CN113737713A - riverID bank surrounding repair equipment - Google Patents

riverID bank surrounding repair equipment Download PDF

Info

Publication number
CN113737713A
CN113737713A CN202110824771.2A CN202110824771A CN113737713A CN 113737713 A CN113737713 A CN 113737713A CN 202110824771 A CN202110824771 A CN 202110824771A CN 113737713 A CN113737713 A CN 113737713A
Authority
CN
China
Prior art keywords
water
connecting column
plate
clamping
blocking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110824771.2A
Other languages
Chinese (zh)
Inventor
吴诗德
周梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yz Zhongda Gas Spring Co ltd
Original Assignee
Yz Zhongda Gas Spring Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yz Zhongda Gas Spring Co ltd filed Critical Yz Zhongda Gas Spring Co ltd
Priority to CN202110824771.2A priority Critical patent/CN113737713A/en
Publication of CN113737713A publication Critical patent/CN113737713A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/02Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention relates to a riverID bank-around repair device. The device is including the connecting column group that two rows of intervals set up, each connecting column group is including the spliced pole that a plurality of horizontal intervals set up, connect through adjusting the pull rod between the adjacent spliced pole in each connecting column group, all be provided with the water-blocking board between the spliced pole in a connecting column group and the adjacent spliced pole in another connecting column group, all be provided with long banding U type seal groove on each spliced pole surface, each water-blocking board side all is located the U type seal groove and sets up, two adjacent water-blocking boards form the triangle-shaped structure with the adjusting the pull rod that corresponds, the interval is provided with a plurality of clamping mechanism between the double-phase adjacent water-blocking board in the triangle-shaped structure, the device belongs to equipment type equipment, adopt the dam method or enclose the repair of enclosing the bank, be applicable to in the industrial production, have very strong practicality.

Description

riverID bank surrounding repair equipment
Technical Field
The invention belongs to the technical field of riverway treatment equipment, and particularly relates to riverway entity identity (BioTed) coastal repairing equipment.
Background
River channels are criss-cross, shallow and deep, and have different river water functions: the flood control, the waterlogging drainage, the transportation and the agricultural irrigation simultaneously increase the color of the water countryside. Along with the rapid development of economy, the investment for beautifying the environment is increased, particularly the investment for beautifying the riverway surrounding banks is increased, the riverway repairing process is mostly realized by land acquisition, damming, water pumping, river mud dredging, moving out, building the surrounding banks, filling water and damming, and the engineering is performed by using a large excavator, a large crane and a heavy engineering vehicle in a large scale. It is estimated that more than 60% of money is spent on preparation work and renting large equipment, the cost of building the revetment is less than 30% and crops on a large land on the bank are destroyed, so that a revetment repairing device and a method which have low requirements on the environment and have minimum cost are urgently sought.
Disclosure of Invention
The invention aims to solve the technical problem that the existing building of the riverpeople embankment adopts a river-blocking dam, the dam is piled with multipurpose soil or a huge closed iron box is added in the middle of the dam to serve as a dam foundation, the cost is extremely high, and in order to improve the defects, the invention provides the riverpeople embankment repairing equipment.
In order to achieve the purpose, the invention is realized by the following technical scheme:
the riverbank repairing equipment comprises two rows of connecting column groups arranged at intervals, each connecting column group comprises a plurality of connecting columns arranged at intervals horizontally, adjacent connecting columns in each connecting column group are connected through an adjusting pull rod, a water blocking plate is arranged between the connecting column in one connecting column group and the adjacent connecting column in the other connecting column group, a long strip-shaped U-shaped sealing groove is arranged on the outer surface of each connecting column, the side surface of each water blocking plate is arranged in the U-shaped sealing groove, two adjacent water blocking plates and the corresponding adjusting pull rod form a triangular structure, a plurality of clamping mechanisms are arranged between the two adjacent water blocking plates in the triangular structure at intervals, the clamping mechanism comprises a clamping screw rod connected with the outer surface of the connecting column, a pressing plate is sleeved on the clamping screw rod, a hand wheel is screwed on the thread section of the clamping screw rod, and the pressing plate is extruded by the hand wheel, so that the two sides of the pressing plate are butted on the surfaces of the corresponding water blocking plates.
Furthermore, the lower ends of the two sides of the connecting column group are respectively provided with a triangular structure, each triangular structure and the corresponding triangular structure form a diamond structure, the two connecting columns on the short diagonal line in the diamond structure are connected through an adjusting pull rod, a chain is arranged between the two connecting columns on the long diagonal line, both ends of the vertical chain are respectively provided with a thread sleeve, each thread sleeve is screwed on the thread section of the clamping screw in the corresponding clamping mechanism, the obtuse angle in the diamond structure is provided with a first wedge clamp which is arranged in an L shape, one end of the vertical section of the first wedge clamp is connected with the connecting column, the other end of the vertical section is connected with an inclined section, the inner side of the inclined section is provided with a clamping bulge, the clamping bulge is abutted in the clamping groove of the inner surface of the corresponding water blocking plate, the two first wedge clamps at the same obtuse angle form a butterfly structure, the end of the diamond structure facing the bank of the river bank is provided with the water blocking plate, one end of the water blocking plate is connected with the U-shaped sealing groove on the end connecting column of the diamond structure, a water blocking groove is formed in the river bank opposite to the other end of the water blocking plate, backfill soil is filled in the water blocking groove, and the other end of the water blocking plate is inserted into the backfill soil.
Further, rhombus structure lower extreme lateral surface is connected with two water-blocking plates, and a water-blocking plate end is connected with the spliced pole of rhombus structure short diagonal end, and another water-blocking plate end is connected with the spliced pole of rhombus structure long diagonal end, and the water-blocking plate in the outside forms the triangle-shaped structure in two water-blocking plates and the rhombus structure, still is connected with the water-blocking plate of pegging graft in backfill soil on the spliced pole that is located the bottommost, water-blocking plate slope sets up, and sets up with the water-blocking plate parallel and level in the triangle-shaped structure outside, is provided with the second slide wedge clamp between two water-blocking plates, and the second slide wedge clamp is the U type setting, and second slide wedge clamp two otic placode section internal surfaces all are provided with the joint arch, and each joint arch is contradicted in the tight inslot of clamp that corresponds water-blocking plate lateral surface.
Further, the water blocking plate comprises a framework, the framework is formed by welding a plurality of rectangular steel pipes, steel plates are covered on two sides of the framework, the two steel pipes are riveted with the framework through rivets, the edges of the steel plates are welded with the edges of the framework, two strip-shaped clamping grooves are formed in the outer surfaces of the steel plates, the cross sections of the clamping grooves are arranged in a U shape, openings of the two clamping grooves are arranged in opposite directions, and the free end of any panel extends.
Furthermore, the pressing plate is U-shaped, the middle section of the pressing plate is sleeved on the clamping screw, the two lug plate sections of the pressing plate are arranged in parallel with the corresponding water blocking plates, the free ends of the lug plate sections of the pressing plates are located in the clamping grooves of the corresponding water blocking plates, and the free ends of the lug plate sections of the pressing plates are abutted to the inner bottom surfaces of the corresponding clamping grooves.
Furthermore, a silica gel plate is arranged on the inner bottom surface of the U-shaped sealing groove, and the side surface of each water blocking plate is abutted against the silica gel plate.
Further, adjust the pull rod including the adjustable ring, the levogyration screw hole has been seted up to the adjustable ring left end, and the dextrorotation screw hole has been seted up to the right-hand member, the levogyration screw hole has all connect adjusting screw with the dextrorotation screw in the dextrorotation screw hole soon, and each adjusting screw free end is provided with the go-between, and each adjusting screw is just right spliced pole surface interval is provided with two connecting plates, sell the hub connection between go-between and the connecting plate.
Furthermore, each spliced pole is hollow, and the peg graft has powerful stake in, powerful stake is including being located anterior solid pointed end, and solid pointed end afterbody is connected with the hollow tube, and the hollow tube end is connected with and is located terminal solid bar iron, the bar groove has been seted up on the solid bar iron surface.
Furthermore, each spliced pole side all is provided with articulated seat, it has the support batter post all to articulate on the articulated seat, support the batter post and include two sections hollow steel pipes, be provided with solid round steel between two sections hollow steel pipes, solid round steel both ends head all is provided with the external screw thread, has seted up the internal thread in the hollow steel pipe that each end is just right, solid round steel and hollow steel pipe connect soon, and a hollow steel pipe other end is articulated with the articulated seat of spliced pole side, and the other end of another hollow steel pipe is pegged graft at the bottom of a river.
Compared with the prior art, the invention has the beneficial effects that: the device belongs to equipment type equipment, assemble during the use, carry out the fat liquoring when not using and preserve, can carry out the shore repair without stopping navigation in principle, through the equipment mode of difference, adopt and build dam method or enclose the repair that the shore was carried out to the method, it compares in prior art need not to get a large amount of earth and builds the dam to build the dam method, it is little to bank limit soil damage, nevertheless be unsuitable for the river course that has the shipping task, enclose the river course that the method can make the repair and do not navigate, it is less to the ecological balance destruction in the river course, the device can carry out the repair of arbitrary shore segment length simultaneously, the device is applicable to in the industrial production, and the device has very strong practicality.
Drawings
Fig. 1 is a schematic view of the dam construction method for repairing the bank.
FIG. 2 is a schematic diagram of the present invention when the enclosure method is used for repairing the enclosure.
Fig. 3 is a schematic diagram of a first-stage river bank repaired by a method of enclosure and then a next-stage repair is carried out.
Fig. 4 is a schematic view of an assembly structure of the present invention when a damming method is adopted.
Fig. 5 is a partial enlarged view of a portion a in fig. 4.
FIG. 6 is a schematic view of an assembly structure of the present invention using a circling method.
Fig. 7 is a partial enlarged view of fig. 6 at B.
Fig. 8 is a partial enlarged view at C in fig. 6.
FIG. 9 is a schematic view of another assembly structure of the present invention using the circling method.
Fig. 10 is a partial enlarged view of fig. 9 at D.
FIG. 11 is a schematic view showing the structure of the water blocking plate according to the present invention.
Fig. 12 is a schematic view of the structure of the clamping mechanism of the present invention.
Fig. 13 is a schematic structural view of an adjusting pull rod according to the present invention.
FIG. 14 is a schematic view of the connection structure of the chain and the threaded sleeve of the present invention.
Fig. 15 is a schematic structural view of a strength pile according to the present invention.
FIG. 16 is a schematic view of the connection structure of the support diagonal pillar and the connection pillar in the present invention.
In the figure: 1 river bank, 2 river water, 3 backfill, 4 water blocking grooves, 5 connecting columns, 501 connecting plates, 502 hinged seats, 6 adjusting pull rods, 601 adjusting rings, 602 adjusting screws, 603 connecting rings, 7 water blocking plates, 701 steel plates, 702 rivets, 703 clamping grooves, 8U-shaped sealing grooves, 9 clamping mechanisms, 901 clamping screws, 902 pressing plates, 903 hand wheels, 10 chains, 11 thread sleeves, 12 first wedge clamps, 13 clamping protrusions, 14 second wedge clamps, 15 silica gel plates, 16 powerful piles, 1601 solid tips, 1602 hollow tubes, 1603 solid steel rods, 1604 strip-shaped grooves, 17 supporting oblique columns, 1701 hollow steel tubes and 1702 solid round steel.
Detailed Description
The technical solution of the present application will be further described and explained with reference to the accompanying drawings and embodiments.
As shown in fig. 1 and 4, the river-based embankment repair equipment comprises two rows of connecting column groups arranged at intervals, each connecting column group comprises a plurality of connecting columns 5 arranged at intervals horizontally, adjacent connecting columns 5 in each connecting column group are connected through an adjusting pull rod 6, a water blocking plate 7 is arranged between each connecting column 5 in one connecting column group and each adjacent connecting column 5 in the other connecting column group, a long strip-shaped U-shaped sealing groove 8 is arranged on the outer surface of each connecting column 5, the side surface of each water blocking plate 7 is arranged in each U-shaped sealing groove 8, two adjacent water blocking plates 7 and the corresponding adjusting pull rod 6 form a triangular structure, a plurality of clamping mechanisms 9 are arranged at intervals between two adjacent water blocking plates 7 in the triangular structure, each clamping mechanism 9 comprises a clamping screw 901 connected with the outer surface of the connecting column 5, a pressing plate is sleeved on the clamping screw 901, a hand wheel 903 is screwed on the thread section 901 of the clamping screw, the handwheel 903 presses the pressing plate 902, so that the two sides of the pressing plate 902 are abutted against the corresponding surfaces of the water-blocking plates 7. The method comprises the steps of firstly pre-digging two water blocking grooves 4 on two sides of a river bank 1, filling backfill 3 in the water blocking grooves 4, inserting two connecting column sets in the device at the bottom of the river, connecting columns 5 through a water blocking plate 7 and an adjusting pull rod 6 to form a dam, carrying out the same operation on the other side of the river bank 1 through the device, drawing out river water 2 between the two dams after the dam is built, and carrying out shore surrounding repair after the river water is drawn out.
As shown in fig. 2, 3 and 6, the lower ends of the two sides of the connecting column set are respectively provided with a triangular structure, each triangular structure and the corresponding triangular structure form a diamond structure, the two connecting columns 5 on the short diagonal line in the diamond structure are connected through an adjusting pull rod 6, a chain 10 is arranged between the two connecting columns 5 on the long diagonal line, both ends of the vertical chain 10 are respectively provided with a threaded sleeve 11, each threaded sleeve 11 is screwed on the threaded section of a clamping screw 901 in the corresponding clamping mechanism 9, the obtuse angle in the diamond structure is provided with a first wedge clamp 12, the first wedge clamp 12 is arranged in an L shape, one end of the vertical section of the first wedge clamp 12 is connected with the connecting column 5, the other end is connected with an inclined section, the inner side of the inclined section is provided with a clamping protrusion 13, the clamping protrusion 13 is abutted in a clamping groove 703 of the inner surface of the corresponding water blocking plate 7, and the two first wedge clamps 12 at the same obtuse angle form a butterfly structure, the end of the rhombic structure facing the bank of the river bank is provided with a water blocking plate 7, one end of the water blocking plate 7 is connected with a U-shaped sealing groove 8 on the end connecting column 5 of the rhombic structure, the river bank 1 opposite to the other end of the water blocking plate is provided with a water blocking groove 4, backfill soil 3 is filled in the water blocking groove 4, and the other end of the water blocking plate 7 is inserted into the backfill soil 3. Enclosing a section of enclosing bank needing to be repaired, inserting a water blocking plate 7 into backfill soil 3 of a water blocking groove 4, pumping water in the enclosed space out, and building the enclosing bank, wherein the method can determine the length of the enclosed bank section at the free end; the ecological balance in the river channel is slightly damaged, particularly fishes; the same step is to build the revetment, but the engineering scale is a little smaller, and only one small excavator, a small or simple crane and an agricultural transport vehicle are needed, so that the work can be done by a small construction team of several people.
As shown in fig. 9, the outer side surface of the lower end of the rhombic structure is connected with two water-blocking plates 7, the end of one water-blocking plate 7 is connected with the connecting column 5 at the end of the short diagonal of the rhombic structure, the end of the other water-blocking plate 7 is connected with the connecting column 5 at the end of the long diagonal of the rhombic structure, the two water-blocking plates 7 and the water-blocking plates 7 at the outer sides of the rhombic structure form a triangular structure, the connecting column 5 at the bottommost part is further connected with the water-blocking plate 7 inserted in the backfill soil 3, the water-blocking plates 7 are obliquely arranged and are flush with the water-blocking plates 7 at the outer sides of the triangular structure, a second wedge clamp 14 is arranged between the two water-blocking plates 7, the second wedge clamp 14 is in a U-shaped arrangement, the inner surfaces of the two lug plate sections of the second wedge clamp 14 are both provided with clamping protrusions 13, and each clamping protrusion 13 abuts against a clamping groove 703 corresponding to the outer side surface of the water-blocking plate 7. Compared with the assembled structure in fig. 6, the water-blocking plate 7 in the assembled structure can bear higher pressure of water flow, and is suitable for enclosing a bank in a river with larger water flow impact, and is suitable for enclosing a bank in a river (such as a dead water river) with smaller water flow impact in fig. 6.
As shown in fig. 11 to 16, the water blocking plate 7 includes a frame formed by welding a plurality of rectangular steel pipes, steel plates 701 are covered on both sides of the frame, the two steel pipes are riveted with the frame by rivets 702, the edges of the steel plates 701 are welded with the edges of the frame, two strip-shaped clamping grooves 703 are provided on the outer surface of each steel plate 701, the cross sections of the clamping grooves 703 are arranged in a U shape, the openings of the two clamping grooves 703 are oppositely arranged, and the free end of any panel is extended. The clamp plate 902 is U-shaped, the middle section of the clamp plate 902 is sleeved on the clamping screw 901, two lug plate sections of the clamp plate 902 are arranged in parallel with the corresponding water-blocking plate 7, the free end of the lug plate section of each clamp plate 902 is positioned in the clamping groove 703 corresponding to the water-blocking plate 7, and the free end of the lug plate section of the clamp plate 902 abuts against the inner bottom surface corresponding to the clamping groove 703. The inner bottom surface of the U-shaped sealing groove 8 is provided with a silica gel plate 15, and the side surfaces of the water blocking plates 7 are abutted against the silica gel plate 15. The adjusting pull rod 6 comprises an adjusting ring 601, a left-handed threaded hole is formed in the left end of the adjusting ring 601, a right-handed threaded hole is formed in the right end of the adjusting ring 601, adjusting screws 602 are screwed in the left-handed threaded hole and the right-handed threaded hole, the free ends of the adjusting screws 602 are provided with connecting rings 603, two connecting plates 501 are arranged on the surface of a connecting column 5 which is right opposite to the adjusting screws 602 at intervals, and the connecting rings 603 and the connecting plates 501 are connected through pin shafts. Each spliced pole 5 is hollow form setting, and spliced pole 5 interpolation has powerful stake 16, and powerful stake 16 is including being located anterior solid point 1601, and solid point 1601 end connection has hollow tube 1602, and hollow tube 1602 end connection has and is located terminal solid bar 1603, has seted up bar groove 1604 on the solid bar 1603 surface. The setting of powerful stake 16 can be through the hollow department pile of spliced pole 5 to the river bottom, improves the equipment rigidity of whole device, and the hammering is carried out when solid rod iron 1603's setting is convenient for lower stake, uses when simultaneously the setting of bar groove 1604 is convenient for pull out the stake. The side of each connecting column 5 is provided with a hinged seat 502, the hinged seat 502 is hinged with a supporting inclined column 17, the supporting inclined column 17 comprises two sections of hollow steel pipes 1701, a solid round steel 1702 is arranged between the two sections of hollow steel pipes 1701, the two ends of the solid round steel 1702 are provided with external threads, the hollow steel pipes 1701 with the opposite ends are provided with internal threads, the solid round steel 1702 is connected with the hollow steel pipes 1701 in a screwing mode, the other end of one hollow steel pipe 1701 is hinged with the hinged seat 502 on the side of the connecting column 5, and the other end of the other hollow steel pipe 1701 is inserted into the river bottom. The provision of the support batter post 17 provides greater structural stability of the overall assembly device.
The present invention is not limited to the above-mentioned embodiments, and based on the technical solutions disclosed in the present invention, those skilled in the art can make some substitutions and modifications to some technical features without creative efforts according to the disclosed technical contents, and these substitutions and modifications are all within the protection scope of the present invention.

Claims (9)

1. The riverID bank enclosing repair equipment is characterized in that: comprises two rows of connecting column groups arranged at intervals, each connecting column group comprises a plurality of connecting columns arranged at intervals horizontally, adjacent connecting columns in each connecting column group are connected through an adjusting pull rod, a water-blocking plate is arranged between the connecting column in one connecting column group and the adjacent connecting column in the other connecting column group, a long strip-shaped U-shaped sealing groove is arranged on the outer surface of each connecting column, the side surface of each water-blocking plate is arranged in the U-shaped sealing groove, two adjacent water-blocking plates and the corresponding adjusting pull rod form a triangular structure, a plurality of clamping mechanisms are arranged between the two adjacent water-blocking plates in the triangular structure at intervals, the clamping mechanism comprises a clamping screw rod connected with the outer surface of the connecting column, a pressing plate is sleeved on the clamping screw rod, a hand wheel is screwed on the thread section of the clamping screw rod, and the pressing plate is extruded by the hand wheel, so that the two sides of the pressing plate are butted on the surfaces of the corresponding water blocking plates.
2. A human-based bank repair apparatus according to claim 1, wherein: the lower ends of two sides of the connecting column group are respectively provided with a triangular structure, each triangular structure and the corresponding triangular structure form a diamond structure, two connecting columns on the short diagonal line in the diamond structure are connected through an adjusting pull rod, a chain is arranged between two connecting columns on the long diagonal line, both ends of the vertical chain are respectively provided with a thread sleeve, each thread sleeve is screwed on the thread section of a clamping screw in the corresponding clamping mechanism, a first wedge clamp is arranged at an obtuse angle in the diamond structure and is arranged in an L shape, one end of the vertical section of the first wedge clamp is connected with the connecting column, the other end of the vertical section is connected with an inclined section, the inner side of the inclined section is provided with a clamping protrusion, the clamping protrusion is abutted in a clamping groove on the inner surface of the corresponding water blocking plate, two first wedge clamps at the same obtuse angle form a butterfly structure, and the water blocking plate is arranged towards the end of the diamond structure on the bank side, one end of the water blocking plate is connected with the U-shaped sealing groove on the end connecting column of the diamond structure, a water blocking groove is formed in the river bank opposite to the other end of the water blocking plate, backfill soil is filled in the water blocking groove, and the other end of the water blocking plate is inserted into the backfill soil.
3. A human-based bank repair apparatus according to claim 2, wherein: the lateral surface of the lower end of the rhombic structure is connected with two water-blocking plates, one water-blocking plate end is connected with a connecting column at the short diagonal end of the rhombic structure, the other water-blocking plate end is connected with a connecting column at the long diagonal end of the rhombic structure, the water-blocking plates on the outer sides of the two water-blocking plates and the rhombic structure form a triangular structure, the connecting column at the bottommost part is also connected with the water-blocking plate inserted in backfill soil, the water-blocking plates are obliquely arranged and are parallel and level to the water-blocking plates on the outer sides in the triangular structure, a second wedge clamp is arranged between the two water-blocking plates, the second wedge clamp is in a U-shaped arrangement, the inner surfaces of two lug plate sections of the second wedge clamp are provided with clamping protrusions, and each clamping protrusion is abutted to a clamping groove corresponding to the lateral surface of the water-blocking plate.
4. A human-based parity repair device according to any of claims 1-3, wherein: the water blocking plate comprises a framework, the framework is formed by welding a plurality of rectangular steel pipes, steel plates are covered on two sides of the framework, the two steel pipes are riveted with the framework through rivets, the edges of the steel plates are welded with the edges of the framework, two strip-shaped clamping grooves are formed in the outer surface of each steel plate, the cross sections of the clamping grooves are in U-shaped arrangement, openings of the two clamping grooves are oppositely arranged, and the free end of any panel extends.
5. A human-based bank repair apparatus according to claim 4, wherein: the clamp plate is U style of calligraphy setting, and the interlude of clamp plate cup joints on pressing from both sides tight screw rod, and two otic placode sections and the water blocking plate parallel arrangement that corresponds of clamp plate, the otic placode section free end of each clamp plate is located the tight inslot of pressing from both sides that corresponds the water blocking plate and sets up, and the otic placode section free end of clamp plate contradicts on the interior bottom surface that corresponds the tight inslot of clamp.
6. A human-based bank repair apparatus according to claim 5, wherein: and a silica gel plate is arranged on the bottom surface in the U-shaped sealing groove, and the side surface of each water-blocking plate is abutted against the silica gel plate.
7. A human-based bank repair apparatus according to claim 6, wherein: the adjusting pull rod comprises an adjusting ring, a left-handed threaded hole is formed in the left end of the adjusting ring, a right-handed threaded hole is formed in the right end of the adjusting ring, adjusting screws are screwed in the left-handed threaded hole and the right-handed threaded hole, the free ends of the adjusting screws are provided with connecting rings, two connecting plates are arranged on the connecting column surface opposite to the adjusting screws at intervals, and the connecting rings are connected with the connecting plates through pin shafts.
8. A human-based bank repair apparatus according to claim 7, wherein: each connecting column is arranged in a hollow shape, a strong pile is inserted into each connecting column, each strong pile comprises a solid tip positioned at the front part, the tail part of each solid tip is connected with a hollow pipe, the end of each hollow pipe is connected with a solid steel bar positioned at the tail end, and the outer surface of each solid steel bar is provided with a strip-shaped groove.
9. A human-based perimeter repair apparatus according to claim 8, wherein: each the spliced pole side all is provided with articulated seat, it has the support batter post all to articulate on the articulated seat, support the batter post and include two sections hollow steel pipes, be provided with solid round steel between two sections hollow steel pipes, solid round steel both ends head all is provided with the external screw thread, has seted up the internal thread in the hollow steel pipe that each end is just right, solid round steel connects with hollow steel pipe soon, and a hollow steel pipe other end is articulated with the articulated seat of spliced pole side, and the other end of another hollow steel pipe is pegged graft at the bottom of a river.
CN202110824771.2A 2021-07-21 2021-07-21 riverID bank surrounding repair equipment Pending CN113737713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110824771.2A CN113737713A (en) 2021-07-21 2021-07-21 riverID bank surrounding repair equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110824771.2A CN113737713A (en) 2021-07-21 2021-07-21 riverID bank surrounding repair equipment

Publications (1)

Publication Number Publication Date
CN113737713A true CN113737713A (en) 2021-12-03

Family

ID=78728904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110824771.2A Pending CN113737713A (en) 2021-07-21 2021-07-21 riverID bank surrounding repair equipment

Country Status (1)

Country Link
CN (1) CN113737713A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201990989U (en) * 2009-12-10 2011-09-28 上海华滋奔腾防汛设备制造有限公司 Movable flood control wall diagonal brace
US20130020331A1 (en) * 2011-05-24 2013-01-24 SteelWaterz LLC Portable Dam Assemblies And Methods for Assembling Same
CN103669397A (en) * 2013-12-25 2014-03-26 青岛天力建筑加固工程有限公司 Flexible retaining wall
CN204456180U (en) * 2015-02-27 2015-07-08 重庆大学 Folded plate pile retaining wall
CN107386306A (en) * 2017-09-14 2017-11-24 安徽金贺财建筑工程有限公司 A kind of environmentally friendly cofferdam being easily installed
CN207032268U (en) * 2017-04-10 2018-02-23 代超 A kind of prefabricated cofferdam structure of hydraulic engineering
CN109604920A (en) * 2019-01-04 2019-04-12 武汉船用机械有限责任公司 A kind of adjustable welding tool setup
CN110670609A (en) * 2019-08-19 2020-01-10 浙江双和环境建设有限公司 Anti-seepage combined water-resisting device
CN210766620U (en) * 2019-10-06 2020-06-16 广州名铸科技有限公司 Reinforced support structure of portable water baffle
CN111809640A (en) * 2020-07-27 2020-10-23 福建兴港建工有限公司 Cofferdam structure and construction method thereof
CN213470119U (en) * 2020-10-10 2021-06-18 湖南电气职业技术学院 Clamp for connecting plates
CN113089586A (en) * 2021-05-12 2021-07-09 桃源县水电工程建设有限责任公司 Pier anti-scouring device

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201990989U (en) * 2009-12-10 2011-09-28 上海华滋奔腾防汛设备制造有限公司 Movable flood control wall diagonal brace
US20130020331A1 (en) * 2011-05-24 2013-01-24 SteelWaterz LLC Portable Dam Assemblies And Methods for Assembling Same
CN103669397A (en) * 2013-12-25 2014-03-26 青岛天力建筑加固工程有限公司 Flexible retaining wall
CN204456180U (en) * 2015-02-27 2015-07-08 重庆大学 Folded plate pile retaining wall
CN207032268U (en) * 2017-04-10 2018-02-23 代超 A kind of prefabricated cofferdam structure of hydraulic engineering
CN107386306A (en) * 2017-09-14 2017-11-24 安徽金贺财建筑工程有限公司 A kind of environmentally friendly cofferdam being easily installed
CN109604920A (en) * 2019-01-04 2019-04-12 武汉船用机械有限责任公司 A kind of adjustable welding tool setup
CN110670609A (en) * 2019-08-19 2020-01-10 浙江双和环境建设有限公司 Anti-seepage combined water-resisting device
CN210766620U (en) * 2019-10-06 2020-06-16 广州名铸科技有限公司 Reinforced support structure of portable water baffle
CN111809640A (en) * 2020-07-27 2020-10-23 福建兴港建工有限公司 Cofferdam structure and construction method thereof
CN213470119U (en) * 2020-10-10 2021-06-18 湖南电气职业技术学院 Clamp for connecting plates
CN113089586A (en) * 2021-05-12 2021-07-09 桃源县水电工程建设有限责任公司 Pier anti-scouring device

Similar Documents

Publication Publication Date Title
EP3502352B1 (en) Polygonal sprout system with nodes for reinforcing excavations
CN106284296B (en) A kind of supporting construction and its construction method of double steel sheet pile
CN207109795U (en) A kind of recyclable HC engineering methods steel diaphram wall
US8545129B2 (en) Cofferdam modules
CN110424411A (en) A kind of irregular foundation pit assembled steel support device and its construction and application method
CN108824461B (en) Larsen steel sheet pile cofferdam and construction method thereof
CN208844415U (en) For changing the aqueduct of the flow direction in the river above piping lane to be onstructed
CN102677592A (en) Method for erecting deepwater steel trestle and platform on exposed bedrock in shallow sea
CN113737713A (en) riverID bank surrounding repair equipment
CN105133622B (en) A kind of closed retaining design of odd-shaped cross section support pile and its construction method
CN207775909U (en) A kind of cofferdam with combination shaped steel plate pile
CN109881685A (en) A kind of assembled piling bar and its assembly method with the edge of a wing
CN218376517U (en) Tunnel reinforcing and supporting device
CN108301397A (en) A kind of multiple wing sheet-pile structure and construction method suitable for soft soil foundation
CN110468870A (en) One kind can have enough to meet the need Tower Crane Foundation by Steel Lattice Column structure
CN205975551U (en) A construction platform for construction of aquatic steel sheet pile
CN214737800U (en) Hydraulic engineering is with slope protection net of dismouting of being convenient for
CN214784068U (en) Support arrangement for steel sheet pile
CN205501988U (en) Stake of binocular shape hasp
CN113653079A (en) Combined temporary cofferdam for crossing river channel and construction method thereof
CN215715333U (en) Pre-buried device of flow plasticity geology bottom plate construction
CN210887229U (en) Irregular foundation pit assembled steel strutting arrangement
CN203559387U (en) Layered, heightened, folding and self-balancing retention wall
CN207934041U (en) A kind of double Larsen steel sheet pile rigit-frame beam
CN210597271U (en) H-shaped steel sheet pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211203

RJ01 Rejection of invention patent application after publication