- CN113719133A CN113719133A CN202110899927.3A CN202110899927A CN113719133A CN 113719133 A CN113719133 A CN 113719133A CN 202110899927 A CN202110899927 A CN 202110899927A CN 113719133 A CN113719133 A CN 113719133A
- Authority
- CN
- China
- Prior art keywords
- rope
- fixing
- clamp
- measuring
- steel bars
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
- E04G21/1841—Means for positioning building parts or elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention comprises a steel bar laying device, which is characterized in that: including wheel hub, solid fixed ring, fixation clamp, survey rope, gu fixed ring installs the wheel hub surface, survey rope one end is connected gu fixed ring is last, fixation clamp one end is for pressing the handle to connect on the survey rope, the other end is for pressing the mouth to be used for the centre gripping reinforcing bar, is provided with a plurality of fixation clamp on a survey rope. The invention also comprises a using method of the reinforcing steel bar device. The invention greatly saves the space of a construction site and the labor cost, reduces the potential safety hazard and the construction period existing in the construction site, avoids the need of manual measurement and paying off when reinforcing steel bars are bound on the site, and can also be used as a tool for checking and rechecking the spacing of the reinforcing steel bars.
Description
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a steel bar laying device and a using method thereof.
Background
In the building engineering work progress, the reinforcing bar often has a large amount of user demands as one of the main material, and general steel bar laying all chooses to send the reinforcing bar to the job site, sets up reinforcing bar processing canopy scene and carries out reinforcing bar processing, ligature, has occupied the space of a large amount of time limit for a project and job site, has brought a lot of inconveniences for the construction like this to work efficiency is not high.
Disclosure of Invention
The invention aims to assemble the reinforcing steel bars in advance, save construction production space and shorten construction period.
In order to achieve the purpose, the invention adopts the following technical scheme:
the utility model provides a steel bar laying device, includes wheel hub, solid fixed ring, fixation clamp, survey rope, gu fixed ring installs the wheel hub surface, survey rope one end is connected gu fixed ring is last, fixation clamp one end is for pressing the handle to connect on the survey rope, the other end is for pressing the mouth to be used for the centre gripping reinforcing bar, is provided with a plurality of fixation clamp on a survey rope.
Further, the wheel hub comprises a wheel shaft and two baffle plates, the two baffle plates are arranged at two ends of the wheel shaft, and the fixing ring is arranged on the wheel shaft.
Furthermore, one end of the fixing clamp, which is connected with the measuring rope, is provided with a rope hole, the measuring rope penetrates through the rope hole, and a clamping piece is arranged in the rope hole and used for fixing the measuring rope.
Furthermore, scale marks are marked on the measuring rope.
Furthermore, the inside of one end of the clamping opening of the fixing frame is circular.
Further, the measuring rope can be replaced by different lengths.
Preferably, the measuring rope is a flexible nylon rope.
The invention also comprises a using method of the steel bar laying device, which comprises the following steps:
step 5, placing each steel bar at the corresponding fixing clamp, pressing the press handle to open the clamp opening of the fixing clamp, placing the steel bars in the clamp opening, loosening the press handle to enable the fixing clamp to clamp the steel bars, and repeating the steps to enable all the fixing clamps at the same position to clamp the corresponding steel bars;
step 6, rolling the hub until the rolling of the reinforcing steel bars is completed;
and 7, firstly unfolding the steel bars on the construction site, pressing a pressing handle of the fixing clamp, removing the steel bars from the clamp opening, detaching the fixing clamp after all the fixing clamps are separated from the steel bars, rolling the wheel hub, and collecting the measuring rope.
The invention has the beneficial effects that:
1. the invention solves the problem that the traditional steel bars need to be laid one by one on site when being laid, the procedure of processing the steel bars is moved to the outside of the site, and the steel bar coils are directly laid and unfolded on site, thereby greatly saving the space and labor cost of a construction site and reducing the potential safety hazard and the construction period existing in the construction site;
2. the arranged measuring rope can be arranged into different lengths according to the design requirement, so that the flexibility and the applicability are strong, the manual measurement and paying-off during the binding of the reinforcing steel bars on site are avoided, and the measuring rope can also be used as a tool for checking and rechecking the spacing between the reinforcing steel bars;
3. the hub, the measuring rope and the fixing frame can be adjusted according to the steel bar spacing and the steel bar diameter under different construction conditions, and the hub, the measuring rope and the fixing frame are wide in applicability and popularization and can be used repeatedly.
Drawings
FIG. 1 is a schematic view of a use state of the present invention;
FIG. 2 is a schematic view of a hub construction according to the present invention;
FIG. 3 is a schematic view of a fixing clip according to the present invention;
FIG. 4 is a schematic view of a retaining clip according to the present invention;
FIG. 5 is a schematic view of another use state of the present invention;
in the figure: 1 hub, 11 baffles, 12 fixing rings, 13 axles, 2 measuring ropes, 21 graduation lines, 3 fixing clamps, 31 sliding buttons, 32 clamping pieces, 33 rope holes, 34 pressing handles, 35 clamping openings, 36 springs and 4 steel bars.
Detailed Description
In order to make the technical solutions of the present invention better understood, the following description of the technical solutions of the present invention with reference to the accompanying drawings of the present invention is made clearly and completely, and other similar embodiments obtained by a person of ordinary skill in the art without any creative effort based on the embodiments in the present application shall fall within the protection scope of the present application.
Example (b):
referring to fig. 1, a reinforcing bar 4 laying device includes wheel hub 1, solid fixed ring 12, fixation clamp 3, measuring rope 2.
Referring to fig. 1, the hub 1 includes a wheel axle 13 and a baffle 11, two baffles 11 are installed at two ends of the wheel axle 13, the fixing ring 12 is installed on the surface of the wheel axle 13, and the baffle 11 plays a role in accommodating the measuring cable 2 when the measuring cable 2 is retracted through the hub 1.
With combined reference to fig. 1, 2 and 4, one end of the measuring line 2 is connected to the fixing ring 12.
Referring to fig. 3 and 4, the fixing clip 3 is in a spring type clip shape, one end of the fixing clip 3 is a pressing handle 34, a rope hole 33 is formed in the pressing handle 34, the measuring rope 2 penetrates through the rope hole 33 to be connected with the fixing clip 3, and the other end of the fixing clip 3 is a clip opening 35 for clipping the reinforcing steel bar 4, preferably, the inside of the clip opening 35 is circular to facilitate clipping the reinforcing steel bar 4. When in use, a plurality of fixing clamps 3 are arranged on one measuring rope 2. The measuring rope is characterized in that a clamping piece 32 is arranged in the rope hole 33, a sliding groove is formed in the pressing handle 34, the clamping piece 32 is arranged in the sliding groove through a spring, a sliding button 31 is arranged on the clamping piece 32, a groove is formed in the side wall of the pressing handle 34, the sliding button 31 is limited to move in the groove, the sliding button 31 is pushed upwards to enable the clamping piece 32 to compress the spring and pack in the sliding groove of the pressing handle 34, the measuring rope 2 can penetrate into the rope hole 33, the sliding button 31 is loosened, and the clamping piece 32 is popped out of the sliding groove through the spring to clamp the measuring rope 2 to be fixed.
Referring to fig. 3, the measuring string 2 is marked with scale marks 21 for confirming the interval distance between the fixing clips 3 and facilitating reading.
In addition, when in use, the measuring rope 2 can be replaced by different lengths according to different laying distances.
With combined reference to fig. 1-5, the invention also includes a method for using said device for laying steel reinforcement 4, comprising the following steps:
step 5, placing each steel bar 4 at the corresponding fixing clamp 3, pressing the press handle 34 to open the clamp opening 35 of the fixing clamp 3, placing the steel bars 4 in the clamp opening 35, loosening the press handle 34 to enable the fixing clamp 3 to clamp the steel bars 4, and repeating the steps to enable all the fixing clamps 3 at the same position to clamp the corresponding steel bars 4;
step 6, rolling the hub 1 until the rolling of the reinforcing steel bars 4 is completed;
and 7, firstly unfolding the steel bars 4 on the construction site, pressing the pressing handle 34 of the fixing clamp 3 to remove the steel bars 4 from the clamp opening 35, detaching the fixing clamp 3 after all the fixing clamps 3 are separated from the steel bars 4, rolling the hub 1, and collecting the measuring rope 2.
Claims (8)
1. The utility model provides a rebar paving device which characterized in that: including wheel hub, solid fixed ring, fixation clamp, survey rope, gu fixed ring installs the wheel hub surface, survey rope one end is connected gu fixed ring is last, fixation clamp one end is for pressing the handle to connect on the survey rope, the other end is for pressing the mouth to be used for the centre gripping reinforcing bar, is provided with a plurality of fixation clamp on a survey rope.
2. A rebar laying device as claimed in claim 1, wherein: the wheel hub comprises a wheel shaft and two baffle plates, the two baffle plates are arranged at two ends of the wheel shaft, and the fixing ring is arranged on the wheel shaft.
3. A rebar laying device as claimed in claim 2, wherein: the fixing clamp and the measuring rope are connected, one end of the fixing clamp is provided with a rope hole, the measuring rope penetrates through the rope hole, and a clamping piece is arranged in the rope hole and used for fixing the measuring rope.
4. A rebar laying device as claimed in any one of claims 1-3, wherein: the inside of one end of the clamping opening of the fixing frame is circular.
5. A rebar laying device as claimed in any one of claims 1-3, wherein: and scale marks are marked on the measuring rope.
6. A rebar laying device as claimed in any one of claims 1-3, wherein: the measuring rope can be replaced by different lengths.
7. A rebar laying device as claimed in any one of claims 1-3, wherein: the measuring rope is a flexible nylon rope.
8. A method of using a rebar laying device as claimed in any one of claims 1 to 3 comprising the steps of:
step 1, selecting a measuring rope with a certain length according to a required laying distance, connecting one end of the measuring rope to a fixing ring of a hub, and unfolding the other end of the measuring rope to a distance;
step 2, preparing at least two hubs and two measuring ropes according to the method in the step 1, wherein the measuring ropes are arranged in parallel at a certain distance, and connecting lines between the hubs are perpendicular to the measuring ropes;
step 3, penetrating fixing clamps with the same number into each measuring rope through rope holes, determining the distance between the fixing clamps on each measuring rope according to the interval distance of the steel bars to be laid, moving each fixing clamp to the corresponding scale mark on the measuring rope, and clamping the measuring rope through a clamping piece;
step 5, placing each steel bar at the corresponding fixing clamp, pressing the press handle to open the clamp opening of the fixing clamp, placing the steel bars in the clamp opening, loosening the press handle to enable the fixing clamp to clamp the steel bars, and repeating the steps to enable all the fixing clamps at the same position to clamp the corresponding steel bars;
step 6, rolling the hub until the rolling of the reinforcing steel bars is completed;
and 7, firstly unfolding the steel bars on the construction site, pressing a pressing handle of the fixing clamp, removing the steel bars from the clamp opening, detaching the fixing clamp after all the fixing clamps are separated from the steel bars, rolling the wheel hub, and collecting the measuring rope.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110899927.3A CN113719133B (en) | 2021-08-06 | 2021-08-06 | Reinforcing steel bar laying device and using method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110899927.3A CN113719133B (en) | 2021-08-06 | 2021-08-06 | Reinforcing steel bar laying device and using method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113719133A true CN113719133A (en) | 2021-11-30 |
CN113719133B CN113719133B (en) | 2023-07-18 |
Family
ID=78674988
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110899927.3A Active CN113719133B (en) | 2021-08-06 | 2021-08-06 | Reinforcing steel bar laying device and using method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113719133B (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1998002615A1 (en) * | 1996-07-11 | 1998-01-22 | Leonard Francis Beyers | Mobile work station for assembling and laying reinforcing bars |
WO2014117214A1 (en) * | 2013-02-01 | 2014-08-07 | Leonard Francis Beyers | Rebar mesh and method of production |
JP2016000941A (en) * | 2014-06-12 | 2016-01-07 | 清水建設株式会社 | Reinforcing bar arrangement jig |
CN207105236U (en) * | 2017-06-15 | 2018-03-16 | 河北晶通建筑科技股份有限公司 | A kind of instrument for laying reinforcing bar |
CN210563472U (en) * | 2019-09-07 | 2020-05-19 | 江剑斌 | Steel bar positioning structure based on construction of building main body structure |
CN210563469U (en) * | 2019-06-12 | 2020-05-19 | 西京学院 | Reinforcing bar binding apparatus for construction |
CN210689591U (en) * | 2019-10-25 | 2020-06-05 | 中铁二十局集团第二工程有限公司 | Embedded strain gauge convenient to fix |
CN212531606U (en) * | 2020-05-14 | 2021-02-12 | 建科机械(天津)股份有限公司 | Steel band net coiling mechanism |
CN213174850U (en) * | 2020-05-21 | 2021-05-11 | 中建八局第一建设有限公司 | Line pipe spacing positioning device |
-
2021
- 2021-08-06 CN CN202110899927.3A patent/CN113719133B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1998002615A1 (en) * | 1996-07-11 | 1998-01-22 | Leonard Francis Beyers | Mobile work station for assembling and laying reinforcing bars |
WO2014117214A1 (en) * | 2013-02-01 | 2014-08-07 | Leonard Francis Beyers | Rebar mesh and method of production |
JP2016000941A (en) * | 2014-06-12 | 2016-01-07 | 清水建設株式会社 | Reinforcing bar arrangement jig |
CN207105236U (en) * | 2017-06-15 | 2018-03-16 | 河北晶通建筑科技股份有限公司 | A kind of instrument for laying reinforcing bar |
CN210563469U (en) * | 2019-06-12 | 2020-05-19 | 西京学院 | Reinforcing bar binding apparatus for construction |
CN210563472U (en) * | 2019-09-07 | 2020-05-19 | 江剑斌 | Steel bar positioning structure based on construction of building main body structure |
CN210689591U (en) * | 2019-10-25 | 2020-06-05 | 中铁二十局集团第二工程有限公司 | Embedded strain gauge convenient to fix |
CN212531606U (en) * | 2020-05-14 | 2021-02-12 | 建科机械(天津)股份有限公司 | Steel band net coiling mechanism |
CN213174850U (en) * | 2020-05-21 | 2021-05-11 | 中建八局第一建设有限公司 | Line pipe spacing positioning device |
Also Published As
Publication number | Publication date |
---|---|
CN113719133B (en) | 2023-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113719133A (en) | Steel bar laying device and using method thereof | |
CN201838934U (en) | Novel portable adjustable rod upper platform | |
CN103560437B (en) | A kind of optical cable pulley based on single-wheel sister block hangs and annex installation method | |
CN204190267U (en) | A kind of stay wire making tool | |
CN214661276U (en) | Protective function's elephant trunk staple bolt sealing connection subassembly | |
CN201927935U (en) | Guy wire binding device | |
CN214116689U (en) | Geogrid tensioning device for reinforced retaining wall | |
CN205330147U (en) | Scaffold is ligature device for board | |
CN208119477U (en) | Grounding wire pole bundled device | |
CN215055461U (en) | Reinforcing cage manufacturing tool | |
CN208502078U (en) | A kind of fixed device of construction floor construction reinforced bar | |
CN212371071U (en) | Bending tool for tubular pile reinforcement cage | |
CN204658312U (en) | A kind of automobile interior exterior decorations part buckle is done over again dismounting aid | |
CN211815417U (en) | Curb grabbing device | |
CN213234346U (en) | Traction device for laying plastic film | |
CN220972878U (en) | Quick wire-wound diamond rope saw | |
CN221189253U (en) | Round bamboo classification binding device | |
CN214023310U (en) | Front axle forging shifting-out device for friction press | |
CN212380852U (en) | Hand-held type cable promotes handle | |
CN207110476U (en) | It is a kind of be used to adding beam bottom protective layer cushion block facilitate instrument | |
CN211710857U (en) | A convenient assembled is transferred and is transported device for curb is built by laying bricks or stones | |
CN210341575U (en) | Rebar pulling-out tool | |
CN202866278U (en) | Building template fixture | |
CN213560360U (en) | Electric socket wrench and matched door-shaped steel bar bracket | |
CN203398954U (en) | Rapid dismounting device for enameled wire of motor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |