381 B CN 113738381B CN 202111116977 A CN202111116977 A CN 202111116977A CN 113738381 B CN113738381 B CN 113738381B
Authority
CN
China
Prior art keywords
pile
shield
station
reinforced concrete
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111116977.6A
Other languages
Chinese (zh)
Other versions
CN113738381A (en
Inventor
左建周
孔恒
聂泽文
杨威
徐文耀
王亚杰
田星晨
王旭
李志佳
蔡东海
张亮
喻凯
杜博然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN202111116977.6A priority Critical patent/CN113738381B/en
Publication of CN113738381A publication Critical patent/CN113738381A/en
Application granted granted Critical
Publication of CN113738381B publication Critical patent/CN113738381B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Abstract

The invention relates to a construction method of a pile body at a joint of a hidden excavation station and a shield zone, which belongs to the technical field of subway station construction and comprises the following steps: s1, constructing a first reinforced concrete pile and a plain pile below a section pipe piece at a tunnel portal; s2, pouring mortar into the upper part of the plain pile to the inverted arch of the transverse channel; s3, shield pile grinding and station entering; s4, digging holes to construct a second reinforced concrete pile above the pipe piece, and then constructing a pile top crown beam. The second-layer transverse channels of the vertical shafts at the two ends of the station can be fully utilized; after the shield passes, the upper pile is constructed for the second time, the shield segment is firmly connected with the upper pile body, and the potential safety hazards such as pile body inclination, unstable pile body and surrounding soil body and the like and quality risk hazards are avoided during the subsequent earth excavation of the station and the inter-pile net hanging anchor spraying construction, and the post-treatment is not needed, so that the construction period is not delayed; the shield pile grinding time is greatly shortened, and meanwhile, the abrasion to a cutter head of a shield machine is also reduced; when the segment near the position is removed, the loosening is not easy to occur.

Description

Construction method for pile body at joint of underground excavation station and shield zone
Technical Field
The invention relates to the technical field of subway station construction, in particular to a pile body construction method at a joint of a underground excavation station and a shield zone.
Background
Subway stations are places for providing railway trains to stop for urban rail transit systems (urban rail systems for short) for carrying goods or taking passengers. The subway station at the present stage does not refer to a station built in an environment below the ground, but refers to a station arranged along the subway system, and the subway station can be built underground, semi-underground or on the ground or on an overhead.
When a subway station is constructed, in order to facilitate shield pile grinding and station passing, a glass fiber reinforced pile is adopted as an end pile at the joint of a station and a tunnel portal in a shield section, and the following problems exist in the current construction method: 1. the transverse clearance size in the transverse channels of the vertical shafts No. 1 and No. 4 of the station is 4m, and the clearance size of the lower part in the transverse channel is reduced to 2.1m after the construction of the crown beam in the transverse channel is finished, so that the utilization rate of the transverse channel is greatly reduced; 2. after the shield passes, the pile body above the shield segment is in a cantilever state, and when the soil excavation of the subsequent station and the inter-pile net hanging anchor spraying construction are carried out, the potential safety hazards such as pile body inclination, unstable pile body and surrounding soil body and the like easily occur, and the post treatment can cause a construction period delay; 3. the time for shield station passing pile grinding is longer; 4. because the pile body is in the cantilever state, the soil body at the top of the segment is unstable, the embedding force between the segment and the surrounding soil body is reduced, and the segment is easy to loosen when the segment near the negative two-layer portal is removed.
In order to avoid the adverse effects, it is necessary to invent a construction method of the pile body at the joint of the station underground excavation station and the shield zone, so as to overcome the defects of the prior art and ensure the stability of the pile body after the shield pile is ground and passes through the station.
Disclosure of Invention
The invention aims to provide a construction method of a pile body at the joint of a hidden excavation station and a shield zone, which aims to solve the problems in the background technology.
In order to achieve the above purpose, the present invention provides the following technical solutions:
a construction method of a pile body at the joint of a hidden excavation station and a shield zone comprises the following steps:
s1, constructing a first reinforced concrete pile and a plain pile below a section pipe piece at a tunnel portal;
s2, pouring mortar into the upper part of the plain pile to the inverted arch of the transverse channel;
s3, shield pile grinding and station entering;
s4, digging holes to construct a second reinforced concrete pile above the pipe piece, and then constructing a pile top crown beam.
As a further technical scheme of the invention, the first reinforced concrete pile in the S1 is arranged at the bottom of the plain pile, and an extension pile is arranged at the bottom of the first reinforced concrete pile.
As a further technical scheme of the invention, the mortar in the S2 is M5 mortar.
As a still further technical scheme of the invention, the shield pile grinding in the step S3 comprises a left line shield station crossing and a right line shield station crossing.
Compared with the prior art, the invention has the beneficial effects that:
1. the second layer transverse channels of the vertical shafts at the two ends of the station can be fully utilized;
2. after the shield passes, the upper pile is constructed for the second time, the shield segment is firmly connected with the upper pile body, and the potential safety hazards such as pile body inclination, unstable pile body and surrounding soil body and the like and quality risk hazards are avoided during the subsequent earth excavation of the station and the inter-pile net hanging anchor spraying construction, and the post-treatment is not needed, so that the construction period is not delayed;
3. the shield pile grinding time is greatly shortened, and meanwhile, the abrasion to a cutter head of a shield machine is also reduced;
4. when the segment near the position is removed, the loosening is not easy to occur.
Drawings
FIG. 1 is a process diagram of the invention S1;
FIG. 2 is a process diagram of the invention S2;
FIG. 3 is a process diagram of the invention S3;
fig. 4 is a process diagram of the invention S4.
In the figure: 1-portal, 2-first reinforced concrete pile, 3-plain pile, 4-lengthened section pile, 5-mortar, 61-left line shield station crossing, 62-right line shield station crossing, 7-transverse channel inverted arch, 8-second reinforced concrete pile and 9-pile crown beam.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
The embodiment of the invention is realized in such a way that the construction method of the pile body at the joint of the underground excavation station and the shield zone shown in figures 1-4 comprises the following steps:
s1, constructing a first reinforced concrete pile 2 and a plain pile 3 below a section pipe piece at a tunnel portal 1;
s2, pouring M5 mortar 5 at the upper part of the plain pile 3 to a transverse channel inverted arch 7 (a pile top crown beam is not constructed temporarily);
s3, shield pile grinding and station entering, specifically a left line shield station passing 61 and a right line shield station passing 62;
s4, digging a hole to construct a second reinforced concrete pile 8 above the pipe piece, and then constructing a pile top crown beam 9.
In practical application, the pile length is shortened after adjustment, so that the pile body below the shield segment, namely the first reinforced concrete pile 2 and the plain pile 3, is firstly manufactured stably, and the lengthened section pile 4 at the lower part of the first reinforced concrete pile is also reinforced concrete, and the optimized length of the lengthened section pile 4 is 2m; considering the possible errors generated when the diameter of the shield excavation is 6.16m and the shield machine is tunneled to the station end pile, the length range of the plain pile 3 is as follows: 200mm below the lowest point of connection between the bottom of the element pile 3 and the outer wall of the duct piece, and 200mm above the highest point of connection between the top of the element pile 3 and the outer wall of the duct piece, so that the element pile 3 and the upper square pipe piece are tightly combined after shield pile grinding, and the support is stable.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present disclosure describes embodiments, not every embodiment is provided with a separate embodiment, and that this description is provided for clarity only, and that the disclosure is not limited to the embodiments described in detail below, and that the embodiments described in the examples may be combined as appropriate to form other embodiments that will be apparent to those skilled in the art.

Claims (3)

1. The construction method of the pile body at the joint of the underground excavation station and the shield zone is characterized by comprising the following steps:
s1, constructing a first reinforced concrete pile and a plain pile below a section pipe piece at a tunnel portal;
s2, pouring mortar into the upper part of the plain pile to the inverted arch of the transverse channel;
s3, shield pile grinding and station entering;
s4, digging a hole to construct a second reinforced concrete pile above the pipe piece, and then constructing a pile top crown beam;
in S1, a first reinforced concrete pile is arranged at the bottom of the plain pile, and an extension pile is arranged at the bottom of the first reinforced concrete pile.
2. The construction method of the pile body at the joint of the underground excavation station and the shield section according to claim 1, wherein the mortar in the step S2 is M5 mortar.
3. The construction method of the pile body at the joint of the underground excavation station and the shield section according to claim 1, wherein the shield pile grinding in the step S3 comprises left line shield station crossing and right line shield station crossing.
CN202111116977.6A 2021-09-23 2021-09-23 Construction method for pile body at joint of underground excavation station and shield zone Active CN113738381B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111116977.6A CN113738381B (en) 2021-09-23 2021-09-23 Construction method for pile body at joint of underground excavation station and shield zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111116977.6A CN113738381B (en) 2021-09-23 2021-09-23 Construction method for pile body at joint of underground excavation station and shield zone

Publications (2)

Publication Number Publication Date
CN113738381A CN113738381A (en) 2021-12-03
CN113738381B true CN113738381B (en) 2023-11-14

Family

ID=78740530

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111116977.6A Active CN113738381B (en) 2021-09-23 2021-09-23 Construction method for pile body at joint of underground excavation station and shield zone

Country Status (1)

Country Link
CN (1) CN113738381B (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101086209A (en) * 2007-07-23 2007-12-12 北京交通大学 Shield tunneling and shallow tunneling combined construction method for building underground station
CN201241335Y (en) * 2008-07-01 2009-05-20 北京住总集团有限责任公司 Pile and post in one foundation structure of underground engineering
CN204551452U (en) * 2015-04-17 2015-08-12 上海三凯建设管理咨询有限公司 A kind of composite pile improving bearing capacity of foundation soil
CN105003272A (en) * 2015-07-26 2015-10-28 北京工业大学 Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN106050244A (en) * 2016-08-01 2016-10-26 中铁第勘察设计院集团有限公司 Water-rich sand-cobble stratum shield entry and exit reinforcing system and construction method thereof
CN106968690A (en) * 2017-04-20 2017-07-21 中冶建工集团有限公司 The method for tunnel construction for soil property of caving in
CN106988753A (en) * 2017-05-08 2017-07-28 中建三局基础设施工程有限公司 A kind of U-shaped plain concrete ground-connecting-wall adds steel bushing shield structure and its method of reseptance
CN107575237A (en) * 2017-08-23 2018-01-12 广州地铁设计研究院有限公司 A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
CN109707415A (en) * 2018-11-21 2019-05-03 广州地铁设计研究院股份有限公司 A kind of joint construction method and its joint structure of Shield-bored tunnels and station
CN109706909A (en) * 2019-02-21 2019-05-03 郑州市市政工程总公司 The structures foundation reinforcing structure and its construction method worn under reply metro shield
CN109797665A (en) * 2019-01-29 2019-05-24 北京城建设计发展集团股份有限公司 Statically indeterminate structure bridge pile foundation actively underpins top lift determination and displacement control method
CN111396061A (en) * 2020-03-24 2020-07-10 西安建筑科技大学 Shield construction method, construction working face thereof and mixed pile body in working face
CN112411614A (en) * 2020-11-17 2021-02-26 中铁第四勘察设计院集团有限公司 Connecting structure capable of transferring force across existing component, reinforcing structure and construction method
CN112983446A (en) * 2021-04-22 2021-06-18 中铁一局集团第二工程有限公司 Construction method for shield cutting of existing station reinforced concrete fender post

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101086209A (en) * 2007-07-23 2007-12-12 北京交通大学 Shield tunneling and shallow tunneling combined construction method for building underground station
CN201241335Y (en) * 2008-07-01 2009-05-20 北京住总集团有限责任公司 Pile and post in one foundation structure of underground engineering
CN204551452U (en) * 2015-04-17 2015-08-12 上海三凯建设管理咨询有限公司 A kind of composite pile improving bearing capacity of foundation soil
CN105003272A (en) * 2015-07-26 2015-10-28 北京工业大学 Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN106050244A (en) * 2016-08-01 2016-10-26 中铁第勘察设计院集团有限公司 Water-rich sand-cobble stratum shield entry and exit reinforcing system and construction method thereof
CN106968690A (en) * 2017-04-20 2017-07-21 中冶建工集团有限公司 The method for tunnel construction for soil property of caving in
CN106988753A (en) * 2017-05-08 2017-07-28 中建三局基础设施工程有限公司 A kind of U-shaped plain concrete ground-connecting-wall adds steel bushing shield structure and its method of reseptance
CN107575237A (en) * 2017-08-23 2018-01-12 广州地铁设计研究院有限公司 A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
CN109707415A (en) * 2018-11-21 2019-05-03 广州地铁设计研究院股份有限公司 A kind of joint construction method and its joint structure of Shield-bored tunnels and station
CN109797665A (en) * 2019-01-29 2019-05-24 北京城建设计发展集团股份有限公司 Statically indeterminate structure bridge pile foundation actively underpins top lift determination and displacement control method
CN109706909A (en) * 2019-02-21 2019-05-03 郑州市市政工程总公司 The structures foundation reinforcing structure and its construction method worn under reply metro shield
CN111396061A (en) * 2020-03-24 2020-07-10 西安建筑科技大学 Shield construction method, construction working face thereof and mixed pile body in working face
CN112411614A (en) * 2020-11-17 2021-02-26 中铁第四勘察设计院集团有限公司 Connecting structure capable of transferring force across existing component, reinforcing structure and construction method
CN112983446A (en) * 2021-04-22 2021-06-18 中铁一局集团第二工程有限公司 Construction method for shield cutting of existing station reinforced concrete fender post

Also Published As

Publication number Publication date
CN113738381A (en) 2021-12-03

Similar Documents

Publication Publication Date Title
CN101858220B (en) Tunnel double upper sidewall heading construction method
CN100554646C (en) Shield method combines the job practices of building the subway station with shallow burial hidden digging
CN103032081B (en) Cross-river large-diameter slurry shield excavation and double-lining parallel construction method
CN204457792U (en) A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building
CN105822310A (en) Rapid low-risk station tunnel digging method
CN101392654A (en) Shield tunnel segment lining-anchor rod structure system
CN106193117B (en) A kind of assembling and construction method of the prefabricated pipe gallery in underground
CN203684234U (en) Hoisting reserved-well supporting structure for track panel construction
CN208669320U (en) The anti-horizontal ovalizing deflection shield tunnel ruggedized construction of pre-embedded steel slab
CN107130968A (en) A kind of tunnel construction mid-board
CN206346737U (en) A kind of supporting major diameter curve pipe curtain
CN113738381B (en) Construction method for pile body at joint of underground excavation station and shield zone
CN204436457U (en) The prefabricated evacuation platform of a kind of shield structure running tunnel
CN102747725B (en) Bored pile construction method with tiny disturbance
CN105927252B (en) It is a kind of to excavate big cross section underground space structure transforming methods of structural system using rectangular top pipe
CN104653222B (en) Prefabricated evacuation platform for shield interval tunnel
CN205347899U (en) Monorail train pillar construction
CN208734343U (en) A kind of station tunnel excavation structure with interim middle spacer post support
CN113431588B (en) Construction method for branch tunnel
CN202482767U (en) Steel tube bailey beam column type support
CN112879033B (en) Crossline section tunnel structure combined with shield tunnel
CN112012752B (en) Miniature shield winding method for building underground excavated subway station
CN202628105U (en) Automatic programming machine (APM) track structure applicable to circular section of shield tunnel
CN208870627U (en) A kind of novel load-carrying air crossing
CN213743435U (en) Step multiple leading small conduit arrangement structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant